PROJECT : TELANGANA SUPER THERMAL POWER PROJECT PHASE 1 : (2x800 MW)

CUSTOMER : NTPC LIMITED


CONTRCTOR: TATA PROJECTS LIMITED
DOCUMENT : FRONT AVAILABILITY
Cumm. Balance Status of Work front Released
SL.NO. Areas Description Unit Scope of QTY Work Status
Achieved Cumm Front available Front not available
Fire Tanks-2 nos TON 160
Erection TON 160 160 0 Work Completed and
1 Tank Area Front Available commissioned
Water filling test TON 160 160 0
Sort Blasting & Painting m2 4200 1100 3100
Fire Pumps (Erection) Nos 9 9 0
Piping Mtr 462 422 40
Valves (GV,) Nos 43 35 8
Work Completed and
2 Fire Water Pump House NRV Nos 12 12 0 Front Available
commissioned
Busket Starainer Nos 3 0 3
PRV Nos 2 0 2
Motorised Valves Nos 2 0 2
Spray system M 265 265
U/G 55 55
1) 95% completed erectiion
A/G 210 0 210 Front available balance and hydro test completedand
3 Switch yard Area-8
Hydrant system M 948 948 work under progress commissined.
U/G 213 213 2) Balance 5% under progress
A/G 735 84 651
Total M 2021 2021
4 Area -7 (Ash Handling Area) U/G 1290 150 1140 Front not available
A/G 731 150 581
Total M 4882 4882
5 Area-6 (WTP,DM Plant area) U/G 383 30 353 Front not available
A/G 4499 2940 1559
Total M 15588 15588
6 Area-5 (CHP Area) U/G 648 648 Front not available
A/G 14940 14940
Total M 2738 2738 Front available
Half Front available but need
7 Area-4 (Fuel Oil Area /GYP Area)) U/G 1030 200 830 Balance excavation wrapping coating agency
A/G 1708 1708 RCC Pedestal Not available
Total M 2131 2131
8 Area-3 ( ESP &Chimney Area) U/G & Pipe RCC Trench 1557 600 957 Front not available
A/G 574 574
Total M 5175 5175
9 TG & BOILER AREA ( AREA-2) U/G & Pipe RCC Trench 2457 650 1807 Front not available
A/G (Trestle) 2718 2718
Total M 2748 2748
10 Transformer Yard (Area-1) A/G 658 50 608 Front not available
U/G 2090 500 1590
Internal Hydrant for 3 stairs
TG Riser line ( 4 nos) Mtr 227 160 67 Front available
completed, one balance
Work Completed and
Main Oil Tank (HVWS) Mtr 406 406 0 Front available
commissioned
Work Completed and
11 PHB(U#1) COT & DOT(HVWS) Mtr Front available
commissioned
Work Completed and
OIL Canel(HVWS) Mtr 362 362 0 Front available
commissioned
Administration Building Riser Mtr 30 30 Front not available
Service buld. Riser ( 1no) M 32 32 Front not available
Boiler Riser ( 12 nos) for U #1 &2 M 900 900 Front Available for U # 1(450M)
Booster pumps Nos 4 4 Front not available
12 Boiler (PHB & Boiler) (U#1) MS piping for Booster pumps Mtr 114 114 Front not available
BBF (U#1&2) --- HVWS Mtr 0 Front not available
MS Pipe/Ms Galv Mtr 1600 1600 Front not available

Mtr 375.5 375.5 0 Work Completed and


EL+0.0 commissioned

Mtr 400 150 250 Work in progress( Front


EL+5 available )
Work in progress( Front
Mtr 400 400
13 Cable Gallery (GI ) MVW system(U#1) EL+9.0 available )
EL+14.0 Mtr 400 400 Front available
EL +25.0 Mtr 300 300 Front available
ESP Mtr 300 300 Front not available
13 Cable Gallery (GI ) MVW system(U#1)

Work Completed and


Mtr 218 218 0
Switch Yard commissioned
Work Completed and
Mtr 850 800 50
CER (U#1,2),CCR, UPS& Battery room,Programmer MS Seamless pipe work commissioned
14
room(Argonite System)
Nos 80 80 work balance( Front available)
Cylinder room (80 nos Cydinder)
GT-3nos Mtr 1204 1204 Front not available

Mtr 1144 286 858 balance 1 no work in progress


UAT-2 Nos
15 Transformer Yard (HVWS)(U#1)
UT-2 N0 Mtr 1144 Front not available

Mtr 300 300 0 Work Completed and


ST-01 No commissioned
GT-3nos Mtr 1204 Front not available
UAT-2 Nos Mtr 1005 Front not available
16 Transformer Yard (HVWS)(U#2)
UT-2 N0 Mtr 1144 Front not available
ST-02 No Mtr 581 Front not available
17 Switch Yard Bus Reactor Mtr 385 350 35 Front available work in progress
MVW spray system piping
Balance piping excavation ,RCC
18 LDO tanks ( 2 nos) -- MVWS Mtr 1385 1140 245 network both the tanks
Pedestal Not available
completed
LDO Tanks
Foam Bladder Tank Nos 2 2
Piping(MS Galv.) Mtr
19 LDO tanks ( 2 nos) -- Foam System Front not available
Foam Pourier , Foam Seal and
other accessries

Layout of internal Hydrant TP -33 Mtr 478 Front not available


Layout of internal Hydrant TP -34 Mtr 567 Front not available
Layout of internal Hydrant TP -35 Mtr 474 Front not available
Layout of internal Hydrant TP -37 Mtr 758 Front available
Layout of internal Hydrant TP -42 Mtr 1106 Front available
Layout of internal Hydrant TP -43 Mtr 673 Front available
20
Layout of internal Hydrant TP -44 Mtr 259 Front available
Layout of internal Hydrant TP -45 Mtr 556 Front not available
Layout of internal Hydrant TP -46 Mtr 571 Front not available
Layout of internal Hydrant TP -47 Mtr 365 Front not available
Layout of internal Hydrant TP -48 Mtr 630 Front not available
Layout of internal Hydrant TP -49 Mtr 411 Front not available
MVW conveyor 1st Bunker Mtr 615 Front not available
MVW conveyor 2nd Bunker Mtr 619 Front not available
MVW conveyor 3rd Bunker Mtr 617 Front not available
MVW conveyor 4rd Bunker Mtr 411 Front not available
21
MVW conveyor 5st Bunker Mtr 795 Front not available
MVW conveyor 6nd Bunker Mtr 805 Front not available
MVW conveyor 7rd Bunker Mtr 799 Front not available
MVW conveyor 8rd Bunker Mtr 805 Front not available
Conv 35A/B(MVWS) Mtr 1319 Front not available
Conv 36A/B(MVWS) Mtr 3805 Front not available
Conv 37A/B(MVWS) Mtr 6180 Front not available
Conv 38A/B(MVWS) Mtr 3543 Front not available
Conv 39 A/B(MVWS) Mtr 4910 Front not available
Conv 40A/B(MVWS) Mtr 1481 Front not available
Conv 41A/B(MVWS) Mtr 1725 Front not available
Conv 44A/B(MVWS) Mtr 5364 Front not available
Conv 45A/B(MVWS) Mtr 12672 Front not available
22
Conv 46A/B(MVWS) Mtr 779 Front not available
Conv 46A/B(MVWS) Mtr 1,582 Front not available
Conv 47 A/B(MVWS) Mtr 6811 Front not available
Conv 49A/B(MVWS) Mtr 717 Front not available
Conv 50A/B(MVWS) Mtr 653 Front not available
Conv 51A/B(MVWS) Mtr 11868 Front available
Conv 52A/B(MVWS) Mtr 5615 Front not available
Fuel Oil unloading Pump House-MVWS Mtr 248 Front not available
Fuel Oil Presure rising Pump House-MVWS Mtr 353 Front not available
23
Day oil Tank-MVWS Mtr 283 Front not available
Crasher House Mtr 2991 Front not available
CT Service Transformer -2.5MVA (HVWS) ADDITIONAL ORDER Mtr 958 Front not available
WT Service Transformer -2.5 MVA ADDITIONAL ORDER Mtr 232 Front available
FWPH Service Transformer -2.5 MVA ADDITIONAL ORDER Mtr 232 Front available
24
Zypsum Service Transformer - 2.5 MVA ADDITIONAL ORDER Mtr 240 Front not available
CHP Service Transformer - 7.5 MVA Mtr 230 Front not available
TAC/HCHD Service Transformer -2.5 MVA ADDITIONAL ORDER Mtr 2 Front not available

Total piping scope 139 KM


completed as on date 15 KM
front available after Lock Down 20 KM(chp area 13KM
period and other area 7KM