Project name: Reinforcement of Batinah Water

Transmission System
PROGRESS REPORT
Remaing works for J-174 Reporting Date: 8-Oct-2022
Client: As per Completed Completed Expecting
Consultant: A
Water Persentage Date to Remarks
Description Unit BOQ/Drawings Cumulative Cumulative Qty Completed finish
Cumulative Qty Qty -Till Date -Previous Week

SUWAIQ 19.50%
Main Contractor: E
PS , CB & GH 35.0%
- Paint work sqm 2,350 2,350 100.0% Final coat rem
Sub Contractor: T
- Ceramic flore tiles sqm 212 212 100.0% scartine 51 m re
- Plat form % 100
SECTION 2 Site Manpower - Epoxy paint % 100 10 10.0% in progress
Plant & Equipment
- Raised flooring % 100
- False ceiling % 100
HAZM BPT KHAB&MOSN
Designation/Trade Total SUWAIQ Mosanaha EXI
Res 15000 cum.: 40.0% Description &EXISTING EXI
- Paint for external wall % 100 100 100.0% Final coat rem NO Date NO Date NO Date NO Date
SUPERVISORY STAFF & OFFICE PERSONNEL
- Byffel Curtine % 100 50 50.0% Excavator 1 2 1
Section Engineer 1 - HDPE Liner % 100 50 50.0% Boom Loader
PMV Engineer 1 - GRP Covers NOS 6 Shovel 1
Surveyor 2 - Staircase NOS 8 JCB 2 1 1
General Foreman 1 Fire room building : 56.7% Mobile Crane 1 2 1
Foreman ( Civil ) 1 - Excavation % 100 100 100.0% Tipper 18cum 1 1
ASST FO ( Civil ) 1 - PCC % 100 100 100.0% Tower Crane
Forman ( Pipeline ) 2 - Footing % 100 100 100.0% Bob Cat
ASST FO ( Pipeline ) 1 - Plenth beam % 100 100 100.0% 2.5 Ton Roller
ASST FO ( Steel ) - Columes % 100 100 100.0% 1 Ton Roller 1 1
ChargeHand ( Painter ) - Roof % 100 Plate Compactor 1 1
ASST FO ( Mason ) 1 - Block work % 100 10 10.0% bellow ground Steel Cutter mashine 1 1
ChargeHand ( Mason ) 1 - Plaster work % 100 Steel binding mashine 1 1
HSE Officer Expat 3 - Finishing work % 100 Concrete site mixer 1
Yard Piping works : 35.4% Mini Bus 1 1
-Excavation Lm. 1,129 573 50.8% Bus 60 seater 1 1
-Piping Works CS joint Nos 152 47 30.9% 3 Ton Pick-up 1
Sub-total A 15 -Piping Works CS length Lm. 600 40 6.7% clerance fro TIS 1 Ton Pick-up 1
LABOUR -Piping Works DI Lm. 231 Generator 275 kva 1
Carpenter 29 -Piping Works HDPE Lm. 298 213 71.5% fire system rem Generator 150 kva 1 1
Steel fixer 20 -Thrust Blocks Nos 14 in progress Generator 40 kva 1 2
Mason 17 -Road crossing Nos 7 in progress 4X4 car
Pipe Fitter/Plumber 8 -Backfilling Lm. 1,129 213 18.9%
Helper 4 -Chambers Nos 15 12 80.0%
TIS Team 37 -Over flow chambers Nos 3 2 66.7% Total 13 18 5
Regar -W/O chambers Nos 5 5 100.0%
Operator 15 -Cover slabs Nos 23
Electrician 2 Instrument / FO CABLE
Chainman 2 -Excavation % 100 QTY to be check Total 36
Painter 4 -Duct laying for road % 100 QTY to be check
Cleaners 2 -Sarounding % 100 QTY to be check Location: SUWAIQ , HAZM BPT , HAZM EXISTING ,KHABORAH & MOSANHA
ASST CH ( Carpentar ) 1 -Cable tiles % 100 QTY to be check
ASST CH ( Scafolder ) 1 -Warning tabe % 100 QTY to be check
ASST CH ( Pipeline ) -Back filling % 100 QTY to be check
Watch man - Omani 6 Cabel routing (CCTV&FLP)
labour - Omani 4 -Excavation % 100 QTY to be check
Drivers - Omani 5 -Duct laying for road % 100 QTY to be check
-Sarounding % 100 QTY to be check
Sub-total B 157 -Cable tiles % 100 QTY to be check
TOTAL (A+B) 172 -Warning tabe % 100 QTY to be check
-Back filling % 100 QTY to be check
Requirements : Boundry wall 53.7%
-Excavation Lm. 463 313 67.6%
-Structure work Lm. 463 313 67.6% Hold bec of YP
- Block work sqm 926 626 67.6%
- Plaster work sqm 1,740 1,140 65.5%
- Paint work sqm 1,740
External Drain Channel Lm. 292
Internal Drain Channel Lm. 343
Karbstone & interlock (wake way) Lm. 453 60 13.2%
karbstone (Roads) Lm. 473
Isphalt road Lm. 473
Project name: Reinforcement of Batinah Water
Transmission System
PROGRESS REPORT
Remaing works for J-174 Reporting Date: 8-Oct-2022
Client: As per Completed Completed Expecting
Consultant: A
Water Persentage Date to Remarks
Description Unit BOQ/Drawings Cumulative Cumulative Qty Completed finish
Cumulative Qty Qty -Till Date -Previous Week

HAZM BPT 18.21%


PS , CB & GH 28.0%
- Paint for external wall % 100 100 100.0% Final coat rem
- Plat form % 100 in progress
- Epoxy paint % 100 40 40.0%
- Raised flooring % 100
- False ceiling % 100
Res 5000 cum.: 40.0%
- Paint for external wall % 100 100 100.0% Final coat rem
- Byffel Curtine % 100 50 50.0%
- HDPE Lining % 100 50 50.0%
- GRP Covers NOS 6
- Staircase NOS 8
Fire room building : 11.1%
- Excavation % 100 100 100.0%
- PCC % 100 in progress
- Footing % 100
- Plenth beam % 100
- Columes % 100
- Roof % 100
- Block work % 100
- Plaster work % 100
- Finishing work % 100
Yard Piping works : 39.8%
-Excavation Lm. 385 282 73.2%
-Piping Works CS joint Nos 95 15 15.8%
-Piping Works CS length Lm. 221
-Piping Works HDPE Lm. 164 134 81.7%
-Thrust Blocks Nos 3
-Road crossing Nos 7 1 14.3%
-Backfilling Lm. 385 134 34.8%
-Chambers Nos 9 8 88.9%
-Over flow chambers Nos 2
-W/O chambers Nos 3 3 100.0%
-Cover slabs Nos 14 4 28.6%
Instrument / FO CABLE
-Excavation % 100 QTY to be check
-Duct laying for road % 100 QTY to be check
-Sarounding % 100 QTY to be check
-Cable tiles % 100 QTY to be check
-Warning tabe % 100 QTY to be check
-Back filling % 100 QTY to be check
Cabel routing (CCTV&FLP)
-Excavation % 100 QTY to be check
-Duct laying for road % 100 QTY to be check
-Sarounding % 100 QTY to be check
-Cable tiles % 100 QTY to be check
-Warning tabe % 100 QTY to be check
-Back filling % 100 QTY to be check
Boundry wall 73.3%
-Excavation Lm. 386 350 90.7% Hold bec of YP
-Structure work Lm. 386 350 90.7% Hold bec of YP
- Block work sqm 866 801 92.5% Hold bec of YP
- Plaster work sqm 1,740 1,610 92.5% Hold bec of YP
- Paint work sqm 1,740
External Drain Channel Lm. 413 109 26.4%
Internal Drain Channel Lm. 273
Karbstone & interlock (wake way) Lm. 316
karbstone (Roads) Lm. 396
Isphalt road Lm. 397
Project name: Reinforcement of Batinah Water
Transmission System
PROGRESS REPORT
Remaing works for J-174 Reporting Date: 8-Oct-2022
Client: As per Completed Completed Expecting
Consultant: A
Water Persentage Date to Remarks
Description Unit BOQ/Drawings Cumulative Cumulative Qty Completed finish
Cumulative Qty Qty -Till Date -Previous Week

EXISTING HAZM 7.62%


Res 8000 cum.: 40.0%
- Paint for external wall % 100 100 100.0% Final coat rem
- Byffel Curtine % 100 50 50.0%
- HDPE Lining % 100 50 50.0%
- GRP Covers NOS 6
- Staircase NOS 8
Yard Piping works : 28.6%
-Excavation Lm. 325 290 89.2%
-Piping Works CS joint Nos 18 9 50.0%
-Piping Works CS length Lm. 102 clerance fro TIS
-Piping Works DI Lm. 98 80 81.6%
-Piping Works HDPE Lm. 125 80 64.0%
-Thrust Blocks Nos 11 4 36.4%
-Road crossing Nos 4
-Backfilling Lm. 325
-Chambers Nos 4
-Over flow chambers Nos 3
-W/O chambers Nos 4
-Cover slabs Nos 14 3 21.4%
Instrument / FO CABLE
-Excavation % 100 QTY to be check
-Duct laying for road % 100 QTY to be check
-Sarounding % 100 QTY to be check
-Cable tiles % 100 QTY to be check
-Warning tabe % 100 QTY to be check
-Back filling % 100 QTY to be check
Cabel routing (CCTV&FLP)
-Excavation % 100 QTY to be check
-Duct laying for road % 100 QTY to be check
-Sarounding % 100 QTY to be check
-Cable tiles % 100 QTY to be check
-Warning tabe % 100 QTY to be check
-Back filling % 100 QTY to be check
External Drain Channel % 100 QTY to be check
Internal Drain Channel % 100 QTY to be check
Karbstone & interlock (wake way) Lm. 110
karbstone (Roads) Lm. 104
Isphalt road Lm. 104
MUSANAHA EXISTING 26.78%
Yard Piping works : 53.6%
-Excavation Lm. 82 82 100.0%
-Piping Works DI Lm. 125 110 88.0% Above the ground
-Thrust Blocks Nos 4 2 50.0%
-Backfilling Lm. 82
-Chambers Nos 6 5 83.3%
-Cover slabs Nos 6
Instrument / FO CABLE
-Excavation % 100 QTY to be check
-Duct laying for road % 100 QTY to be check
-Sarounding % 100 QTY to be check
-Cable tiles % 100 QTY to be check
-Warning tabe % 100 QTY to be check
-Back filling % 100 QTY to be check
KHABORAH EXISTING 33.58%
Yard Piping works : 67.2%
-Excavation Lm. 171 171 100.0%
-Piping Works DI Lm. 250 250 100.0% Above the ground
-Thrust Blocks Nos 7
-Road crossing Nos 2 2 100.0%
-Backfilling Lm. 171 120 70.2%
-Chambers Nos 4 4 100.0%
-Cover slabs Nos 4
Instrument / FO CABLE
-Excavation % 100 QTY to be check
-Duct laying for road % 100 QTY to be check
-Sarounding % 100 QTY to be check
-Cable tiles % 100 QTY to be check
-Warning tabe % 100 QTY to be check
-Back filling % 100 QTY to be check