You are on page 1of 1

` Doc No : FM-DUTA-REPT-01

PT. DUTA UTAMA TEHNIK ABADI Page :1


MECHANICAL -ELECTRICAL - CONSTRUCTION DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Improvement Security Post Jetty-1 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : Security Post Jetty-1
Client : PT. Vopak Terminal Merak Date : September 12, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : September 12, 2019 TOMORROW : September 13, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Working at Site 1 Working at Site


- Backcasting F 100%
- Sand Band F 100% 2 Working at Workshop PT. DUTA
- Concretting C 70%

2 Working at Workshop PT. DUTA


- Fabrication steel structure C 95%

Weather & Hour Notes :


Shinny Hour Till : F = Finish
Cloudly Hour Till : C = Continue
Rainy Hour Till : UP = Under Progress
P = Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 8 72
2 2 Supervisor 1 prs 1 9 8 72
3 3 Foreman 2 prs 2 18 15 135
4 4 Safety Man 1 prs 1 9 8 72
5 5 Administration 1 prs 1 9 8 72
6 6 Skill Worker 2 prs 2 18 15 135
7 7 QC 1 prs 1 9 7 63
8 8 Semi Skill Worker 2 prs 2 18 15 135
9 9 Welder 2 prs 2 18 10 90
10 10 Helper 1 prs 1 9 8 72
11 11 Mech./Elect. 0 prs 0 0 0 0
12 12 Tool Keeper 1 prs 1 9 8 72
13 Total 15 prs 15 135 110 990
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :