AUX. CONDENSER ALL CONNECTION INLET AND OUTLET TO BE REMOVED CONDENSOR ALL
TUBES TO BE CLEANED, CHOKED TUBE TO BE CLEARED, LEAKY TUBE 5 NOS TO BE RENEWED,
AFTER RENEWAL CONDENSOR TO BE PRESSURE TESTED, INCASE ANY FURTHER LEAK SAME
TO BE RENEWED & PRESSURE TESTED. END COVER ANNODE TO BE RENEWED.
ALL CONNECTIONS TO BE FITTED BACK.
3. 4000.3 ACCOM. A/C SUCTION FILTER FRAME & WIRE MESH TO BE FABRICATED, INLET
FILTER FIXING CHANNEL WASTED SAME NEW CHANNEL TO BE FABRICATED.
LOCATION: A/C ROOM
5 4000.5 ACCOM A/C FRESH AIR INTAKE FLAP IN POOP DECK TO BE REPAIRED. OPERATING
HANDLE SHAFT SLEVEE AND PIN HAVING PLY SAME TO BE RECTIFIED.
LOCATION: POOP DECK
6. 5000.1 FWG & HOT WELL TRAY DRAIN LINE TO ENGINE ROOM BILGE, PIPE LINE VARIOUS
SECTION IN COPT PLATFORM UPTO E/R BILGES TO BE CROPPED AND RENEWED. (APPROX 30
MTRS)
STAGING REQUIRED 3MX2MX2M
PIPE DIA -48MM
FLANGE OD = 120MM
FLANGE PCD =95MM
4 BOLTS M12 SIZE
7. 5000.2 EMCY FIRE PUMP DRAIN PIPE TO AFT BILGE VARIOUS SECTION TO BE CROPPED AND
RENEWED.(APPROX-15 M).
STAGING REQUIRED 3MX2MX2M
PIPE DIA -73MM
FLANGE OD = 160MM
FLANGE PCD =128MM
4 BOLTS M12 SIZE
DAMAGED PIPE
10 5000.4 STEAM RETURN LINE AT BOTTOM PLATFORM STBD SIDE SECTION TO BE CROPPED
AND RENEWED. LENGTH APPROX 5 MTRS
PIPE DIA -34MM
FLANGE OD = 95MM
FLANGE PCD =73MM
4 BOLTS M10 SIZE
OLD REFRACTORIES TO BE REMOVED UPTO THE INNER SHELL PLATE, INSPECT OLD ANCH. ROD ,
IF FOUND DAMAGED NEED ROD TO BE WELDED
( ANGLE 60 DEG, HEIGHT : 50 MM , PITCH 175 MM )
ROD MATERIAL : SUS 304
ROD DIA : 6 MM.
NEW REFRACTORY MATERIAL : PLAST PL36
THICKNESS OF REFRACORY : 75 MM
SURFACE AREA : 9.5 SQ. M
12. 1000.1 PORT ANCHOR FLUKE BENT AND UNABLE TO HOUSE IN POSITION.
1.) FLUKE OF PORT ANCHOR IS BEND ,SAME TO BE CORRECTED.(SIZE OF ANCHOR CHAIN - 14
CABLE , GRADE SB0690, ANCHOR WEIGHT 15T , TYPE AC-14 STOCKLESS )
2.) PORT ANCHOR UNABLE TO HOUSE IN POSITION, SAME TO BE ADJUSTED .
14. 1000.7 NO-1 & NO-2 LIFE BOATS OUTER HULL COLOR FADED/STAINED, SAME TO BE REPAINTED
YARD TO REMOVE BOTH LIFE BOATS FROM STOWED POSITION AND TAKE THEM ASHORE.
OUTER HULL TO BE WASHED AND BUFFED AND PREPARED FOR PAINTING.
EXTERNAL GRAB LINE FITTED ON THE LIFE BOAT HULL TO BE RENEWED, INCLUDING HOLDING
CLIPS/RINGS
PAINTING TO HULL AREA TO BE CARRIED OUT UNDER THE SUPERVISION OF OWNER'S REP/PAINT SUPER
AFTER PAINTING, MARKING ON THE HULL TO BE DONE, REFLECTIVE TAPE TO BE RENEWED BY YARD
PACKING FOR ENTRANCE HATCHES, FOR'D AND AFT OPENING TO BE RENEWED BY YARD.
ITEM FOR YARD / WORKSHOP SUPPLY : GRAB LINE / CLIPS / PACKING FOR L/B HATCHES, OPENINGS
ITEM FOR OWNER SUPPLY : PAINT , REFLECTIVE TAPES
DIMENSIONS AS FOLLOW:-
AUTHORISED WORK SHOP TO CARRY OUT RENEWAL OF LIFEBOAT (P & S) SEAT BELTS /SECURING BELTS.
EACH LIFE BOAT CONTAIN 36 NOS OF SELT BELTS/SECURING BELTS. ALL DEFECTED SEAT BELTS TO BE
RENEWED
ITEM FOR YARD / WORKSHOP SUPPLY : SEAT BELTS/SECURING BELTS AND WORK REPORT.
AUTHORISED WORKSHOP TO INSPECT , REPAIR AND ARREST THE LEAKAGE FROM SPRINKLER PUMP STBD
LIFEBOAT.
18. 1000.11 MOB MARKER/LIFE BUOY MOUNTING FRAME BASE CORRODED/WASTED, TEMPERORYLY
DOUBLER PLATE IS FITTED FOR KEEPING L/BUOY IN PLACE -- 2 NOS (PORT & STBD)
EXISTING STAND ON PORT & STBD NAV BRIDGE WINGS, TO BE CROPPED, NEW FRAME ALONG WITH
MOB MARKER BRACKET TO BE FABRICATED, DIMENTIONS AS PER EXISTING FRAME, NEW FRAME /
MARKER BRACKET TO BE WELDED ON THE NAV BRIDGE DECK COAMINGS.
HANGING STAGGING MAY HAVE TO BE RIGGED FOR THE JOB AS PER YARD REGULATIONS, QUOTE
SHOULD INCLUDE THE COST OF STAGING (IF ANY)
LIFE BUOY WITH LINE BOX BASE AND HINGE WASTED AND BROKEN , SAME TO BE
FABRICATED ,DIMENTIONS AS PER EXISTING FRAME, NEW FRAME / MARKER BRACKET TO BE WELDED ON
THE SHIP SIDE RAILING .
20. 1000.13 EMERGENCY LIGHT ARRANGEMENT STAND FOR FORWARD LIFERAFT BADLY CORRODED AND
WASTED( NEAR PORT AND STBD WINDLASS AREA) , SAME TO BE RENEWED
EMERGENCY LIGHT ARRANGEMENT STAND FOR FORWARD LIFERAFT BADLY CORRODED AND
WASTED( NEAR PORT AND STBD WINDLASS AREA ) , SAME TO BE RENEWED
22. 1000.15 DRESSOR COUPLING SUPPORT & STUB PIECE OF PIPELINES TO BE CROPPED
AND RENEWED.
YARD TO CROP WASTED SUPPORTS AND FABRICATE NEW AS PER BELOW DIMENSIONS AND FIT
IN PLACES
Pipelines :
1.Cargo pipelines – ( 6 supports)
2.Marpol line – ( 12 supports)
3.COW line – ( 22 supports )
4.Fire line – ( 24 supports )
5.Foam line – ( 24 supports )
6.Bunker line – ( 12 supports )
7.Ig Line - ( 9 supports )
SUPPOR
T
O LAYOU
T
50 MM
m
m
0
5
2
7
0 270 mm
m
m
6
0
60 MM
50
mm( CARGO
LINE & IG
ONLY)
40 mm ( FOR
REMAINING
LINES)
23. 1000.16 WBT BALLAST LINE DRESSOR COUPLING BOLTS BADLY CORRODED REQUIRED
RENEWAL
Yard to carry out renewal of ballast line dressor coupling packings and bolts renewal
Inside ballast tanks. Upon completion lines to be tested for integrity and all leakage from the
coupling to be made good. Testing to be witness by ship staff
Total no of dressor coupling: 26 nos
Dressor coupling size : 550 a
No of bolts per coupling:12
Size: m 16 x 270 mm
24. 1000.17 Railing of Port /stbd hose handling cranes to be cropped & renewed.
25. 1000.18 Fixed Metallic Hydraulic pipelines on Port & Stbd Hose handling cranes to be
renewed.
Fixed mettalic pipelines on midship cranes to be cropped and renewed by shipyard.
SIZE OF PIELINES:
1 O.D 24 mm : 5.0 m length Approx
2.O.D 34 mm : 20 m length Approx
3.O.D 14 mm : 10 m length Approx
4. O.D 44 mm : 5.0 m length Approx
27 1000.20 REMOTE VALVE OPERATION HYDRAULIC LINE LEAKAGE NEAR 3C COT HYD. BOXES
TO BE ARRESTED.
Below mentioned hydraulic boxes have leakage in metallic pipelelines. Same to be cropped
and fitted with new T section unions / joints and leak rectified:
-Hyd box near 3C COT
-Hyd box used for line master/ drop valves.
LEAKING POINT
SIZE OF PIPES : 34 MM OD
APPROX LENGTH: 120 METRES
SIZE OF PIPES : 28 MM OD
APPROX LENGTH: 100 METR
BADLY CORRODED PIPES
Stbd windlass shaft Claw coupling found worn out resulting in gap between them . Need to
built up the same.
30. 1000.24 DECK WINCH HYDRAULIC LINES NEEDS TO BE RENEWED AT VARIOUS LOCATIONS
AFTER INSPECTION.
Hydraulic lines on main deck for winches have corroded . Need to renewpipes at assorted
locations. Need to identify during drydock locations requiring renewal.
PRESSURE SIDE PIPE SIZE: 65A / 50A / 40A SCH 160 STPT370S ( 22.6 MPA PRESSURE)
PRESSURE PIPE APPROX LENGTH RENEWAL : 10 METERS FOR EACKH SIZE
RETURN LINE PIPE SIZE: 80A/65A / 50A / 40A ( 0.98 MPA PRESSURE)
RETURN PIPE APPROX LENGTH RENEWAL : 10 METERS FOR EACKH SIZE
DRAIN LINE PIPE SIZE: 40A/ 25A ( 0.98 MPA PRESSURE)
RETURN PIPE APPROX LENGTH RENEWAL : 10 METERS FOR EACKH SIZE
Port & Stbd gangway hoisting winch found broken . Presetly secured using temporary means .
Need to overhaul and fabricate new foundation plates of both sides.
TEMPORARY SECURING
BROKEN LIGHTING
34. 1000.28 FABRICATION OF NEW DIESEL OIL BUNKERING LINE FROM MANIFOLDS TILL SLOP TANKS
CONNECTING TO EXISTING DIESEL OIL BUNKER LINE BEFORE THE VALVE.
MANUFACTURE : STANDARD
TYPE : GX-5550
PLACE OF INSTALLATION : FLUSH MOUNT ON NAV CONSOLE.
Quote for the Installation of New set / Repair of UHF radiotelephony by owner supply material.
Test the UHF set after Installation.
36. 6000.7 RADARS SERVICING & SOFTWARE UPGRADATION
Quote for the routine maintenance / inspection & Upgradation of software of Radars.
Radar software to be updated to latest so that interface with Ecdis is made operational .
o'hauling and inspection of moving parts to be done as required.
Radar internal Pcb's condition / health check to be carried out, internal cleaning of
circuit board to be done.
Magnetron condition / performance monitor condition and readings to be checked. Gyro /
speed log feeds signals to be check for accuracy,
Quote for the Installation of New Backup FURUNO FMD 3300 ECDIS . The new ECDIS will be
supplied by owners. Test the new ECDIS after Installation and all data input from various
equipments (GPS , AIS ,)
Type : WPS2N-I-2300VI-IS2
Serial number : 4383 Motor
Stroke length : 2300 mm speed control induction motor
Power source : ACllOV,l@ ,GoHz Rating : Continuous rating
Return strokes : 0-25 times ~ emrin ute Rated power source :ACllOV, I @ , GOHz
Rated current : 5. 4 A Rated output : 200 W
Arm length : 600 mm Rated current : 5.4 A
Blade length : 600 mm Number of poles : 4 Poles
Deicing heater : AC110V-345W Class of insulation : Class B
Weight(mass) : 40. 1 kg Speed controlled unit by : FSP200-1
39. 6000.10 REPLACEMENT OF CCR UHF
.
Quote for the Installation of new set of UHF in CCR. The present Set Signal is very week .Some
time unable to communicate, Install the new set of UHF by owner supply material. Test the UHF
after Installation.
MANUFACTURE : STANDARD
MODEL : GX-5550
Authorised tech to do the fault finding and correct the same / renew parts as req'd. Test prints & auto
winding of printed paper to be checked.
SOFT PATCHES
9000.2 EGB WASH DRAIN TANK DRAIN PIPE LINE CONNECTION TO BE MADE TO SEPARATOR
BILGE OIL TANK , LENGTH APPROX 50 MTRS,
PIPE DIA -73MM
FLANGE OD = 155MM
FLANGE PCD =120MM
4 BOLTS M16 SIZE