PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Monday, January 15, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Cangkul 4 Unit
Blencong 4 Unit Site Manager 1 man 09.00 - 10.00 clear
pengki 3 Unit
palu 2 Unit QC Officer man 10.00 - 11.00 clear
gergaji 1
Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear
Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Survey lokasi pekerjaan Volume : 1. Volume :
2. Pengiriman material Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1. Besi tulangan pondasi tiang lampu
2. Besi tulangan pondasi kontainer
3. Peralatan kerja

PROBLEM OCCURED
1. PT.MNA tidak menerima penyimpanan material kerja kontraktor
2.
3.

CORRECTIVE ACTION
1. Alat kerja kontraktor dibawa kembali
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Tuesday, January 16, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 8:30 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Blencong Unit
Palu Unit QC Officer man 10.00 - 11.00 clear
Pengki Unit
Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear
Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Wednesday, January 17, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Thursday, January 18, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Friday, January 19, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Saturday, January 20, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Sunday, January 21, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Monday, January 22, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Tuesday, January 23, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Wednesday, January 24, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Thursday, January 25, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Friday, January 26, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Saturday, January 27, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Sunday, January 28, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Monday, January 29, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Tuesday, January 30, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Wednesday, January 31, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Wednesday, January 31, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Wednesday, January 31, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Wednesday, January 31, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Wednesday, January 31, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Wednesday, January 31, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Wednesday, January 31, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager
PT MULTIMAS NABATI ASAHAN - SERANG

DAILY REPORT
PROJECT NAME PERUBAHAAN JALUR KABEL DAN DATE Wednesday, January 31, 2018
INSTALLASI CONTAINER OFFICE PROJECT

CONTRACTOR PT.CTA CONTRACT NUMBER 001/E-IDAN-16-043/MNA-CTA/XII/2017

LOCATION Office Project dan Kawasan

DATE OF SCHEDULE SCHEDULED ACTUAL PROGRESS SCHEDULED (%) ACTUAL % ENVIRONMENT HEALTH SAFETY

Start 8:00 13:00 Today


Finished 17:00 17:00 Overall
Total Days
Status Delayed/Ahead
Remaining Day

TOOLS & HEAVY EQUIPMENT MAN POWER WEATHER


Hour Condition Remarks

Name Qty Project Manager man 08.00 - 09.00 clear


Civil Tools Pacul Unit
Linggis Unit Site Manager 1 man 09.00 - 10.00 clear
Unit
Unit QC Officer man 10.00 - 11.00 clear

Mechanic Tools Unit EHS Officer 1 man 11.00 - 12.00 clear


Unit
Unit Skill 2 man 13.00 - 14.00 clear
Unit
Helper 3 man 14.00 - 15.00 clear
Electrical Tools Unit
Unit Security man 15.00 - 16.00 clear
Unit
Unit Quality Inspector man 16.00 - 17.00 clear

Supervisor Electrical 1 man 17.00 - 18.00

Adm man 18.00 - 19.00

Total 8 Total 19.00 - 20.00

WORK DESCRIPTION
Location : Office Projek Location : Kawasan
Work : Work :
1. Penggalian pondasi Volume : 1. Survey lokasi PJU dan traffic light Volume :
2. Volume : 2. Volume :
3. Volume : 3. Volume :

Documentation : Documentation :

MATERIAL INCOMING
1.
2.
3.

PROBLEM OCCURED
1.
2.
3.

CORRECTIVE ACTION
1.
2.
3.

PREPARED BY CHECKED BY APPROVED BY


Contractor PT. MNA Serang PT. MNA Serang

RIZKY RIAN ISROFI


Site Manager Site Engineer Site Manager