1) The civil daily report provides an update on restoration work from a landslide at an oil well site.
2) Today's activities included area cleaning for filled soil and preparations for tomorrow's plans which include more area cleaning, moving stone materials, cleaning an area by a river, and diverting surface water.
3) Weather was reported as heavy rain which impacted the work schedule, and surface water management is noted as important to prevent water reaching the work area during rains.
1) The civil daily report provides an update on restoration work from a landslide at an oil well site.
2) Today's activities included area cleaning for filled soil and preparations for tomorrow's plans which include more area cleaning, moving stone materials, cleaning an area by a river, and diverting surface water.
3) Weather was reported as heavy rain which impacted the work schedule, and surface water management is noted as important to prevent water reaching the work area during rains.
1) The civil daily report provides an update on restoration work from a landslide at an oil well site.
2) Today's activities included area cleaning for filled soil and preparations for tomorrow's plans which include more area cleaning, moving stone materials, cleaning an area by a river, and diverting surface water.
3) Weather was reported as heavy rain which impacted the work schedule, and surface water management is noted as important to prevent water reaching the work area during rains.
MANAGEMENT Qty No. DESCRIPTION 1. Project Manager 1 1 Area Cleaning for Filled Soil 2. Deputy Manager 1 3. Field Manager 1 4. Field Engineer 1 5. Drafter 1 6. Administration 1 FIELD 7. Safety Officer 1 8. Operator 1 TOMORROW'S PLANS 9. Surveyor No. DESCRIPTION 10. Foreman 1 Area Cleaning for Filled Soil 11. Mandor (M) 2 Mobility of stone materials 12. Man Power/Helper 3 Cleaning the river under the work area 4 Diversion of surface water at the entrance to the work area
HSE (Safety Officer)
1. Briefing regarding Work Safety, in certain areas 2. Briefing regarding the use of APD WORKING HOURS : 08.00 - 09,30 Ok 10.00 - 12.00 Ok 13.00 - 14.30 Rain 15.00 - 17.00 Rain OVERTIME : WEATHER HEAVY RAIN SUNNY 08.00 - 10.00 Wib 10.00 - 17.00 Wib DRIZZLING x Wib MATERIAL Qty EQUIPMENT Qty 1. Landfill around the area 1. Excavator PC 200 1
Note Completion Wittness By, Prepare by,
1. Surface water when it rains leads to the work Directs surface water area into channels away from SARULLA OPERATION Ltd CV. GRESS IBOT the work area
(Titin Saragih) (Tulus H Pangaribuan)
Civil Construction Supervisor Engineer
RAP/FML/PRO-19 (R.01) - 141114
BAY / IMS / NFL JOB VISUAL REPORT Project : LANDSLIDE RESTORATION AT SIL-2 WELLPAD Location : SIL - 2 Day Of : Wednesday Date Of : 06-Mar-24
Creation of Shelter Points Creation of Shelter Points Measurement of existing topography
Measurement of existing topography Measurement of existing topography Measurement of existing topography