Question 1:
Calculate the materials and cost for 25 cu m of concrete of following proportions
I. 1: 2: 4
II. 1: 3: 6
III. 1: 4: 8
Coarse aggregate = Rs 300 per cu m
Sand = Rs 150 per cu m
Cement = 1000 per bag (CLO 2), (10).
Solution:
Volume of wet concrete = 25 m3
Volume of dry concrete = 25 m3 * 1.54
= 38.5 m3
(a) 1:2:4
Sum of proportions = 1+2+4 = 7

CEMENT:

Cement = 1/7 * 38.5 = 5.5 m3

1 bag of cement = 0.035m3

No. of cement bags = 5.5 /0.035

No. of cement bags = 157.14 ≈ 158 bags

Cost of cement = 158 * 1000

= Rs. 158,000

SAND:

Sand = 2/7 * 38.5 = 11 m3

Cost of sand = 11 * 150

= Rs. 1650

COARSE AGGREGATE:

Coarse Aggregate = 4/7 * 38.5 = 22 m3

Cost of c. aggregate = 22 * 300

= Rs. 6600
Total material cost = Rs. 166,250

(b) 1:3:6
Sum of proportions = 1+3+6 = 10

CEMENT:

Cement = 1/10 * 38.5 = 3.85 m3

1 bag of cement = 0.035m3

No. of cement bags = 3.85 /0.035

No. of cement bags = 110 bags

Cost of cement = 110 * 1000

= Rs. 110,000

SAND:

Sand = 3/10 * 38.5 = 11.55 m3

Cost of sand = 11.55 * 150

= Rs. 1732.5 ≈ Rs. 1733

COARSE AGGREGATE:

Coarse Aggregate = 6/10 * 38.5 = 23.1 m3

Cost of c. aggregate = 23.1 * 300

= Rs. 6930

Total material cost = Rs. 118,663

(c) 1:4:8

Sum of proportions = 1+4+8 = 13

CEMENT:

Cement = 1/13 * 38.5 = 2.96 m3

1 bag of cement = 0.035m3

No. of cement bags = 2.96 /0.035

No. of cement bags = 84.57 ≈ 85 bags

Cost of cement = 85 * 1000

= Rs. 85,000

SAND:

Sand = 4/13 * 38.5 = 11.85 m3


Cost of sand = 11.85 * 150

= Rs. 1777.5 ≈ Rs. 1778

COARSE AGGREGATE:

Coarse Aggregate = 8/13 * 38.5 = 23.69 m3

Cost of c. aggregate = 23.69 * 300

= Rs. 7107

Total material cost = Rs. 93,885

Question 2:

A room has a clear dimension of 3.5m x 7.5m. It has an R.C.C slab as shown in figure 1. Calculate
steel in kg for given slab and prepare bar bending schedule. (CLO 2),

(10)

Solution:
Steel in slab:
Main Bars:

L= 3.5 + 0.23 + 0.23 – 2(clear cover) + 2(hooks i.e., 6d)

= 3.96 – 2(0.05) + 12(0.012)

= 4.004 m

No. of bars 7.5 – 2(0.05) +2 (0.23))


= (2∗.15) +1
= 27.2 ≈ 28 bars

Total length = 28 x 4.004

= 112.112 m
Bent Up Bars:

For 45o bent:

X = 0.12 – 2(clear cover) – 2(half dia. of bar)

= 0.12 – 2(0.02) – 2(0.5*0.012)

= 0.068 m

L= 3.5 + 0.23 + 0.23 – 2(clear cover) + 2(hooks i.e., 6d) + 2(0.45x)

= 3.96 – 2(0.05) + 12(0.012) + 2(0.45*0.068)

= 4.0652 m

7.5 – 2(0.05) +2 (0.23))


No. of bars
= (2∗.15)

= 26.2 ≈ 27 bars

Total length = 27 x 4.0652

= 109.7604 m

Distribution Bars:

L = 7.5 + 0.23 + 0.23 – 2(clear cover) + 2(hooks i.e., 6d)

= 7.96 – 2(0.05) + 12(0.006)

= 7.932 m

Bottom layer:

No. of bars = 3.5 – 2(0.05) +2 (0.23))


.18 +1
= 22.44 ≈ 23 bars
Total length = 23 x 7.932

= 182.436 m
Top layer:

No. of bars (0.45)+ (0.23)− (0.05)−(𝑥/ tan 45)


.18 +1
=
= 4.12 ≈ 5 bars
For both sides = 5*2

= 10 bars

Total length of bottom distribution bars = 10*7.932

= 79.32 m

Total Steel:

Total steel (12mm bar) = 112.112 + 109.7604


= 221.8724 m

Total steel (6mm bars) = 182.436 + 79.32

= 261.756 m

Total weight of steel (12mm) = Unit weight * length * area

= 7850*221.8724 * (π*0.0122/4)

=196.98 kg

Total weight of steel (6mm) = Unit weight * length * area

= 7850*261.756* (π*0.0062/4)

= 58.1 kg

Bar bending Schedule:

No Member Dia. and type Shape and size Length No. Total L Total
. m m wt.kg
1 Slab 12mm dia 4.004 28 112.112 99.54
(main bar)

2 Slab 12mm dia 4.0652 27 109.7604 97.45


(bent up bar)

3 Slab 6mm dia 7.932 33 261.756 58.1


(distribution
bar)
Question 3:

Calculate the quantities in Excel sheet. (CLO 2), (10)

Solution:
MEASUREMENT

No. Item No. Length Width Depth Qty. Total


(L) (B) (D)
1 Cement Concrete (1:1.5:3) without reinforcement
L = 10 + 0.3 0.3 1 10.6 0.3 0.5 1.59 1.59 m3
= 10.6 m
2 Centering work for beam
Bottom 1 10 0.3 3 13.9 m2
Sides 2 10.6 0.5 10.6
Ends 2 0.3 0.5 0.3
3 HYSD Steel bars
A type (straight bars) 3 10.86 32.58 m @ 80.15 80.15 kg
L = 10.6 – 2(0.05) + 2(9*0.02) = 10.86 2.46 kg/m
H type (pins @ 21 cm c/c) 26 0.25 6.5 @ 15.99 15.99 kg
L = 0.3 – 2 (0.025) = 0.25 m 2.46 kg/m
Span = 10.6 – 2(0.05) – 2(1.8) – 2(0.9)
= 5.1 m
5.1
No. of pins = +1
0.21
= 26 pins
B type (Bent up bars) 2 11.16 22.32 @ 35.27 35.27 kg
X = 0.5 – 2(0.025) – 2(0.01) – 1.58kg/m
2(0.5*0.016) = 0.41m
L = 10.6 – 2(0.05) + 2(9*0.016)
+ 2(0.45*0.41)
= 11.16 m
C type (Bent up bars) 2 11.13 22.26 @ 35.17 35.17 kg
X = 0.5 – 2(0.025) – 2(0.008) – 0.02 – 1.58 kg/m
0.02 – 2(0.5*0.016) = 0.378 m
L = 10.6 – 2(0.05) + 2(9*0.016)
+ 2(0.45*0.378)
= 11.13 m
D type (Anchor Bars) 2 10.72 21.44 @ 19.08 19.08 kg
L = 10 + 0.3 + 0.3 + 2(9*0.012)- 2(0.05) 0.89kg/m
= 10.72
4 Mild Steel Bars
E type (stirrups @ 10 cm c/c) 38 1.56 59.28 @ 36.75 36.75 kg
Span = 1.8m 0.62 kg/m
1.8
No. of stirrups = + 1
0.1
= 19
Both ends = 19*2 = 38
L = 2(x + y) + 24d
x = 0.5 – 2(0.025)-2(0.01) = 0.43 m
y = 0.3 – 2(0.025)-2(0.01) = 0.23 m
L = 2 (.43+.23) + 24 (0.01)
= 1.56 m
F type (stirrups @ 15 cm c/c) 12 1.53 18.36 @ 7.16 7.16 kg
Span = 0.9 m .39 kg/m
0.9
No. of stirrups =
0.15
=6
Both ends = 6*2 =
12 L = 2(x + y) + 24d
x = 0.5 – 2(0.025)-2(0.008) = 0.434 m
y = 0.3 – 2(0.025)-2(0.008) = 0.234 m
L = 2 (.434+.234) + 24 (0.008)
= 1.53 m
G type (stirrups @ 20 cm c/c) 26 1.5 39 @ 8.58 8.58 kg
Span = 10.6 – 2(1.8) – 2(0.9) – 2(0.05) 0.22 kg/m
= 5.1
5.1
No. of stirrups =
0.2
= 26
L = 2(x + y) + 24d
x = 0.5 – 2(0.025)-2(0.006) = 0.438 m
y = 0.3 – 2(0.025)-2(0.006) = 0.238 m
L = 2 (.438+.238) + 24 (0.006)
= 1.5 m

ABSTRACT

No. Item Qty. Per Rate Rs. Amount Rs.


1 Cement concrete (1:1.5:3) 1.59 cu. m 6480 10303.2
2 Centering work for beam 13.9 sq. m 350 4865
3 HYSD steel bars 185.66 kg 64.60 11993.64
4 Mild steel bars 52.49 kg 64.60 3390.85
Total 30552.69
Add 5% contingencies 1527.64
Grand total 32080.33
Say 32100.00

(i) Requirement of materials

No. Item Quantity per cubic meter Quantity of Total Say


concrete Qty.
(cu m)
1
1 Cement ∗ 1.54= 8 bags 1.59 12.72 13 bags
5.5∗0.03 5
1.5
2 Sand ∗ 1.54 = 0.42 cu m 1.59 0.67 0.7 cu m
5.5
3
3 Grit-kapchi ∗ 1.54 = 0.84 cu m 1.59 1.34 1.35 cu m
5.5
(ii) Percentage volume of steel reinforcement in beam:

For weight of 1 cu m of steel is assumed as 7850 kg.

Volume of concrete = 1.59 cu m

Weight of steel = (185.66 + 52.49)

= 238.15 kg
238.15∗100
Percentage of steel
= 7850∗1.59

= 1.91 say 2%

(iii) Cost of beam per meter:

Length of beam without bearing = 10 meters

Total cost of beam = Rs. 32100

Hence the cost of beam per meter is Rs. 3210/-

(iv) Bar bending schedule:

No Member Dia. and Shape and size L No Total L Weight Total


. type cm m . m kg/m wt.kg
1 A type 20 mm 10.86 3 32.58 2.46 80.1
dia. 5
HYSD bar

2 B type 16 mm 11.16 2 22.32 1.58 35.2


dia. 7
HYSD bar

3 C type 16 mm 11.13 2 22.26 1.58 35.1


dia. 7
HYSD bar

4 D type 12 mm 10.72 2 21.44 0.89 19.0


dia. 8
HYSD bar

5 E type 10 mm 1.56 38 59.28 0.62 36.7


dia. 5
Mild steel
6 F type 8 mm dia. 1.53 12 18.36 0.39 7.16
Mild steel

7 G type 6 mm dia. 1.5 26 39 0.22 8.58


Mild steel

8 H type 20 mm .25 26 6.5 2.46 15.9


dia. 9
HYSD bar

The end