You are on page 1of 18

BILL OF QUANTITIES (BOQ)

The BoQ is inconclusive and indicative only, and bidders shall include all items they deem have been omitted.
Note: This bill of quantities is for proposal evaluation purposes only and will have no legal bearing on the actual
contract for works.

BOQ LOT A

Unit Price Total


Item Activity Unit Quantity
(USD) Price
(USD)

00 DESIGN AND PRELIMINARIES

Design of Lot A: Budzi River


00.01 Crossing/ Bridge No.1

00.02 Preliminaries and General including


insurances (see section 6.4),
performance bonds and/or
guarantees, advance payment bonds
and/or guarantees, mobilisation,
compliance costs, storage, site
establishment, demobilizations,
transport etc

01 BUDZI RIVER CROSSING/BRIDGE NO 1

01.01 Demolition and site clearance

Clearance of trees and plants on


01.01.01 the riverbed

Demolition of existing river


01.01.02 crossing/bridge superstructure

Demolition of existing abutments


01.01.03 and wing walls

Demolition of existing river


crossing/ bridge foundation
01.01.04

Load, transport and disposal of


01.01.05
demolished material to landfill
01.02 Earthworks

Excavation for foundations


(including demolition with
01.02.01 hydraulic hammer if necessary)

Excavation for abutments, wing


walls, reinforced concrete walls,
01.02.02 approaching roads.

Disposal and transport of


01.02.03 excavation material

01.03 Reinforced Concrete

Lean Concrete for footings (Bidder


01.03.01 to include fc= kg/cm2)

Footing for Abutment (Bidder to


01.03.02 include fc= kg/cm2)

Abutment Walls (Bidder to include


01.03.03 fc= kg/cm2)

01.03.04 Footing for intermediate piers


(support structure)

Wing Walls (Bidder to include


01.03.05 fc= kg/cm2)

Beam Concrete Superstructure


01.03.06
bridge (Bidder to include fc=
kg/cm2)

Approximation Slabs (Bidder to


01.03.07 include fc= kg/cm2)
Reinforced Concrete Walls (Bidder
01.03.08 to include fc= kg/cm2)

Steel Structure option


01.04

01.04.01 Steel beams

01.04.02 Braces beams at support

01.04.03 Braces beams at Spans

01.05 Finishing Layer - Asphalt

01.05.01 Dense graded hot asphalt mixture or


spray and chip

01.05.02 Prime Coat

01.05.03 Tack Coat

01.06 Others

01.06.01 Expansion Joint

01.06.02 Bridge Drainage


01.06.03 French Drain

01.06.05 Bearings

01.06.06 Barriers

01.06.07 Handrail

Embankment river protection


01.06.08 under the bridge.

02.01 Piling

Bored cast in place concrete piles


02.01.01 (Bidder to include fc= kg/cm2)

02.02 Structural Steelwork

02.02.01 Fabricate and Deliver Structural


Steelwork to Site

Installation of Structural Steel


Bridge
02.02.02

02.01 Piling

Bored cast in place concrete piles


02.01.01 (Bidder to include fc= kg/cm2)
02.02 Structural Steelwork

02.02.01 Fabricate and Deliver Structural


Steelwork to Site

Installation of Structural Steel


Bridge
02.02.02

02.03 Others

02.03.01 Side drains

02.03.02 Retaining Gabion baskets

03 BRIDGE APPROACHES

03.01 Site clearance

Clearance of trees, shrubs and


03.01.01
bushes on both sides of the River
Crossing/Bridge

03.02 Earthworks

03.02.01 Excavation on both Bridge Approaches.

Load, transport and disposal of


03.02.02 excavation material
03.02.03 Compacted Fill

03.02.04 Compacted Subgrade

Compacted Granular Base


03.02.05

03.02.06 Reinforced Concrete Approach


Slab

03.03 Others

03.04.01 Kerb and slipper drain

TOTAL LOT A
BOQ LOT B

Unit Total
Item Activity Unit Quantity
Price Price
(USD (USD)

00 DESIGN AND PRELIMINARIES

Design of Lot B: Chibasi River


00.01 Crossing/ Bridge No.2

00.02 Preliminaries and General including


insurances, mobilisation, compliance
costs, storage site establishment
demobilizations, transport etc

01 CHIBASI RIVER CROSSING/BRIDGE NO 2

01.01 Demolition and site clearance

Clearance of trees and plants on the


01.01.01 riverbed

Demolition of existing river


01.01.02 crossing/bridge superstructure

Demolition of existing abutments and


01.01.03 wing walls

Demolition of existing river crossing/


bridge foundation
01.01.04

Load, transport and disposal of


01.01.05
demolished material to landfill

01.02 Earthworks

Excavation for foundations (including


demolition with hydraulic hammer if
01.02.01 necessary)

Excavation for abutments, wing walls,


reinforced concrete walls, approaching
roads.
01.02.02

Disposal and transport of excavation


01.02.03 material

01.03 Reinforced Concrete

Lean Concrete for footings (Bidder to


01.03.01 include fc= kg/cm2)

Footing for Abutment (Bidder to include


01.03.02 fc= kg/cm2)

Abutment Walls (Bidder to include fc=


01.03.03 kg/cm2)

01.03.04 Footing for intermediate piers


(support structure)

Wing Walls (Bidder to include fc=


01.03.05 kg/cm2)

Beam Concrete Superstructure


01.03.06
bridge (Bidder to include fc=
kg/cm2)

Approximation Slabs (Bidder to include


01.03.07 fc= kg/cm2)

Reinforced Concrete Walls (Bidder to


01.03.08 include fc= kg/cm2)

Steel Structure option


01.04

01.04.01 Steel beams


01.04.02 Braces beams at support

01.04.03 Braces beams at Spans

01.05 Finishing Layer - Asphalt

01.05.01 Dense graded hot asphalt mixture or


spray and chip

01.05.02 Prime Coat

01.05.03 Tack Coat

01.06 Others

01.06.01 Expansion Joint

01.06.02 Bridge Drainage

01.06.03 French Drain

01.06.05 Bearings

01.06.06 Barriers
01.06.07 Handrail

Embankment river protection


01.06.08 under the bridge.

02.01 Piling

Bored cast in place concrete piles


02.01.01 (Bidder to include fc= kg/cm2)

02.02 Structural Steelwork

02.02.01 Fabricate and Deliver Structural


Steelwork to Site

Installation of Structural Steel Bridge

02.02.02

02.01 Piling

Bored cast in place concrete piles


02.01.01 (Bidder to include fc= kg/cm2)

02.02 Structural Steelwork

02.02.01 Fabricate and Deliver Structural


Steelwork to Site

Installation of Structural Steel Bridge

02.02.02
02.03 Others

02.03.01 Side drains

02.03.02 Retaining Gabion baskets

03 BRIDGE APPROACHES

03.01 Site clearance

Clearance of trees, shrubs and


03.01.01
bushes on both sides of the River
Crossing/Bridge

03.02 Earthworks

03.02.01 Excavation on both Bridge Approaches.

Load, transport and disposal of


03.02.02 excavation material

03.02.03 Compacted Fill

03.02.04 Compacted Subgrade

Compacted Granular Base


03.02.05
03.02.06 Reinforced ApproachConcrete
Slab

03.03 Others

03.04.01 Kerb and slipper drain

TOTAL LOT B
BOQ LOT C

Unit Total
Item Activity Unit Quantity
Price Price
(USD) (USD)

00 DESIGN AND PRELIMINARIES

Design of Lot C: Chibasi River


00.01 Crossing/ Bridge No.3

00.02 Preliminaries and General including


insurances, mobilisation,compliance
costs, storage site establishment
demobilizations, transport etc

01 CHIBASI RIVER CROSSING/BRIDGE NO 3

01.01 Demolition and site clearance

Clearance of trees and plants on the


01.01.01 riverbed

Demolition of existing river


01.01.02 crossing/bridge superstructure

Demolition of existing abutments and


01.01.03 wing walls

Demolition of existing river crossing/


bridge foundation
01.01.04

Load, transport and disposal of


01.01.05
demolished material to landfill

01.02 Earthworks

Excavation for foundations (including


demolition with hydraulic hammer if
01.02.01 necessary)

Excavation for abutments, wing walls,


reinforced concrete walls, approaching
roads.
01.02.02

Disposal and transport of excavation


01.02.03 material

01.03 Reinforced Concrete

Lean Concrete for footings (Bidder to


01.03.01 include fc= kg/cm2)

Footing for Abutment (Bidder to include


01.03.02 fc= kg/cm2)

Abutment Walls (Bidder to include fc=


01.03.03 kg/cm2)

01.03.04 Footing for intermediate piers


(support structure)

Wing Walls (Bidder to include fc=


01.03.05 kg/cm2)

Beam Concrete Superstructure


01.03.06
bridge (Bidder to include fc=
kg/cm2)

Approximation Slabs (Bidder to include


01.03.07 fc= kg/cm2)

Reinforced Concrete Walls (Bidder to


01.03.08 include fc= kg/cm2)

Steel Structure option


01.04

01.04.01 Steel beams


01.04.02 Braces beams at support

01.04.03 Braces beams at Spans

01.05 Finishing Layer - Asphalt

01.05.01 Dense graded hot asphalt mixture or


spray and chip

01.05.02 Prime Coat

01.05.03 Tack Coat

01.06 Others

01.06.01 Expansion Joint

01.06.02 Bridge Drainage

01.06.03 French Drain

01.06.05 Bearings

01.06.06 Barriers
01.06.07 Handrail

Embankment river protection


01.06.08 under the bridge.

02.01 Piling

Bored cast in place concrete piles


02.01.01 (Bidder to include fc= kg/cm2)

02.02 Structural Steelwork

02.02.01 Fabricate and Deliver Structural


Steelwork to Site

Installation of Structural Steel Bridge

02.02.02

02.01 Piling

Bored cast in place concrete piles


02.01.01 (Bidder to include fc= kg/cm2)

02.02 Structural Steelwork

02.02.01 Fabricate and Deliver Structural


Steelwork to Site

Installation of Structural Steel Bridge

02.02.02
02.03 Others

02.03.01 Side drains

02.03.02 Retaining Gabion baskets

03 BRIDGE APPROACHES

03.01 Site clearance

Clearance of trees, shrubs and


03.01.01
bushes on both sides of the River
Crossing/Bridge

03.02 Earthworks

03.02.01 Excavation on both Bridge Approaches.

Load, transport and disposal of


03.02.02 excavation material

03.02.03 Compacted Fill

03.02.04 Compacted Subgrade

Compacted Granular Base


03.02.05
03.02.06 Reinforced Approach Concrete
Slab

03.03 Others

03.04.01 Kerb and slipper drain

TOTAL LOT C

USD LUMP SUM GRAND TOTAL (LOT A +LOT B+ LOT C)

TOTAL AMOUNT IN WORDS: