DEVON

Page 1 of 3
Daily Report
OFFSHORE ORIG DRLG
WELL NAME 24 HRS PROG TMD TVD DFS REPT NO. DATE
PANYU 5-1-A06H 42 2,419 2,139 15.00 16 2004-3-14
RIG NAME & NO. FOREMAN AFE NO. AUTH MD AUTH TVD API NO.
DEVON ENERGY PANYU 5-1 BUSH, BOB 111179 3,462 2,161 -
LAST CASING NEXT CASING DATE OF LAST SAFETY MEETING LAST BOP PRES TEST INCIDENT IDENTIFICATION
13.375 (in) @ 598.00 (m) 9.625 (in) @ 2,534.00 (m) 2004-3-14 2004-3-3 NONE
FIELD NAME LEAKOFF MW WI NRI
PANYU 5-1 9.30 24.50000 24.5000
LITHOLOGY DAILY DRLG DAILY COMP COST DAILY TOTAL COST
SD/SH/CLAY 71,401 0 71,401
CURRENT STATUS CUM DRLG CUM COMP COST CUM TOTAL WELL COST
WORK PIPE & CIRCULATE. 1,269,550 0 1,269,550
24 HR FORECAST AFE DHC AFE COMP COST AFE TOTAL PROJ COST
DRILL AHEAD TO TD. 2,674,361 1,368,356 4,042,717

DAILY OPERATIONAL COMMENTS: DRILL TO 2419 M. REPAIR #1 MUD PUMP. WIPER TRIP TO SHOE. SLIP & CUT DRILLING
LINE.SERVICE TDS, FIXED MUD PUMP #1, RIH, WORK PIPE & CIRC @ REDUCED FLOW RATE.

OPERATIONS SUMMARY
FROM TO HOURS PHASE STEP OPER TASK DESCRIPTION
00:00 07:30 7.50 INTR1 DRLG DRLG DRILL AHEAD FROM 2377 M TO 2419 M.
07:30 10:00 2.50 INTR1 MISC RIGSER TRIG PISTON FAILED ON #1 MUD PUMP. FOUND PONY EXTENTION ROD
DAMAGED WHILE PULLING PISTON. NO SPARE ON RIG. SENT PONY
ROD TO SHEKOU FOR REPAIR.
10:00 12:30 2.50 INTR1 DRLG STRIP TRIG WIPER TRIP TO 1478 M. TIGHT SPOT: 1859M O/P 50K, 1635M, O/P 50K
1478 M, O/ P 70K.
12:30 13:00 0.50 INTR1 MISC RIGSER TRIG REAMING FROM 1479 M TO 1455 M.
13:00 15:00 2.00 INTR1 DRLG TRIP TRIG WIPER TRIP TO SHOE. HOLE SLICK. INSTALL TIW SAFETY VALVE.
15:00 18:00 3.00 INTR1 MISC RIGSER TRIG SLIP & CUT DRILLING LINE.
18:00 19:30 1.50 INTR1 MISC RIGSER TRIG SERVICE TDS WHILE FIXING & INSTALLING PONY EXTENTION ROD ON
MUD PUMP #1.
19:30 20:00 0.50 INTR1 DRLG STRIP TRIG RIH @752 M, TEST MWD, OK.
20:00 23:30 3.50 INTR1 DRLG STRIP TRIG RIH TO BOTTOM.HOLE SLICK. WASH DOWN LAST STAND.
23:30 00:00 0.50 INTR1 DRLG CIRC WORK PIPE & CIRC AT REDUCED RATE WHILE CLEANING UP
SHAKERS.

NOTE 1: 0000 TO 0030 WORK PIPE & CIRC AT REDUCED RATE.


0030 TO 0100 DRILL AHEAD F/ 2419M TO 2423 M.
0100 TO 0130 CIRC WHILE CHANGING OUT PISTON#3 ON MUD
PUMP #2.
0130 TO 0600 DRILL AHEAD F/ 2423 M TO 2446 M.

NOTE 2: DOWN HOLE LOSS LAST 24 HRS: 142 BBLS.


TOTAL DOWN HOLE LOSS :1263 BBLS.

DENSITY(ppg) 9.30 PP ECD 9.50 MUD DATA DAILY COST CUM COST 8,525
FV PV/YP GELS WL/HTHP FC/T.SOL OIL/WAT %Sand/MBT Ph/pM Pf/Mf Cl Ca H2S LIME ES
80 24/42 10/15 4.00/ 1.00/ / 0.10/2.50 9.00/0.10 0.10/1.00 45,000 440

BITS
BIT / RUN SIZE MANUF. TYPE SERIAL NO. JETS OR TFA DEPTH IN DATE IN I-O-D-L-B-G-O-R
4RR1 / 8 12.250 REED RSX163DGS
206275 14/14/14/15/15/15 2,206.00 2004-3-12 -------

BIT OPERATIONS
BIT / RUN / CHK# WOB RPM GPM PRESS P BIT HRS 24Hr DIST 24Hr ROP CUM HRS CUM DEPTH CUM ROP
4RR 8/ 1 5,000 / 12,000 100 / 120 853 2,600 664 7.50 42.0 5.60 36.00 213.00 5.92

Printed: 2005-11-1 10:48:12


DEVON
Page 2 of 3
Daily Report
OFFSHORE ORIG DRLG
WELL NAME 24 HRS PROG TMD TVD DFS REPT NO. DATE
PANYU 5-1-A06H 42 2,419 2,139 15.00 16 2004-3-14

BHA / HOLE CONDITIONS


BHA NO. 8 BIT NO. 4RR1 JAR HRS OF SERVICE 36 BHA HRS SINCE INSP 36
BHA WT. BELOW JARS STRING WT. UP STRING WT. DN STRING WT. ROT TORQUE / UNITS BHA LENGTH
14 250 210 225 15,000 ft-lbf 178.360
ITEM DESCRIPTION NO JTS LENGTH O.D. I.D. CONN SIZE CONN TYPE
POLYCRYSTALLINE DIAMOND BIT 1 0.270 12.250
POWER DRIVE 900 Xtra 1 4.460 9.250 3.0000
PD Xtra Reciever 1 1.870 8.000 3.0000
InLine Flex Joint 1 2.870 6.625 3.0000
ARC-8 1 5.720 8.250 2.8100
Power Pulse MWD 1 8.300 8.250 5.1100
ADN-8 1 6.480 8.250 2.8100
CROSS OVER 1 0.710 7.380 2.8100
HEAVY WEIGHT DRILL PIPE 6 55.350 6.625 3.0000
DRILLING JAR 1 9.210 6.625 2.7500
HEAVY WEIGHT DRILL PIPE 9 83.120 6.650 3.0000

SURVEY DATA
M.D. INCL. AZIMUTH T.V.D. N/S CUM E/W CUM SECTION M.D. INCL. AZIMUTH T.V.D. N/S CUM E/W CUM SECTION
2,383.15 72.25 86.12 2,129.05 -14.15 727.57 726.57 2,412.31 75.21 85.79 2,137.22 -12.17 755.49 754.55

PUMP / HYDRAULIC DATA


NO. MAKE OF PUMP STROKE (in) LINER (in) SPM Q (gpm) PRESS. (psi) TOTAL Q KILL SPM / PRESSURE
1 NATIONAL - OILWELL 12.000 6.500 88 441.43 2,600 882.86 (50/340) (40/270) (30/200)
2 NATIONAL - OILWELL 12.000 6.500 88 441.43 2,600 882.86 (50/330) (40/270) (30/200)

MUD VOLUMES (bbl) / ANNULAR VELOCITIES (ft/min)


HOLE PIT 1 PIT 2 PIT 3 PIT 4 TOTAL MUD LOST MUD DUMPED ANN VEL DP ANN VEL DC ANN VEL RISER
1,091.1 171.0 193.0 225.0 304.0 1,984.1 142.0 167.6 243.5 130.5

MATERIALS / CONSUMPTION
ITEM UNITS USAGE ON HAND ITEM UNITS USAGE ON HAND
WATER, DRL BBLS 720 BENTONITE TONS 31
BARITE TONS 73 FUEL HELICOPTE LITRE 197 5,962
CEMENT TONS 68 DIESEL CU MT 3 156

PERSONNEL DATA Total POB: 87


COMPANY SERVICE NO. HOURS COMPANY SERVICE NO. HOURS
COSL CEMENTER 1 BHI MUD 3
GEOSERVICES 4 SCHLUMB 6
DEVON ENERGY DRLG 4 CSE 1
DEVON ENERGY PROD 15 BHI DIRECTIONAL DRIL
COSL DRLG 32 ROTARY 2
SLC 13 WOODGROUP 1
OILTOOL 1 SOS 1
SCM TOTAL ON BOARD 87
JUTAL 3

Printed: 2005-11-1 10:48:12


DEVON
Page 3 of 3
Daily Report
OFFSHORE ORIG DRLG
WELL NAME 24 HRS PROG TMD TVD DFS REPT NO. DATE
PANYU 5-1-A06H 42 2,419 2,139 15.00 16 2004-3-14

WEATHER DECK LOAD


WIND WAVE CURRENT
TIME SPEED / DIR HT / DIR / PERIOD SPEED / DIR HEAVE PITCH ROLL VISIBILITY TEMP
04:00 18 45 3.0 45 6 18 / 24

SUPPORT CRAFT
TYPE NO. REMARKS TYPE NO. REMARKS
BOAT, WORK 1 NANHAI 207 @ FPSO BOAT, WORK 1 NANHAI 220 @ FPSO
BOAT, WORK 1 NANHAI 209 @ PY5-1 BOAT, WORK 1 NANHAI 211 @ CHIWAN
BOAT, WORK 1 NANHAI 219 @ PY4-2

REQUIREMENTS
EVACUATION TIME SCHEDULE

1.5HRS: CIRCULATE HOLE CLEAN


9.0HRS: POOH, L/D EXCESS DRILL PIPE.
1.0HRS: DOWN LOAD & REMOVE RADIOACTIVE SOURCE.
2.0HRS: L/D BHA "DIRECTIONAL TOOLS ONLY"
0.5HRS: RETRIEVE WEARBUSHING
1.0HRS: TIH W/ STORM PKR & SET @ +/- 180 m. PKR @ +/- 20 m BELOW MUDLINE
0.5HRS: TEST TO 500 PSI.
1.0HRS: SET TEST PLUG W/ 5 STANDS BELOW.
2.0HRS: CLOSE BLIND RAMS AND LOCK SAME. SECURE PIPE IN DERRICK

18.5 HRS TOTAL.

Printed: 2005-11-1 10:48:12