You are on page 1of 3

DAILY REPORT

Project : Installation Equipment Machince Cutter Fujimaki Day : Tuesday


Location : PT Dayasa Aria Prima, Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November 7th, 2023
Contractor : PT. ERATAMA DAYA KONSTRUKSI Hours : 08.00 - 16.00
P/O No. :-

MANPOWER DESCRIPTION WORK & LOCATION VOLUME PROGRESS


I. MANAGEMENT
Site Manager : Yopi Gunawan 1 Setting and Instlallation FG 5
PIC : Muhammad Rozaq 1 I. Setting
Safety Offiver : Eko Mulyadi 1 1. Continue Adjsting Soleplate 2 unit 100%
Supervisor : Syaiful R. 1 2. Continue Setting Soleplate Adjuster 2 unit 100%
3. Continue Fabricate Anchor 20 unit 100%
II. Installation
Sub Total I 4 1. Continue Installing Fujimaki Part 1 unit 100%
II. DIRECT 2. Continue Repair Fujimaki Part 2 unit 100%
Construction :
Abdul Kasib M. 1
Al. Amin 1
Aryanto 1
Ahmad Rizki 1
Sukardi 1
Dwi Bagus S. 1
Sabidun 1
Heri Sumanto 1
Randik Yulianto 1
Adi Winarto 1
Edi Hari W. 1

PROBLEM
---

SOLUTION
---
Sub Total II 11
Total Man Power 15
Material Unit Qty Tools Unit Qty Tool Unit Qty
Oxygen Cylinder Unit 1 Cutter Grinding Set 1 Apar Unit 1
Gas Cylinder Unit 1 Cutting Torch set 1
Wrench set 1
Welding Machine Set 1
Forklift Unit 1
Rai Note :
Referensi (Drawing/Information) : Weather Bright Cloudy
n Some soleplate is ready for grouting
Morning ✔
Midday ✔
Afternoon ✔
Night
Prepared By, Approved By,

Muhammad Rozaq Yopi Gunawan


DOCUMENTATION DAILY REPORT

Project : Installation Equipment Machince Cutter Fujimaki Day : Tuesday


Location : PT Dayasa Aria Prima Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November 7th, 2023
Contractor : PT. ERATAMA DAYA KONSTRUKSI Hours : 08.00 - 16.00
P/O No. :-

1. Daily TBM all team PT. ERATAMA DAYA KONSTRUKSI

2. Setting

3. Installing
MASTER SCHEDULE (07-11-23)
PROJECT : Installation Equipment Machine Cutter Fujimaki
P/O No. : -
VENDOR : PT. ERATAMA DAYA KONSTRUKSI
October 2023 until December 2023
PROGRESS Oct-23 Nov-23 Dec-23
NO DESCRIPTION QTY UNIT Weight
ACTIVITIES (%) W01 W02 W03 W04 W05 W06 W07 W08 W09 W10 W11 W12 W12
2-8 9-15 16-22 23-28 30-5 6-12 13-19 20-26 27-03 4-10 11-17 18-24 25-31
1,0

1 Installation
1 lot 0,256 Actual 31,15 0,014 0,014 0,014 0,014 0,016 0,007
1.1 Installation All Equipment Machine Cutter Fujimaki
Plan 25,00 0,032 0,032 0,032 0,032 0,032 0,032 0,032 0,032

1 lot 0,009 Actual 90,00 0,001 0,001 0,001 0,001 0,002 0,002
1.2 Dismantle and Installation Rail Track 2 Unit
Plan 70,00 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001

1 lot 0,060 Actual 10,00 0,005 0,001 -


1.3 Installation Panel Box
Plan 25,00 0,007 0,007 0,007 0,007 0,007 0,007 0,007 0,007

1 lot 0,060 Actual 59,41 0,005 0,005 0,005 0,005 0,010 0,004
1.4 Allignment Sole Plate C/w Report
Plan 75,00 0,007 0,007 0,007 0,007 0,007 0,007 0,007 0,007

1 lot 0,026 Actual 0,00


1.5 Allignment C/w Report
Plan - 0,006 0,006 0,006 0,006

1 lot 0,043 Actual 0,00


1.6 Repainting Frame Machine "Nippon - Putih Tulang"
Plan - 0,043

1 lot 0,000 Actual #DIV/0!


1.7 Replace Seal Air Cylinder (27 pcs)
Plan #DIV/0!
1 lot 0,000 Actual #DIV/0!
1.8 Replace Seal Hydraulic Cylinder
Plan #DIV/0!
1 lot 0,043 Actual 10,00 0,004 0
1.9 Installation Piping Air Compressor And Hydraulic
Plan 25,00 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005

1 lot 0,000 Actual #DIV/0!


1.10 Bolt & Nut - HTB 8.8 C/w Washer
Plan #DIV/0!

Relocate Broke Trik C/w Installation Ductiong Blower 1 lot 0,281 Actual 33,00 0,019 0,019 0,019 0,019 0,019 -
1.11
Cutter Plan 47,50 0,028 0,028 0,028 0,028 0,021 0,021 0,021 0,021 0,021 0,021 0,021 0,021

1 lot 0,045 Actual 46,15 0,003 0,003 0,003 0,003 0,003 0,003
1.12 Safety & Scaffolding
Plan 46,15 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003

1 lot 0,162 Actual 50,00 0,013 0,013 0,013 0,013 0,013 0,013
1.13 Tool Set
Plan 50,00 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013

1 lot 0,017 Actual 0,00


1.14 Commissioning Test
Plan - 0,017

GRAND TOTAL 1,0


CUM. ACTUAL 5,62 11,24 16,86 22,99 29,72 32,76 0,00 0,00 0,00 0,00 0,00 0,00 0,00

CUM. PLAN 5,33 10,67 16,00 21,34 30,50 39,66 48,82 57,98 66,90 75,83 84,75 97,95 100,00

VARIANCE 0,29 0,57 0,86 1,66 -0,77 -6,90 -48,82 -57,98 -66,90 -75,83 -84,75 -97,95 -100,0

Diperiksa Oleh,
PT. ERATAMA DAYA KONSTRUKSI