Professional Documents
Culture Documents
1
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
CONTENTS
Page
1. GENERAL 3
1.1 Scope 3
1.2 Related Sections 3
1.3 Standards and Regulations 3
1.4 Trade Preambles 4
1.5 Definition 12
2. PERFORMANCE REQUIREMENTS 13
2.1 Contractor’s Design 13
2.2 Falsework 13
2.3 Ground Movements and Vibrations 13
2.4 Noise Nuisance 13
2.5 Works within Railway Protection Zone and Railway Safety Zone 14
4. WORKMANSHIP 16
4.1 Survey 16
4.2 Demolition Methods 16
4.3 Precautions Against Uncontrolled Collapse 16
4.4 Safety Measures 16
4.5 Temporary Structures 18
4.6 Excavation 18
4.7 Adjoining Properties 18
4.8 Partly Demolished Structures 18
4.9 Works within Railway Protection Zone and Railway Safety Zone 19
4.10 Removal of Asbestos Material 19
4.11 Precautions against Vibrations and Concussion 20
4.12 Site Drainage 20
4.13 Unknown Hazards 20
4.14 Open Basements 20
4.15 Filling of Basements 21
4.16 Reinstatement and Making Good to Disturbed Areas 21
4.17 Completion 21
4.18 Preparation for Cultivation with Turfing 22
4.19 Other Particular Requirement 22
2
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
1. GENERAL
Read with the General Requirements section, and all other contract documents.
This document specifies project specific data to be read in conjunction with section
C1/10 of NPQS. All modification and additions noted in this document take
precedence over clauses noted in NPQS. Clause references in this document tie with
those in C1/10 with the same clause title.
1.1 Scope
This section covers the requirements for works involving the demolition of existing
buildings and other structures and general site clearance.
1.3.1 Standards
Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant
requirements of the Standards and Codes listed below or referenced in the body of
the Specification. Alternative Standards and Codes may be proposed for approval by
the SO, provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All Standards and Codes
quoted are the current version, unless specific year references are noted.
In the event that the Standards or Codes are partially superseded or become
obsolete, refer to the latest edition or the approved substitution for the relevant
clauses.
SS CP 11 Demolition
BS 6187 Code of Practice for Demolition
3
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
BS 5228: Part 1 Noise and vibration control on construction and open sites – Code
of practice for basic information and procedures for noise and
vibration control
BS 5395: Part 1 Stairs, ladders and walkways - Code of practice for the design
construction and maintenance of straight stairs and winders
BS 5607 Code of practice for safe use of explosives in the construction
industry
BS 5973 Code of practice for access and working scaffolds and special
scaffold structures in steel
BS 5974 Temporary installed suspended scaffolds and access equipment
(partially superseded by BS EN 1808)
BS 5975 Code of practice for falsework
BS EN 1808 Safety requirements on suspended access equipment - design
calculations, stability criteria, construction - tests
1.4.2.1 General
Engage a PE (Civil) and other qualified and experienced personnel to prepare all
drawings and calculations for the following works:
a. Temporary support structures
b. Temporary hoarding
c. Scaffolding and staging
1.4.3 Supervision
1.4.3.1 Demolition
Engage a full-time competent supervisor with appropriate demolition experience to
supervise the work strictly in accordance with the directions of the engaged
Professional Engineer.
A competent supervisor shall have sufficient professional or technical training,
knowledge and actual experience to enable them to:
5
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
a. carry out their assigned duties at the level of responsibility allocated to them
b. understand fully any potential hazards related to the work under consideration.
c. detect any technical defects or omissions in that work, recognize any implications
for health and safety caused by those defects or omissions.
d. be able to specify a remedial action to mitigate those implications.
1.4.4 Qualifications
Provide evidence of past experience for all personnel to the SO for acceptance prior
to commencement of the Works.
6
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
1.4.9.1 General
Do not permit any person to do anything not in accordance with the generally
accepted principles of safe and sound practice.
Ensure a safe environment on the Site at all times. Maintain all safety provisions
properly and do not remove any specific equipment etc without the written
acceptance of the SO.
Ensure that all personnel take necessary and sufficient safety precautions
7
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
1.4.13.1 General
Erect protective hoarding, safety netting/catch platform or other structures to ensure
public safety prior to starting demolition works.
Provide, erect and maintain a continuous hoarding around the entire contract
boundary prior to commencement of the works.
Erect the hoarding at not less than 300mm away from any permanent structure such
as footway, drain, pipeline, etc. unless otherwise agreed.
8
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
Category E: Metal hoarding shall be minimum 2metres high where the distance
between the building edge and the hoarding is more than 1½ times the height of the
building.
Refer to PSD for the category of hoarding required for the project.
The category of hoarding required for this project is
1.4.16 Rubbish
Take all reasonable steps to minimise waste production on site
Dispose rubbish and unwanted non-hazardous materials at NEA approved tips and
keep the site clean and tidy.
Remove all rubbish, dirt and residues from voids and cavities before filling or closing
in.
Sort and dispose of recyclable material at an NEA approved Material Recycling
Facility where applicable.
9
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
1.4.18.1 General
Avoid damage to existing structures, pavements and properties.
Reinstate and make good any damage caused by or as a result of the Works.
Reinstatement and making good shall also include all affected fixtures, fittings and
finishes.
1.4.18.2 Consents
If it is found necessary to break up existing pavement, road, footpath, etc for
purposes as required in the Contract, notify the SO accordingly prior to
commencement of Works.
If work is to be carried out on public roads, obtain permission from LTA.
1.4.19 Security
Adequately safeguard the site, products, materials, plants and any existing buildings
affected by the Works from theft.
1.4.21.1 General
Take all reasonable precautions to prevent pollution of the site and the general
environment including streams and waterways. If pollution occurs, inform the
10
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
appropriate authorities and the SO immediately and provide them with all relevant
information.
1.5 Definition
a. Temporary Works All construction works that are not part of the Permanent
Works but are required in order to complete the
Permanent Works
11
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
2. PERFORMANCE REQUIREMENTS
2.2 Falsework
2.2.1 Foundations
Foundations for false work shall be suitable to sustain the calculated maximum loads
without failure or unacceptable settlement.
2.5 Works within Railway Protection Zone and Railway Safety Zone
Comply with all the provisions under the latest Land Transport Authority (LTA) Code
of Practice for Railway Protection and the Guide to Carrying Out Restricted Activities
within Railway Protection and Safety Zones for the Works and other activities within
the railway protection zone and railway safety zone.
13
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
3.1 Falsework
Comply with the requirements of BS 5975.
14
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
4. WORKMANSHIP
4.1 Survey
Prior to the commencement of the Works, verify all available information. Carry out a
detailed visual survey and examination of the physical condition and structural
stability of the building(s) to be demolished and other surrounding buildings.
Take photographs where necessary.
Carry out a further survey and examination of the structures on completion of the
Works.
4.4.1 Sequence
Demolish buildings and other structures in the reverse order to that of their
construction. The order of demolition for buildings should be progressive storey-by-
storey, having regard to the type of construction.
4.4.2 Debris
greater. In any case, ensure the erection of protective hoarding, safety netting/catch
platform or other structures to protect public safety prior to starting demolition works.
In cases when demolished material is allowed to fall freely externally, provide a
covered hoarding with catch fan. In other cases, use chutes or skips.
Prior to demolition of walls, sections of the floors should be removed by hand
demolition to facilitate the free fall of debris.
16
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
4.6 Excavation
Refer to Section C2-20 ‘General Earthworks (Excavation and Filling)’, Clause 4.2.
17
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
4.9 Works within Railway Protection Zone and Railway Safety Zone
4.10.2 Regulations
Undertake all asbestos removal work in strict accordance to the “Guidelines on
Handling Asbestos Materials” and “Code of Practice for Handling of Asbestos
18
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
19
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
4.16.1 Services
Temporarily disconnect and/or divert all affected services prior to the commencement
of Works and reinstate immediately upon Substantial Completion of the Works.
Reinstate and make good the affected Works and services in such a manner that
upon substantial completion they shall be in as good order and condition as they
were at the commencement of the contract.
4.17 Completion
Clean all rubbish, debris and surplus materials and leave the whole site clean and
tidy. Complete to the required final condition of the site as described in the PSD.
20
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
21
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
22
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
23
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
5.1.8 Works within Railway Protection Zone and Railway Safety Zone
Submit proposals on effective measures for the protection of MRT above ground
structure together with the detail of activities of mobile cranes, tower cranes and other
mechanical equipment adjacent to MRT structures to the SO for acceptance at least
one month prior to the use of such equipment.
24
Version 1.0
NPQS
C1-10 Demolition and Site Clearance
25
Version 1.0