Professional Documents
Culture Documents
Index of Appendices
Business Case
TINKLEMAN E-Books
Programme Office Version 2.0
Business Case Date: 11/04/2014
Template Version 1.01
PROTECTED - Management
Business Case
E-Books Project
Status: Approved
Version: 2
PROTECTED - Management
Business Case Approval Sheet
Project Approval: the following officers must have had the opportunity (5 working
days minimum) to consider the final version of the business case and their comments
must be incorporated into this business case, or if not incorporated, then noted in
the comment section below.
Name Comment
Change History
Date Version Change Description Change Author
V0.4
Reference Documents
[e.g. the Project Charter, Project Brief, Work Requests (WRs), SSGQG Pro-forma or
any presentations/ strategies]
PROTECTED - Management
PROTECTED - Management
Table of Contents
1. Executive Summary ................................................................................... 5
2. Rationale and Purpose................................................................................ 6
3. Objectives and Options .............................................................................. 7
3.1. Objectives ........................................................................................... 7
3.2. Options Considered ............................................................................. 8
4. Proposed Solution ...................................................................................... 9
5. Scope (of recommended Option) ............................................................ 10
5.1. Included in Project Scope ................................................................. 10
5.2. Out of Project Scope ......................................................................... 10
6. Critical Success Factors ........................................................................... 11
7. Business Benefits ..................................................................................... 13
8. Strategic Fit ............................................................................................. 13
8.1. Strategic Themes and objectives .................................................... 13
8.2. TCF and Customer Experience ......................................................... 13
8.3. IS Principles, Milestones and Compliance........................................... 13
9. Financials.................................................................................................. 14
9.1. Cost Benefit Summary ...................................................................... 14
10. Key Milestones ...................................................................................... 15
11. Resources Required .............................................................................. 16
12. Project Context .................................................................................... 17
12.1. Constraints ..................................................................................... 17
12.2. Assumptions .................................................................................. 17
12.3. Dependencies ................................................................................. 17
12.4. Project Risks .................................................................................. 18
12.5. Business Risks ................................................................................ 18
12.6. Issues ............................................................................................. 18
12.7. Opportunities ................................................................................. 18
13. Change Requests .................................................................................. 18
13.1. DDF Changes .................................................................................. 18
13.2. Issue Papers ................................................................................... 18
13.3. WR Changes ................................................................................... 19
14. Appendices .......................................... Error! Bookm ark not defined.
PROTECTED - Management
1. Executive Summary
Electronic Books (E-books) have finally taken off globally and are
forecast to be the next big revenue stream for Tinkleman. By partnering
exclusively with SSGQG the Emerging markets team estimates that a
modest estimation of market share we can capture in our first year
following launch is 5% and can grow that share by 20% year over year.
(These numbers have been verified and signed off by the CFO’s -
Jaylene Ruth – Finance and Business Insight team leader).
In order to deliver on the above Tinkleman needs to get this project delivered by end
of Q3 (i.e. end September 2014) so that the E-Book product is available well in time
for the Christmas 2014 market.
The project fits well with the Tinkelman overall growth strategy. Specific budget
($250,000) has been allocated via the 2014 planning round and approved by the
EXCO.We also undertook a joint planning exercise with our partners SSGQG where we
have agreed on resource requirements in terms of people, cost estimates and IT
equipment.
The timeline for the project has also been set out (see page 16).
This project has been categorised as a Priority 1 project (highest priority) by EXCO.
Other benefits
Direct channel Increase value Effectiveness
PROTECTED - Management
Change context
To leverage the IT structure created for the initial e-books business along with
features created to support the digital music business so that we can QUICKLY and
CHEAPLY create the updated e-book web interface.
Benefit/outcome
External research has shown that the e-book business has grown by 23% over the
previous year and represents a $2.3BN business in 2013. If Tinkelman can deliver
capability through this project then additional revenue of $11.5m in Year 1 is
estimated with a projection as verified by SSGQG that the minimum revenue through
the partnership will be at least $8.7m p.a. when fully operational. This represents a
huge RIO (to be calculated and signed off by FB&I at a later date).
PROTECTED - Management
3.1. Objectives
2. Once Operational to ensure that the business case Revenue targets are
met
PROTECTED - Management
3.2. Options Considered
Disadvantages Very risky and not enough data to make informative decisions
Disadvantages Will stretch resources and will require significant work re the PM culture
Conclusion This option improves customer experience and can be delivered for Go Live
date
Assessment The best that could be achieved with the timescale and fits with growth
strategy
PROTECTED - Management
4. Proposed Solution
.
Rationale Solution improves the customer journey while meeting the fixed Go Live
date
Impact Meets the Go Live date which is key while improving direct channel access
by giving the customer ability to manage their account on line and will
increase revenue in line with targets
Conclusion This option improves customer experience and can be delivered for Go Live
date
PROTECTED - Management
Change from
Ref Scope item Description Impact
Brief
ISC 1.Project Professionalise As per the Charter Inc Productivity
Mngtmt. Design and sign off Legal protection
2.SSGQG H/w, S/w and Functionality
contract Network
Functionality
3. E-book Deliver and test
platform Increase
In time for Xmas business
4. E-book
platform
5. Launch
PROTECTED - Management
Critical Success Factor: Something which must be in place for a Project or Programme to deliver its benefits or outcomes. A Critical
Success Factor (CSF) is often what makes the difference between just delivering something and really making a difference.
For instance, producing guidance is not sufficient to change behaviours: other things must be in place (such as appropriate attitudes in the
target population, and effective training Programmes).
These other elements are critical to the success of the work and are therefore Critical Success Factors. CSFs are internal or external
factors that generally the organisation undertaking the Project can control or strongly influence.
In a Project context they are generally more about culture than about what must be done or delivered. Analysis of critical success factors
will generate activities that should be undertaken to ensure the conditions are in place for success (for example a communications
strategy to explain the benefits of doing things differently or development of a training Programme).
PROTECTED - Management
CO1 Comms. Strategy Per Project H Comms Team, Comms Plan for Internal and
that assists Charter Product staff and External Comms,
customers Development Customers Marketing and HR
through team departments.
transition to new
product with
complete testing
completed on
time and within
budget whilst
developing
market share per
the specified
targets (ROI etc.)
PROTECTED - Management
7. Business Benefits
Growth strategy requirements incorporate:
Start with the E-books project which will then set the path for future
ways of working
Benefits
• Less reliance on legacy systems
• More professional ways of working
• Easier processes to understand
• Sustainable future ways of working
• Utilising leveraging and lessons learned
• All round more experienced staff making the business fit for purpose and the
future.
PROTECTED - Management
8. Financials
NOTE:
PROTECTED - Management
Available m ilestone:
Go Live – 30-09-2014
PROTECTED - Management
PROTECTED - Management
11.1. Constraints
Ref Constraint
CON001 . Budgets and other resource (people/IT) constraints
11.2. Assumptions
Ref Assumption
1 Forecasting and Business Insight assumptions
11.3. Dependencies
PROTECTED - Management
11.4. Project Prioritised Risks are covered in a separate
report
11.7. Opportunities
To maximize existing investment for parallel projects.
PROTECTED - Management
12.3. W ork Request Changes Logs
• WR - Testing
• WR - Sign off
• WR - Auto calculate
• WR - Confirmation
Initiation Report
PMO – CONFIDENTIAL
Deliverables:
Risks: Tinkleman suffered heavy losses from the first purchase of an eBooks
line in the ‘90s, and there are fears that a similar mistake has been made in
this most recent down the same path.
Mitigations: The recent growth of the E-Book business in the previous year
would suggest that the time is now ripe for a move into the E-Books
business, unlike the first attempt in the ‘90s, which may have been
premature.
Com pany Strategy Fit: Due to recent successes, and with the acquirement
of its largest competitor, the company is in a position of strength. This has
led to an expansionist mood among board members. The move into the
growing E-Books industry will allow Tinkleman to expand without undue risk.
Stakeholder Register
PMO – CONFIDENTIAL
Stakeholder Map
PMO – CONFIDENTIAL
Table of Contents
INTRODUCTION 2
IDENTIFY STAKEHOLDERS 2
KEY STAKEHOLDERS 3
STAKEHOLDER ANALYSIS 3
Introduction
Identify Stakeholders
2. Does the person or their organization hold a position from which they
can influence the project?
5. Does the person potentially benefit from the project or are they in a
position to resist this change?
Any individual who meets one or more of the above criteria will be identified as
a stakeholder. Stakeholders from the same organization will be grouped in order to
simplify communication and stakeholder management.
Key Stakeholders
Stakeholder Analysis
Once all E-Book Project stakeholders have been identified, the project team
will categorize and analyze each stakeholder. The purpose of this analysis is to
determine the stakeholders’ level of power or influence, plan the management
approach for each stakeholder, and to determine the appropriate levels of
communication and participation each stakeholder will have on the project.
utilize a power/interest matrix to illustrate the potential impact each stakeholder may
have on the project. Based on this analysis the project team will also complete a
stakeholder analysis matrix which illustrates the concerns, level of involvement, and
management strategy for each stakeholder.
The chart below will be used to establish stakeholders and their levels of power
and interest for use on the power/interest chart as part of the stakeholder analysis.
Below is the power/interest chart for E-book Project stakeholders. Each letter
represents a stakeholder in accordance with the key in the chart above.
5
F
Power
A G
C D
1
1 5
Interest
Based on the power and interest analysis and chart above, stakeholders A, C,
and D will require minimal management effort as they reside in the lower left
quadrant of the matrix. Stakeholder F, in the upper left quadrant, must be kept
satisfied by ensuring concerns and questions are addressed adequately. Stakeholder
G, in the lower right quadrant, must be kept informed through frequent
communication on project status and progress. Stakeholders B and E, in the upper
right quadrant, are key players and must be involved in all levels of project planning
and change management. Additionally, stakeholders B and E should be participatory
members in all project status meetings, gate reviews, and ad hoc meetings as
required.
Sponsor Acceptance
Harry Pearson
CIO
Meeting Objective
The meeting objective is to discuss the best way we can execute the
eBooks projects on time and on schedule so that we can
The project fits well with the Tinkelman overall growth strategy. We will
also discuss future plans and rollout when this project is finished.
Agenda
• Introductions of attendees
• Review of the project background
• Review of project-related documents (business case, project charter)
• Discussion of project organizational structure
• Discussion of project scope, time, and cost goals
• Discussion of other important topics
• List of action items from meeting
Attendees
Meeting Opening:
John Frum gave a brief overview of the rationale and the main objectives and
the target outcomes.
Agenda:
• Introduction of attendees
• Background of project
• Review of project-related documents (i.e. business case, project charter
sign off)
• Discussion of project organizational structure
• Discussion of project scope, time, and cost goals
• Discussion of other important topics
• List of action items from meeting
Project Charter
PMO – CONFIDENTIAL
1. Project Background
2. Project Goals
3. Project O bjectives
4. Scope
5. Stakeholders
6. Success Criteria
• Budget restraints
• Time restraints
• Resource restraints
• Optimistic forecasting
• Customer interest
• SSGQ’s interest in exclusive partnership
• Digital Jam compatibility
• Digital Jam quote
• Project Management success
9. Budget
10. Authorizations
Lewis Curtis
Innovation 03/ 03/ 14
Don Johnson
Project Manager 03/ 03/ 14
1 1.0 eBook Project All work required to implement new eBook Digital Asset Management
System project.
2 1.1 Initiating Work required for the initiation stage of the project.
3 1.1.2 Identify key stakeholders Determine all key stakeholders to the project.
3 1.1.3 Stakeholder register and stakeholder List all stakeholders, external and internal, their level of influence and
management strategy interest, and potential management strategies.
3 1.1.5 Hold project kick-off meeting Project is officially started with a kick-off meeting. PM, sponsor and project
team to attend.
3 1.1.6 Project charter sign off Project sponsor signs off on charter authorizing Planning stage to
commence.
2 1.2 Planning Work required for the planning stage of the project.
3 1.2.1 Determine project team PM to decide on project team and request availability of resources for life
of project.
3 1.2.2 Develop team contract PM to develop a team contract to promote teamwork and clarify
communications.
3 1.2.4 Prepare schedule and costs PM to document a breakdown of time and resource requirements.
breakdown
4 1.2.5.1 Determine task durations PM to determine how long each task will take.
4 1.2.5.2 Determine task resources PM to determine what resources are required for each task.
4 1.2.5.3 Create Gantt chart PM to create Gantt chart showing all project tasks and their start and end
dates.
3 1.2.6 Prepare risk register PM to create and document risks and procedures for managing them.
4 1.2.6.1 Identify risks PM to identify risks to the project, their probability and impact.
3 1.2.7 Develop contracts with external PM to develop and finalize contracts of work with any external
stakeholders stakeholders.
4 1.2.7.1 Digital JAM for DAM development Digital JAM will be the primary developer for our eBook Digital Asset
Management system.
4 1.2.7.2 SSGQG for delivery SSGQG will be our exclusive content partner.
4 1.2.7.3 Additional delivery vendors We also aim to provide eBooks via top 3 readers on market.
2 1.3 Executing Work required for the Executing stage of the project.
3 1.3.1 External kick-off meeting PM holds a kick-off meeting with project team including Digital JAM and
SSGQG to review and validate requirements.
3 1.3.2 Design eBook DAM Design of eBook Digital Asset Management system, outsourced to Digital
JAM.
3 1.3.3 Procure hardware All hardware required for project delivery to be acquired.
3 1.3.4 Procure software All software required for project delivery to be acquired.
3 1.3.5 System development Hardware, software and network to be integrated and customized for
requirements.
3 1.3.6 System testing Select a small group of users to test eBook DAM system.
3 1.3.8 eBook DAM launch Launch of new Tinkleman eBook Digital Asset Management system
2 1.4 Monitoring and Controlling Work required for the Monitoring and Controlling stage of the project.
3 1.4.1 Project management PM to perform overall project management for duration of project; manage
scope, risks, etc. throughout project life.
Gantt Chart
Name Duration Start Finish Predecessors
1 E-Books Project 167.875 ... 3 / 2 6 / 1 4 9 : 0 0 A M 11/14/14 5:00 PM
2 Initiating 21.875 d... 3 / 2 6 / 1 4 9 : 0 0 A M 4/24/14 5:00 PM
3 Evaluation 1 day? 3/26/14 9:00 AM 3/27/14 9:00 AM
4 Identify Key Stakeholders 1 day? 3/27/14 9:00 AM 3/28/14 9:00 AM 3
5 Stakeholder register and stakeholder manage... 15.875 d... 3/28/14 9:00 AM 4/18/14 5:00 PM 4
6 Develop Project Charter 16.875 d... 3/27/14 9:00 AM 4/18/14 5:00 PM 3
7 Project Charter sign-off 0 days? 4/18/14 5:00 PM 4/18/14 5:00 PM 5;6
8 Hold project kick-off meeting 0 days? 4/21/14 8:00 AM 4/21/14 8:00 AM 7
9 Minutes of kick-off meeting 3 days? 4/22/14 8:00 AM 4/24/14 5:00 PM 8
10 Planning 33.875 da... 3 / 2 7 / 1 4 9 : 0 0 A M 5/13/14 5:00 PM
11 Determine project team 18.875 d... 3/27/14 9:00 AM 4/22/14 5:00 PM
12 Develop Team Contract 5.875 days? 4/18/14 9:00 AM 4/25/14 5:00 PM
13 Determine scope 6.875 days? 4/18/14 9:00 AM 4/28/14 5:00 PM
14 Prepare schedule and cost breakdown 9.875 days? 4/18/14 9:00 AM 5/1/14 5:00 PM
15 Prepare WBS 12.875 d... 4/18/14 9:00 AM 5/6/14 5:00 PM
16 Prepare Risk Register 14.875 d... 4/18/14 9:00 AM 5/8/14 5:00 PM
17 Develop contracts with external stakeholders 17.875 d... 4/18/14 9:00 AM 5/13/14 5:00 PM
18 Executing 110.875 d... 5 / 1 4 / 1 4 9 : 0 0 A M 10/15/14 5:00 PM
19 External kick-off meeting 0.875 days? 5/14/14 9:00 AM 5/14/14 5:00 PM 17
20 Design E-Book DAM 10.875 d... 5/14/14 9:00 AM 5/28/14 5:00 PM
21 Procure hardware 12 days? 5/29/14 8:00 AM 6/13/14 5:00 PM 20
22 Procure software 12 days? 5/29/14 8:00 AM 6/13/14 5:00 PM 20
23 System development 56.875 d... 5/29/14 9:00 AM 8/15/14 5:00 PM 20
24 System testing 21 days? 8/18/14 8:00 AM 9/15/14 5:00 PM 23
25 Training 8.875 days? 9/16/14 9:00 AM 9/26/14 5:00 PM 24
26 E-Book DAM launch 0.875 days? 10/15/14 9:00 AM 10/15/14 5:00 PM
27 Monitoring and Controlling 167.875 d... 3 / 2 6 / 1 4 9 : 0 0 A M 11/14/14 5:00 PM
28 Project management 167.875 ... 3/26/14 9:00 AM 11/14/14 5:00 PM
29 Progress reports 145.875 ... 3/26/14 9:00 AM 10/15/14 5:00 PM
30 Change Management 145.875 ... 3/26/14 9:00 AM 10/15/14 5:00 PM
31 Closing 22.875 da... 1 0 / 1 5 / 1 4 9 : 0 0 A M 11/14/14 5:00 PM
32 Prepare final project report 1 day? 10/15/14 9:00 AM 10/16/14 9:00 AM
33 Document Lesson Learned 7.875 days? 10/15/14 9:00 AM 10/24/14 5:00 PM
34 Formal acceptance from Sponsor 0.875 days? 10/17/14 9:00 AM 10/17/14 5:00 PM 32
35 Formal project archiving 0.875 days? 11/14/14 9:00 AM 11/14/14 5:00 PM 32;33;34
3/28
4/18
4/21
5/14
5/14
10/15
10/17
11/14
Network Diagram
E-Books Project Initiating Evaluation Identify Key Stakeholders
Duration 167.875 days? Duration 21.875 days? Duration 1 day? Duration 1 day?
Start 3/26/14 9:00 AM Start 3/26/14 9:00 AM Start 3/26/14 9:00 AM Start 3/27/14 9:00 AM
Finish 11/14/14 5:00 PM Finish 4/24/14 5:00 PM Finish 3/27/14 9:00 AM Finish 3/28/14 9:00 AM
Determine scope
Duration 6.875 days?
Start 4/18/14 9:00 AM
Finish 4/28/14 5:00 PM
Prepare WBS
Duration 12.875 days?
Start 4/18/14 9:00 AM
Finish 5/6/14 5:00 PM
Procure software
Duration 12 days?
Start 5/29/14 8:00 AM
Finish 6/13/14 5:00 PM
System development
Duration 56.875 days?
Start 5/29/14 9:00 AM
Finish 8/15/14 5:00 PM
Progress reports
Duration 145.875 days?
Start 3/26/14 9:00 AM
Finish 10/15/14 5:00 PM
Change Management
Duration 145.875 days?
Start 3/26/14 9:00 AM
Finish 10/15/14 5:00 PM
oject Charter Project Charter sign-off Hold project kick-off meeting Minutes of kick-off meeting
16.875 days? Duration 0 days? Duration 0 days? Duration 3 days?
3/27/14 9:00 AM Start 4/18/14 5:00 PM Start 4/21/14 8:00 AM Start 4/22/14 8:00 AM
4/18/14 5:00 PM Finish 4/18/14 5:00 PM Finish 4/21/14 8:00 AM Finish 4/24/14 5:00 PM
ck-off meeting
0.875 days?
5/14/14 9:00 AM
5/14/14 5:00 PM
rdware
12 days?
5/29/14 8:00 AM
6/13/14 5:00 PM
tware
12 days?
5/29/14 8:00 AM
6/13/14 5:00 PM
Milestone Report
PMO – CONFIDENTIAL
Initiating
Stakeholders identified 26/03/2014 Completed PM, Lewis Curtis
Planning
Determine project team 22/04/2014 Completed PM
Executing
External kick-off meeting 14/05/2014 Completed PM
held
Closing
Final project report and 16/10/2014 Completed PM
presentation completed
Table of Contents
Introduction 2
Definitions of Change 2
Introduction
The Change Management Plan was created for the E-Books Project in order to
set expectations on how the approach to changes will be managed, what defines a
change, the purpose and role of the change control board, and the overall change
management process. All stakeholders will be expected to submit or request
changes to the Project Manager, Don Johnson in accordance with this Change
Management Plan and all requests and submissions will follow the process detailed
herein.
The Change Management approach for the E-Books Project will ensure that all
proposed changes are defined, reviewed, and agreed upon so they can be properly
implemented in a timely fashion and communicated to all stakeholders. This
approach will also ensure that only changes within the scope of this project are
approved and implemented.
The Change Management process has been designed to make sure this
approach is followed for all changes. By using this approach methodology, the E-
Book Project Team will prevent unnecessary change from occurring and focus its
resources only on beneficial changes within the project scope.
Definitions of Change
There are several types of changes which may be requested and considered
for the E-Books Project. Depending on the extent and type of proposed changes,
changes project documentation and the communication of these changes will be
required to include any approved changes into the project plan and ensure all
stakeholders are notified. Types of changes include:
• Budget Changes: changes which will impact the approved project budget.
These changes may require requesting additional funding, releasing funding
which would no longer be required, or adding to project or management
reserves. May require changes to the cost baseline.
• Scope Changes: changes which are necessary and impact the project’s
scope which may be the result of unforeseen requirements which were not
initially planned for. These changes may also impact budget and schedule.
These changes may require revision to WBS, project scope statement, and
other project documentation as necessary.
The project manager must ensure that any approved changes are
communicated to the project stakeholders. Additionally, as changes are approved,
the project manager must ensure that the changes are captured in the project
documentation where necessary. These document updates must then be
communicated to the project team and stakeholders as well.
The Change Control Board (CCB) is the approval authority for all proposed
change requests pertaining to the IS Project. The purpose of the CCB is to review all
change requests, determine their impacts on the project risk, scope, cost, and
schedule, and to approve or deny each change request. The following chart provides
a list of the CCB members for the E-Books Project:
The following are the roles and responsibilities for all change management
efforts related to the E-Book Project:
Project Sponsor:
Project Manager:
• Participate on CCB
Project Team/Stakeholders:
The Change Control Process for the E-Book Project will follow the
organizational standard change process for all projects. The project manager has
overall responsibility for executing the change management process for each change
request.
2. Log change in the change request form (Project Manager) – The project
manager will keep a log of all submitted change requests throughout the
project’s lifecycle in Change Log.
5. Obtain Decision on change request (CCB) – The CCB will discuss the
proposed change and decide whether or not it will be approved based
on all submitted information. This decision will be made within 48hours
of submission.
Sponsor Acceptance
Harry Pearson
CIO
Required approvals:
Required approvals:
Risk: low, SME has been highly recommended by indust ry expert s and has
over 3 2 years document ed t echnology experience, t he last 1 5 years working
wit h E-Book plat f orms.
Other: none
Required approvals:
#001 Cost This change calls for a further D.Johnson 26/03/2014 26/03/2014 APPROVE This change was
allocation of $10,000 to project D approved immediately to
budget to cover legal costs. allow the project to
progress.
#002 Time This change calls for delaying the D.Johnson 01/04/2014 02/04/2014 APPROVE This change was
current project schedule by 6 D approved, in agreement
weeks to allow external contracts that the project will still be
to be completed. This delay was delivered in time for the
unforeseen, initial budgeting Christmas market.
lacked thorough research.
#003 This change calls for hiring a D.Johnson 06/04/2014 07/04/2014 APPROVE This change was
Subject Matter Expert to work D approved in order to
alongside the Project Manager improve the overall
which was not considered in the project scope and future
original project plan success of the project and
company.
With E-Books being the next big revenue stream, we find this project to
be fitting with our business growth strategy
As this project was building upon the failures of first venture into the E-
Book business in the 1990s, which resulted in a considerable loss. We hope
through better research and risk planning to avoid the failures of the past.
equipment. Assigned
to Desmond O’Malley,
IT Procurement.
Risk Matrix
IMPACT
Prioritized Risks
PMO – CONFIDENTIAL
STRENGTHS WEAKNESSES
OPPORTUNITIES THREATS
The Diagram below shows Porter’s Five Forces. These are external
forces that can impact on the viability of a project.
We knew at the onset of this project that Digital JAM & the Publishing
houses had significant bargaining power, in particular the Publishing houses
who could make our break our project depending on the margins on offer.
This is why we spent a lot of time putting together strong contracts with our
suppliers to ensure a lucrative relationship going forward with a focus on
positive gains for all parties. We acknowledged at this stage that our
relationship with Publishing houses could be detrimental to the future success
of the project if not managed properly.
All Such risks should then be monitored using a Risk Log. In Tinkleman
our Risk Log had the following Column Headings:
• Unique ID (Category)
• Category
• Risk
• Likihood
• Impact
• Timescales
• Cost
• Owner
• Residual Risk
This was done on the previous report using the list of prioritized risks
reports. We can also look at:
Risks should also be costed and contingencies budgeted for. This can be
done using EMV (Expected Monetary Value)
For Example, with Tinkleman we saw the risk that contracts with
external suppliers might cost more than expected. We calculated the
probability of such an event at 75% and the cost at 10k. The calculation was
then:
For each risk evaluated, the project team needs to decide if the
risk/cost justifies the continuation of the project, or if the risk needs to be
mitigated.
Communications Plan
PMO – CONFIDENTIAL
Distribute Project All stakeholders Distribute Plan to alert Before Kick Off Meeting Document distributed
Initiation Plan stakeholders of project scope Before Project Start Date via hardcopy or
and to gain buy in. electronically. May be
posted on project
website or OIT
Blackboard site.
PPM Templates: Project
Snapshot or “Lite”
Initiation Plan
Project Kick Off All stakeholders Communicate plans and At or near Project Start Date Meeting(Skyp/teleconfe
stakeholder rence only in extreme
roles/responsibilities. circumstances) ideally
Encourage communication all in one place and face
among stakeholders. to face.
Status Reports All stakeholders Update stakeholders on Regularly Scheduled. Distribute electronically
and Project progress of the project. Monthly is recommended for and post via INTRANET
Office large/midsize projects. web
PPM Template: Status
Report
Team Meetings Entire Project To review detailed plans Regularly Scheduled. Meeting
Team. (tasks, assignments, and Weekly is recommended for PPM Template: Detailed
Individual action items). entire team. Weekly or bi- Plan
meetings for sub- weekly for sub-teams as
teams, technical appropriate.
team, and
Functional teams
as appropriate.
Project Advisory Project Advisory Update Project Advisory Group Regularly Scheduled. Meeting
Group Meetings Group and on status and discuss critical Monthly is recommended.
(this may apply Project Manager issues. Work through issues
only to larger and change requests here
projects) before escalating to the
Sponsor(s).
Sponsor Steering Sponsor(s) and Update Sponsor(s) on status Regularly scheduled Meeting
Committee Project Manager and discuss critical issues. Recommended biweekly or
Meetings Seek approval for changes to monthly and also as needed
Project Plan. when issues cannot be
resolved or changes need to
be made to Project Plan.
Post Project Project Office, Identify improvement plans, End of Project or end of major Meeting/Report
Review Project Manager, lessons learned, what worked phase Project Office will
key stakeholders, and what could have gone produce report.
and sponsor(s). better. Review
accomplishments.
Quarterly Project Project Office, Review overall health of the Quarterly depending on size Meeting/Report
Review Project Manager, project and highlight areas and criticality of the project. Project Office will
and key that need action. Scheduled by the Project produce report using
stakeholders. Office. internal template.
Tinkleman ALL Project Central location to house Update monthly with Status Electronic
Intranet Site Team Members. Status Reports, meeting Reports; otherwise, as Communications Venue
minutes, Project description, necessary.
and Project Plan. For any
communications that can be
shared with all OIT staff.
Periodic Demos Specific Focus To gain input from special Once product has enough to Presentation/Discussion
and Target Groups or End groups and keep them abreast “show”. As you complete
Presentations Users. of the Project’s status. critical phases or make major
Examples: enhancements.
Product
Managers,
Marketing,
Operational
Users, Help Desk,
Dept Mgrs., etc.
Financial Plan
Appendix H.1 – Five Year Financial Plan
Project: E-Books Project
Prepared by: Don Johnson, Project Manager Date: 18/04/2014
Assumptions
1. Wll capture 5% of a $2.3BN total market share in Year 1
2. Will grow 20% of that market share year on year
3. SSGQG partnerhsip will contribute to circa 75% of Revenues year on year
4. Total market share will remain constant @ $2.3bn so this is a conservative assumption
2 Profitability Forecasts
$M
Year 1 0.35
Year 2 0.41
Year 3 0.66
Year 4 0.89
Year 5 1.19
Assumptions
1. Rate of return in Years 1 & 2 will be equal to rate of return for competitor ACME 3%
2. Rate of returns in Years 3,4 and 5 will increase to 3.5%, 4% and 4.5% respectively
3. IT Costs will reduce as expected by CFO thus contributing to increased profitability.
The proposed Revenue Stream and Profitability forecasts are supported by signed off (by Head of Finance) financial
analysis models, accompanied by the assumptions (risks) in the notes setting the scene for discussions around how to
mitigate etc. Ownership of theses models lay with Finance but delivery on the numbers lies with all stakeholders so a
joint up approach is vital in order to succeed.
An Earned Value Management (EVM) diagram was used to help monitor and control the project costs
Conclusion
Based on an initial outlay of $250k on the project this makes make the E-BOOKS project VALUE FOR MONEY
Payback will be in year 1 based on the above numbers and assumptions (and still year 1 despite the budget over run).
Positive NPVs and ROI's make this project value adding in a very quick timescale.
Appendix I.1
Procurement Plan
PMO – CONFIDENTIAL
Tim efram e
The team has been assured by Digital JAM that these changes are final,
and that no others will be required. However, it is uncertain, to the project
team, as to whether this would be the case.
Mitigations
In keeping with the concern for the long-term viability of Digital JAM’s
proposed changes, three of its other clients who had had similar alterations
made to their system were contacted by the team. The team reported
satisfactory results from the other three clients, suggesting that the
proposed changes to the system would not be a hindrance in the future.
As these changes to the system are essential for the project to proceed
and succeed, it has been decided to continue ahead with procuring Digital
JAM’s changes to the system at the given price.
Progress Report
PMO – CONFIDENTIAL
A brainstorming session was held between the primary project team and
the project sponsor. This was broken into two parts for convenience: firstly,
focusing on internal stakeholders within Tinkelman; and secondly, a focus on
external stakeholders. Who qualified as a stakeholder was determined by five
points of criteria (see above: ‘Identify Stakeholders’). In addition, the key
stakeholders among them were determined, to show where the team could
best concentrate on.
Considerable work went into pitching the E-Books project to the internal
stakeholders as identified on the Tinkleman corporate board. There were a
couple of other projects in consideration, some which would have been
preferred by certain board members. For example, Elise Morrison showed an
interest in the Gaming System Modification project as it looked to improve
Tinkleman’s current gaming sales. However, she supported the E-Book Project
as such a system might be applicable to the gaming sales department in the
future. As a result of such ‘canvassing’ on the part of the project team, the
project was able to secure the support and confidence of internal
stakeholders.
The project met its time, scope and cost goals, and so it can be
considered a success.
W hat w ere the success criteria listed in the project statem ent?
The Digital Asset Management system purchased for the E-Book system
was previously limited to music titles. Due to early contact with custom
vendor involved, Digital JAM, and allocation of budget funds, the system was
successfully updated to support books as well as music.
The Services shall commence on April 30, 2014, and shall continue
through August 30, 2014.
Scope of W ork
Fixed price contract so Digital JAM incur all other costs beyond quote.
Deliverable Materials
Contractor Responsibilities
Client Responsibilities
Make sure all staff at Tinkleman IT Department work with our engineers
and project management and to have weekly and daily meetings.
Fee Schedule
TInkleman Wholesale,
411 Elm St, Dallas Don Johnston IT Department
64311
Client will be invoiced monthly for the consulting services and T&L
expenses. Standard Contractor invoicing is assumed to be acceptable.
Invoices are due upon receipt.
Contractor shall have fulfilled its obligations when any one of the
following first occurs:
Assum ptions
• Both Project Managers will review the proposed change and approve it
for further investigation or reject it. Contractor and Client will mutually
agree upon any charges for such investigation, if any. If the
investigation is authorized, the Client Project Managers will sign the
PCR, which will constitute approval for the investigation charges.
Contractor will invoice Client for any such charges. The investigation
will determine the effect that the implementation of the PCR will have
on SOW price, schedule and other terms and conditions of the
Agreement.
For Tinkleman
SIGNATURE: ______________________
POSITION: CIO
DATE: 30/04/2014
SIGNATURE: ______________________
POSITION: IT Director
DATE: 30/04/2014
Completion/Acceptance Plan
Appendix J.1 – Com pletion/Acceptance Plan
Distribution
• Handover Plans
• Training Plans
Responsible
Those who do the work to achieve the task. There is typically one role
with a participation type of Responsible, although others can be
delegated to assist in the work required.
Accountable
The one ultimately answerable for the correct and thorough completion
of the deliverable or tasks. Typically the Accountable role delegates the
completion of the deliverable to the Responsible role. There must be
only one Accountable specified for each task or deliverable.
Consulted
Inform ed
Those who are kept up to date on status throughout the lifecycle of the
deliverable, and with whom there is just one way communication. These
are the "key consumers" of the information
4. Review Process
The Project Status report will give people an overall view of the status
of the project, however for any area where the status is Orange or Red,
additional updates will be required. These will be processed as follows:
Health Key Milestone Project Deliverable Manager/Assigned to Workstream Phase Expected finish date Actual finish Date Recent Progress Last Update
Initiating
Stakeholder Register Initiation
Green – Complete Stakeholders identified PM, Lewis 26/03/14 26/03/14 complete
Green – Complete Project charter signed Project Charter PM, Sponsor 18/04/14 18/04/14 complete
Green – Complete Project kick-off meeting held Kick off meeting held PM 21/04/14 21/04/14 complete
22/04/14 22/04/14 complete
Planning
Green – Complete Determine project team PM & Project Sponsor 25/04/14 25/04/14 complete
Green – Complete Team contract signed Team Contract PM & All of Team 28/04/14 28/04/14 complete
Green – Complete Scope analysis completed Scope Statement PM in conjunction with core team 01/05/14 01/05/14 complete
Cost Estimate & Financial s
Green – Complete Schedule and costs breakdown completed complete PM & Finance 06/05/14 06/05/14 complete
Work Breakdown Structure
document completed & signed
Green – Complete WBS completed off PM 08/05/14 08/05/14 complete
Green – Complete Risk register completed PM & All of Team 14/05/14 14/05/14 Group Legalcomplete
have been in
negotiations with Publishing
Houses to Agree best pricing
strategy for E-books
procurement, The due date for
this deliverable is currently
Legal Contracts between overdue and is being monitored
Tinkleman & Publishing Houses closely. Daily phone meeting
Amber – Late & SSGQG to confirm pricing & with an update on the status to
Delivery External stakeholders contracts in place deliverables. PM, Sponsor & Legal Team 14/05/14 be held. PM to co-ordinate. 12/05/14
A meeting was held this week in
advance of due date. It was
agreed that the team would
meet on Tuesday's and
Thursday with external
providers for update on
Green – WIP External kick-off meeting held PM Execution 14/05/14 13/05/14 progress 14/05/14
Sign off of E-book Design Design document is now signed
Document/ Requirements Digital Jam Project Team/PM & off and Development is
Green – WIP eBook DAM design completed document Project Sponsor 28/05/14 underway 14/05/14
Des has advised that there is a
one week lead time on
obtaining software and
hardware which is an acceptable
timeline. Overtime
arrangements with staff have
been agreed and all is currently
Green – WIP Hardware and software procured IT – Des O' Malley 13/06/14 on schedule 14/05/14
Page 1
Appendix J.4
RACI Chart
RACI Chart
Page 1
Appendix J.5
Handover Plan
PMO – CONFIDENTIAL
Governance
1. Project Custom er
2. Project sponsor
3. Project Manager
Stakeholders
Stakeholder
Stakeholder area Responsibility Interest or context
representative
Tinkleman Harry Pearson Project Sponsor Ensuring project
(CIO) meets
organizational
needs
Project purpose
1. Background
2. Success Criteria
6. Operational Handover
Handover Checklist
PMO – CONFIDENTIAL
Project Governance has been agreed. Customer, PM, Sponsor have been
agreed and have accepted their responsibilities
Operational Issues:
• Issues relevant to managing project deliverables on an ongoing
basis have been identified
• Actions or instructions for dealing with these issues have been
identified.
Training Plan
PMO – CONFIDENTIAL
1. Introduction
• E-Books Software
• Internal Intranet site holding all project background/monitoring
documentation
• Webex training
2. Training Scope
The PM will ensure training materials are put in place but the responsible
for delivering and administering training will remain with SME”s in each
department co-ordinated by Jerry Maguire the main SME for E-Books. He will
be responsible for putting together training documentation and ensuring daily
webex training is completed. Jerry will also be responsible for ensuring all
staff have access to training material via our internal Intranet site
3. Training Program
All SME's will need to ensure they are 100% up to date with the
functionality required for their business area and are aware of the reporting
Objective
The objective of this project as detailed in our project charter was as follows:
Our eBooks solution was ready for release on the 15th October 2014
after much work and dedication from the team.
Our decision to release prior to the strong Christmas market has paid
off. Sales are already excellent and forecast sales bring up ahead of our goal
of taking a 5% share in the E-Books market ($2.3 billion worldwide market in
E-Books) by end of Quarter 3 2015. We have also decided to enter the digital
games market, with a project due to start in January 2015. As we already
have products in this market, this is an obvious direction for our company to
take.
• Our internal Project team collaborated with Digital JAM and created a
project toolkit which ensured that the progress of the project was
monitored, that there were clear milestones and an effective structure
to ensure its success
• This project, as it was stand alone, did not impact as much on other
areas of the company, whilst at the same time creating a positive
attitude to projects and a toolkit for project work that we could use in
future projects
** Legal costs were higher than initially expected and a new contractor had
to hired for the duration of the project with eBooks expertise
• Grow market share year on year to the lasting future of the company.
2. Increased market share and a new digital direction for the company
At the start of the project, it took some time to get contracts agreed
with publishing houses. We had to fight hard to get good margins on the
products we would eventually be selling. This was an important aspect of the
project so it was worth spending the time ensuring these agreements were in
place.
Initially Elise Morrison and the CEO were not in agreement with taking on
this project, they both saw the gaming line of business as the top priority.
We acknowledged that this was an issue, but that current PM skills in the
company were not ready to embrace such an important project. This, and the
potential of the company to increase market share of digital games put the
Gaming project as the next area of priority in 2015 and the eBooks project to
be the first completed in 2015.
As Digital JAM was initially a provider of digital music, there was a steep
learning curve to understand the nuances of the eBooks platform/market. As
a result we hired a contractor with expertise in the area to work as a Subject
Matter Expert (SME) on the project.
Transition Plan
Marketing - Review of the marketing plan, advertising revenue from the site,
customer feedback analysis.