STATEMENT OF WORK ACCOMPLISHMENT

Project Title PROPOSED ADDITIONAL ELECTRICAL WORKS FOR NEW EMERGENCY ROOM
Location Ground Floor, NMMC, Capitol Compound, CDOC

Item No. Description Qty Unit Unit Cost Total Cost


SUPPLY, DELIVERY AND INSTALLATION OF
ELECTRICAL WORKS FOR NEW EMERGENCY
1 PVC Pipe 1/2 dia. 90 95.00 8,550.00
2 PVC Pipe 3/4 dia. 20 100.00 2,000.00
3 PVC Pipe 1 1/2 dia. 7 275.00 1,925.00
4 PVC Elbow 1 1/2 dia. 6 100.00 600.00
5 PVC connector 1/2 35 10.00 350.00
6 THHN Wire wire 5.5mm 7 7,925.00 55,475.00
7 THHN Wire wire 3.5mm (Green) 3 4,900.00 14,700.00
8 PVC Moulding #1 12 75.00 900.00
9 Switch Box 33 70.00 2,310.00
10 Square Box 1 65.00 65.00
11 Junction Box with cover 12 24.00 288.00
12 THHN Wire #30 63 320.00 20,160.00
13 Panel Board TQC Bolt on #P 250v 8hole 1 7,250.00 7,250.00
14 MCCB 100A Bolt on 3 Phase 1 5,100.00 5,100.00
15 20amp Circuit Breaker bolt-on 2 pole 10 340.00 3,400.00
16 30amp Circuit Breaker bolt-on 2 pole 1 540 540.00
17 Electrical Tape 12 55 660.00
18 2 Gang Switch 2 155 310.00
19 Single Switch 2 135 270.00
20 Aircon outlet 6 245 1,470.00
21 THHN wire #8 (green) 17 98 1,666.00
22 Duplex Universal C.O 19 260 4,940.00
23 Exhaust Fan 1 2400 2,400.00
Paint Works -
1 Latex White 4 867 3,468.00
2 Baby Roller 7 83 581.00
Includes the following -
1 OCM 10% 1 13937.8 13,937.80
2 Labor Cost 0.30% 1 41813.4 41,813.40
3 CP 10% 1 18119.14 18,119.14
4 VAT 12% 1 25589.8 25,589.80
-
TOTAL 238,838.14

Prepared By: Checked By: Verified by: Recommending Approval: Approved:

Myke Saarenas, AR, UAP Illuminado D. Quicho Jr , REE Jovy M. Cañete, CE, MSCE Aurelia B. Tacandong, CPA, MM Jose C. Chan, MD, MHA, FPCS, FPOA, FPCHA
Project Manager Engineer III Engineer IV Chief Administrative Officer Medical Center Chief II
OIKEA BUILDERS