CIVIL DAILY REPORT

PROJECT : LANDSLIDE RESTORATION AT SIL-2 WELLPAD


CONTRACT NUMBER : SOL-AGR II-1676 R00

REPORT NUMBER OF : 03/DR/GI/SIL-II/III/2024


DAY/DATE OF : Wednesday/06 March 2024

LABOR TODAY'S ACTIVITIES


MANAGEMENT Qty No. DESCRIPTION
1. Project Manager 1 1 Area Cleaning for Filled Soil
2. Deputy Manager 1
3. Field Manager 1
4. Field Engineer 1
5. Drafter 1
6. Administration 1
FIELD
7. Safety Officer 1
8. Operator 1 TOMORROW'S PLANS
9. Surveyor No. DESCRIPTION
10. Foreman 1 Area Cleaning for Filled Soil
11. Mandor (M) 2 Mobility of stone materials
12. Man Power/Helper 3 Cleaning the river under the work area
4 Diversion of surface water at the entrance to the work area

HSE (Safety Officer)


1. Briefing regarding Work Safety, in certain areas
2. Briefing regarding the use of APD
WORKING HOURS : 08.00 - 09,30 Ok
10.00 - 12.00 Ok
13.00 - 14.30 Rain
15.00 - 17.00 Rain
OVERTIME :
WEATHER
HEAVY RAIN
SUNNY 08.00 - 10.00 Wib
10.00 - 17.00 Wib
DRIZZLING x Wib
MATERIAL Qty EQUIPMENT Qty
1. Landfill around the area 1. Excavator PC 200 1

Note Completion Wittness By, Prepare by,


1. Surface water when it rains leads to the work Directs surface water
area into channels away from SARULLA OPERATION Ltd CV. GRESS IBOT
the work area

(Titin Saragih) (Tulus H Pangaribuan)


Civil Construction Supervisor Engineer

RAP/FML/PRO-19 (R.01) - 141114


BAY / IMS / NFL
JOB VISUAL REPORT
Project : LANDSLIDE RESTORATION AT SIL-2 WELLPAD
Location : SIL - 2
Day Of : Wednesday
Date Of : 06-Mar-24

Creation of Shelter Points Creation of Shelter Points Measurement of existing topography

Measurement of existing topography Measurement of existing topography Measurement of existing topography