11-Sep-22

PROJECT : SUMMARY OF RESOURCES AS AT 11-SEP-22

SN Description 14-Aug-22 21-Aug-22 28-Aug-22 04-Sep-22 11-Sep-22 REMARKS


01 STAFF 016 016 016 015 014 civil engineer vacation/release
02 WORKERS 044 044 044 045 042 ac mechanic released; 2 masons resigned
03 NATIONAL PERSONNEL 004 004 005 005 005 no change
04 HIRED STAFF 000 000 000 000 000 no change
05 HIRED WORKERS 000 000 000 000 004 4 rejoined for office demobilization
06 SUBCONTRACTOR STAFF 004 004 002 004 003 GDS: MEP supervisor released
07 SUBCONTRACTOR WORKERS 032 032 032 032 028 GDS: 5 masons released; AL SHAM: 1 worker joined
08 EQUIPMENT OPERATORS 004 004 004 004 004 no change
09 RENTAL EQUIPMENT OPERATORS 007 007 007 007 007 no change
10 SUBCONTRACTOR EQUIPMENT OPERATORS 006 006 006 005 004 GDS: dump truck released for repair
GRAND TOTAL MANPOWER 117 117 116 117 111
11 MACHINERY (EQUIPMENT AND VEHICLES) 009 009 009 009 009 no change
12 MACHINERY (EQUIPMENT AND VEHICLES) 008 008 008 008 008 no change
GRAND TOTAL MACHINERY 017 017 017 017 017

MANPOWER VARIANCE 1 0 (1) 1 (6) TGT: 4 released/resigned, 4 rejoined for office demob; GDS: 7 released; AL SHAM: 1 joined

MACHINERY VARIANCE 0 0 0 0 0