DAILY SITE RECORD Wednesday, March 18, 2020 DAILY SITE PHOTO
GROUT PILES
PILE CAP CONSTRUCTION IN PROGRESS
total completed to date: 100 nos.
Total number of GROUT Piles 141 nos. 70.92%
Grout Pile " 8" PILE GROUT Today
Architectural
work
M & E Work
REBAR WORKS AND FORWORKS IN PROGRESS ON FOUR PILE CAPS P41, P40, P39 AND P45
Weather
FAIR
Manpower
8:30 18:00 TOTAL : 16 TOTAL : 12 TOTAL : 0 TOTAL : 0 28 ON GOING EXCAVATION WORKS TO PLATFORM LEVEL
REBAR WORKS AND FORWORKS IN PROGRESS ON FOUR PILE CAPS P41, P40, P39 AND P45
REMARKS :
8 CBP PILES HACKING DONE, 4 HACKED USING BIG MACHINE BREAKER PLUS 4 TRIMMING MANUAL HACKING
USING JACK HAMMER
noise level reading: AT 10:50AM TILL 10:55AM NOISE READING Exceeded, reading 92.3dB and 91.8dB 8 CBP PILES HACKING DONE, 4 HACKED USING
BIG MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER