Professional Documents
Culture Documents
O M P
PLANNING/ DESIGN DEVELOPMENT 15 22.5 30
PRESENTATION/REVISION 7 10.5 14
MOBILIZATION/ DEMOBILIZATION 7 10.5 14
SITE PREPARATION 7 10.5 14
SECURITY FENCE 2 3 4
EXCAVATION 30 45 60
REBAR, FORM, POUR CONCRETE( FOUNDATION el. -3.5m) 30 45 60
SEPTIC TANK 25 37.5 50
DRAINAGE 30 45 60
1st Lift of Columns (el.+6 M) 14 21 28
LAYING CHB WALLS 4 6 8
Form, Pour Concrete(READY MIX) (2nd flr Slab el.+6.0 M) 5 7.5 10
2nd Lift of Columns (el.+6 M) 14 21 28
LAYING CHB WALLS 4 6 8
Form, Pour Concrete(READY MIX) (3rd flr Slab el.+6.0 M) 5 7.5 10
3rd Lift of Columns (el.+4 M) 14 21 28
LAYING CHB WALLS 4 6 8
Form, Pour Concrete(READY MIX) (4th flr Slab el.+4.0 M) 5 7.5 10
4th Lift of Columns (el.+4 M) 14 21 28
LAYING CHB WALLS 4 6 8
Form, Pour Concrete(READY MIX) (5th flr Slab el.+4.0 M) 5 7.5 10
PLASTERING/FINISHING 30 45 60
WINDOW WORKS 45 67.5 90
COMPLETED
1.2
0.8
0.6
0.4
0.2
0
0.6
0.4
0.2
0
1 2 3 4 5 6 7 8 9 101112131415161718192021222324252
Dependency Cost Relative Wt Target Completion % Completion 1 2
7
7
2
7 8 7 8
7 8 7 8
8 8 9
7 8 7 8
7 7
4
5
7 7
4
5
7 7
4
5
7 7
4
5
10 10 10
7 7 7 8 8 8
38
E
2 W
286
We will only use the duration, early start&early fin
ABCDFGHJKLMNOPQRSTUVW
288 PATH 1
ABCDE
38 PATH 2
ABCDI
66 PATH 3
duration, early start&early finish
A. GENERAL REQUIREMENTS
Temporary Facilities 1.00
Power and Water Utility 1.00
As-Built Plans 1.00
Permits (Leg Works only) 1.00
TOTAL A:
B. EARTHWORKS
Excavation 378.00
Backfilling & Compaction 278.00
Layout and Staking 1.00
TOTAL B:
C. CONCRETE WORKS
Foundation, 3000psi 100.00
Rebars 7,850.00
Formworks 60.00
GI Tie Wire #16 10.00
TOTAL C:
D. STRUCTURAL STEEL WORKS
W14X6
TOTAL D:
F. ARCHITECTURAL WORKS
Painting
Waterproofing
TOTAL F:
E. SANITARY WORKS
TOTAL F:
G. MECHANICAL WORKS
TOTAL G:
H. ELECTRICAL WORKS
TOTAL H:
GRAND TOTAL :
MATERIAL LABOR
UNIT UNIT COST
UNIT COST AMOUNT UNIT COST AMOUNT
5,407,959.34 511,604.29
TOTAL ITEM NO.
A.
200,000.00
2,200,000.00
20,000.00
50,000.00
0.00
2,470,000.00
B.
678,143.88
498,740.74
89,701.57
0.00
0.00
1,266,586.19
C.
1,022,597.91
563,325.87
90,419.18
48,438.85
0.00
1,724,781.81
D.
0.00
0.00
0.00
0.00
0.00
0.00
F.
0.00
0.00
0.00
0.00
0.00
0.00
E.
0.00
0.00
0.00
0.00
0.00
G.
0.00
0.00
0.00
0.00
0.00
0.00
H.
0.00
0.00
0.00
0.00
0.00
5,461,368.00
DESCRIPTION QTY UNIT
GENERAL REQUIREMENTS
Temporary Facilities 1.00 lot
Power and Water Utility 1.00 lot
As-Built Plans 1.00 lot
Permits (Leg Works only) 1.00 lot
TOTAL A:
EARTHWORKS
Excavation 378.00 cu.m
Backfilling & Compaction 278.00 cu.m
Layout and Staking 1.00 LOT
TOTAL B:
CONCRETE WORKS
Foundation, 3000psi 100.00 cu.m
Rebars 7,850.00 kgs
Formworks 60.00 sq.m
GI Tie Wire #16 10.00 rols
TOTAL C:
STRUCTURAL STEEL WORKS
W14X6 kgs
TOTAL D:
ARCHITECTURAL WORKS
Painting
Waterproofing
TOTAL F:
SANITARY WORKS
TOTAL F:
MECHANICAL WORKS
TOTAL G:
ELECTRICAL WORKS
TOTAL H:
GRAND TOTAL :
MATERIAL LABOR
UNIT COST TOTAL
UNIT COST AMOUNT UNIT COST AMOUNT
4,137,400.00
Profit/Overhead 20%
4,964,880.00
VAT 10%
5,461,368.00
1.794031426
Project: Proposed Five-Storey Mixed-Used Commercial Building
Location: Naga City
Duration: 540 Calendar Days
Subject: TECHNICAL BID
I. #REF!
UNIT