COST ESTIMATION OF REMAINING WORKS FOR HULL NO.

FMC-67
192 TEUs multi-purpose Container vessel
Owner: The Bismillah Marine Service
Shipbuilder: FMC Dockyard Ltd.

Approx. Cost to fix up the following remaining work:


S/L Items Description Quantity Procure Installation Foreign/Local Value/Budg Remarks
cost (BDT) /labor Items et (Approx.)
Cost (BDT)
1. Design, Class & Design cost - √ - L
Approval
Class approval & - √ - L
supervision
Certification fees for - √ - L
DOS
2. Remaining Hull works Fitting & welding - - 200000 - 200000

3. Plate, Angle Bar for Fabrication, fitting & 36 Ton - 1152000 - 1152000 Can be estimated precisely
Hatch Coaming welding once design received
[@32000BDTX36 ton]
4. Hatch cover Fitting & - - 1800000 - 1800000
installation commissioning
5. Propulsion Main Engine & - - 500000 - 500000
machineries Generator
installation &
commissioning
6. Pumps & Auxiliaries All pumps 14 nos. - 200000 - 200000

F.O. purifier 1 nos. - 100000 - 100000

Oily bilge separator 1 set √ 100000 F

Sewage treatment 1 set √ 100000 F


Plan
7. Piping System Fuel and lube oil 1 set √ 1800000 L/F
line (M/E & others)
Cooling line (M/E,
Generator, Auxil.)
Exhaust line (M/E,
Generator)
Steering system Pipes to be Class Approved.
hydraulic line
Air & Sounding NB: Estimation of quantity
system of pipe can be done once
Sanitary line design received.

Fire & Deck wash NB: Only compressor to be


line procured.
Sea water & Fresh
water line
Air system (M/E) √ 100000 F
including
Compressor & Air
bottle
8. Valves All valves, and √ - L/F Type approved required.
Hoses as per Valves for bilge & ballast are
requirement (FW, available.
SW, Hydraulic, Oil, NB: Estimation of quantity
Fuel) of valves can be done once
design received.
9. Pipe accessories MS Nut bolt, M20 to - √ - L/F NB: Can be estimated once
M8, Gasket, elbow, pipe line drawing received.
tee, reducer
10. Deck machinery & Gantry Crane (SWL 1 set - 200000 - 200000
outfitting 20T)
Mooring rope - - - -
Windlass 1 set - 100000 - 100000 Fitting complete but have
some works
Mooring winch 1 set √ 100000 F

Container socket - - 600000 - 600000


including loose
lashing gear
Hatch cover W.T. 1 L.S. √ 200000 L/F
equipment
Water-tight door 2 nos. √ 140000 F Fitting & welding.

Fender 1 set √ 150000 L/F Design/confirmation not


found.
11. Navigational Items RADER with an 1 nos. - 500000 - 500000 Approved type and already
antenna purchased from abroad.
Echo sounder 1 nos. -
Magnetic compass 2 nos. -

GPS Navigator 1 nos. -


Bridge Navigation 1 nos. -
Watch Alarm
Navigation lights 1 set -
Wireless Radio 1 nos. -
Telephone
VHF Radio with 1 nos. -
Continuous watch
receiver with DSC
Electronic Plotting 1 nos. -
Aid
Internal 1 nos. -
communication
system
Window Wipers, 1 L.S. -
Rudder Position
Indicator, Air horn,
Fog horn, Electrical
whistle,
Anemometer,
Marine clock,
Chronometer,
Aneroid barometer,
Hygrometer, Brass
bell, Smatic
Binoculars Etc.
PA system 1 L.S. √ 100000 L
12. LSA & FFA Life rafts as per 2 nos. √ 700000 L
POMMD
recommendation
(12 persons)
Life Buoy 12 nos. √ L
Life jacket (Adult) as 18 nos. √ L
per POMMD
Self-Ignition lights, 1 L.S. √ L
Parachute as per
POMMD
Rocket, hand flare 1 L.S. √ L
as per POMMD
Fire extinguisher 1 L.S. √ L
Fire bucket, sand 1 L.S. √ L
Box, Fire House,
Fireman Axe
Fireman’s Outfit, 1 L.S. √ L
Fireman Kit, Fire
Blanket, Fire
Detector, Heat
Detector, etc.
Fire system alarm 1 nos. - 400000 - 400000 NB: Only Contractor bill,
supply with material
CO2 system 1 nos. - 900000 - 900000 NB: Only Contractor bill,
supply with material
13. Ventilation system Engine room supply 2 nos. √ 650000 L
vent fan
Vent fan for galley 1nos. √ L
Vent fan for sanitary 8 nos. √ L
spaces
14. Electric work Air conditioning 1 L.S. √ 650000 L
Marine Electrical 1 L.S. √ L
Cables Class
Approved marine
type
Main electrical 1 L.S. √ L
switch board, C/B,
switches, magnetic
contact
Shore connection
equipment
Gas burner, Rice 1 L.S. √ L
Cooker, Utensils
Refrigerator, TV 1 L.S. √ L
light, Fan, etc.
Paneling/ducting 1 L.S. √ L
Emergency battery 1 L.S. √ L
2×200 AH, as per
design
15. Painting & protection Sand ballasting & 1 L.S. √ 2200000 L NB: Ballasting full hull and 4
Coating for Outside coat paint including A.F.
hull and ballast
tank, Sigma/Jotun /
International with
Class certificate
Accommodation Bed/shelf/Sofa 1 L.S. √ 1200000 L
16.
Toilet & sanitary 1 L.S. √ L
Insulation 1 L.S. √ L
Accommodation 1 L.S. √ L
fitting
17. Consumable Welding electrode 1 L.S. √ - L 2000 packs
Oxygen 1 L.S. √ - L 375 bottles
LP Gas 1 L.S. √ - L 50 bottles
18. Dock/undocking Labor cost - - 500000 - 500000
19. Others Misc. Outfitting - - 300000 - 300000
Works
FMC production 5 - 800000 - 800000 For 5 Month salary
staff salary persons
Vat & Taxes
20 Inclination and
Stability Testing Fees
Total=

*** Last updated on 13 May 2023.


*** The items indicated as ( √ ) to be estimated by commercial department.