SCHEDULE 

4.5
PROGRAM SCHEDULE
(This must be completed by Contractor and returned with their proposal)

WEIGHT DURATION Weight


NO WORK DESCRIPTION UNITS VOL
(%) (week) per week Weeks
Minggu ke - 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
I GENERAL WORK & DESIGN ENGINEERING 20.38 3.00 6.79 6.79 6.79 6.79 100
II PARTITION WORKING 17.59 5.00 3.52 3.52 3.52 3.52 3.52 3.52
80
III CEILING 8.13 5.00 1.63 1.63 1.63 1.63 1.63 1.63
IV FLOORING 9.13 4.00 2.28 2.28 2.28 2.28 2.28 60
V FURNISHING 33.06 7.00 4.72 4.72 4.72 4.72 4.72 4.72 4.72 4.72
40
VI MECHANICAL & ELECTRICAL 3.44 2.00 1.72 1.72 1.72
VII TOILET ROOM 7.64 5.00 1.53 1.53 1.53 1.53 1.53 1.53 20
VIII FINISHING 0.63 1.00 0.63 0.63 0
TOTAL 100.00 PLAN 6.79 6.79 10.31 9.87 13.68 13.68 13.68 10.16 7.97 6.44 0.63 - -
COMULATIF 6.79 13.59 23.90 33.76 47.44 61.12 74.79 84.95 92.92 99.37 100.00
ACTUAL
COMULATIF

Engineering work

Civil Work

Furnishing work