DVX-DAA-L-017

April 14, 2023

Attention: Ar. John Alvin Aviso (PM-SMEDD-PMG)

Thru: Engr. Ryan Lintag (DAAA)

Subject: GUARANTEED MAX QUANTITY/ GMQ – CEMENT

Good day,

Please see table below showing the quantities of cement for the corresponding areas for reference.

ESTIMATED BUFFER GMQ


ITEM DESCRIPTION
UOM QTY UOM QTY UOM QTY
I MALL AREA BULK 413,090.00 BULK 20,654.00 BULK 433,745.00
II PARKING AREA BULK 181,909.00 BULK 9,096.00 BULK 191,005.00
III FINISHING/ ARCHITECTURAL BAGS 80,120.00 BAGS 4,006.00 BAGS 84,126.00

TOTAL BAGS OF CEMENT (40KG) 708,876.00

Engr. Kim Sidrick Escobar Engr. Erik Alejandro Mendoza Engr. Ryan Lintag
QS Manager Project Manager Project Manager (DAAA)
SM Deparo Project SM Deparo Project SM Deparo Project
PROJECT: SM CITY DEPARO
LOCATION: DEPARO RD. BRGY. 171, BAGUMBONG, NORTH CALOOCAN CITY
SUBJECT: GUARANTEED MAX QUANTITY (MALL AREA)
DATE: APRIL 14, 2023

GUARANTEED MAX QUANTITY(STRUCTURAL)


MALL AREA SM STANDARD
ITEM/DESCRIPTION
QUANTITY UNIT CEMENT FACTOR BULK

FOUNDATION
Concrete (4000 psi @ 28 days) 1,687.88 m³ 14.5 24,474.25

COLUMN
Concrete (6000 psi @ 28 days)
Footing to Ground Floor 245.41 m³ 19 4,662.87
Ground to Second Floor 629.20 m³ 19 11,954.71
Second to Third Floor 574.93 m³ 19 10,923.71
Third to Roof Deck 489.34 m³ 19 9,297.51
Roof D to Clerestory 36.92 m³ 19 701.47

PLANTED COLUMN
Concrete (6000 psi @ 28 days) 3.84 m³ 19 72.96
BEAMS AND GIRDERS
Concrete (6000 psi @ 28 days)
Second Floor 2,705.37 m³ 19 51,402.01
Third Floor 2,753.07 m³ 19 52,308.29
Roof Deck 1,882.83 m³ 19 35,773.72
Clerestory 425.04 m³ 19 8,075.83

SLAB ON GRADE
Concrete (3000 psi @ 28 days) 2,365.73 m³ 12 28,388.74

SUSPENDED SLAB
Concrete (6000 psi @ 28 days)
Second Floor 1,892.30 m³ 19 35,953.62
Third Floor 1,964.73 m³ 19 37,329.86
Roof Deck 1,652.54 m³ 19 31,398.34
Clerestory 237.59 m³ 19 4,514.18

RETAINING WALL
Retaining Wall - Footing (4000 psi @ 28 days) 246.42 m³ 14.5 3,573.09
Retaining Wall - Wall (6000 psi @ 28 days) 347.27 m³ 19 6,598.13

CISTERN TANK
Tank - Potable
Base (3000 psi @ 28 days) 249.36 m³ 12 2,992.32
Slab (6000 psi @ 28 days) 106.40 m³ 19 2,021.60
Beams and Girders (6000 psi @ 28 days) 55.99 m³ 19 1,063.85
Wall (6000 psi @ 28 days) 93.60 m³ 19 1,778.40

STP
Slab (6000 psi @ 28 days)
Bottom Slab 402.50 m³ 19 7,647.50
Mid Slab 31.77 m³ 19 603.54
Top Slab 113.63 m³ 19 2,158.93
Beams and Girders (6000 psi @ 28 days)
Mid 33.88 m³ 19 643.80
Top 121.70 m³ 19 2,312.38
Wall (6000 psi @ 28 days)
Interior 505.31 m³ 19 9,600.87
Exterior 455.64 m³ 19 8,657.10
CANOPY
Concrete
Foundation (4000 psi @ 28 days) 10.43 m³ 14.5 151.25
Slab on Grade (3000 psi @ 28 days) 140.58 m³ 12 1,686.91
Column (6000 psi @ 28 days)
Footing to Ground Floor 46.25 m³ 19 878.76
Ground Floor to 2nd Floor 71.96 m³ 19 1,367.21
Suspended Slab (6000 psi @ 28 days) 60.23 m³ 19 1,144.28
Beams and Girders (6000 psi @ 28 days) 119.96 m³ 19 2,279.18

STAIRS
Concrete (6000 psi @ 28 days) 103.82 m³ 19 1,972.66

CINEMA
Concrete (6000 psi @ 28 days)
Beams and Girders 91.78 m³ 19 1,743.74
Column 29.70 m³ 19 564.37

COOLING TOWER PEDESTAL


Concrete (6000 psi @ 28 days)
Beams and Girders 14.24 m³ 19 270.56
Column 179.87 m³ 19 3,417.48

HELIPAD PAD
Concrete (6000 psi @ 28 days) 38.40 m³ 19 729.60
TOTAL 23,217.40 m³ 413,089.57
PROJECT: SM CITY DEPARO
LOCATION: DEPARO RD. BRGY. 171, BAGUMBONG, NORTH CALOOCAN CITY
SUBJECT: GUARANTEED MAX QUANTITY (PARKING AREA)
DATE: APRIL 14, 2023

GUARANTEED MAX QUANTITY(STRUCTURAL)


PARKING AREA SM STANDARD
ITEM/DESCRIPTION
QUANTITY UNIT CEMENT FACTOR BULK

FOUNDATION
Concrete (4000 psi @ 28 days) 693.25 m³ 14.5 10,052.11
-
COLUMN -
Concrete (6000 psi @ 28 days) -
Footing to Ground Floor 22.74 m³ 19 432.10
Ground to Second Floor 216.32 m³ 19 4,110.14
Second to Third Floor 332.22 m³ 19 6,312.18
Third to Roof Deck 189.12 m³ 19 3,593.28
Roof D to Clerestory - m³ 19 -
-
PLANTED COLUMN -
Concrete (6000 psi @ 28 days) 47.76 m³ 19 907.44
BEAMS AND GIRDERS -
Concrete (6000 psi @ 28 days) -
Second Floor 766.05 m³ 19 14,554.95
Third Floor 1,284.78 m³ 19 24,410.79
Roof Deck 1,175.32 m³ 19 22,331.08
Clerestory - m³ 19 -
-
SLAB ON GRADE -
Concrete (3000 psi @ 28 days) 1,396.30 m³ 12 16,755.60
-
SUSPENDED SLAB -
Concrete (6000 psi @ 28 days) -
Second Floor 693.11 m³ 19 13,169.14
Third Floor 1,084.77 m³ 19 20,610.63
Roof Deck 1,088.56 m³ 19 20,682.71
Clerestory m³ 19 -
-
RETAINING WALL -
Retaining Wall - Footing (4000 psi @ 28 days) 532.30 m³ 14.5 7,718.41
Retaining Wall - Wall (6000 psi @ 28 days) 733.43 m³ 19 13,935.12
-
CISTERN TANK -
Tank - Potable -
Base (3000 psi @ 28 days) 12 -
Slab (6000 psi @ 28 days) 19 -
Beams and Girders (6000 psi @ 28 days) 19 -
Wall (6000 psi @ 28 days) 19 -
-
STP -
Slab (6000 psi @ 28 days) -
Bottom Slab 19 -
Mid Slab 19 -
Top Slab 19 -
Beams and Girders (6000 psi @ 28 days) -
Mid 19 -
Top 19 -
Wall (6000 psi @ 28 days) -
Interior 19 -
Exterior 19 -
CANOPY -
Concrete -
Foundation (4000 psi @ 28 days) m³ 14.5 -
Slab on Grade (3000 psi @ 28 days) m³ 12 -
Column (6000 psi @ 28 days) -
Footing to Ground Floor m³ 19 -
Ground Floor to 2nd Floor m³ 19 -
Suspended Slab (6000 psi @ 28 days) m³ 19 -
Beams and Girders (6000 psi @ 28 days) m³ 19 -
-
STAIRS -
Concrete (6000 psi @ 28 days) 122.78 m³ 19 2,332.74
-
CINEMA -
Concrete (6000 psi @ 28 days) -
Beams and Girders 19 -
Column 19 -
-
COOLING TOWER PEDESTAL -
Concrete (6000 psi @ 28 days) -
Beams and Girders 19 -
Column 19 -
-
HELIPAD PAD -
Concrete (6000 psi @ 28 days) 19 -
TOTAL 10,378.82 m³ 181,908.43
PROJECT: SM CITY DEPARO
LOCATION: DEPARO RD. BRGY. 171, BAGUMBONG, NORTH CALOOCAN CITY
SUBJECT: GUARANTEED MAX QUANTITY FINISHING/ARCHITECTURAL)
DATE: APRIL 14, 2023

GUARANTEED MAX QUANTITY - ARCHITECTURAL


QTY UNIT CEMENT FACTOR CEMENT BAG
CHB 6 24,515.85 m² 1 24,515.85
PLASTERING 24,515.85 m² 0.45 11,032.13
STIFFENER 4,251.60 m² 10 42,516.00
TOPPING 2,935.91 m² 0.7 2,055.14
80,119.13