DAILY / WEEKLY PROJECT PROGRESS (DAYS)/30

HARI : JUMAT
TANGGAL : 17 NOVEMBER 2023
PROYEK : BCC JAKARTA

ITEM DI BQ KEGIATAN PROGRESS VOLUME YANG BOBOT (M2 / FOTO FOTO TARGET JUMLA REMAKS
C. Atrium dan Corridor KERJA (%) DIKERJAKAN lot ) SELESAI
16-Nov-2023 HOrang
2 MP

1. Repair Atrium dan Corridor


Walls 100 625 625

2. Epoxy Mowilex
100 625 625

A. 1 F Walls ( 12. Outdoor wall 1st floor ) Epoxy Mowilex 7 Orang


10 30 308

Repair Acian
52 160 308

Kupas Cat Existing


68 210 308

1F. Floor Leveling concrete, kemiringan 24-Nov-2023 2 Orang


16 30 185
drainase
Sub Structure for Wpc ( Jasa
Instalasi ) 2

Decking Wpc ( Jasa Instalasi )


185

IX. Lain Lain Base Money Machine 19-Nov-2023 2 Orang

Wiremesh Concrete Flooring,


andesit samping 30 0 1

A. 1 F Window and Door Ewe + Ewi 30-Nov-2023 4 Orang

Repair , Repaint
93 42 45

24-Nov-2023
B. 2 F Floor EF - 2 2 Orang

Clean, Repair
40 120 300

Polish
5 15 300

MEP. PLUMBING AIR KOTOR 22-Nov-2023 2 Orang

Septictank
30 0,3 1

B. ME 1 F Perapihan kabel instalasi 22-Nov-2023 4 Orang


100 1 1

Pasang Socket Outlet


100 50 50