You are on page 1of 2

DAILY REPORT

Project : Installation Equipment Machince Cutter Fujimaki Day : Thursday


Location : PT Dayasa Aria Prima, Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November 2nd, 2023
Contractor : PT. ERATAMA DAYA KONSTRUKSI Hours : 08.00 - 16.00
P/O No. :-

MANPOWER DESCRIPTION WORK & LOCATION VOLUME PROGRESS


I. MANAGEMENT
Site Manager : Yopi Gunawan 0 Dismantle and Moving PM 1
PIC : Muhammad Rozaq 1 I. Dismantle
Safety Offiver : Eko Mulyadi 1 1. Dismantle DC Fujimaki Part 1 unit
Supervisor : Syaiful R. 1 II. Moving
1. Continue Moving Fujimaki Part 10 unit 100%

Sub Total I 3 Setting


II. DIRECT I. Setting
Construction : 1. Continue Adjsting Soleplate 5 unit 100%
Abdul Kasib M. 1
Al. Amin 1
Aryanto 1
Ahmad Rizki 1
Sukardi 1
Dwi Bagus S. 1
Sabidun 1
Heri Sumanto 1
Randik Yulianto 1
Adi Winarto 1
Edi Hari W. 1

PROBLEM
---

SOLUTION
---
Sub Total II 11
Total Man Power 14
Material Unit Qty Tools Unit Qty Tool Unit Qty
Oxygen Cylinder Unit 1 Cutter Grinding Set 1 Autolevel Set 1
Gas Cylinder Unit 1 Cutting Torch set 1
Wrench set 1
Welding Machine Set 1
Apar Unit 1
Rai Note :
Referensi (Drawing/Information) : Weather Bright Cloudy
n Material for Support and Anchor isnt ready yet
Morning ✔
Midday ✔
Afternoon ✔
Night
Prepared By, Approved By,

Muhammad Rozaq Yopi Gunawan


DOCUMENTATION DAILY REPORT

Project : Installation Equipment Machince Cutter Fujimaki Day : Thursday


Location : PT Dayasa Aria Prima Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November 2nd, 2023
Contractor : PT. ERATAMA DAYA KONSTRUKSI Hours : 08.00 - 16.00
P/O No. :-

1. Daily TBM all team PT. ERATAMA DAYA KONSTRUKSI

2. Dismantle

3. Setting

4. Moving