You are on page 1of 3

Philip Jude E.

Divina | CENG424 - GC41Ar | Quantity Surveying (Quiz 1)

Instruction: Given the figure below, Compute for the quantity of:
1. Concrete hollow blocks
2. Cement and sand for block laying
3. Cement, sand and gravel filler for hollow core or cell
4. Cement and sand for plastering
5. Cement, sand and gravel filler for foundation or footing
6. Reinforcing steel bars
7. GI tie wire

3.9m

11.80m
`

1. Assuming 4” Concrete hollow blocks (4” = 0.1m)


Area = [(2)(20.00m) + (12.00m–0.1m–0.1m) + (2)(4.00m-0.1m)] x (2.60m)
Area = (59.60m) (2.60m)
Area = 154.96m2
12.5𝑝𝑐𝑠
NCHB = Area x 𝑚2
12.5𝑝𝑐𝑠
NCHB = 154.96m2 x 𝑚2
NCHB =1937pcs

2. Cement and sand for block laying (Class B – 1:3 Proportion)


Block laying mortar for 4” = 0.0005m 3/pc
m3
VBLM = (1937pcs) x (0.0005 pc )
VBLM = 0.9685m3 ≈ 0.97m3

Nbags = (VBLM) x (12 bags of Cement/m3)


Nbags = (0.97m3) x (12 bags of Cement/m3)
Nbags = 11.64 bags ≈ 12 bags of cement

m3
Volsand = (0.97m3) x (1 m3 ) = 0.97m3
Philip Jude E. Divina | CENG424 - GC41Ar | Quantity Surveying (Quiz 1)

3. Cement, sand and gravel filler for hollow core (Class B – 1:3 Proportion)
Mortal Fill for 4” = 0.003m3/pc
m3
VMF = (1937pcs) x (0.003 pc )
VMF = 5.811m3 ≈ 5.81m3

Nbags = (VMF) x (12 bags of Cement/m3)


Nbags = (5.81m3) x (12 bags of Cement/m3)
Nbags = 69.72 bags ≈ 70 bags of cement

m3
Volsand = (5.81m3) x (1 m3 ) = 5.81m3

4. Cement and sand for plastering (Class B – 1:3 Proportion) (0.019m thickness)
AWALL (Ext) = [(2)(20.00m) + (12.00m) + (2)(4.00m)] x (2.60m)
AWALL (Ext) = 156.00 m2

AWALL (Int) = [(2)(20.00-0.2m)+(12.00m–0.2m)+ (2)(4.00m-0.1m)] x (2.60m)


AWALL (Int) = 153.92 m2

ATOTAL = AWALL (Ext) + AWALL (Int) = 156.00 m2 + 153.92 m2


ATOTAL = 309.92m2

VolPlaster = (ATOTAL) x (0.019m)


VolPlaster = (309.92 m2) x (0.019m)
VolPlaster = 5.88848m3 ≈ 5.89m3

Rough Plaster
Nbags = (VMF) x (12 bags of Cement/m3)
Nbags = (5.89m3) x (12 bags of Cement/m3)
Nbags = 70.68 bags ≈ 71 bags of cement

m3
Volsand = (5.89m3) x (1 m3 ) x 1.33 = 7.8337m3 ≈ 7.83m3

FINE PLASTER
2.5kgs 1bag
Nbags = (ATOTAL) x ( ) x (40kgs)
m2
2.5kgs 1bag
Nbags = (309.92m2) x ( ) x (40kgs)
m2
Nbags = 19.37bags ≈ 20 bags of cement
Philip Jude E. Divina | CENG424 - GC41Ar | Quantity Surveying (Quiz 1)

6. Reinforcing steel bars (1m2 = 5m rebar) (1pc Rebar = 6m) (1.1 Factor of Safety)
Area = [(2)(20.00m) + (12.00m–0.1m–0.1m) + (2)(4.00m-0.1m)] x (2.60m)
Area = (59.60m) (2.60m)
Area = 154.96m2

5m Rsb
LRSB = (Awall) x ( ) x F.S
1m2
5m Rsb
LRSB = (154.96m2) x ( ) x (1.1)
1m2
LRSB = 852.28m

1pc
NRSB = (852.28m) x ( 6m )
1pc
NRSB = (852.28m) x ( 6m )
NRSB = 142.04667pcs ≈ 143pcs RSB

7. GI tie wire (L – 0.3m) (6 ties/m2) (1kg = 53m)


6 ties 0.3m
Ltie = (Awall) x ( 1m2 ) x ( )
tie
6 ties 0.3m
Ltie = (154.96m2) x ( 1m2 ) x ( )
tie
Ltie = 278.928m ≈ 278.93m

1kg
Wtie = (278.93m) x (53m )
Wtie = 5.26kg ≈ 6kg

SUMMARY
Block Mortar Rough Fine
TOTAL
Laying Fill Plastering Plastering
Cement (# of Bags) 11.64 69.72 70.68 19.37 171.41 ≈ 172
Sand (m3) 0.97 5.81 7.83 14.61 ≈ 15

SUMMARY
Hollow Blocks 1937pcs - 4”
Reinforcing Steel Bars 143pcs – 6m
Tie Wire 6kg

You might also like