GEDUNG KANTOR
I PEKERJAAN PONDASI
1 Pembersihan Lapangan 10.00 x 45.00 = 450.00 450.00 M2
3 Galian Tanah Pondasi memanjang 0.80 x 0.80 x 42.00 x 2.00 = 53.76 109.76 M3
0.80 x 0.80 x 6.00 x 2.00 = 7.68
0.80 x 0.80 x 7.50 x 1.00 = 4.80
6 Pas. Pondasi Bt. Kali 1:4 0.25 + 0.60 / 2.00 x 0.60 = 0.26 41.82 M3
0.26 x 164.00 = 41.82
II PEKERJAAN BETON/DINDING
1 Pek. Sloof Praktis 15/20
a Pek. Pembesian besi 12 tul pokok 4.00 x 167.00 x 0.89 = 594.52 967.38 Kg
c Pek. Stamp beton K 175 0.15 x 0.25 x 3.50 x 44.00 = 5.78 5.78 M3
c Pek. Stamp beton K 175 0.13 x 0.13 x 3.50 x 16.00 = 0.95 0.95 M3
8 Pas. Dinding Bata 1:4 Rabat / teras 0.55 x 45.00 x 2.00 = 90.00 112.00 M2
0.55 x 11.00 x 2.00 = 22.00 +
= 112.00
2 Pek Gording Kayu 0.05 x 0.10 x 45.00 x 11.00 x 2.00 = 4.95 6.64 M3
0.05 x 0.10 x 9.50 x 11.00 x 2.00 = 1.05
0.05 x 0.10 x 5.87 x 11.00 x 2.00 = 0.65 +
= 6.64
6 Pas. Atap Seng BJLS 20 warna 45.00 + 32.00 / 2.00 x 7.50 x 2.00 = 577.50 667.50 M2
12.00 x 7.50 / 2.00 x 2.00 = 90.00 +
= 667.50
IV PEKERJAAN PLESTERAN
1 Pek. Plesteran Dinding 1 : 2 61.50 x 2.00 = 123.00 123.00 M2
2 Pek. Plesteran Dinding 1:4 240.06 x 2.00 = 480.12 480.12 M2
3 Pek. Acian Dinding 480.12 + 123.00 = 603.12 603.12 M2
4 Pek. Acian Beton kolom 0.80 x 3.50 x 44.00 = 123.20 123.20 M2
4 Pas. Dinding Keramik 20x25 cm km/wc t= 1,5 m 1.50 x 6.00 x 4.00 = 36.00 36.00 M2
V PEKERJAAN PLAFOND
1 Pas. Rangka Plafond Kayu 12.50 x 46.00 = 575.00 575.00 M2
VI PEKERJAAN LANTAI
1 Timbunan Tanah Bawah Lantai 0.30 x 9.00 x 42.00 = 113.40 113.40 M3
NO URAIAN KEGIATAN URAIAN PERHITUNGAN VOLUME
3 Cor Lantai Beton K 175 tbl 5 cm 0.05 x 9.00 x 42.00 = 18.90 18.90 M3
5 Pas. Lantai Keramik 40x40 cm unpolish Teras teras belakang 2.00 x 45.00 = 90.00 162.00 M2
lobby 6.00 x 8.00 = 48.00
teras depan 6.00 x 4.00 = 24.00 +
= 162.00
6 Pas. Lantai Keramik 20x20 cm km/wc 1.35 x 1.85 x 4.00 = 9.99 9.99 M2
2 Pas. Pintu Panil Kayu Lapis Seng Plat P3=4 Bh 0.70 x 2.10 x 4.00 = 5.88 5.88 M2
2 Pas. Rangka Jendela + Kaca 5 mm 1.15 x 0.60 x 2.00 x 20.00 = 27.60 27.60 M2
3 Pas. Jalusi Kayu J1=20 Bh 0.14 x 0.60 x 8.00 x 4.00 x 20.00 = 53.76 59.14 M2
P1=2 Bh 0.14 x 0.60 x 8.00 x 2.00 x 2.00 = 2.69
P2=2 Bh 0.14 x 0.60 x 8.00 x 2.00 x 2.00 = 2.69 +
= 59.14
1 Pas. Pipa Air Kotor PVC dia 3" AW + Acc = 25.00 25.00 M1
1 Pas. Pipa Air Kotor PVC dia 4" AW + Acc = 25.00 25.00 M1
2 Pas. Pipa Air Bersih PVC 3/4" + Acc = 25.00 25.00 Bh
3 Pas. Kloset Jongkok = 4.00 4.00 Bh
3 Pas. Kran Air = 4.00 4.00 Bh
3 Pas. Flour Drain = 4.00 4.00 Bh
5 Timbunan Tanah Bawah Lantai 0.11 x 1.20 x 45.00 x 2.00 = 12.19 15.44 M3
0.11 x 1.20 x 12.00 x 2.00 = 3.25 +
= 15.44
7 Cor Lantai Beton K 175 tbl 5 cm 0.05 x 1.20 x 45.00 x 2.00 = 5.40 6.84 M3
0.05 x 1.20 x 12.00 x 2.00 = 1.44 +
= 6.84
I PEKERJAAN PENDAHULUAN
a Pembersihan Lapangan m2 56.00 18,000.00 1,008,000.00
b Pas. Papan Bouplank M1 17.00 70,330.00 1,195,610.00
c FASILITAS SMK3
Penyiapan RKB :
Pembuatan Manual,Prosedur, Intruksi Set 1.00 500,000.00 500,000.00
Alat Pendukung :
Topi Pelindung (Safety Helmet) bh 4.00 90,000.00 360,000.00
Rompi Keselamatan (Safety vest) bh 4.00 90,000.00 360,000.00
Sepatu Keselamatan (Boots) psg 4.00 150,000.00 600,000.00
Rambu-Rambu Peringatan (Plang Nama, Spanduk Utama Keselamatan kerja) bh 1.00 50,000.00 50,000.00
Fasilitas Sarana Kesehatan :
Peralatan P3K kotak 1.00 150,153.75 150,153.75
Asuransi Ketenagakerjaan :
BPJS Ketenagakerjaan dan Keselamatan Kerja Ls 1.00 236,210.00 236,210.00
JUMLAH 4,459,973.75
II PEKERJAAN PONDASI
1 Pek. Pondasi
a Galian Tanah Pondasi M3 7.68 82,920.00 636,825.60
b Pas. Aanstampang Bt. Kali M3 2.56 463,250.00 1,185,920.00
c Pas. Pondasi Bt. Kali 1:4 M3 4.32 844,940.00 3,650,140.80
d Urugan Tanah Kembali M3 1.92 38,750.00 74,400.00
e Pas. Pondasi Tapak M3 1.48 1,390,320.00 2,052,894.38
JUMLAH 7,600,180.78
IV PEKERJAAN KAP/ATAP
a Pek Kuda-kuda Baja Ringan C 0.75 M2 47.81 305,190.00 14,591,133.90
b Pas. Atap Seng BJLS 20 warna M2 47.81 69,860.00 3,340,006.60
c Pek Seng Bubung M' 7.38 30,460.00 224,642.50
d Pek Lisplank Seng Superdex M' 14.75 48,210.00 711,097.50
e Pek Talang M' 2.88 88,530.00 254,523.75
f Pek. Singok M2 5.73 55,310.00 316,926.30
JUMLAH 19,438,330.55
HARGA JUMLAH JUMLAH
NO URAIAN PEKERJAAN STN VOLUME SATUAN HARGA STN TOTAL
(Rp) (Rp) (Rp)
V PEKERJAAN PLESTERAN
a Pek. Plesteran Dinding 1 : 2 M2 17.88 74,150.00 1,325,802.00
b Pek. Plesteran Dinding 1 : 4 M2 56.69 69,020.00 3,912,743.80
c Pek. Acian Dinding M2 74.57 42,420.00 3,163,259.40
JUMLAH 8,401,805.20
VI PEKERJAAN PLAFOND
a Pemasangan Besi Hollow M2 25.00 305,190.00 7,629,750.00
b Cat Menie Rangka Plafond M2 21.60 42,413.97 916,141.64
c Pas. Plafond Triplek 6 mm M2 25.00 61,130.00 1,528,250.00
d Pas. Les Profil 5x5 cm M1 15.00 15,000.00 225,000.00
JUMLAH 10,299,141.64
JUMLAH 48,043,296.00
IX PEKERJAAN PENGECETAN
1 Pengecatan Tembok Baru (1 x Plamir,1 x Cat Dasar,2 x Cat Penutup) M2 113.47 43,800.00 4,969,812.55
2 Pengecatan Tembok Lama ( 1 X Cat Dasar ,2 x Cat Penutup ) M2 80.08 134,090.00 10,737,927.20
JUMLAH 15,707,739.75
Dibuat Oleh :
KONSULTAN PERENCANA
CV. JAYA PERMAI CONSULTANT
EDI SURYA, ST
Direktur
REKAPITULASI
PROGRAM : PENGELOLAAN PENDIDIKAN SEKOLAH DASAR
KEGIATAN : PEMBANGUNAN SARANA, PRASARANA DAN UTILITAS SEKOLAH
PEKERJAAN : PEMBANGUNAN RUANG MAJELIS GURU BESERTA PARABOTNYA SDN 06 SINTUK TOBOH GADANG
LOKASI : SINTOGA
TAHUN ANGGARAN : 2021
JUMLAH HARGA
NO URAIAN PEKERJAAN
( Rp )
JUMLAH 165,181,818.19
PPN 10 % 16,518,181.82
TOTAL 181,700,000.00
Terbilang : Seratus delapan puluh satu juta tujuh ratus ribu rupiah
EDI SURYA, ST
MAYULIS, S.Pd.MM EFINALDI, ST.MT. Direktur
Nip. 19650208 1988810 1 001 Nip. 19711104 200212 1 004
JUMLAH MINGGU
NO URAIAN PEKERJAAN bobot 1 2 3 4 5 6 7 8 9 10 11 12 Ket.
(%)
III PEKERJAAN BETON/DINDING 20.77 2.9666312 2.96663 2.96663 2.96663 2.96663 2.9666 2.9666
IV PEKERJAAN KAP/ATAP 11.77 1.4709799 1.47098 1.47098 1.47098 1.47098 1.471 1.471 1.471
V PEKERJAAN PLESTERAN 5.09 0.6358 0.6358 0.6358 0.6358 0.6358 0.6358 0.6358 0.6358
REN- JUMLAH BOBOT PER MINGGU 100.00 2.2702396 2.2702396 5.3578311 5.99363 7.0328 6.11258 13.3839 13.384 18.049 18.252 3.8056 4.0877
CANA JUMLAH BOBOT AKUMULATIF 0.00 2.2702396 4.5404792 9.8983102 15.8919 22.9247 29.0373 42.4212 55.805 73.854 92.107 95.912 100
Rencana Waktu Pelaksanaan = 120 (Seratus Dua Puluh ) Hari Kalender
PADANG, Mei 2021
DIBUAT OLEH
KONSULTAN PERENCANA
CV. JAYA PERMAI CONSULTANT
EDI SURYA, ST
Direktur
PERHITUNGAN VOLUME
I PEKERJAAN PENDAHULUAN
1 Pembersihan Lapangan 8.00 x 7.00 = 56.00 56.00 M2
II PEKERJAAN PONDASI
1 Galian Tanah Pondasi 0.80 x 0.60 x 16.00 = 7.68 7.68 M3
3 Pas. Pondasi Bt. Kali 1:4 0.30 + 0.60 / 2.00 x 0.60 = 0.27 4.32 M3
0.27 x 16.00 = 4.32
b Pek. Bekisting kolom (bahan 2x pemakaian) 0.80 x 3.50 x 14.00 = 39.20 39.20 M2
c Pek. Stamp beton K 175 0.20 x 0.20 x 3.10 x 14.00 = 1.74 1.74 M3
NO URAIAN KEGIATAN URAIAN PERHITUNGAN VOLUME
IV PEKERJAAN KAP/ATAP
1 Pek Kuda-kuda Baja Ringan C 0.75 47.81 M2
7.38 x 2.54 x 2.00 = 12.46
22.96 x 6.20 x 2.00 = 35.36
V PEKERJAAN PLESTERAN
1 Pek. Plesteran Dinding 1 : 2 8.94 x 2.00 = 17.88 17.88 M2
VI PEKERJAAN PLAFOND
1 Pas. Rangka Plafond Besi Hollow 9.00 + 8.00 = 25.00 25.00 M2
2 Cor Lantai Beton K 175 tbl 5 cm 9.00 x 8.00 x 0.05 = 3.60 3.60 M3
2 Pas. Rangka Jendela + Kaca 5 mm J1=5 Bh 1.00 x 1.75 x 2.10 x 5.00 = 18.38 18.38 M2
3 Pas. Jalusi Kayu J1=5 Bh 5.00 x 0.14 x 0.60 x 2.10 = 0.88 0.98 M2
P=1 Bh 1.00 x 0.14 x 0.60 x 1.20 = 0.10
RUANG LABOR
I PEKERJAAN PONDASI
1 Pembersihan Lapangan 10.00 x 15.00 = 150.00 150.00 M2
6 Pas. Pondasi Bt. Kali 1:4 0.25 + 0.60 / 2.00 x 0.60 = 0.26 14.99 M3
0.26 x 58.80 = 14.99
II PEKERJAAN BETON/DINDING
1 Pek. Sloof Praktis 15/20
a Pek. Pembesian besi 12 tul pokok 4.00 x 58.80 x 0.89 = 209.33 264.57 Kg
c Pek. Stamp beton K 175 0.15 x 0.25 x 3.50 x 15.00 = 1.97 1.97 M3
c Pek. Stamp beton K 175 0.13 x 0.13 x 3.50 x 4.00 = 0.24 0.24 M3
8 Pas. Dinding Bata 1:4 Rabat / teras 0.55 x 12.00 x 2.00 = 24.00 40.00 M2
0.55 x 8.00 x 2.00 = 16.00 +
= 40.00
3 Pas. Atap Seng BJLS 20 warna 18.00 + 4.50 / 2.00 x 7.50 x 2.00 = 168.75 258.75 M2
12.00 x 7.50 / 2.00 x 2.00 = 90.00 +
= 258.75
IV PEKERJAAN PLESTERAN
1 Pek. Plesteran Dinding 1 : 2 25.08 x 2.00 = 50.16 50.16 M2
V PEKERJAAN PLAFOND
1 Pas. Rangka Plafond Kayu 12.00 x 18.00 = 216.00 216.00 M2
= 68.40
VI PEKERJAAN LANTAI
1 Timbunan Tanah Bawah Lantai 0.20 x 10.00 x 15.00 = 30.00 30.00 M3
3 Cor Lantai Beton K 175 tbl 5 cm 0.05 x 10.00 x 15.00 = 7.50 7.50 M3
5 Pas. Lantai Keramik 40x40 cm meja beton 0.70 x 4.00 x 2.00 = 5.60 5.60 M2
6 Pas. Lantai Keramik 40x40 cm unpolish Teras 2.00 x 15.00 = 30.00 30.00 M2
2 Pas. Rangka Jendela + Kaca 5 mm J1=9 Bh 1.15 x 0.60 x 2.00 x 9.00 = 12.42 12.42 M2
3 Pas. Jalusi Kayu J1=9 Bh 0.14 x 0.60 x 8.00 x 4.00 x 9.00 = 24.19 28.22 M2
P1=1 Bh 0.14 x 0.60 x 8.00 x 2.00 x 1.00 = 1.34
P2=2 Bh 0.14 x 0.60 x 8.00 x 2.00 x 2.00 = 2.69 +
= 28.22
4 Timbunan Tanah Bawah Lantai 0.10 x 1.20 x 15.00 x 2.00 = 3.60 6.48 M3
0.10 x 1.20 x 12.00 x 2.00 = 2.88 +
= 6.48
6 Cor Lantai Beton K 175 tbl 5 cm 0.05 x 1.20 x 15.00 x 2.00 = 1.80 3.24 M3
0.05 x 1.20 x 12.00 x 2.00 = 1.44 +
= 3.24
GUDANG DAN KM / WC
I PEKERJAAN PONDASI
1 Pek. Pondasi
a Pembersihan Lapangan M3 24.00 18,000.00 432,000.00
b Pas. Papan Bouplank M1 11.00 70,330.00 773,630.00
c Galian Tanah Pondasi M3 7.56 82,920.00 626,875.20
d Pas. Aanstampang Bt. Kali M3 2.52 463,250.00 1,167,390.00
e Pas. Pondasi Bt. Kali 1:4 M3 4.10 844,940.00 3,460,029.30
f Urugan Tanah Kembali M3 1.89 38,750.00 73,237.50
JUMLAH 6,533,162.00
II PEKERJAAN BETON/DINDING
1 Pek. Sloof Praktis 15/20
a Pek. Pembesian Kg 74.18 15,450.00 1,146,009.31
b Pek. Bekisting sloof M2 4.20 178,920.00 751,464.00
c Pek. Stamp beton K 175 M3 0.63 1,010,040.00 636,325.20
IV PEKERJAAN PLESTERAN
1 Pek. Plesteran
a Pek. Plesteran Dinding 1 : 2 M2 21.00 74,150.00 1,557,150.00
b Pek. Plesteran Dinding 1:4 M2 58.44 69,020.00 4,033,528.80
JUMLAH #REF!
V PEKERJAAN LANTAI
1 Pek. Lantai
a Timbunan Tanah Bawah Lantai M3 2.06 136,260.00 281,240.64
b Urugan Pasir M3 1.20 #REF! #REF!
c Cor Lantai Beton K 175 tbl 5 cm M3 1.20 1,010,040.00 1,212,048.00
JUMLAH #REF!
VI PEKERJAAN PINTU/JENDELA
1 Pek. Pintu / Jendela
a Pas. Pintu Panil Kayu M2 7.28 797,070.00 5,802,669.60
b Pas. Kaca Bening 5 mm M2 0.49 138,830.00 68,026.70
2 Pengantung/Pengunci
a Pas. Kunci Pintu 2 x Slagh Bh 1.00 #REF! #REF!
b Pas. Engsel Pintu 4" Bh 15.00 #REF! #REF!
c Pas. Gerendel Pintu Bh 8.00 #REF! #REF!
JUMLAH #REF!
GUDANG DAN KM / WC
I PEKERJAAN PONDASI
1 Pembersihan Lapangan 3.00 x 8.00 = 24.00 24.00 M2
6 Pas. Pondasi Bt. Kali 1:4 0.25 + 0.40 / 2.00 x 0.60 = 0.20 4.10 M3
0.20 x 21.00 = 4.10
II PEKERJAAN BETON/DINDING
1 Pek. Sloof Praktis 15/20
a Pek. Pembesian besi 10 tul pokok 4.00 x 21.00 x 0.62 = 52.08 74.18 Kg
c Pek. Stamp beton K 175 0.13 x 0.13 x 3.00 x 16.00 = 0.81 0.81 M3
3 Pas. Atap Seng BJLS 20 warna 3.00 x 10.00 x 2.00 = 60.00 60.00 M2
IV PEKERJAAN PLESTERAN
1 Pek. Plesteran Dinding 1 : 2 10.50 x 2.00 = 21.00 21.00 M2
V PEKERJAAN PLAFOND
1 Pas. Rangka Plafond Kayu 3.00 x 8.00 = 24.00 24.00 M2
VI PEKERJAAN LANTAI
1 Timbunan Tanah Bawah Lantai 0.09 x 3.00 x 8.00 = 2.06 2.06 M3
3 Cor Lantai Beton K 175 tbl 5 cm 0.05 x 3.00 x 8.00 = 1.20 1.20 M3
4 Pas. Lantai Keramik 20x20 cm unpolish Teras 5.00 x 8.00 = 40.00 40.00 M2
1 Pas. Pipa Air Kotor PVC dia 3" AW + Acc = 10.00 10.00 M1
2 Pas. Pipa Air Kotor PVC dia 4" AW + Acc = 10.00 10.00 M1
3 Pas. Pipa Air Bersih PVC 3/4" + Acc = 10.00 10.00 Bh
4 Pas. Kloset Jongkok = 4.00 4.00 Bh
5 Pas. Kran Air = 4.00 4.00 Bh
6 Pas. Flour Drain = 4.00 4.00 Bh
GEDUNG PUSTAKA
I PEKERJAAN PONDASI
1 Pek. Pondasi
a Pembersihan Lapangan M3 120.00 18,000.00 2,160,000.00
b Pas. Papan Bouplank M1 21.68 70,330.00 1,524,754.40
c Galian Tanah Pondasi M3 28.16 82,920.00 2,335,027.20
d Pas. Aanstampang Bt. Kali M3 7.04 463,250.00 3,261,280.00
e Pas. Pondasi Bt. Kali 1:4 M3 11.22 844,940.00 9,480,226.80
f Urugan Tanah Kembali M3 7.04 38,750.00 272,800.00
JUMLAH 19,034,088.40
II PEKERJAAN BETON/DINDING
1 Pek. Sloof Praktis 15/20
a Pek. Pembesian Kg 250.18 15,450.00 3,865,243.92
b Pek. Bekisting sloof M2 8.80 178,920.00 1,574,496.00
c Pek. Stamp beton K 175 M3 1.32 1,010,040.00 1,333,252.80
IV PEKERJAAN PLESTERAN
1 Pek. Plesteran
a Pek. Plesteran Dinding 1 : 2 M2 36.50 74,150.00 2,706,475.00
b Pek. Plesteran Dinding 1:4 M2 137.82 69,020.00 9,512,336.40
c Pek. Acian Dinding M2 174.32 42,420.00 7,394,654.40
d Pek. Acian Beton M2 42.00 42,420.00 1,781,640.00
JUMLAH 21,395,105.80
V PEKERJAAN PLAFOND
1 Pek. Plafond
a Pas. Rangka Plafond Kayu M2 196.00 #REF! #REF!
b Cat Menie Rangka Plafond M2 87.68 42,413.97 3,718,644.38
c Pas. Plafond Triplek 4 mm M2 196.00 61,130.00 11,981,480.00
d Pas. Les Profil 5x5 cm M1 104.00 15,000.00 1,560,000.00
JUMLAH #REF!
VI PEKERJAAN LANTAI
1 Pek. Lantai
a Timbunan Tanah Bawah Lantai M3 36.00 136,260.00 4,905,360.00
b Urugan Pasir M3 12.00 #REF! #REF!
c Cor Lantai Beton K 175 tbl 5 cm M3 6.00 1,010,040.00 6,060,240.00
d Pas. Lantai Keramik 40x40 cm M2 84.00 687,870.00 57,781,080.00
e Pas. Lantai Keramik 40x40 cm unpolish Teras M2 24.00 687,870.00 16,508,880.00
JUMLAH #REF!
2 Pengantung/Pengunci
a Pas. Kunci Pintu 2 x Slagh Bh 2.00 #REF! #REF!
b Pas. Engsel Pintu 4" Bh 6.00 #REF! #REF!
c Pas. Engsel Jendela 3" Bh 30.00 #REF! #REF!
d Pas. Gerendel Jendela Bh 30.00 #REF! #REF!
e Pas. Kait Angin Jendela Bh 30.00 #REF! #REF!
f Pas. Tangan-tangan Jendela Bh 15.00 #REF! #REF!
JUMLAH #REF!
GEDUNG PUSTAKA
I PEKERJAAN PONDASI
1 Pembersihan Lapangan 10.00 x 12.00 = 120.00 120.00 M2
6 Pas. Pondasi Bt. Kali 1:4 0.25 + 0.60 / 2.00 x 0.60 = 0.26 11.22 M3
0.26 x 44.00 = 11.22
II PEKERJAAN BETON/DINDING
1 Pek. Sloof Praktis 15/20
a Pek. Pembesian besi 12 tul pokok 4.00 x 47.00 x 0.89 = 167.32 250.18 Kg
c Pek. Stamp beton K 175 0.15 x 0.25 x 3.50 x 15.00 = 1.97 1.97 M3
c Pek. Stamp beton K 175 0.13 x 0.13 x 3.50 x 4.00 = 0.24 0.24 M3
8 Pas. Dinding Bata 1:4 Rabat / teras 0.55 x 14.00 x 2.00 = 28.00 50.00 M2
0.55 x 11.00 x 2.00 = 22.00 +
= 50.00
3 Pas. Atap Seng BJLS 20 warna 14.00 + 2.10 / 2.00 x 7.50 x 2.00 = 120.75 210.75 M2
12.00 x 7.50 / 2.00 x 2.00 = 90.00 +
= 210.75
IV PEKERJAAN PLESTERAN
1 Pek. Plesteran Dinding 1 : 2 18.25 x 2.00 = 36.50 36.50 M2
V PEKERJAAN PLAFOND
1 Pas. Rangka Plafond Kayu 14.00 x 14.00 = 196.00 196.00 M2
3 Cor Lantai Beton K 175 tbl 5 cm 0.05 x 10.00 x 12.00 = 6.00 6.00 M3
5 Pas. Lantai Keramik 40x40 cm unpolish Teras 2.00 x 12.00 = 24.00 24.00 M2
2 Pas. Rangka Jendela + Kaca 5 mm J1=7 Bh 1.15 x 0.60 x 2.00 x 7.00 = 9.66 9.66 M2
3 Pas. Jalusi Kayu J1=7 Bh 0.14 x 0.60 x 8.00 x 4.00 x 7.00 = 18.82 22.85 M2
P1=1 Bh 0.14 x 0.60 x 8.00 x 2.00 x 1.00 = 1.34
P2=2 Bh 0.14 x 0.60 x 8.00 x 2.00 x 2.00 = 2.69 +
= 22.85
4 Pas. Kaca Bening 5 mm J1=7 Bh 0.60 x 0.85 x 2.00 x 7.00 = 7.14 7.14 M2
4 Timbunan Tanah Bawah Lantai 0.10 x 1.20 x 10.00 x 2.00 = 2.40 5.28 M3
0.10 x 1.20 x 12.00 x 2.00 = 2.88 +
= 5.28
= 2.64
6 Cor Lantai Beton K 175 tbl 5 cm 0.05 x 1.20 x 10.00 x 2.00 = 1.20 2.64 M3
0.05 x 1.20 x 12.00 x 2.00 = 1.44 +
= 2.64
JENIS PEKERJAAN : PEMASANGAN 1 M2 DINDING (BATA MERAH 5x11x22) CM TEBAL 1/2 BATA
BATU CAMP. 1PC : 4 PASIR PASANG
HARGA SATUAN : Rp 140,980 /M2
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.300 Rp 96,000 Rp 28,800
Tukang Batu L.02 OH 0.100 Rp 124,900 Rp 12,490
Kepala Tukang L.03 OH 0.010 Rp 130,100 Rp 1,301
Mandor L.04 OH 0.015 Rp 135,300 Rp 2,030
JUMLAH Rp 44,621
B BAHAN
Bata Merah M3 70.000 Rp 900 Rp 63,000
Semen Portland PCC 50 kg Kg 11.500 Rp 1,300 Rp 14,950
Pasir Pasang M3 0.043 Rp 130,100 Rp 5,594
JUMLAH 83,544
C PERALATAN
JUMLAH
JUMLAH TOTAL Rp 128,165
Over Head + Fee 10% Rp 12,816
JUMLAH Rp 140,981
DIBULATKAN Rp 140,980
JENIS PEKERJAAN : PEMASANGAN 1 M2 PLASTERAN 1PC : 2 PASIR PASANG TEBAL 15 MM
HARGA SATUAN : Rp 74,150 /M2
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.300 Rp 96,000 Rp 28,800
Tukang Batu L.02 OH 0.150 Rp 124,900 Rp 18,735
Kepala Tukang L.03 OH 0.015 Rp 130,100 Rp 1,952
Mandor L.04 OH 0.015 Rp 135,300 Rp 2,030
JUMLAH Rp 51,516
B BAHAN
Semen Portland PCC 50 kg Kg 10.224 Rp 1,300 Rp 13,291
Pasir Pasang M3 0.020 Rp 130,100 Rp 2,602
JUMLAH 15,893
C PERALATAN
JUMLAH
JUMLAH TOTAL Rp 67,409
Over Head + Fee 10% Rp 6,741
JUMLAH Rp 74,150
DIBULATKAN Rp 74,150
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.300 Rp 96,000 Rp 28,800
Tukang Batu L.02 OH 0.150 Rp 124,900 Rp 18,735
Kepala Tukang L.03 OH 0.015 Rp 130,100 Rp 1,952
Mandor L.04 OH 0.015 Rp 135,300 Rp 2,030
JUMLAH Rp 51,516
B BAHAN
Semen Portland PCC 50 kg Kg 6.240 Rp 1,300 Rp 8,112
Pasir Pasang M3 0.024 Rp 130,100 Rp 3,122
JUMLAH 11,234
C PERALATAN
JUMLAH
JUMLAH TOTAL Rp 62,750
Over Head + Fee 10% Rp 6,275
JUMLAH Rp 69,025
DIBULATKAN Rp 69,020
JENIS PEKERJAAN : PEMASANGAN 1 M2 ACIAN
HARGA SATUAN : Rp 42,420 /M2
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.200 Rp 96,000 Rp 19,200
Tukang Batu L.02 OH 0.100 Rp 124,900 Rp 12,490
Kepala Tukang L.03 OH 0.010 Rp 130,100 Rp 1,301
Mandor L.04 OH 0.010 Rp 135,300 Rp 1,353
JUMLAH Rp 34,344
B BAHAN
Semen Portland PCC 50 kg Kg 3.250 Rp 1,300 Rp 4,225
JUMLAH 4,225
C PERALATAN
JUMLAH
JUMLAH TOTAL Rp 38,569
Over Head + Fee 10% Rp 3,857
JUMLAH Rp 42,426
DIBULATKAN Rp 42,420
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.120 Rp 96,000 Rp 11,520
Tukang Kayu L.02 OH 0.060 Rp 124,900 Rp 7,494
Kepala Tukang L.03 OH 0.006 Rp 130,100 Rp 781
Mandor L.04 OH 0.006 Rp 135,300 Rp 812
JUMLAH Rp 20,606
B BAHAN
Atap Seng Gelombang Lbr 0.700 Rp 60,400 Rp 42,280
Paku Atap Kg 0.020 Rp 31,300 Rp 626
JUMLAH 42,906
C PERALATAN
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.100 Rp 96,000 Rp 9,600
Tukang Kayu L.02 OH 0.100 Rp 124,900 Rp 12,490
Kepala Tukang L.03 OH 0.010 Rp 130,100 Rp 1,301
Mandor L.04 OH 0.005 Rp 135,300 Rp 677
JUMLAH Rp 24,068
B BAHAN
Tripleks Biasa t = 4 mm Lbr 0.375 Rp 72,900 Rp 27,338
Paku Biasa Kg 0.250 Rp 16,700 Rp 4,175
JUMLAH 31,513
C PERALATAN
JENIS PEKERJAAN : PEMBUATAN DAN PEMASANGAN 1M3 KOZEN PINTU / JENDELA KAYU Kls II
HARGA SATUAN : Rp 8,273,430 /M1
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 6.000 Rp 96,000 Rp 576,000
Tukang kayu L.02 OH 18.000 Rp 124,900 Rp 2,248,200
Kepala Tukang L.03 OH 1.800 Rp 130,100 Rp 234,180
Mandor L.04 OH 0.300 Rp 135,300 Rp 40,590
JUMLAH Rp 3,098,970
B BAHAN
Balok kayu kelas II M3 1.200 Rp 3,641,800 Rp 4,370,160
Paku 10 Cm Kg 1.250 Rp 16,700 Rp 20,875
Lem kayu Kg 1.000 Rp 31,300 Rp 31,300
JUMLAH 4,422,335
C PERALATAN
JUMLAH
JUMLAH TOTAL Rp 7,521,305
Over Head + Fee 10% Rp 752,131
JUMLAH Rp 8,273,436
DIBULATKAN Rp 8,273,430
JENIS PEKERJAAN : PEMBUATAN DAN PEMASANGAN 1 M2 DAUN PINTU PANEL KAYU kls II
HARGA SATUAN : Rp 797,070 /M2
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 1.000 Rp 96,000 Rp 96,000
Tukang kayu L.02 OH 3.000 Rp 124,900 Rp 374,700
Kepala Tukang L.03 OH 0.300 Rp 130,100 Rp 39,030
Mandor L.04 OH 0.500 Rp 135,300 Rp 67,650
JUMLAH Rp 577,380
B BAHAN
Papan Kayu M3 0.040 Rp 3,641,800 Rp 145,672
Lem Kayu Kg 0.050 Rp 31,300 Rp 1,565
JUMLAH 147,237
C PERALATAN
JUMLAH
JUMLAH TOTAL Rp 724,617
Over Head + Fee 10% Rp 72,462
JUMLAH Rp 797,079
DIBULATKAN Rp 797,070
JENIS PEKERJAAN : Pengecatan Tembok Baru (1 x Plamir,1 x Cat Dasar,2 x Cat Penutup)
HARGA SATUAN : M2 / Buah
Kode Analisa : AHSP PU A.4.7.1.10
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.020 Rp 96,000 Rp 1,920
Tukang Cat L.02 OH 0.063 Rp 124,900 Rp 7,869
Kepala Tukang L.03 OH 0.006 Rp 130,100 Rp 820
Mandor L.04 OH 0.003 Rp 135,300 Rp 338
JUMLAH Rp 10,947
B BAHAN
1 Plamir Tembok KG 0.100 Rp 26,100 Rp 2,610
2 Cat Dasar Tembok KG 0.100 Rp 31,300 Rp 3,130
3 Cat Tembok / Penutup 2X KG 0.260 Rp 89,000 Rp 23,140
C PERALATAN
JUMLAH
JUMLAH TOTAL Rp 39,827
Over Head + Fee 10% Rp 3,983
JUMLAH Rp 43,809
DIBULATKAN Rp 43,800
C PERALATAN
JUMLAH
JUMLAH TOTAL Rp 121,906
Over Head + Fee 10% Rp 12,191
JUMLAH Rp 134,097
DIBULATKAN Rp 134,090
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.100 Rp 96,000 Rp 9,600
Tukang Kayu L.02 OH 0.200 Rp 124,900 Rp 24,980
Kepala Tukang L.03 OH 0.020 Rp 130,100 Rp 2,602
Mandor L.04 OH 0.005 Rp 135,300 Rp 677
JUMLAH Rp 37,859
B BAHAN
Seng tebal 0.20 11 bd warna setara swan brand lbr 0.083 Rp 60,400 Rp 5,031
Paku (1 1/2 1 )" RRC Kg 0.030 Rp 31,300 Rp 939
JUMLAH 5,970
C PERALATAN
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.300 Rp 96,000 Rp 28,800
Tukang Kayu L.02 OH 0.150 Rp 124,900 Rp 18,735
Tukang Besi L.02 OH 0.200 Rp 124,900 Rp 24,980
Kepala Tukang L.03 OH 0.020 Rp 130,100 Rp 2,602
Mandor L.04 OH 0.005 Rp 135,300 Rp 677
JUMLAH Rp 75,794
B BAHAN
Besi Hollow 4x4 (zincalume) M'' 0.008 Rp 4,100 Rp 33
Paku 1 (1/2") Kg 0.750 Rp 16,700 Rp 12,525
Paku (1 1/2 1 )" RRC kg 0.150 Rp 31,300 Rp 4,695
Seng Plat BJLS 30 lbr 0.100 Rp 62,500 Rp 6,250
JUMLAH Rp 23,503
C PERALATAN
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.100 Rp 96,000 Rp 9,600
Tukang Besi L.02 OH 0.100 Rp 124,900 Rp 12,490
Kepala Tukang L.03 OH 0.010 Rp 130,100 Rp 1,301
JUMLAH Rp 23,391
B BAHAN
` Besi Hollow 4x4 (zincalume) M' 1.050 Rp 4,100 Rp 4,305
JUMLAH Rp 4,305
C PERALATAN
HARGA
NO. UPAH DAN BAHAN KODE SATUAN KOOFISIEN JUMLAH HARGA
SATUAN
A TENAGA
Pekerja L.01 OH 0.100 Rp 96,000 Rp 9,600
Tukang Kayu L.02 OH 0.100 Rp 124,900 Rp 12,490
Kepala Tukang L.03 OH 0.010 Rp 130,100 Rp 1,301
Mandor L.04 OH 0.005 Rp 135,300 Rp 677
JUMLAH Rp 24,068
B BAHAN
Kaso-Kaso (5x7)cm Kayu Kelas II Marsawa M3 0.014 Rp 3,641,800 Rp 50,985
Paku (1 1/2 1 )" RRC Kg 0.250 Rp 31,300 Rp 7,825
RENG (3x4) Kayu Kelas II Marsawa M3 0.0072 Rp 3,641,800 Rp 26,221
JUMLAH Rp 85,031
C PERALATAN
HARGA SATUAN
NO JENIS BAHAN SATUAN (RP) KET
JUMLAH HARGA
NO URAIAN PEKERJAAN
( Rp )
JUMLAH 16,636,363.64
PPN 10 % 1,663,636.36
TOTAL 18,300,000.00
I PENGADAAN MEBELUER
2.00 1,400,000.00 2,800,000.00
1 Lemari Bh
6.00 860,000.00 5,160,000.00
2 Meja Guru Bh
3 Kursi Guru Bh 6.00 321,060.61 1,926,363.64
4 Papan Statistik Bh 1.00 450,000.00 450,000.00
5 Papan Pengumuman Bh 1.00 450,000.00 450,000.00
6 Kursi Tamu Sofa Set Set 1.00 4,500,000.00 4,500,000.00
7 Meja Tamu Set 1.00 1,350,000.00 1,350,000.00
JUMLAH 16,636,363.64
Dibuat Oleh :
KONSULTAN PERENCANA
CV. JAYA PERMAI CONSULTANT
EDI SURYA, ST
Direktur
RENCANA ANGGARAN BIAYA
KEGIATAN : PEMBANGUNAN UNIT SEKOLAH BARU SMAN 2 LINGGO SARI BAGANTI
PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR
LOKASI : PUNGGASAN KABUPATEN PESISIR SELATAN
GEDUNG KANTOR
I PEKERJAAN PONDASI
1 Pek. Pondasi
a Pembersihan Lapangan M3 450.00 18,000.00 8,100,000.00
b Pas. Papan Bouplank M1 62.00 70,330.00 4,360,460.00
c Galian Tanah Pondasi M3 109.76 82,920.00 9,101,299.20
d Pas. Aanstampang Bt. Kali M3 26.24 463,250.00 12,155,680.00
e Pas. Pondasi Bt. Kali 1:4 M3 41.82 844,940.00 35,335,390.80
f Urugan Tanah Kembali M3 27.44 38,750.00 1,063,300.00
JUMLAH 70,116,130.00
II PEKERJAAN BETON/DINDING
1 Pek. Sloof Praktis 15/20
a Pek. Pembesian Kg 967.38 15,450.00 14,946,008.64
b Pek. Bekisting sloof M2 65.60 178,920.00 11,737,152.00
c Pek. Stamp beton K 175 M3 4.92 1,010,040.00 4,969,396.80
IV PEKERJAAN PLESTERAN
1 Pek. Plesteran
a Pek. Plesteran Dinding 1 : 2 M2 123.00 74,150.00 9,120,450.00
b Pek. Plesteran Dinding 1:4 M2 480.12 69,020.00 33,137,882.40
c Pek. Acian Dinding M2 603.12 42,420.00 25,584,350.40
d Pek. Acian Beton M2 123.20 42,420.00 5,226,144.00
e Pas. Dinding Keramik 20x25 cm km/wc t= 1,5 m M2 36.00 #REF! #REF!
JUMLAH #REF!
V PEKERJAAN PLAFOND
1 Pek. Plafond
a Pas. Rangka Plafond Kayu M2 575.00 #REF! #REF!
b Cat Menie Rangka Plafond M2 267.60 42,413.97 11,349,977.03
c Pas. Plafond Triplek 4 mm M2 575.00 61,130.00 35,149,750.00
d Pas. Les Profil 5x5 cm M1 324.00 15,000.00 4,860,000.00
JUMLAH #REF!
VI PEKERJAAN LANTAI
1 Pek. Lantai
a Timbunan Tanah Bawah Lantai M3 113.40 136,260.00 15,451,884.00
b Urugan Pasir M3 37.80 #REF! #REF!
c Cor Lantai Beton K 175 tbl 5 cm M3 18.90 1,010,040.00 19,089,756.00
d Pas. Lantai Keramik 40x40 cm M2 294.00 687,870.00 202,233,780.00
e Pas. Lantai Keramik 40x40 cm unpolish Teras M2 162.00 687,870.00 111,434,940.00
e Pas. Lantai Keramik 20x20 cm km/wc M2 9.99 #REF! #REF!
JUMLAH #REF!
2 Pengantung/Pengunci
a Pas. Kunci Pintu 2 x Slagh Bh 8.00 #REF! #REF!
b Pas. Engsel Pintu 4" Bh 30.00 #REF! #REF!
c Pas. Engsel Jendela 3" Bh 40.00 #REF! #REF!
d Pas. Gerendel Jendela Bh 40.00 #REF! #REF!
e Pas. Kait Angin Jendela Bh 40.00 #REF! #REF!
f Pas. Tangan-tangan Jendela Bh 20.00 #REF! #REF!
JUMLAH #REF!
HARGA JUMLAH JUMLAH
NO URAIAN PEKERJAAN STN VOLUME SATUAN HARGA STN TOTAL
(Rp) (Rp) (Rp)
2 Pek. Sanitasi
a Pas. Pipa Air Kotor PVC dia 3" AW + Acc M1 25.00 #REF! #REF!
b Pas. Pipa Air Kotor PVC dia 4" AW + Acc M1 25.00 #REF! #REF!
c Pas. Pipa Air Bersih PVC 3/4" + Acc M1 25.00 #REF! #REF!
d Pas. Kloset Jongkok Bh 4.00 #REF! #REF!
e Pas. Kran Air Bh 4.00 #REF! #REF!
f Pas. Flour Drain Bh 4.00 #REF! #REF!
g Pas. Bak Air Fiber Bh 2.00 435,000.00 870,000.00
JUMLAH #REF!
RUANG LABOR
I PEKERJAAN PONDASI
1 Pek. Pondasi
a Pembersihan Lapangan M3 150.00 18,000.00 2,700,000.00
b Pas. Papan Bouplank M1 24.00 70,330.00 1,687,920.00
c Galian Tanah Pondasi M3 37.63 82,920.00 3,120,445.44
d Pas. Aanstampang Bt. Kali M3 9.41 463,250.00 4,358,256.00
e Pas. Pondasi Bt. Kali 1:4 M3 14.99 844,940.00 12,669,030.36
f Urugan Tanah Kembali M3 9.41 38,750.00 364,560.00
JUMLAH 24,900,211.80
II PEKERJAAN BETON/DINDING
1 Pek. Sloof Praktis 15/20
a Pek. Pembesian Kg 264.57 15,450.00 4,087,550.88
b Pek. Bekisting sloof M2 23.52 178,920.00 4,208,198.40
c Pek. Stamp beton K 175 M3 1.76 1,010,040.00 1,781,710.56
IV PEKERJAAN PLESTERAN
1 Pek. Plesteran
a Pek. Plesteran Dinding 1 : 2 M2 50.16 74,150.00 3,719,586.45
b Pek. Plesteran Dinding 1:4 M2 214.40 69,020.00 14,797,749.96
c Pek. Acian Dinding M2 264.56 42,420.00 11,222,677.62
d Pek. Acian Beton M2 42.00 42,420.00 1,781,640.00
JUMLAH 31,521,654.03
V PEKERJAAN PLAFOND
1 Pek. Plafond
a Pas. Rangka Plafond Kayu M2 216.00 #REF! #REF!
b Cat Menie Rangka Plafond M2 68.40 42,413.97 2,901,115.21
c Pas. Plafond Triplek 4 mm M2 216.00 61,130.00 13,204,080.00
d Pas. Les Profil 5x5 cm M1 128.00 15,000.00 1,920,000.00
JUMLAH #REF!
VI PEKERJAAN LANTAI
1 Pek. Lantai
a Timbunan Tanah Bawah Lantai M3 30.00 136,260.00 4,087,800.00
b Urugan Pasir M3 15.00 #REF! #REF!
c Cor Lantai Beton K 175 tbl 5 cm M3 7.50 1,010,040.00 7,575,300.00
d Pas. Lantai Keramik 40x40 cm M2 120.00 687,870.00 82,544,400.00
e Pas. Lantai Keramik 40x40 cm meja beton M2 5.60 #REF! #REF!
f Pas. Lantai Keramik 40x40 cm unpolish Teras M2 30.00 687,870.00 20,636,100.00
JUMLAH #REF!
2 Pengantung/Pengunci
a Pas. Kunci Pintu 2 x Slagh Bh 3.00 #REF! #REF!
b Pas. Engsel Pintu 4" Bh 12.00 #REF! #REF!
c Pas. Engsel Jendela 3" Bh 36.00 #REF! #REF!
d Pas. Gerendel Jendela Bh 36.00 #REF! #REF!
e Pas. Kait Angin Jendela Bh 36.00 #REF! #REF!
f Pas. Tangan-tangan Jendela Bh 18.00 #REF! #REF!
HARGA JUMLAH JUMLAH
NO URAIAN PEKERJAAN STN VOLUME SATUAN HARGA STN TOTAL
(Rp) (Rp) (Rp)
JUMLAH #REF!
M I N G G U K E
NO URAIAN PEKERJAAN Bobot 1 2 3 4 5 6 7 8 Ket.
(%)
REN- JUMLAH BOBOT PER MINGGU #REF! 5.00 5.76 5.42 5.42 12.57 41.65 #REF! #REF!
CANA JUMLAH BOBOT AKUMULATIF 0.00 5.00 10.76 16.18 21.61 34.18 75.83 #REF! #REF!
EDI SURYA, ST
Direktur