Daily Report
OFFSHORE ORIG DRLG
WELL NAME 24 HRS PROG TMD TVD DFS REPT NO. DATE
PANYU 5-1-A06H 307 307 307 1.00 2 2004-2-29
RIG NAME & NO. FOREMAN AFE NO. AUTH MD AUTH TVD API NO.
DEVON ENERGY PANYU 5-1 HEWITT,WILL 111179 3,462 2,161 -
LAST CASING NEXT CASING DATE OF LAST SAFETY MEETING LAST BOP PRES TEST INCIDENT IDENTIFICATION
24.000 (in) @ 201.00 (m) 13.375 (in) @ 600.00 (m) 2004-2-29 NONE
FIELD NAME LEAKOFF MW WI NRI
PANYU 5-1 9.00 24.50000 24.5000
LITHOLOGY DAILY DRLG DAILY COMP COST DAILY TOTAL COST
MUDSTONE 41,731 0 41,731
CURRENT STATUS CUM DRLG CUM COMP COST CUM TOTAL WELL COST
DRLG. 41,731 0 41,731
24 HR FORECAST AFE DHC AFE COMP COST AFE TOTAL PROJ COST
DRLG TO TD @ 598 M. WIPER TRIP. RUN CASING. 2,674,361 1,368,356 4,042,717
DAILY OPERATIONAL COMMENTS: N/U 21 1/4" DIVERTER SYSTEM AND SLIP JOINT. P/U & M/U BHA. TAG MUD LINE @ 157 M. WASH
OUT 24" CONDUCTOR & DISPLACE HOLE W/ PRE-HYDRATED GEL. DRILL AHEAD TO 307 M.
OPERATIONS SUMMARY
FROM TO HOURS PHASE STEP OPER TASK DESCRIPTION
00:00 08:30 8.50 DRVP BOPS BOPS INSTALL OVERBOARD LINE, N/U 21 1/4" DIVERTER SYSTEM & SLIP
JOINT.
08:30 11:00 2.50 DRVP MISC RIGSER L/D 8 STANDS OF 5" HWDP F/ INSPECTION.
11:00 17:00 6.00 DRVP DRLG BHA P/U 9 1/2" MUD MOTOR, CHANGE OUT 12 1/8" STABILIZER SLEEVE TO 17
3/8" SLEEVE. ADJUST BENT ANGLE TO 1.2 DEG. P/U & M/U 17 1/2" BHA.
17:00 17:30 0.50 DRVP DRLG TRIP RIH W/ BHA, TAG MUD LINE @ 157 M.
17:30 19:00 1.50 DRVP DRLG DRLG WASH OUT 24" CONDUCTOR TO 190 M, DISPLACE HOLE W/
PRE-HYDRATED GEL MUD WHILE DRILLING AHEAD TO 220 M. PUMP
HI-VIS & CIRC OUT.
19:00 20:30 1.50 DRVP DRLG DEVSUR DROP GYRO DATA SURVEY AND PUMP DOWN. POOH W/ GYRO &
RETRIEVE GYRO TOOL.
20:30 21:00 0.50 DRVP DRLG DEVSUR RIH. WASH DOWN LAST STAND. NO FILL.
21:00 00:00 3.00 DRVP DRLG DRLG DRILLING AHEAD F/ 220 T/ 307 M.
NOTE:
0000-0230 - DRLG F/ 307 M T/ 367 M. UNABLE TO OBTAIN AZIMUTH DUE
TO MAGNETIC INTERFERENCE.
0230-0400 - COMPARE WELL TRAJECTORY W/ A02H, WELL PATH
SEPERATION = 0.04 M, BASED ON WORST CASE SCENARIO. CONSULT
SHEKOU OFFICE. PUMP HI-VIS & CIRC OUT. PREPARE GYRO TOOL.
0400-0600 - DROP GYRO & PUMP SAME DOWN. POOH W/ GYRO. HOLE
IS SLICK.
DENSITY(ppg) 9.00 PP ECD MUD DATA DAILY COST 2,471 CUM COST 8,525
FV PV/YP GELS WL/HTHP FC/T.SOL OIL/WAT %Sand/MBT Ph/pM Pf/Mf Cl Ca H2S LIME ES
48 11/12 7/9 5.80/ 1.00/5.00 / /20.00 9.00/0.30 0.15/0.45 12,000 640 0.10
BITS
BIT / RUN SIZE MANUF. TYPE SERIAL NO. JETS OR TFA DEPTH IN DATE IN I-O-D-L-B-G-O-R
1/ 1 17.500 SMITH MGSSH+CPS
MM4251 22/22/22/24// 157.00 2004-2-29 1-1-WT-A-E-0-WT-BHA
BIT OPERATIONS
BIT / RUN / CHK# WOB RPM GPM PRESS P BIT HRS 24Hr DIST 24Hr ROP CUM HRS CUM DEPTH CUM ROP
1/ 1/ 1 / 5,000 40 / 42 1,003 1,650 345 4.50 150.0 33.33 4.50 150.00 33.33
SURVEY DATA
M.D. INCL. AZIMUTH T.V.D. N/S CUM E/W CUM SECTION M.D. INCL. AZIMUTH T.V.D. N/S CUM E/W CUM SECTION
0.00 0.00 0.00 0.00 -9.70 -0.07 0.00 112.00 0.03 266.47 112.00 -9.69 -0.08 -0.01
25.80 0.02 339.15 25.80 -9.70 -0.07 0.00 127.20 0.07 288.01 127.20 -9.69 -0.09 -0.02
42.30 0.02 18.52 42.30 -9.69 -0.07 0.00 140.70 0.14 300.27 140.70 -9.67 -0.12 -0.04
58.20 0.03 234.12 58.20 -9.69 -0.07 0.00 155.50 0.29 315.43 155.50 -9.64 -0.16 -0.08
70.50 0.02 241.20 70.50 -9.69 -0.08 -0.01 171.40 0.39 325.14 171.40 -9.57 -0.22 -0.14
83.40 0.01 44.24 83.40 -9.69 -0.08 -0.01 184.40 0.54 325.29 184.40 -9.48 -0.28 -0.20
98.50 0.02 25.32 98.50 -9.69 -0.08 -0.01
MATERIALS / CONSUMPTION
ITEM UNITS USAGE ON HAND ITEM UNITS USAGE ON HAND
CEMENT TONS 120 FUEL HELICOPTE LITRE 4,597
BARITE TONS 64 DIESEL CU MT 150
BENTONITE TONS 34 WATER, DRL BBLS 790
SUPPORT CRAFT
TYPE NO. REMARKS TYPE NO. REMARKS
BOAT, WORK 1 NANHAI 207 @ FPSO STBY BOAT, WORK 1 NANHAI 220 @ BASE
BOAT, WORK 1 NANHAI 209 @ NE ROUTE FIELD BOAT, WORK 1 NANHAI 211 @ PY 4-2 STBY
BOAT, WORK 1 NANHAI 219 @ PY5-1 STBY