PERHITUNGAN VOLUME

TAHUN 2011

I PEKERJAAN GORONG-GORONG
1 Galian tanah : 0.70 x 0.70 x 7.50 ( 2.00 ) = 7.35 m3
: 0.30 x 0.60 x 7.50 = 1.35 m3
= 8.70 m3

2 Pas. Batu kali 1:5 : 0.70 x 0.70 x 7.50 ( 2.00 ) = 7.35 m3


: ( 0.70 + 0.50 ) x 0.60 x 7.50 ( 2.00 ) = 5.40 m3
2
: ( 0.30 + 0.50 ) x 0.40 x 7.50 ( 2.00 ) = 2.40 m3
2
: 0.30 x 0.60 x 7.50 = 1.35 m3
: 0.45 x 0.60 x 2.00 ( 2.00 ) = 1.08 m3
= 17.58 m3

3 Plesteran 1:3 : 0.80 x 7.50 ( 2.00 ) = 12.00 m2


: 0.60 x 7.50 ( 1.00 ) = 4.50 m2
: 0.60 x 0.50 ( 4.00 ) = 1.20 m2
: 1.70 x 2.00 ( 2.00 ) = 6.80 m2
= 24.50 m2

4 Cat Tembok : 1.20 + 6.80 = 8.00 m2

5 Beton K-225 : 0.20 x 0.20 x 7.50 ( 2.00 ) = 0.60 m3


: 0.20 x 1.00 x 7.50 = 1.50 m3
Pelat injak : 0.10 x 0.50 x 5.00 ( 2.00 ) = 0.50 m3
= 2.60 m3

6 Acuan beton : 0.60 x 7.50 = 4.50 m2


: 0.20 x 7.50 ( 2.00 ) = 3.00 m2
= 7.50 m2

7 Penulangan beton :
f 12mm balok : 0.888 x 7.60 x 4.00 ( 2.00 ) = 53.99 kg
f 8mm balok : 0.395 x 0.65 x 37.50 ( 2.00 ) = 19.26 kg
f 12mm pokok : 0.888 x 1.10 x 37.50 ( 1.00 ) = 36.63 kg
f 12mm bengkok : 0.888 x 1.25 x 37.50 ( 1.00 ) = 41.63 kg
f 10mm susut : 0.617 x 1.10 x 37.50 ( 1.00 ) = 25.45 kg
f 10mm bagi : 0.617 x 7.60 x 5.00 ( 2.00 ) = 46.89 kg
= 223.84 kg

8 Urugan Sirtu : 0.20 x 0.55 x 7.50 ( 2.00 ) = 1.65 m3

9 Pembersihan lokasi : = LS
II PEKERJAAN TALUD
1 Galian tanah : 0.50 x 0.50 x 11.50 ( 1.00 ) = 2.88 m3

2 Pas. Batu kali 1:5 : 0.50 x 0.50 x 11.50 ( 1.00 ) = 2.88 m3


: ( 0.30 + 0.50 ) x 0.90 x 11.50 ( 1.00 ) = 4.14 m3
2 = 7.02 m3

3 Plesteran 1:3 : 0.35 x 11.50 ( 1.00 ) = 4.03 m2

4 Siaran 1:2 : 0.90 x 11.50 ( 1.00 ) = 10.35 m2

5 Suling2 f 2" : = 2.00 ljr

6 Urugan tanah : 0.40 x 0.90 x 11.50 ( 1.00 ) = 4.14 m3


RENCANA ANGGARAN BIAYA
TAHUN 2011

No. Uraian Pekerjaan Volume Analisa Harga Satuan Jumlah Harga


Rp. Rp.
1 2 3 4 5 6
I PEKERJAAN GORONG-GORONG
1 Galian tanah 8.70 m3 K.224 27,595.00 240,076.50
2 Pas. Batu kali 1:5 17.58 m3 Pn.6.3 465,230.00 8,178,743.40
3 Plesteran 1:3 24.50 m2 Pl.6.14 34,478.10 844,713.45
4 Cat Tembok 8.00 m2 Pc.6.14. 11,409.40 91,275.20
5 Beton K-225 2.60 m3 K.722 779,970.82 2,027,924.13
6 Acuan beton 7.50 m2 K.710 78,452.00 588,390.00
7 Penulangan beton 223.84 kg K.715 11,769.15 2,634,464.20
8 Urugan Sirtu 1.65 m3 W.1.a 136,859.53 225,818.22
9 Pembersihan lokasi - LS 148,958.96 148,958.96
Jumlah I 14,980,364.07
II PEKERJAAN TALUD
1 Galian tanah 2.88 m3 K.224 27,595.00 79,335.63
2 Pas. Batu kali 1:5 7.02 m3 Pn.6.3 465,230.00 3,263,588.45
3 Plesteran 1:3 4.03 m2 Pl.6.14 34,478.10 138,774.35
4 Siaran 1:2 10.35 m2 Pl.6.26 26,388.00 273,115.80
5 Suling2 f 2" 2.00 ljr LS 34,800.00 69,600.00
6 Urugan tanah 4.14 m3 A.16+A.15 47,155.00 195,221.70
Jumlah II 4,019,635.93

REKAPITULASI
I PEKERJAAN GORONG-GORONG 14,980,364.07
II PEKERJAAN TALUD 4,019,635.93
JUMLAH 19,000,000.00

( Terbilang : Sembilan belas juta rupiah )