You are on page 1of 1

BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Wednesday, March 18, 2020 DAILY SITE PHOTO

Activities Location Description of works Remarks

FOUNDATION Bored Pile


Piling work in progress.
total completed to date: 128 nos.
total Number foundation Bored Piles 128 nos. 100.00%
Structural work

CONTIGUOUS Bored Pile ( CBP )

total completed to date: 141 nos.


Total number of contiguous Bored Piles 141 nos. 100.00%

GROUT PILES
PILE CAP CONSTRUCTION IN PROGRESS
total completed to date: 100 nos.
Total number of GROUT Piles 141 nos. 70.92%
Grout Pile " 8" PILE GROUT Today
Architectural
work
M & E Work

REBAR WORKS AND FORWORKS IN PROGRESS ON FOUR PILE CAPS P41, P40, P39 AND P45

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE
P Manager 1 Supervisor Generator 2
Site Supervisor 3 Safety officer 1 Excavator 2
08:30 17:30 Safety officer 1 Pil Rig Operator BIG BREAKER 1
Site engineer 1 Safety office 1
RTO 1 Rigger Worker 4 MINI EXCAVATOR 1
REMARKS Administrator 1 hacking team 2 vibro hammer 1
Coordinator 1 gen Worker 4 NEW crawler crane 1
G Worker 7 grout machine 1

Weather

FAIR

Manpower
8:30 18:00 TOTAL : 16 TOTAL : 12 TOTAL : 0 TOTAL : 0 28 ON GOING EXCAVATION WORKS TO PLATFORM LEVEL

Housekeeping work inprogress,

REBAR WORKS AND FORWORKS IN PROGRESS ON FOUR PILE CAPS P41, P40, P39 AND P45

ON GOING EXCAVATION WORKS TO PLATFORM LEVEL

REMARKS :
8 CBP PILES HACKING DONE, 4 HACKED USING BIG MACHINE BREAKER PLUS 4 TRIMMING MANUAL HACKING
USING JACK HAMMER

noise level reading: AT 10:50AM TILL 10:55AM NOISE READING Exceeded, reading 92.3dB and 91.8dB 8 CBP PILES HACKING DONE, 4 HACKED USING
BIG MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER

You might also like