Daily Report

Project Name: Myanmar Aquarium Project

Project Code: 4YG - 04700 Report Date : 7-Jun-2017 Wednesday No. of Day Report No. DPR- 637

Proj Start Date 2014 Contract Period 1 Year Calendar Day AM PM Fine
Weather
Estimate Completion Date 14-Nov-2017 Remain Period 161 Calendar Day 6~8 8~10 10 ~12 12~2 2~4 4~6 Rain
Work Force
Office
Trades PM PE SSE Site Engr QA/QC QS Admin Safety Security Site Store Driver Surveyer Geotech Workers Mason Carpenter Smith Welder
Staff
Today 1 3 1 1 3 2 1 11 4 35 49 3
Steel Roofing D&W Ceiling Water
Trades Scaffolder Painter Aluminium Total
Erector worker Installer worker Proofing
Today 5 119

Description previous Today Cum. Remarks Description previous Today Cum. Remarks Description previous Today Cum. Remarks
Excavator 60 Ton Crane Car Crane
Dozer 50 Ton Crane Folk Lift
1.5 Ton Roller 25 Ton Crane Rummer 1
Boom Lift Generator Truck
Material Delivery On Site
Quantity Quantity Quantity
Description Unit Description Unit Description Unit Remarks
Today Total Today Total Today Total

FO-OP-01 REV-00 Page: 1/3


Daily Report

Project Name: Myanmar Aquarium Project

Project Code: 4YG - 04700 Report Date : 7-Jun-2017 Wednesday No. of Day Report No.
Test Item Remarks
Sampl
e
LTI Free Day UA,UC Near Miss FAI MTC LTA Daily TBT Conducted
HSE How to motivate work practices for employees.
712124 0 0 0 0 0 By Safety Officer

Works Carried out Details


Trades Of Work Location Remark
I Block(A) F&B Building
1 Kalzip Wall Clading installation. InProgress

II Block(B) Aquarium Building


1 Formwork installation & Rebar Fixing work For 2nd Floor Beam. (GL:B9 to B13') In Progress
2 Cleaning work on the Floor that casted yesterday. Finish
3 Formwork Production & installation For Main Fish Tank Wall (1st Floor to 2nd Floor) In Progress
4 Rebar installation For Main Fish Tank (1st Floor to 2nd Floor) In Progress Continuous Rain till noon.
5 Rebar production & installation For Fish Tank Exhibit 1.3 In Progress
6 Formwork installation for Lift B-3 In Progress
7 Rebar Fixing For Roof Beam (37.85m Level) In Progress

III External Work

IV Other Work
1 Excavation For Drain (near Block-B) In Progress

Special Event
Visitors Site
Purpose
on Site FO-OP-01 REV-00 Instruction Page: 2/3
Daily Report

Project Name: Myanmar Aquarium Project

Project Manager Project Engineer Prepare By: Site Engineer


Project Code: 4YG - 04700 Report Date : 7-Jun-2017 Wednesday No. of Day Report No.
Name Name Sai Thing Nun Name Lin Naing Soe

Signature Signature Signature

Rebar fixing & Formwork installation at 2nd Floor Beam&Slab Rebar Fixing at Main Fish Tank

FO-OP-01 REV-00 Page: 3/3