DAY DATE

DAILY REPORT
BUNYUT HYBRID SOLAR PV PROJECT
Friday 31-Dec-21
MELAK - KALIMANTAN TIMUR

No. Previous Activities No. Current Activities QTY Unit Remark No. Next Action
1 General 1 General 1 General
a. General drawing a. Civil drawing a. Civil drawing
Plan and Section Temporary Facilities PV-Inverter mounting structure Layout & Details Foundation Submit document

PV Power Plant Layout & Details Revision b. Electrical drawing b. Electrical drawing

b. Electrical drawing Solar PV Transformer General Arrangement & Particulars Still on progress

Typical Installation & Termination -


BESS Transformer General Arrangement & Particulars
Combiner Box / Junction Box
Wiring PV Module Low Voltage Compartment General Arrangement & Particulars

Wiring inverter Medium Voltage General Arrangement & Particulars

Wiring diagram E house trafo 2 Submit Surat Ijin Mulai Bekerja

2 Submit 3 civil drawing 3 Submit 5 electrical ITP


3 Submit 3 mechanical drawing 4 Submit presentation PJO revision
4 Submit 1 civil ITP

MAN POWER HEALTH, SAFETY, ENVIRONMENT


Time Weather FIELD CONDITION
No. Position QTY COMPANY Occurance Action Remark
1 Project Manager 1 SEC
2 Project Coordinator 1 SEC
3 Project Engineer 1 SEC
4 Electrical Engineer 4 SEC
5 Civil Engineer 1 SEC
6 Drafter 4 SEC
7 Project Admin 1 SEC
8 HSE Representative 1 SEC

Hour PRODUCTION
06.00 - 08.00 08.00 - 10.00 10.00 - 12.00 12.00 - 14.00 14.00 - 16.00 16.00 - 18.00 LEGEND
Equipment VOL WORK HOUR
R Rain / Heavy Rain
L Light Rain
C Cloudy
S Sunny
Prepared by Approval by
PT. SEC PT. IBP/TCM