F.Y. 2080/8
Specification no.
Norms Item no.
3.0 Construction of Embankment with Material Deposited from Borrow pit material
3.1 9.9 909,910 Providing, laying, spreading and compacting embankment with
borrow material mechanically as per Drawing and Technical Cu M 752.02
Specifications.
9.2 2000 20.2 A Providing and laying of Plain/Reinforced Cement Concrete PCC
Grade M 15 (1:2:4 C:S:A Nominal mix) with formwork for
Cu M 11,747.68
P.C.C in Foundation complete as per Drawing and Technical
Specifications.
B) In Substructure components (Road concreting)
9.3 2000 20.4 A Providing and laying of Plain/Reinforced Cement Concrete in
Sub-Structure PCC Grade M 15 (1:2:4 for nominal mix) for
P.C.C height upto 5m complete as per Drawing and Technical Cu M 12,278.11
Specifications.
9.4 2000 20.4 B Providing and laying of Plain/Reinforced Cement Concrete PCC
Grade M 20(1:1.5:3 for nominal mix) for P.C.C with formwork Cu M 12,762.86
complete as per Drawing and Technical Specifications.
9.5 2000 20.4 C Providing and laying of Plain/Reinforced Cement Concrete PCC
Grade M 25(1:1:2 for nominal mix) for P.C.C with formwork Cu M 14,135.93
trench depth of 2.2 m below the ground level and the jointing
trench depth of 2.2 m below the ground level and the jointing
21.3 Dolidar 47a Laying, fitting of hume pipe having a length 1 m or more. It
includes all operations required to complete the work up to a
trench depth of 2.2 m below the ground level and the jointing
of pipes with 1:2 cement sand mortar
Rcc Hume pipe-Np3
a Dolidar 47a For one or first pipe.
b Dolidar 47a Pipe having 150 mm diameter. R.m 1,424.30
c Dolidar 47a Pipe having 200 mm diameter. R.m 1,859.30
c Dolidar 47a Pipe having 300 mm diameter. R.m 3,321.80
d Dolidar 47a Pipe having 450 mm diameter. R.m 4,681.80
e Dolidar 47a Pipe having 600 mm diameter. R.m 6,473.00
f Dolidar 47a Pipe having 750 mm diameter. R.m 8,873.00
g Dolidar 47a Pipe having 900 mm diameter. R.m 12,547.00
LYSIS
F.Y. 2080/81
Contractor Remarks
Vatable Rate Rate (Including
Overhead)
10.35
826.00
59.50 80.88
64.70 229.90
959.44
178.50 242.65
991.20
89.25 121.33
97.06 295.30
1,203.60
238.00 323.53
736.03 864.83
300.84 385.07
117.82 173.39
23.00
0.93 13.72
48.59
2,987.01 3,485.66
2,369.71 2,773.47
4,519.12 5,251.61
4,365.25 5,071.79
140.99 173.32
132.00 156.77
23,275.16 27,001.25
14,180.34 19,584.89
679.55 784.48
107.59 124.70
806.59 1,238.08
1,335.82 1,984.70
3,218.22 7,840.95
8,636.12 11,633.54
9,707.69 13,509.84
9,255.86 14,119.83
10,231.99 14,677.30
11,552.24 16,256.32
10,155.27 14,024.56
11,552.24 15,631.08
10,763.12 16,517.59
10,461.56 16,170.79
162.16 600.49
110.57 141.99
137.74 420.60
65.81 307.68
6,301.68 12,076.94
5,840.54 11,546.62
6,937.56 11,497.19
4,705.29 7,308.59
4,782.48 7,397.35
4,988.24 7,806.47
5,005.01 7,825.76
4,949.82 7,685.63
7,852.95
8,134.82
8,293.06
8,561.74
9,096.10
9,796.00
9,640.49
8,900.47
411.70
370.30
81.94
2,950.04 4,496.54
Combining
16,17,18
6,908.47
6,983.85
7,209.97
7,209.97
7,209.97
7,285.34
7,511.47
7,812.95
7,888.32
8,114.44
9,018.92
9,094.28
7,812.93
117.76
570.00 786.26
1,260.00 1,657.38
1,852.00 2,338.18
2,740.00 3,489.10
3,870.00 4,788.60
5,835.00 7,176.00
831.11
1,789.29
2,470.09
3,884.14
5,272.77
8,274.86
1,310.00 1,637.95
1,791.80 2,138.20
3,140.00 3,820.07
4,500.00 5,384.07
6,200.00 7,443.95
8,600.00 10,203.95
12,172.00 14,429.05
1,682.11
1,813.70 2,182.36
3,273.90 3,954.74
4,633.90 5,491.83
6,584.72 7,867.44
7,869.72 9,349.13
8,984.72 10,628.21
12,807.22 15,473.33
1,225.02 1,460.52
325.20 994.98
48.78 401.10
765 1949.25
655.50
966.00
1380.00
स्थानीय तह म.ले.प.फारम नं: ५०३
टोखा नगरकार्यपालिकाको कार्यालय साबिकको फारम नं:१७१
कार्यालय कोड नं.:
नापी किताब
पाना नं: 1
सम्झौता विवरणः
नापी नं: 1
टोल विकास संस्थाको नामः
सम्झौता भएको मितिः२०८०/०८/१३
ठेक्का नं: कार्य सम्पन्न गर्नुपर्ने मितिः२०८०/१२/१२
निर्माण कार्यको नामःबखुन्डोल हाईट सडक स्तरोन्नती कार्य आदेश मितिः२०८०/०८/१३
कार्य स्थलःबखुन्डोल , टोखा-३ नापी लिइएको मिति:२०८०/०९/११
कार्य सम्पन्न मितिः२०८०/०९/११
कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कै फियत
एकाइ
नापी किताबको मुख्य र सहायक क्रियाकलाप
पाना नं परिमाण ठेक्कामा स्वीकृ त दर जम्मा रकम परिमाण स्वीकृ त दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ ३ ४ ५ ६ ६ ८ ९ १० ११=५x१० १२ १३=५x१२ १४=१०-१२ १५=१४x५ १६ १७
Roadway excavation in all types of soil by mechanical means as per
drawing and technical specification, including removal of stumps and
१ Cu M 11.85 70.33 833.42 47.69 3,354.08 - - 47.69 3,354.08
other deleterious matter, with all lifts and lead as drawing and instruction
of engineer.
Providing and laying of Stone Masonry Work in Cement Mortar 1:6 in
१ Cu M 90.34 10,040.53 907,075.35 91.06 914,275.29 - - 91.06 914,275.29
Foundation complete as per Drawing and Technical Specifications.
Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for
१ nominal mix) in Foundation complete as per Drawing and Technical Cu M 9.41 10,116.12 95,149.85 2.25 22,806.79 - - 2.25 22,806.79
Specifications.
१ Information Board L/S 1.00 1,000.00 1,000.00 1.00 450.00 - - 1.00 450.00
Total 1,004,058.63 940,886.17 940,886.17
Vat(13%) 79,244.94 72,037.94 72,037.94
Total with vat 1,083,303.57 1,012,924.11 1,012,924.11
Contengency(3%) 30,000.00 30,000.00 30,000.00
Total Amount 1,113,303.57 1,042,924.11 1,042,924.11
Municipality Contribution 1,000,000.00 936,783.22 936,783.22
यो बिलबमोजिम काम भएको जम्मा रूः 1,042,924.11 With vat हाल काम भएको बाँकी दिनुपर्ने रूः 1,042,924.11 यस बिल बमोजिम गरिएको भुक्तानी
अघिल्लो बिलसम्म भुक्तानी भएको रूः - कट्टा गर्नु पर्ने रू भौचर नं:
अघिल्लो भुक्तानी बिलको क्रम सङ्ख्याः - क. मोबिलाइजेसन पेस्की रूः - भुक्तानी मिति:
अघिल्लो भुक्तानी बिलको भौ.नं. - ख. मालसामानको पेस्की रूः - भुक्तानी रकम रू
ग. मेसिनरी औजारको बहाल रूः -
घ. अग्रीम आय कर रकम रूः
ङ. धरौटी रकम रूः
च. अन्य कट्टी गर्ने पर्ने रकम रूः
खुद दिनु पर्ने रकम रूः
उपभोक्ता/निर्माण व्यवसायीको सही/छाप: तयार गर्नेको सहीः जाँच गर्नेको सहीः स्वीकृ त गर्नेको सहीः
नाम: नाम नाम नाम
पदः दर्जाः दर्जाः दर्जाः
मितिः मितिः मितिः मितिः
स्थानीय तह
म.ले.प.sफारम नं: ५१४
टोखा नगरकार्यपालिकाको कार्यालय
कार्यालय कोड नं.:
जनसहभागितामा सम्पादित कार्यको प्रतिवेदन
कार्याक्रम/ आयोजनाको नामःबखुन्डोल हाईट सडक स्तरोन्नती कार्याक्रम/ आयोजनाको लागत रकम रूः११,१३,३०३/५७ प्रतिवेदन नं:
उपभोक्ता समिति/ सामुदायिक संस्था/ गै.स.स.को नामः अनुदान प्राप्त रकम रूः१०,००,००० प्रतिवेदन मितिः
समिति गठन मिति जनसहभागिता रकम रूः१,१३,३०३/५७ प्रविधिक मूल्याङ्कनबमोजिमको रकम
संस्था / समिति दर्ता मितिः अन्य लागत सहभागिता रूः यो प्रतिवेदनको रकमः रू
बैङ्क खाता नम्वर कार्यारम्भ आदेश मिति:२०८०/०८/१३ अघिल्लो अवधिसम्मको भुक्तानी रकम
बैङ्कको नाम कार्यसम्पन्न गर्नुपर्ने मिति:२०८०/१२/१२ भुक्तानी दिन बाँकी रकम
कार्य सम्पन्न भएको मिति:२०८०/०९/११ भुक्तानी मिति
लागत अनुमानबमोजिमको प्राविधिक मुल्याङकन बमोजिमको जनसहभागिताबाट भएको कामको खुद भुक्तानी गर्नुपर्ने
सि.नं एकाइ कै फियत
परिमाण दर जम्मा परिमाण दर जम्मा परिमाण दर जम्मा परिमाण दर जम्मा
जनसहभागीता सम्वन्धित कामको विवरण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२ १३=७-१० १४ १५=१३*१४ १६
Roadway excavation in all types of
soil by mechanical means as per
drawing and technical
specification, including removal of
1.00 Cu M 11.85 70.33 833.42 47.69 70.33 3,354.08 47.69 70.33 3,354.08
stumps and other deleterious
matter, with all lifts and lead as
drawing and instruction of
engineer.
Providing and laying of Stone
Masonry Work in Cement Mortar
2.00 1:6 in Foundation complete as per Cu M 90.34 10040.53 907,075.35 91.06 10,040.53 914,275.29 10.24 10,040.53 102,786.80 80.82 10,040.53 811,488.49
Drawing and Technical
Specifications.
Providing and laying of Plain
Cement Concrete M 10 ( or 1:3:6
for nominal mix) in Foundation
3.00 Cu M 9.41 10116.12 95,149.85 2.25 10,116.12 22,806.79 2.25 10,116.12 22,806.79
complete as per Drawing and
Technical Specifications.
4.00 Information Board L/S 1.00 1000.00 1,000.00 1.00 1,000.00 1,000.00 1.00 1,000.00 1,000.00
Sub-Total 1,004,058.63 941,436.17 106,140.88 835,295.29
Vat 79,244.94 72,037.94 - 72,037.94
Total with vat 1,083,303.57 1,013,474.11 106,140.88 907,333.22
Contengency 30,000.00 30,000.00 - 30,000.00
Total 1,113,303.57 1,043,474.11 106,140.88 937,333.22