No.
Gambar Sket Perhitungan Volume
B. Kolom 30/30
0.30 x 0.30 x 3.80 x#REF! Bh
#REF! m3
0.30 x 0.30 x 4.00 x 14 Bh
5.040 m3 #REF! m3
C. Sloef 20/25
Vertikal
0.20 x 0.25 x 35.20
1.760 m3
Horisontal
0.20 x 0.25 x 59.78
2.989 m3 4.749 m3
D. Balok 25/35
Vertikal
0.25 x 0.35 x 59.00
5.163 m3
Horisontal
0.25 x 0.35 x 58.80
5.145 m3 10.308 m3
Perhitungan Volume :
0.3 + 0.6
x 0.6 x 10
2
= 2.70 M3
Analisis Harga :
1M3 Pas. Pondasi Batu Gunung 1 : 5
1.100 Batu Gunung @ 135,000 Rp. 148,500
0.544 Pasir @ 105,000 Rp. 57,120
DEPAN KM 136.000 Semen Portland @ 1,360 Rp. 184,960
0.600 Tukang Batu @ 55,000 Rp. 33,000
Bawah Tangga 1.500 Pekerja @ 45,000 Rp. 67,500
Jumlah 491,080
RAB :
2.70 x ### = 1,325,916.00
PERHITUNGAN VOLUME PEKERJAAN
KonsTruksi Listplank
Plat Level
0.10 x 0.80 x 51.80 4.144 m3
ListPlank Beton
0.08 x 0.70 x 51.80 2.901 m3
Kanopi
0.08 x 0.60 x 2.40 x 8 Bh 0.922 m3
0.08 x 0.60 x 0.80 x 7 Bh 0.269 m3
8.667 m3
3.18
3.1683434157
0.03
PERHITUNGAN VOLUME PEKERJAAN
0
6
44
4.05
4.8
1.1
59.95
2.7
PERHITUNGAN VOLUME PEKERJAAN
Lantai II
Dinding Luar :
4.55 x 88.00 400.400
Dinding Ruang Tengah :
3.80 x 24.50 93.100
Dinding WC/KM :
3.80 x 14.95 56.810
Tangga
1.00 x 2.75 2.750
1.00 x 12.30 12.300
Pembungkus Kolom Teras
1.00 x 3.50 x 2 Bh 7.000
Pembungkus Kolom Lt II
0.30 x 3.80 x ###Bh 20.520
Kuda-Kuda Atap
1/2 x 3.25 x 1.40 x 2 Bh 4.550
Dinding Bagian Atas Teras
1.00 x 14.00 14.000
###
Penebalan Dinding Tembok
3.15 x 9.00 x 2 Bh 56.700
0.70 x 11.10 7.770
0.70 x 4.80 3.360
0.70 x 2.85 1.995
0.70 x 4.60 3.220
1.10 x 8.00 x 2 Bh 17.600
0.50 x 8.00 x 4 Bh 16.000
106.645
Bagian Pengurang Dinding Tembok
+ Pintu:
I. PD 1.50 x 2.20 x 1 Bh 3.300
II. PT 1.50 x 2.20 x 3 Bh 9.900
III. PS 1.00 x 2.20 x 1 Bh 2.200
IV. PWC 0.80 x 2.00 x 6 Bh 9.600
+ Jendela
I. JD 0.50 x 1.20 x ###Bh 8.400
II. JS 0.50 x 1.20 x ###Bh 7.200
III. JB 0.50 x 1.20 x ###Bh 20.400
+ Ventilasi
I. VD 0.50 x 0.50 x ###Bh 5.000
II. VS 0.50 x 0.50 x ###Bh 3.000
III. VB 0.50 x 0.50 x ###Bh 6.500
III. VTrs 0.30 x 0.40 x ###Bh 1.440
+ Bukaan
0.90 x 2.00 x 4 Bh 7.200
+ Glass Blok
1.20 x 200 x 1 Bh 240.000
324.140
724.100
II. Pekerjaan Plesteran Dinding Tembok
724.100 x 2 Sisi ###
Bagian Pengurang Kuda-Kuda Dinding Tembok
+ Kuda-Kuda Dinding Tembok
1/2 x 3.25 x 1.40 x 2 Bh 4.550
###
Pekerjaan Plesteran Beton
Lisplank
0.85 x 0.00 x 1 Bh 0.000
1.25 x 0.00 x 1 Bh 0.000
Teras
1.30 x 6.50 x 1 Bh 8.450
Konsol Beton
0.45 x 0.60 x ###Bh 6.480
0.10 x 0.70 x ###Bh 0.840
0.60 x 6.00 x 4 Bh 14.400
Kolom Beton
30/30 1.20 x 3.80 x ###Bh 54.720
1.00 x 3.80 x 5 Bh 19.000
0.80 x 3.80 x 9 Bh 27.360
0.60 x 3.80 x ###Bh 27.360
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
8.4
m2 5.4
m2 13.8
m2
m2
m2
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
Volume Luasan Jendela
Type
J1 1.80 x 1.15 x 8 Bh = 16.56
J3 1.80 x 0.70 x 4 Bh = 5.04
J4 1.15 x 0.70 x 1 Bh = 0.81
m 2
Vj1 0.4 x 0.4 x 18 Bh = 2.88
Vj3 0.4 x 0.4 x 12 Bh = 1.92
m2 Vj4 0.4 x 0.4 x 2 Bh = 0.32
= 27.53
m2 Luasan Pintu
Type
P1 1.30 x 2.1 x 5 Bh = 13.65
P3 x x 2 Bh = 0
m2 P4 0.75 x 1 x 3 Bh = 2.25
= 15.90
m 2
43.43
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
PERHITUNGAN VOLUME PEKERJAAN
2.520
150
#VALUE!
1.5 18 66
150 11 11
### ###
2 9.2
5.5
3.7
1.9
###
464 ### 11 9 6
PERHITUNGAN VOLUME PEKERJAAN
I. Pekerjaan Plafon
Lt 1
1.35 x 1.60 x 2 4.320 m2
1.35 x 1.75 x 2 4.725 m2
1.10 x 2.85 x 2 6.270 m2
8.85 x 11.85 x 1 ### m2
5.85 x 2.85 x 1 16.673 m2
136.410 m2
Lantai 2 :
14.85 x 8.85 x 1 131.298 m2
1.10 x 2.85 x 1 3.135 m2
1.35 x 1.75 x 1 2.363 m2
1.35 x 1.60 x 1 2.160 m2
2.85 x 5.85 x 1 16.673 m2
17.85 x 1.50 x 1 26.775 m2
182.20 m2
Tegel KM/WC 20 x 20
1.35 x 1.60 x 5 Bh 10.80 m2
1.35 x 1.75 x 2 Bh 4.73 m2
15.53 m2
DEPAN KM
TERAS 0.99
Bawah Tangga 0.36
R. STAF
R. STAF
Pintu 1
Pintu 3
0.45
AULA
DEPAN KM
T.W 0.375
PODIUM
Teras
Pintu
Pintu
Plint
0.2
KM
KM
1
1
1
1
114.95
131.85
PEKERJAAN PENGECATAN
1 Pengecatan Dinding
V = ### M2
VENTILASI JEND. 2
S = 0.05 M 0.12 S = 0.05
P = 1.80 M 1.60 P = 4.00
JMLH = 44 BH 44 JMLH = 24
V = 7.920 M2 8.448 V = ###
PINTU 1 PINTU KM
S = 0.05 M 0.12 S = 0.05
P = 5.90 M 5.70 P = 4.65
JMLH = 3 BH 3 JMLH = 5
V = 1.770 M2 2.052 V = ###
PINTU 3 PINTU 4
S = 0.05 M 0.12 S = 0.05
P = 5.10 M 4.90 P = 5.30
JMLH = 5 BH 5 JMLH = 2
V = 2.550 M2 2.940 V = ###
VENTILASI
S = 0.050 M
P = 1.60 M
JMLH = 8 BH
V = 1.280 M2
M 0.12
M 3.80
BH 24
M2 10.944
M 0.12
M 4.45
BH 5
M2 2.670
M 0.12
M 5.10
BH 2
M2 1.224
CV. DIMENSI ORIENT PRIMA Konsultan
PERENCANAAN, P ENGAW ASAN DAN SURVEY P EM ETAAN
Kantor : Jl. Pemuda No.301 Tlp.(0405)22287 Kolaka
HARGA JUMLAH
NO. URAIAN PEKERJAAN SAT. VOLUME SATUAN HARGA
( Rp ) ( Rp )
01 02 03 04 05 06
I PEKERJAAN PERSIAPAN
1 Pek. Papan Nama Proyek Ls 1.000 280,000.00 280,000.00
2 Pek. Pembuatan Direksi Kheet Ls 1.000 2,500,000.00 2,500,000.00
3 Administrasi dan Dokumentasi Ls 1.000 500,000.00 500,000.00
4 Pek. Bouwplank + Pengukuran Ls 1.000 500,000.00 500,000.00
Pembongkaran dan Pembersihan Bangunan
5 Ls 1.000 ### 12,500,000.00
Lama
Jumlah 16,280,000.00
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Pondasi M3 74.082 20,200.00 1,496,456.40
2 Pek. Urugan Tanah Kembali Alur Pondasi M3 44.664 9,685.00 432,570.03
3 Pek. Urugan Tanah bawah Lantai M3 23.776 62,050.00 1,475,313.21
4 Pek. Pasir Urug Bawah Pondasi M3 3.225 131,650.00 424,505.43
5 Pek. Pasir Urug Bawah Lantai M3 9.907 131,650.00 1,304,223.64
6 Pek. Pas. Batu Kosong M3 7.836 256,725.00 2,011,697.10
7 Pek. Pondasi Batu Gunung 1 : 5 M3 17.631 497,245.00 8,766,926.60
Jumlah 15,911,692.40
III PEKERJAAN STRUKTUR BETON
1 Pek. Pondasi Poer P1 (100x100x165) cm M3 7.564 3,619,125.00 27,376,418.67
2 Pek. Pondasi Poer P2 (100x100x150) cm M3 3.467 3,619,125.00 12,547,807.97
3 Pek. Pondasi Poer P3 (70x120x110) cm M3 0.337 3,619,125.00 1,220,097.52
4 Pek. Kolom Utama 30x30 cm M3 7.560 4,535,125.61 34,285,549.64
5 Pek. Kolom Utama 20x20 cm M3 3.360 5,398,162.28 18,137,825.26
6 Pek. Kolom Teras 25x25 cm M3 3.600 4,535,125.61 16,326,452.21
7 Pek. Kolom Teras 20x20 cm M3 1.600 5,398,162.28 8,637,059.65
8 Pek. Kolom Praktis 11x11 cm M3 0.726 6,389,429.11 4,638,725.53
9 Pek. Sloef (20/25) M3 7.150 4,029,696.87 28,812,332.58
10 Pek. Balok anak Lt. 2 (15/20) M3 2.643 4,496,333.17 11,883,808.56
11 Pek. Balok Lt.2 (20/25) M3 3.690 4,440,048.17 16,383,777.73
12 Pek. Balok Induk (20/40) M3 5.280 4,157,734.67 21,952,839.03
13 Pek. Balok anak (15/25) M3 3.416 5,791,125.37 19,783,932.03
14 Pek. Balok anak (15/20) M3 0.195 5,840,656.17 1,138,927.95
15 Pek. Balok Latei (10/10) M3 0.336 4,648,302.67 1,561,829.70
16 Pek. Plat Lantai T=12 cm M3 25.486 5,897,590.86 150,307,180.18
17 Pek. Dak + Leuvel + Listplank Beton + Kanop M3 8.667 4,510,131.84 39,090,214.67
18 Pek. Tangga M3 2.378 5,177,260.00 12,310,488.83
19 Pek. Lantai Kerja Beton 1 : 2 : 3 T = 10 cm M3 3.184 552,100.00 1,757,886.40
20 Pek. Rabat Beton Bawah Lantai 1 : 2 : 3 T=5 M3 9.907 552,100.00 5,469,516.68
Jumlah 433,622,670.77
IV PEKERJAAN PASANGAN / PLESTERAN DINDING
1 Pek. Pas. Batu Bata Trasram 1/2 ( 1:2 ) M2 28.400 80,800.00 2,294,720.00
2 Pek. Pas. Batu Bata ( 1:5 ) M2 378.140 69,484.00 26,274,679.76
3 Pek. Plesteran Trasram ( 1:2 ) M2 56.800 33,211.00 1,886,384.80
4 Pek. Plesteran Tembok ( 1:5 ) M2 756.280 29,210.00 22,090,938.80
5 Pek. Plesteran Beton ( 1:3 ) M2 204.800 38,211.00 7,825,612.80
6 Pek. Acian M2 39.600 15,366.60 608,517.36
Jumlah 60,980,853.52
01 02 03 04 05 06
V PEKERJAAN KUSEN PINTU, JENDELA
1 Pek. Dinding Tripleks Rangkap M2 40.845 135,950.00 5,552,877.75
2 Pek. Kusen Kayu Kelas II M3 1.374 4,236,500.00 5,822,221.95
3 Pek. Daun Pintu Panil M2 6.338 315,750.00 2,001,065.63
4 Pek. Daun Pintu 1 M2 9.240 424,532.86 3,922,683.60
5 Pek. Daun Pintu 2 M2 3.552 332,950.00 1,182,638.40
6 Pek. Daun Pintu 3 M2 8.400 295,430.00 2,481,612.00
7 Pek. Bingkai Jendela Kaca M2 7.480 259,200.00 1,938,816.00
8 Pek. Pas. Kaca Mati 5 mm Jendela M2 16.200 186,113.50 3,015,038.70
9 Pek. Pas. Kaca Mati 5 mm Ventilasi M2 0.720 186,113.50 134,001.72
10 Pek. Engsel Pintu Bh 45.000 36,516.25 1,643,231.25
11 Pek. Pas. Engsel Jendela Bh 72.000 27,677.50 1,992,780.00
12 Pek. Kunci Pintu 2 Slaag Bh 15.000 118,925.00 1,783,875.00
13 Pek. Pas. Hak Angin Bh 72.000 21,516.25 1,549,170.00
14 Pek. Pas. Grendel Jendela Bh 36.000 25,355.00 912,780.00
15 Pek. Pas. Grendel Pintu Tanam Bh 3.000 32,355.00 97,065.00
16 Pek. Pas. Reiling Tangga M2 7.200 253,330.00 1,823,976.00
17 Pek. Pas. Reiling Selasar M2 5.775 277,330.00 1,601,580.75
Jumlah 37,455,413.75
VI PEKERJAAN KM/WC/SANITASI
1 Pek. Pipa PVC Dia.3" (Air Kotor) M1 15.000 118,414.00 1,776,210.00
2 Pek. Pipa PVC Dia.1/2" (Air Bersih) M1 20.000 18,014.00 360,280.00
3 Pek. Pas. Kloset Jongkok Bh 3.000 360,150.00 1,080,450.00
4 Pek. Pas. Stop Kran Biasa Bh 7.000 48,058.75 336,411.25
5 Pek. Pas. Bak KM Bh 3.000 683,850.00 2,051,550.00
6 Pek. Pas. Floor Drain Bh 5.000 24,925.00 124,625.00
7 Pek. Septictank + Peresapan Bh 1.000 2,884,493.86 2,884,493.86
8,614,020.11
VII PEKERJAAN INSTALASI LISTRIK
1 Titik Nyala Titik 69.000 150,000.00 10,350,000.00
2 Lampu SL 18 Watt Bh 18.000 57,925.00 1,042,650.00
3 Lampu SL 10 Watt (Teras) Bh 20.000 47,925.00 958,500.00
4 Saklar Ganda Bh 6.000 36,750.00 220,500.00
5 Saklar Tunggal Bh 13.000 28,750.00 373,750.00
6 Sekring Box MCB Bh 1.000 51,750.00 51,750.00
7 Stop Kontak 100 VA Bh 11.000 34,750.00 382,250.00
Jumlah 13,379,400.00
VIII PEKERJAAN PLAFOND
1 Pek. Rangka Plafond M2 318.613 37,200.00 11,852,385.00
2 Pek. Plafond Tripleks 3 mm M2 318.613 28,827.50 9,184,801.84
3 Pek. List Plafond Profil Kayu 4/4 M1 246.800 15,565.00 3,841,442.00
Jumlah 24,878,628.84
IX PEKERJAAN LANTAI
1 Pek. Lantai Keramik 30/30 cm M2 323.241 149,914.00 48,458,276.32
2 Pek. Dinding Keramik 20/20 cm M2 23.165 136,030.00 3,151,134.95
3 Pek. Lantai Keramik KM/WC 20/20 cm M2 15.525 143,454.00 2,227,123.35
4 Pek. Lantai Keramik Anak Tangga 20/20 cm M2 4.320 143,454.00 619,721.28
Jumlah 54,456,255.90
X PEKERJAAN KONSTRUKSI ATAP
1 Pek. Kuda-kuda Kayu Kelas III 8/12 cm M3 3.818 3,596,000.00 13,730,342.25
2 Pek. Gording Kayu Kelas III 6/12 cm M3 2.292 2,346,000.00 5,377,313.52
3 Pek. Balok Angin Kayu Kelas III 6/12 cm M3 0.373 2,346,000.00 874,964.16
4 Pek. Atap Seng Gelombang BJLS 0.2 M2 330.251 40,790.00 13,470,938.29
5 Pek. Nok Seng Plat BJLS 0.2 M2 18.000 18,590.00 334,620.00
6 Pek. Talang Patahan Seng Plat BJLS 0.2 M2 7.496 57,265.00 429,258.44
7 Pek. Pas. Listplank Kayu Kelas II 2 x (2,5 x 20 M1 60.620 35,010.00 2,122,306.20
Jumlah 36,339,742.86
01 02 03 04 05 06
XI PEKERJAAN PENGECATAN
1 Pengecatan Dinding M2 ### 14,173.50 15,005,838.79
2 Pek. Cat Plafond M2 318.613 14,173.50 4,515,854.27
3 Pek. Cat Seng M2 330.251 21,773.50 7,190,720.15
4 Pek. Cat Kusen, Pintu, Jendela dan Ventilasi M2 126.383 27,792.50 3,512,499.53
Jumlah 30,224,912.73
0.00
20.010
0.00
0.00
16.00
3.60
3.60
0.00
10.00 5.00
0.00
0.00
0.00
0.00
0.00
0.00
820,000,000.00
0.00
CV. DIMENSI ORIENT PRIMA Konsultan
PERENCANAAN, PENGAW ASAN DAN SURVEY PEM ETAAN
Kantor : Jl. Pemuda No.301 Tlp.(0405)22287 Kolaka
2 1 M3 URUGAN KEMBALI
0.192 Oh Pekerja @ Rp 45,000.00 = Rp 8,640.00
0.019 Oh Mandor @ Rp 55,000.00 = Rp 1,045.00
Rp 9,685.00
3 1 M3 URUGAN PASIR
1.200 M3 Pasir urug @ Rp 98,000.00 = Rp 117,600.00
0.300 Oh Pekerja @ Rp 45,000.00 = Rp 13,500.00
0.010 Oh Mandor @ Rp 55,000.00 = Rp 550.00
Rp 131,650.00
4 1 M3 URUGAN TANAH
1.200 M3 Tanah urug @ Rp 40,000.00 = Rp 48,000.00
0.300 Oh Pekerja @ Rp 45,000.00 = Rp 13,500.00
0.010 Oh Mandor @ Rp 55,000.00 = Rp 550.00
Rp 62,050.00
32 1 M2 RANGKA PLAFOND 30 x 60
0.023 M3 Balok Kayu Klass III @ Rp 1,750,000.00 = Rp 40,250.00
0.150 Kg Paku @ Rp 20,000.00 = Rp 3,000.00
0.300 Oh Tukang kayu @ Rp 65,000.00 = Rp 19,500.00
0.030 Oh Kepala tukang @ Rp 70,000.00 = Rp 2,100.00
0.200 Oh Pekerja @ Rp 45,000.00 = Rp 9,000.00
0.010 Oh Mandor @ Rp 55,000.00 = Rp 550.00
Rp 74,400.00
Rangka Plapond 60 x 120 cm Rp 37,200.00
43 1 M2 CAT TEMBOK
0.100 Kg Plamur @ Rp 14,000.00 = Rp 1,400.00
0.100 Kg Cat dasar @ Rp 20,000.00 = Rp 2,000.00
0.260 Kg Cat tembok @ Rp 20,000.00 = Rp 5,200.00
0.063 Oh Tukang cat @ Rp 65,000.00 = Rp 4,095.00
0.0063 Oh Kepala tukang @ Rp 70,000.00 = Rp 441.00
0.020 Oh Pekerja @ Rp 45,000.00 = Rp 900.00
0.0025 Oh Mandor @ Rp 55,000.00 = Rp 137.50
Rp 14,173.50
44 1 M2 CAT PLAFOND
0.100 Kg Cat dasar @ Rp 20,000.00 = Rp 2,000.00
0.260 Kg Cat plafond @ Rp 20,000.00 = Rp 5,200.00
0.100 Kg Plamur @ Rp 14,000.00 = Rp 1,400.00
0.063 Oh Tukang cat @ Rp 65,000.00 = Rp 4,095.00
0.0063 Oh Kepala tukang @ Rp 70,000.00 = Rp 441.00
0.020 Oh Pekerja @ Rp 45,000.00 = Rp 900.00
0.0025 Oh Mandor @ Rp 55,000.00 = Rp 137.50
Rp 14,173.50
45 1 M2 CAT KAYU
0.200 Kg Cat meni @ Rp 16,500.00 = Rp 3,300.00
0.150 Kg Plamur @ Rp 20,000.00 = Rp 3,000.00
0.170 Kg Cat dasar @ Rp 40,000.00 = Rp 6,800.00
0.260 Kg Cat Kilap @ Rp 40,000.00 = Rp 10,400.00
0.009 Oh Tukang cat @ Rp 65,000.00 = Rp 585.00
0.006 Oh Kepala tukang @ Rp 70,000.00 = Rp 420.00
0.070 Oh Pekerja @ Rp 45,000.00 = Rp 3,150.00
0.0025 Oh Mandor @ Rp 55,000.00 = Rp 137.50
Rp 27,792.50
6.46
Tebal Lebar Luas Panjang/m3
Jlh.Tul.PokokDiameter Berat/m' Berat/m3 Jrk Beugel
0.30 0.30 0.09 11.1111 4 16 1.58 70.2222 0.15
0.30 0.30 0.09 11.1111 0 14 1.21 0
0.30 0.30 0.09 11.1111 4 12 0.89 39.5556
Tebal Lebar Luas Jlh.Tul.Pokok Pjg/M3 Diameter Jrk BeugelJlh BeugelPjg Beugel
0.10 1.20 0.12 10 83.3333 12 0.2 42 110.04
0.00
0.0115
2.4
0.6
0.84
0.21
0.275 1.54
0.44 0.87662
0.15
0.865
0.02595 0.01685065
0.6 1.76
0.27 0.81
0.06 0.46023
0.0279 0.01585227
1.68 1.68
1.48 0.2 0.81
0.0444 0.11904762 0.48214
0.02643 0.01573129
0.077 0.01444
2.88 0.34722
0.65278 0.71806
1.5
0.5
90
2.4 8.1 2.36842
5.6 5.6 1.63743
5.7
13.7 3.42
4.00585
2.75
0.6 0.6 0.72727
3.35
4.06061 0.825
dia beuge Berat/m'Pnjg Beugel
Jmlh Beugel/m3
Berat/m3 Total Pjg/M3 Diameter Jrk BeugelJlh Beugel
8 0.39 0.800 74.0741 23.1111 132.889 44.4444 14 0.15 75
Berat Berat
P. Total P. Total
Total Total
Pokok Bagi
Pokok Bagi
Jlh Diameter Berat
7.66667 10 0.62 56.5556 63.8889 35.0644 39.6111
7.66667 10 0.62 113.111 127.778 70.1289 79.2222
105.193 118.833
A. UPAH KERJA
1 Pekerja Oh Rp.
2 Tukang Kayu, Batu, Besi, Cat dan Las Oh Rp.
3 Kepala Tukang Oh Rp.
4 Mandor Oh Rp.
5 Tukang Bongkar Mal / Bekisting Oh Rp.
RGA BAHAN
HARGA
45,000.00
65,000.00
70,000.00
55,000.00
45,000.00
2,200,000.00
1,750,000.00
135,000.00
135,000.00
425.00
325,000.00
40,000.00
15,000.00
16,500.00
16,500.00
8,000.00
20,000.00
80,000.00
10,000.00
40,000.00
45,000.00
20,000.00
25,000.00
5,000.00
17,000.00
10,000.00
42,000.00
10,000.00
17,000.00
25,000.00
1,500.00
7,500.00
140,000.00
140,000.00
10,000.00
6,000.00
20,000.00
20,000.00
10,000.00
85,000.00
HARGA
8,500.00
2,500.00
95,000.00
2,500.00
150.00
30,000.00
40,000.00
30,000.00
8,500.00
5,000.00
150.00
25,000.00
10,000.00
100,000.00
22,000.00
20,000.00
25,000.00
2,200,000.00
1,750,000.00
25,000.00
98,000.00
105,000.00
105,000.00
14,000.00
20,000.00
15,000.00
20,000.00
25,000.00
40,000.00
7,500.00
83,000.00
3,500.00
50,000.00
40,000.00
17,000.00
25,000.00
23,000.00
1,300.00
15,000.00
5,350.00
43,200.00
18,000.00
22,000.00
40,000.00
40,000.00
47,000.00
87,000.00
4,860.00
1,880.00
2,450.00
1,000.00
2,700.00