FIELD DAILY ACTIVITY REPORT

CLIENT : PT Sarku Enjinering Utama


SUB-CONTRACTOR : PT Saloi Pusaka Halmahera
CONTRACT : SEU-005-SCA-2103-0001
PROJECT : Pelaksanaan Pekerjaan Jasa Pembangunan Jalan - 2103 Project
Location : Gunung Hamiding
Report No : Rain Recapitulation Table
Date/Day : 22 Augustus 2023 07.00-08.00 08.00-09.00 09.00-10.00 10.00-11.00 11.00-12.00 12.00-13.00 13.00-14.00 14.00-15.00 15.00-16.00 16.00-17.00
Working Hours : 07.00 - 17.00 C : Clear
Work Category : Construction CL : Cloudy C C C C C C C CL CL CL
TR : Tiny Rain
Location : Gn. Hamiding HR : Heavy Rain
Manpower Volume Qty Progress Summary Activities
No. Today Activities / Achievement UNIT Qty Previous Today SUM % No. Tomorrow Activities Plan

1 Pekerjaan Sloop Exca Hyundai. STA. 13.600- STA 13.640 (Refly) 09.00 - 14.00 Continue Pekerjaan Sloop & Galian Katingan STA 13.590-STA 13.640
Pekerjaan Galian Exca Hyundai STA13.600-sta 13.611(Refly) (exca hyundai breakdown gantiM3 115,500
Exca Hitachi. 14.00-17.00

Man Power
No No. Tools Unit Qty
DIRECT QTY INDIRECT Qty
1 Operator 1 1
2 SHE Officer Admin HSE 2
3 Helper 1 HRD Manager 3
4 Flagman PR Manager 4
5 Driver General Admin 1 5
6 Supervisor 1 Project Manager 6
7
8
9
10
TOTAL DIRECT 3 TOTAL INDIRECT 1 TOTAL TOOLS 0
TOTAL MANHOURS 27 9
TOTAL MANHOURS PREVIOUS 0
TOTAL MANHOURS CUMULATIVE 36

No. Equipment Qty No. Material Unit Previous Today Total


1 LV (Double Cabin 4X4) 1 1.
2 Excavator HYUNDAI 1 2.
3 Excavator Hitachi 1 3.
4 Dump Truck 4.
TOTAL EQUIPMENT 3
DAILY PROGRESS REPORT

CLIENT PT Sarku Enjinering Utama


CONTRACTOR PT Saloi Pusaka Halmahera
CONTRACT SEU-005-SCA-2103-0001
PROJECT Pelaksanaan Pekerjaan Jasa Pembangunan Jalan - 2103 Project