You are on page 1of 8

KEGIATAN

PAKET
LOKASI
SUMBER DANA
TAHUN ANGGARAN

NO
: Rencana Box Culvert
:
:
:
: 2022

SKET GAMBAR

BOX CULVERT

PEMBESIAN
PERHITUNGAN

BOX CULVERT

Galian tanah

1.2 X 2 X 8.8

Beton BO

0.05 X 1.4 X 8.8

Beton Struktur

2 X 2 = 4 m3

1.4 X 1 = 1.4
1.8 X 8.8

Begesting
L X P X S
Luar = 2 X 8.8 X 2 =
Dalam = 1.4 X 8.8 X 2 =
Atas = 1 X 8.8 X =
Depan = 0.2 X 1.4 X 2 =
= 0.2 X 1 X 2 =
Belakang = 0.2 X 1.4 X 2 =
= 0.2 X 1 X 2 =

Timbunan grosok = 0.5 X 1.2 X 8.8 X 2

PEMBESIAN
Plat Atas + Lantai
ø10-150

880 + 1 = 60 bt X 2
15

Pembesian
ø10 = 120 X 0.62

Dinding KA + KI
ø10-150

880 + 1 = 60 bt X 4
15

ø10 = 240 X 0.62

Plat + Lantai

140 + 1 = 10 bt X 4
15

ø10 = 40 X 0.62

Dinding KA + KI

100 + 1 = 8 bt X 4
15

ø10 = 32 X 0.62
HASIL SATUAN

= 21.12 m3

= 0.616 m3

= 15.84 m3

35.2
24.64
8.8
0.56
0.4
0.56
0.4
jumlah 70.56 m2

= 10.56 m3

= 120 bt
= 74.4 kg

= 240 bt

= 133.92 kg

= 40 bt

= 24.8 kg

= 32 bt

= 19.84 kg

Jumlah = 252.96 kg