Professional Documents
Culture Documents
CLIENT :
CONTRACTOR :
SUB - CONTRACTOR :
CONTRAC :
PROJECT :
FIC NO. :
REPORT NO. :
CLIENT : LEGEND 06.00-07.00 07.00-08.00
DATE / DAY : C : CLER
WORKING HOURS : Hours CL : CLOUD
WORK CATEGORY : TR : TINY RAIN
LOCATION : HR : HEAVY RAIN
MANPOWER PRODUCTION
NO. TODAY ACTIVIES / ACHIEVEMENT UNIT LAST DAY TODAY QTY SUM
MANPOWER
NO. DIRECT QTY NO
1 Supervisor 1 Construction Manager
2 Foreman 2 Site Manager
3 Surveyor 3 PPC Manager
4 Helper 4 Engineering
5 Craftman 5 Project Control
6 General Labour 6 Logistic Manager
7 Access Control 7 Quality Control
8 First Aider 8 Welding Tracking
9 Operator B Loader 9 Material Control
10 Operator Mixer 10 Line Check
11 Driver 11 Safety Officer
12 Painter
NO. EQUIPMENT
PREPARED BY CHECKED BY
PT. REKAYASA INDUSTRI PT. SUPRACO
PT. REKAYASA INDUSTRI
SUMMARY ACTIVITIES
% NO. TOMORROW ACTIVITIES PLAN
NO TOOLS UNIT QTY
QTY
T TOTAL TOOLS
CHECKED BY APPROVED BY
PT. SUPRACO CHEVRON GEOTHERMAL SALAK, Ltd
CHEVRON GEOTHERMAL SALAK GENERAL PROCURM
SCHEDULE OF WORK
5.00% 5.00%
6.00% 6.00% 6.00%
3.50% 3.50%
26.00% 26.00%
0.00%
AWI 2 CONVERSION
FIP REFERENCE :
REMARKS
WORK PACKAGE :
AWI 2 CONVERSION
FIP REFERENCE :
REMARKS
CONTRUCTION PROGRESS UPDATE
GCSSD PROJECT
Updated: 25-Jul-14
11.64% 96.9% 67% 29-Jun-14 1. Complete all concrete work for 1. Complete all stimulation line pipe
PS, line,
2. Platform foundation and 2. startup line 10" , stimulation pipe
stimulation line foundation, support and platform,
3. Complete install pipe 3. Additional work Drain Line 2" of
downcommer 18" including valves Down comer line 18" tie-in to
existing drain line2" of stimulation
Line 3"
31.61% 96.94% 100.00% 29-Jun-14 1. Complete all stimulation line 1. Completed Installation of
pipe line, insulation,
2. startup line 10" , stimulation 2. finishing cable pulling & backfill
pipe support and platform, 3.finsihing touch up painting.
3. Additional work Drain Line 2" of 4. Punch list Preparation
Down comer line 18" tie-in to
existing drain line2" of stimulation
Line 3"
PLAN TO BE COMPLETED NEXT REMARKS/PROBLEM RESOURCES
WEEK
ACTION BY
REKON - RBS
5/15/2022 3:26
ACTION BY
REKON - RBS