NO PEKERJAAN VOLUME
1 2 3
I .PEKERJAAN TRAY DARI BAK LIMBAH GD6
Pekerjaan pondasi
Pembersihan lokasi kerja
1 Pngukuran dan marking jalur pipa (36,6m + 18,2m + 16,8m + 24,5m 129.4 m1
+ 10,5m + 9,4m + 13,4m)
2 bobok beton rabat 1,7m x 1,4m x 2 2.80 m2
3 Bobok pasangan batu 1,7 m x 1m x 0,4m 0.68 m2
4 Gali tanah ((1,8m x 1m x 0,7m ) + (1,4m x 1,8m x 0,5m)) x 2 4.90 m3
5 Gali strauss pile d2 (0,1m x 0,1m x 3,14 x 2m x 3) 0.19 m3
6 Lt kerja5cm (1,7m x 1,4m) x2 4.76 m2
7 Pembesian tapak (2,5m x 7 x 2 x 1,04kg) `+ pedestal (2m x 14 x 2 x
1,04kg) + d8 (2m x 8 x 2 x 0,395kg) 113.60 kg
12 Pek begisting kayu pet a(0,35m + 0,7m) x 2 x 1,3m x 2 unit + pet 8.19 m2
b(0,35m + 0,7m) x 2 x 1,3m
13 Pasang batu (1,7m x 0,4m x 1m ) 0.68 m3
14 1.26 m3
Urug kembali tanah (gali - vol beton) (2,62m3 + 0,19m3) - 1,56m3
15 Cor rabat (termasuk floor saluran) (1,7m x 1,4m x 0,15m) 0.36 m3
16 Angkur16.400 4 x 6 24 pcs
17 Base plat 12mm (0,2m x 0,2m x 0,012m x 6 x 7850kg) 22.61 kg