Professional Documents
Culture Documents
Kjell O. Berge
Selmer Skanska AS, Oslo
ABSTRACT: A fair and just contract between the Owner and Contractor is essential when dealing with
water control in rock tunnelling. The Norwegian tunnelling contract system implies that the owner is
the risk-taker for the amount of grouting needed to meet water control requirements. The contractor’s
risk is limited to the execution of the work in the best and most effective way, hence the unit price con-
tract system is dominating the water control work.
When the quality of the product is of importance, i.e. minimising the impact of tunnelling on the sur-
roundings, the owner should take the risk of time used to have the grouting made to his satisfaction. The
finishing date in the contract should be regulated for used grouting hours compared to a suggested
number of grouting hours in the tender. This matter is currently subject to discussion whether it may be
an even better solution for the owner to pay per hour used for grouting and in addition pay materials
per kilo when the surroundings are of great importance.
1. THE NORWEGIAN TUNNELING ty of the entire installation upon completion, but also for
CONTRACT SYSTEM the safety of the construction workers during constructi-
on. The purpose of all support work is to re-establish the
Norwegian Tunnelling contract philosophy is based on a stability of the rock as quickly, effectively and cheaply
simple principle of survival: “expect the unexpected”. as possible. This is not something that can be complete-
When forming a contract for a tunnel or cavern project, ly planned on paper, years in advance, sitting in a com-
there must be allowance for eventualities. Typically in fortable office suite with a beautiful view. Decisions
Norway specifications and unit prices covering the enti- have to be made on the spot, kilometres into the moun-
re range of possible rock conditions and configurations tainside or scores of meters below the ocean floor, with
are included in the contract and flexibility is cultivated. crumbling, leaking rock masses overhead. The contract
Woe betide the contractor who installs an unsuitable and must be flexible enough to apply to almost every even-
dangerous supporting structure simply because “that’s tuality or occurrence of changing geological conditions.
what the contract specifies”.
For more than 20 years, the contract system has proven
The Achilles heel of any excavation project is not the that the use of a flexibility results in lower total costs,
drilling and blasting, or boring operation, but the sup- greater safety in tunnel construction and reduction of
port work needed to stabilise and secure the physical disputes, arbitration or litigation.
void left in its wake. This is not only crucial for the safe-
97
N ORWEGIAN T UNNELING S OCIET Y P UBLICATION NO . 12
The Norwegian Tunnelling Contract System includes An important requirement of the Norwegian Tunnelling
the following main elements for a typical tender docu- Contract System is that both the client and the contrac-
ment: tor must have skilled and experienced representatives
present at the site. When problems arise at the tunnel
1. Tender papers include geological and geotechnical face, the parties must be able to inspect and evaluate the
reports conducted by experienced geological engin- situation together and find the best solution without
eers, showing all investigations and surveys that delay and dispute. The contractor who has correctly pri-
have been conducted in connection with the project. ced various support alternatives will be able to advise
These give the contractor a general idea of the rock without being concerned about “ulterior motives”. The
conditions and specify all the facts and assumpti- contract already specifies prices for such work. The
ons. representatives at the site or a consultant must have the
expertise and the authority to decide on the best alterna-
2. Based on these reports, the tender papers list the tive, so that the client pays for the solution that is tech-
types and amounts of rock support and grouting to nically the correct one.
be included in the tender sum, the Bill of Quantity
representing the expected level of such work. The The idea behind the Norwegian Tunnelling Contract
tender papers also include alternative unit prices for System is to financially account for all possible eventu-
work, such as driving pilot headings, probe-drilling, alities at the tender stage. Thus, all parties can work as
grouting, etc. one team during the construction phase to effectuate the
plans and overcome difficulties quickly and efficiently.
The various types of support and grouting works
and their requirements and conditions are clearly 2. THE PRINCIPLES OF RISK
described in the tender documents. SHARING
The support and grouting work is divided into two The principles used for sharing the risk in Norwegian
main categories: The work executed at the tunnel tunnelling contracts were introduced in the 1970’s.
face (which delays the progress of the tunnelling) Earlier contract practices did not provide for enough fle-
and behind the tunnel face (which does not delay xibility with regard to the sharing of risk and responsi-
the progress of the tunnelling). The tender also defi- bility between owner and contractor when ground con-
nes the types and amounts of rigging and equipment ditions became adverse and penalty dates where being
required for support work (steel form, shotcrete and overrun. Still more time was lost during the discussions
injection equipment, special bolts, etc.) that the con- that followed, and in some instances the parties had to
tractor must have available at the site, on a stand-by go to court.
basis. Tender prices are specified for all these speci-
al items. In a paper by Kleivan (1988) the most significant argu-
ments for the introduction of a risk sharing principle in
3. Most importantly, the tender documents must inclu- tunnel contracts were presented. According to Kleivan
de a number of different measures that shall be deli- these were:
verable during construction. This condition allows - The ever present uncertainty of what the actual
the most suitable grouting technique to be appli- ground conditions are: Field investigations normal-
cable at any time dealing with different situations at ly include few, if any, core drillings, and from sur-
the tunnel face. face observations alone it is limited how accurately
the conditions at tunnel level can be predicted at the
4. Delays or savings in total construction time due to time when the contract is signed.
increased or decreased amounts of support work is - The cost: If the contractor should assume all risk he
dealt with in the following way: would necessarily ask for a high price in order to be
safe, a price that in most cases would exceed the
In the tender, the contractor must specify “the equi- actual cost, thus in the end giving the owner less
valent time” for each type of support work. These value for his money. Should on the other hand the
are only used as a key for extending or shortening actual ground conditions be such that the contractor
the construction time. Theses figures make it easy goes broke during the contract period, also this situ-
to calculate the consequences of changes in types ation may have an undesirable effect on the owner’s
and amounts of support and grouting work at a later economy.
date. - Court proceedings in the wake of a contract are
costly and time-consuming, and may do more good
to lawyers than to the parties involved.
98
P UBLICATION NO . 12 N ORWEGIAN T UNNELING S OCIET Y
99
N ORWEGIAN T UNNELING S OCIET Y P UBLICATION NO . 12
100
P UBLICATION NO . 12 N ORWEGIAN T UNNELING S OCIET Y
5. EXPERIENCE
In figure 3 the relationship between planned and used
amount of grouting for 4 tunnels in urban areas is
demonstrated. The need of a minimum drainage effect
on the ground water above the tunnel has been the focus
of decision making.
LITERATURE
Kleivan, E. (1988) Norwegian Tunneling Contract
System, Norwegian Soil and Rock Engineering
Association, publication nr 5 (Tapir 1988)
101