Professional Documents
Culture Documents
JIP-2
43200 /
CONCRETE 26 CUM 26 CUM 260 CUM Jul-25
182700
4900 /
STEEL 2.5 TON 2.5 TON 20 TON Jul-25
15600
EXCAVATION
175,730 CFT
[ GRC ]
976,161 CFT 689,890 CFT 137 / 464 May-25
EXCAVATION
800,431 CFT
[ SUBLET ]
COMPACTION
201,913 CFT
[ GRC ]
662,388 CFT 675,262 CFT 99 / 420 May-25
COMPACTION
460,475 CFT
[ SUBLET ]
BOTTLENECK:
EARTHWROKS
Page 1 of 2
DATE: 11-Feb-24
JIP-2
5) Disty-3 Minor Earthwork from RD 15+000 to 25+000 is in progress.
8) FCC 7-1 Earthwork from RD 0+000 to 3+000, 5+000 to 7+000 & 14+000 to 30+000 is in progress.
STRUCTURES
3) D/Culvert 136+250 base slabs, Walls & Top Slabs are in progress.
4) FCC-6-1 VR Bridge RD 12+920 Working piles 14 out of 14 completed & Pier Shatf in progress
Page 2 of 2