DATE: 11-Feb-24

JIP-2

Achieved by Todate Status /


Activity Total Achieved Planned
GRC/Sublet Party Target Completion

43200 /
CONCRETE 26 CUM 26 CUM 260 CUM Jul-25
182700

4900 /
STEEL 2.5 TON 2.5 TON 20 TON Jul-25
15600

EXCAVATION
175,730 CFT
[ GRC ]
976,161 CFT 689,890 CFT 137 / 464 May-25
EXCAVATION
800,431 CFT
[ SUBLET ]

COMPACTION
201,913 CFT
[ GRC ]
662,388 CFT 675,262 CFT 99 / 420 May-25
COMPACTION
460,475 CFT
[ SUBLET ]

BOTTLENECK:

Less progress due to Rain affect

Monthly Steel Required = 700 Ton

ACTIVITY DESCIRPTION / WORK IN PROGRESS:

EARTHWROKS

1) FCC 6-1 Earthwork from RD 7+750 to 20+283 is in progress.

2) FCC 6 Earthwork from RD 5+000 to 42+000 is in progress.

3) FCC 7-1/1 Earthwork from RD 1+500 to 5+000 is in progress.

4) FCC 7-1/2 Earthwork from RD 1+870 to 3+750 is in progress.

Page 1 of 2
DATE: 11-Feb-24

JIP-2
5) Disty-3 Minor Earthwork from RD 15+000 to 25+000 is in progress.

6) FCC 7-1/3 Earthwork from RD 2+000 to 6+000 is in progress.

7) CC 7-1/4 Earthwork from RD 3+000 to 10+500 is in progress.

8) FCC 7-1 Earthwork from RD 0+000 to 3+000, 5+000 to 7+000 & 14+000 to 30+000 is in progress.

9) FCC 7-4 Earthwork from RD 3+000 to 5+000 is in progress.

10) Main Canal Earthwork from RD 124+000 to 132+000 is in progress.

11) Main Canal Earthwork from RD 150+000 to 180+000 is in progress.

12) Main Canal Earthwork from RD 190+000 to 225+500 is in progress.

STRUCTURES

1) D/Culvert 121+250 D/S Approach Bed Wing walls in progress.

2) D/Culvert 125+750 U/S Approach Bed in progress.

3) D/Culvert 136+250 base slabs, Walls & Top Slabs are in progress.

4) FCC-6-1 VR Bridge RD 12+920 Working piles 14 out of 14 completed & Pier Shatf in progress

5) FCC-6-1 VR Bridge RD 18+386 Working piles 7 out of 14 completed.

6) FCC-8-3 DR Bridge Working piles 48 out of 60 completed.

7) FCC 6-3 AR Bridge Pier shoft & transom in progress.

Page 2 of 2