VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
2 WIREHOUSE
2.3 Pekerjaan Architech
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 127.40 x 0.62 = 314.17
Begel [ 729.00 x 8.00 ] x 0.56 x 0.39 = 161.08 = 475.24 475.24 Kg
Pembesian
Tul- utama [ 6.00 x 10.00 ] x 176.00 x 0.62 = 651.02
Begel [ 1,006.71 x 8.00 ] x 0.56 x 0.39 = 222.44
Begel [ 1,006.71 x 10.00 ] x 0.20 x 0.62 = 124.13 = 997.59 997.59 Kg
Finish lantai gudang flat Flowfresh MF T=3 mm Ex Flow Creed (type 11) Aplicator bebas
D. Super Flat Flowcreed u/ Parkir Forklif
= 7.58 x 11.58 = 87.68
= 87.68 = 87.68 87.68 M2
Retaining Wall
Dalam
As A = 5.65 x 0.65 x 1.00 x 7.00 = 25.71
= 25.71
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
Luar
As-A = 5.65 x 0.90 x 1.00 x 7.00 = 35.60
As-1 = 5.35 x 0.90 x 1.00 x 16.00 = 77.04
= 0.45 x 0.90 x 1.00 x 1.00 = 0.41
As-16 = 107.10 x 0.90 x 1.00 x 1.00 = 96.39
= 209.43
Total Retaining Wall = 25.71 + 209.43 = 235.14
B. Pekerjaan Protector Type 2, Detail Lihat Gambar (''Provesional Sum'') = 1.00 1.00 Unit
C. Pekerjaan Protector Type 2A, Detail Lihat Gambar (''Provesional Sum'') = 1.00 1.00 Unit
D. Pekerjaan Protector Type 3, Detail Lihat Gambar (''Provesional Sum'') = 1.00 1.00 Unit
E. Pekerjaan Protector Type 4, Detail Lihat Gambar (''Provesional Sum'') = 13.00 13.00 Unit
F. Pekerjaan Protector Type 5, Detail Lihat Gambar (''Provesional Sum'') = 17.00 17.00 Unit
E. Sky light t:1,2mm ex Intec, warna putih susu. (lebar efektif 633.3 mm - 3 puncak 2 lembah)
= 923.93 = 923.93 923.93 M'
Pekerjaan Insulation, termasuk material, jasa pemasangan dan alat bantu.
F. Insulation Al- Bubble - AL T; 4mm ex Zeltech type ZT-01B
Luas Atap
Jack Roof = 5.05 x 68.75 x 1.00 x 2.00 = 694.38
Gudang +1290 As (A-C)&(O-Q) = 33.45 x 11.40 x 1.00 x 2.00 = 762.66
= 33.45 x 11.40 x 1.00 x 2.00 = 762.66
As (C-O) = 27.85 x 62.70 x 1.00 x 1.00 = 1,746.20
= 28.35 x 62.70 x 1.00 x 1.00 = 1,777.55
Gudang +800 = 18.15 x 91.55 x 1.00 x 1.00 = 1,661.63
= 7,405.07
Atap Skyligt
Jack Roof = 5.05 x 0.63 x 12.00 x 2.00 = 76.72
Gudang +1290 As (A-C)&(O-Q) = 33.45 x 0.63 x 2.00 x 2.00 = 84.70
= 33.45 x 0.63 x 2.00 x 2.00 = 84.70
As (C-O) = 27.85 x 0.63 x 12.00 x 1.00 = 211.55
= 28.35 x 0.63 x 12.00 x 1.00 = 215.35
Gudang +800 = 18.15 x 0.63 x 16.00 x 1.00 = 183.82
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
= 856.83
Total Luas Atap = 7,405.07 - 856.83 = 6,548.24 = 6,548.24 6,548.24 M2
B. List Plafond Model Curve Material Gypsum. Include perapian dan alat bantu.(Ruang Obat)
Plafon = 38.95 x 1.00 x 1.00 = 38.95 = 38.95 38.95 M'
Corner Guard Pintu Rolling Door, pekerjaan include pemasangan, material, alat bantu dan material bantu
C. Besi Siku 50.50.3,8 Termasuk Pengecatan Warna Kuning Dan Hitam
[ 1.50 x 60.00 ] x 1.00 = 90.00 = 90.00 90.00 M'
3 OFFICE
3.5 Pekerjaan Arsitek Lantai I
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 195.26 x 0.62 = 481.52
Begel [ 1,116.79 x 8.00 ] x 26.34 x 0.39 = 11,606.43 = 12,087.95 12,087.95 Kg
Pembesian
Tul- utama [ 5.00 x 8.00 ] x 19.90 x 0.39 = 39.26
Begel [ 200.00 x 8.00 ] x 0.63 x 0.39 = 49.71 = 88.97 88.97 Kg
Pekerjaan Homogenius tile 600x600mm Type Salsa Crystal Black , include material, adukan dan tenaga kerja.
D. Homogenius tile Area Entrance Depan
= 11.18 = 11.18 11.18 M2
E. Homogenius tile Area Tangga Entrance Depan + Stopnozing
[ 6.40 x 0.48 ] x 5.00 = 15.36 = 15.36 15.36 M2
Pekerjaan Keramik 400x400mm (polished) Ex.Ikad , include material, adukan dan tenaga kerja.
F. Keramik Area Lobby Samping + Tangga
= 13.98 + 4.32 = 18.30 18.30 M2
Pekerjaan Keramik 400x400mm (Unpolished) Ex.Ikad , include material, adukan dan tenaga kerja.
I. Keramik Area Toilet, Pantry dan Janitor
Tempat Wudhuk[ 4.85 x 1.35 ] x 1.00 = 6.55
Pantry [ 2.50 x 2.35 ] x 1.00 = 5.88
[ 3.45 x 1.35 ] x 1.00 = 4.66
Janitor [ 1.85 x 2.35 ] x 1.00 = 4.35
Toilet [ 3.85 x 1.23 ] x 1.00 = 4.72
[ 3.85 x 1.13 ] x 1.00 = 4.33
[ 2.50 x 2.35 ] x 2.00 = 11.75
[ 1.85 x 1.10 ] x 4.00 = 8.14
[ 3.45 x 1.35 ] x 1.00 = 4.66
[ 2.20 x 1.73 ] x 2.00 = 7.57
[ 1.35 x 1.73 ] x 3.00 = 6.99
= 69.58 = 69.58 69.58 M2
Lantai finish Floor hardener, include material, tenaga kerja dan alat bantu
J. Finishing floor hardener area G. MKT, G.GA, G.COKELAT, R. ATK Dan R. Rokok
= 78.69 + 82.51 + 147.99 + 28.64 + 71.48 = 409.31 = 409.31 409.31 M2
= 89.40
Balok Praktis rb [ 195.26 x 0.20 ] x 2.00 = 78.10
Kanopy Beton [ 0.70 x 19.90 ] x 1.00 = 13.93
Reatining wall [ 5.60 x 0.70 ] x 13.00 = 50.96
[ 4.60 x 0.70 ] x 3.00 = 9.66
= 152.65
B. Acian Plesteran
As-T [ 5.60 x 3.55 ] x 13.00 = 258.44 T= 3.55
[ 4.75 x 3.93 ] x 1.00 = 18.64 T= 3.93
[ 3.15 x 1.00 ] x 1.00 = 3.15 T= 3.55
[ 4.50 x 2.75 ] x 1.00 = 12.37 T= 2.75
[ 2.98 x 2.75 ] x 1.00 = 8.18 T= 2.75
[ 5.85 x 3.85 ] x 1.00 = 22.52 T= 3.85
[ 19.38 x 3.85 ] x 1.00 = 74.59 T= 3.85
As-S [ 3.40 x 3.85 ] x 1.00 = 13.09 T= 3.85
[ 5.60 x 3.85 ] x 8.00 = 172.48 T= 3.85
[ 2.80 x 3.85 ] x 1.00 = 10.78 T= 3.85
[ 10.35 x 3.85 ] x 1.00 = 39.85 T= 3.85
[ 3.00 x 3.85 ] x 1.00 = 11.55 T= 3.85
[ 4.65 x 3.85 ] x 1.00 = 17.90 T= 3.85
[ 2.00 x 2.75 ] x 1.00 = 5.50 T= 2.75
As-R [ 2.80 x 3.85 ] x 1.00 = 10.78 T= 3.85
[ 5.60 x 3.85 ] x 2.00 = 43.12 T= 3.85
[ 4.30 x 3.85 ] x 2.00 = 33.11 T= 3.85
As-Q' [ 5.60 x 3.55 ] x 14.00 = 278.32 T= 3.55
Pekerjaan Pengecatan
F. Pengecatan dinding Exterior Ex. Propan
Dinding = 3,257.48 x 0.40 = 1,302.99
= 1,302.99 = 1,302.99 1,302.99 M2
G. Pengecatan dinding Interior Ex. Propan
Dinding = 3,257.48 x 0.60 = 1,954.49
= 1,954.49 = 1,954.49 1,954.49 M2
H. Pekerjaan Naad dan Perapian Dinding Atas Keramik Termasuk Plin Dinding
[ 9.40 x 1.00 ] - 2.91 = 6.49 x 1.00 = 6.49
[ 7.45 x 1.00 ] - 2.91 = 4.54 x 1.00 = 4.54
[ 6.15 x 1.00 ] - 0.69 = 5.46 x 2.00 = 10.92
[ 5.90 x 1.00 ] - 0.69 = 5.21 x 2.00 = 10.42
[ 9.78 x 1.60 ] - - = 15.64 x 1.00 = 15.64
[ 8.65 x 1.00 ] - 1.10 = 7.55 x 1.00 = 7.55
[ 9.60 x 1.00 ] - 2.91 = 6.69 x 1.00 = 6.69
[ 7.45 x 1.00 ] - 0.84 = 6.61 x 1.00 = 6.61
[ 7.84 x 1.00 ] - 2.22 = 5.62 x 1.00 = 5.62
[ 7.46 x 1.00 ] - 2.22 = 5.24 x 1.00 = 5.24
[ 5.70 x 1.00 ] - 0.69 = 5.01 x 2.00 = 10.02
[ 7.55 x 1.00 ] - 0.69 = 6.86 x 1.00 = 6.86
[ 2.50 x 1.00 ] = 2.50 x 1.00 = 2.50
[ 2.65 x 1.00 ] = 2.65 x 1.00 = 2.65
Plin Dinidng = 362.33
= 464.07 = 464.07 464.07 M'
C Pek. Partisi gypsum Dua Sisi H: 1.200 MM, include rangka dan finishing cat
[ 1.53 x 1.20 ] x 1.00 = 1.83
[ 0.30 x 1.20 ] x 2.00 = 0.72
[ 4.40 x 1.20 ] x 1.00 = 5.28
[ 4.60 x 1.20 ] x 1.00 = 5.52
= 13.35 x 2.00 = 26.70 = 26.70 26.70 M2
D. Pek. Partisi Ruang Lobby Multiplek Fin. HPL dan Kalsi Part T=8 MM Fin.Cat Castle Grey Propan
[ 5.85 x 2.70 ] x 1.00 = 15.80 = 15.80 15.80 M2
E. Plin Bawah Dinding Partisi Multiplek T=18 MM Uk. 18x100 MM, Fin. HPL
[ 24.00 x 1.00 ] x 1.00 = 24.00
[ 4.60 x 1.00 ] x 1.00 = 4.60
[ 3.00 x 1.00 ] x 6.00 = 18.00
[ 4.40 x 1.00 ] x 2.00 = 8.80
[ 5.20 x 1.00 ] x 1.00 = 5.20
[ 6.13 x 1.00 ] x 1.00 = 6.13
[ 4.60 x 1.00 ] x 2.00 = 9.20
[ 10.13 x 1.00 ] x 1.00 = 10.13
[ 3.53 x 1.00 ] x 2.00 = 7.05
[ 5.60 x 1.00 ] x 1.00 = 5.60
[ 5.00 x 1.00 ] x 1.00 = 5.00
= 103.70 - 27.37 = 76.33 x 2.00 = 152.66 152.66 M'
F. Profil U Dinding Partisi Multiplek T=18 MM Uk. 5 x10 Cm, Fin. HPL
[ 1.53 x 1.00 ] x 1.00 = 1.53
[ 0.30 x 1.00 ] x 2.00 = 0.60
[ 4.40 x 1.00 ] x 1.00 = 4.40
[ 4.60 x 1.00 ] x 1.00 = 4.60
= 11.13 x 1.00 = 11.13 = 11.13 11.13 M'
Pekerjaan Pintu Rolling Door, Material dan pemasangan Supplay By Owner. Perapian openingan include kontraktor
J. Pintu Rolling Door Type RD1 = 1.00 1.00 Unit
Pekerjaan Pintu & Jendela Kawat Harmonika, detail lihat digambar. Pekerjaan include accesiries.
O. Jendela Kawat harmonika Type JK1 = 2.00 2.00 Unit
P. Jendela Kawat harmonika Type JK4 = 1.00 1.00 Unit
Q. Jendela Kawat harmonika Type JK5 = 1.00 1.00 Unit
R. Jendela Kawat harmonika Type JK6 = 1.00 1.00 Unit
S. Jendela Kawat harmonika Type JK7 = 1.00 1.00 Unit
Pekerjaan Pengecatan
F. Pekerjaan cat plafond gypsum board & beton exposed dibawah tangga
Pekerjaan cat include material, tenaga kerja, alat bantu dan perapian)
Plafond Gipsum = 299.16
Plafon Expose = 607.96
Bawah Tangga = 26.79
= 933.91 = 933.91 933.91 M2
C. Pek. Planter Box + Batu Alam Dinding, (include pekerjaan struktural planter box dan Finishing) = 2.00 2.00 Ls
F. Dudukan Closet Jongkok, Pas. Bata H: 200mm, termasuk alat bantu dan perapian.
Toilet 1 [ 0.75 x 1.10 ] = 0.83 x 2.00 = 1.65
Toilet 2 [ 0.75 x 1.35 ] = 1.01 x 1.00 = 1.01
= 2.66 = 2.66 2.66 M2
Corner Guard Pintu Rolling Door RD1, pekerjaan include pemasangan, material, alat bantu dan material bantu
G. Besi Siku 50.50.3.8 Termasuk Pengecatan (dua warna Kuning dan Hitam)
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
[ 1.50 x 2.00 ] x 1.00 = 3.00 = 3.00 3.00 M'
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 297.53 x 0.62 = 733.70
Begel [ 1,701.14 x 8.00 ] x 0.60 x 0.39 = 402.72 = 1,136.42 1,136.42 Kg
Pembesian
Tul- utama [ 5.00 x 8.00 ] x 50.10 x 0.39 = 98.84
Begel [ 502.00 x 8.00 ] x 0.63 x 0.39 = 124.78 = 223.62 223.62 Kg
Pekerjaan Keramik 400x400mm (Unpolished) Ex.Ikad , include material, adukan dan tenaga kerja.
C. Keramik Area Toilet, Pantry dan Janitor
Tempat Wudhuk[ 4.85 x 1.35 ] x 1.00 = 6.55
Pantry [ 2.85 x 2.85 ] x 1.00 = 8.12
Janitor [ 2.85 x 1.93 ] x 1.00 = 5.49
Toilet 3 [ 2.85 x 1.80 ] x 2.00 = 10.26
[ 1.70 x 1.05 ] x 2.00 = 3.57
[ 1.35 x 1.93 ] x 4.00 = 10.40
Toilet 4 [ 2.35 x 1.80 ] x 1.00 = 4.23
[ 2.35 x 1.05 ] x 1.00 = 2.47
[ 2.98 x 1.80 ] x 1.00 = 5.36
[ 1.70 x 1.05 ] x 1.00 = 1.79
[ 1.35 x 2.28 ] x 3.00 = 9.21
[ 1.35 x 1.78 ] x 1.00 = 2.40
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
= 69.83 = 69.83 69.83 M2
D. Screed Waterproofing,
Tempat Wudhuk [ 5.15 x 1.65 ] x 1.00 = 8.50
Pantry [ 3.15 x 3.15 ] x 1.00 = 9.92
Janitor [ 3.15 x 2.23 ] x 1.00 = 7.01
Toilet 3 [ 3.15 x 2.10 ] x 2.00 = 13.23
[ 2.00 x 1.35 ] x 2.00 = 5.40
[ 1.65 x 2.23 ] x 4.00 = 14.69
Toilet 4 [ 2.65 x 2.10 ] x 1.00 = 5.57
[ 2.65 x 1.35 ] x 1.00 = 3.58
[ 3.28 x 2.10 ] x 1.00 = 6.88
[ 2.00 x 1.35 ] x 1.00 = 2.70
[ 1.65 x 2.57 ] x 3.00 = 12.75
[ 1.65 x 2.07 ] x 1.00 = 3.42
= 93.63 = 93.63 93.63 M2
E. Waterproofing Liquid Membrant Include Overlap ke Dinding 30 Cm
= 93.63 93.63 M2
Plesteran 1 : 4
= 697.84 x 2.00 = 1,395.69 - 250.00 = 1,145.69
Total Plesteran 1 : 4
Plesteran Beton Kolom, Sloof, Balok dan Plat Kano = 344.42
Plesteran 1 : 4 = 1,145.69
Plesteran 1 : 4 Ruang Shaft = 22.24
= 1,167.93 = 1,167.93 1,167.93 M2
B. Acian Plesteran
= 1,167.93 = 1,167.93 1,167.93 M2
C. Plesteran 1:4, Opening Kusen + Acian
P1 [ 1.20 x 1.00 ] x 1.00 = 1.20 x 1.00 Bh = 1.20
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 1.00 Bh = 4.29
P2 [ 0.99 x 1.00 ] x 1.00 = 0.99 x 1.00 Bh = 0.99
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 1.00 Bh = 4.29
P3 [ 0.89 x 1.00 ] x 1.00 = 0.89 x 1.00 Bh = 0.89
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 1.00 Bh = 4.29
P4 [ 0.84 x 1.00 ] x 1.00 = 0.84 x 5.00 Bh = 4.20
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 5.00 Bh = 21.45
P5 [ 0.69 x 1.00 ] x 1.00 = 0.69 x 8.00 Bh = 5.52
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 8.00 Bh = 34.32
PS [ 0.69 x 2.00 ] x 1.00 = 1.38 x 2.00 Bh = 2.76
[ 1.19 x 2.00 ] x 1.00 = 2.38 x 2.00 Bh = 4.76
J2K [ 1.34 x 2.00 ] x 1.00 = 2.67 x 27.00 Bh = 72.09
[ 1.19 x 2.00 ] x 1.00 = 2.38 x 27.00 Bh = 64.26
J2K' [ 1.14 x 2.00 ] x 1.00 = 2.27 x 1.00 Bh = 2.27
[ 1.19 x 2.00 ] x 1.00 = 2.38 x 1.00 Bh = 2.38
J5K [ 1.34 x 2.00 ] x 1.00 = 2.67 x 28.00 Bh = 74.76
[ 1.19 x 2.00 ] x 1.00 = 2.38 x 28.00 Bh = 66.64
BV1 [ 0.69 x 2.00 ] x 1.00 = 1.38 x 10.00 Bh = 13.80
[ 0.49 x 2.00 ] x 1.00 = 0.98 x 10.00 Bh = 9.80
BV2 [ 1.34 x 2.00 ] x 1.00 = 2.67 x 1.00 Bh = 2.67
[ 0.49 x 2.00 ] x 1.00 = 0.98 x 1.00 Bh = 0.98
= 398.61 = 398.61 398.61 M'
Pekerjaan Pengecatan
F. Pengecatan dinding Exterior Ex. Propan
Dinding = 1,167.93 x 0.40 = 467.17
= 467.17 = 467.17 467.17 M2
G. Pengecatan dinding Interior Ex. Propan
Dinding = 1,167.93 x 0.60 = 700.76
= 700.76 = 700.76 700.76 M2
Pintu dan Jendela alumunium Pekerjaan pintu jendela, detail accessories Lihat Di DWS
G. Pintu Dan Jendela Type PJ5 = 1.00 1.00 Unit
Pekerjaan Pengecatan
C. Pekerjaan cat plafond gypsum board
Pekerjaan cat include material, tenaga kerja, alat bantu dan perapian)
Plafond Gipsum = 206.20
= 206.20 = 206.20 206.20 M2
D. Tangga maintenance include pekerjaan pipa baja dia 5'' + siku 50.50.5, chekered plate T: 5mm, = 1.00 1.00 Unit
Reilling Pipa 1"pengecatan, alat bantu dan material bantu.
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 21.65 x 0.62 = 53.39
Begel [ 124.71 x 8.00 ] x 0.60 x 0.39 = 29.52 = 82.91 82.91 Kg
Total Plesteran
Prapet Beton Dak = 285.67
Plesteran 1 : 4 = 571.34
= 857.02 = 857.02 857.02 M2
Pekerjaan Pengecatan
D. Pengecatan dinding Exterior Ex. Propan
Dinding = 857.02 x 1.00 = 857.02
= 857.02 = 857.02 857.02 M2
4 SUPPORTING BUILDING
4.1 POS JAGA
Pembesian
Tul- utama [ 4.00 x 12.00 ] x 8.00 x 0.89 = 28.41
Begel [ 46.71 x 8.00 ] x 0.74 x 0.39 = 13.64 = 42.05 42.05 Kg
B. Pek. Kolom Praktis K1 Uk. 200 x 200 mm, Besi 6 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Beton
[ 0.20 x 0.20 ] x 3.10 = 0.12 x 4.00 = 0.50
= 0.50 0.50 M3
Pembesian
Tul- utama [ 6.00 x 12.00 ] x 12.40 x 0.89 = 66.05
Begel [ 71.86 x 8.00 ] x 0.74 x 0.39 = 20.98 = 87.03 87.03 Kg
C. Pek. Balok Beton Type RB uk. 15 x 25 cm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 12.00 ] x 8.00 x 0.89 = 28.41
Begel [ 46.71 x 8.00 ] x 0.74 x 0.39 = 13.64 = 42.05 42.05 Kg
D. Pek. Balok Beton Type BL uk. 11 x 15 cm,Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 8.00 x 0.62 = 19.73
Begel [ 46.71 x 8.00 ] x 0.46 x 0.39 = 8.48 = 28.21 28.21 Kg
Melintang
Tul- utama [ 3.95 x 20.67 ] x 2.00 = 163.27
[ 2.95 x 27.33 ] x 2.00 = 161.27
= 324.53 x 0.62 = 200.07 = 200.07 200.07 Kg
Melintang
Tul- utama [ 13.80 x 3.33 ] x 1.00 = 46.00
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
[ 0.45 x 92.00 ] x 1.00 = 41.40
= 87.40 x 0.62 = 53.88 = 53.88 53.88 Kg
Pekerjaan pasangan bata ringan dan bata merah alat bantu, perapian dan tenaga kerja.
A. Pasangan Batu Bata 1 : 4
Luas Bidang Kozen Bata
PJ1 [ 0.79 x 2.15 ] x 1.00 = 1.69 x 1.00 Bh = 1.69
[ 0.55 x 1.19 ] x 1.00 = 0.65 x 1.00 Bh = 0.65
J1K [ 1.54 x 1.19 ] x 1.00 = 1.83 x 2.00 Bh = 3.65
J2K [ 1.34 x 1.19 ] x 1.00 = 1.59 x 1.00 Bh = 1.59
= 7.59
Luas Pas. Bata
[ 2.35 x 2.60 ] x 2.00 = 12.22 T= 2.60
[ 1.35 x 2.60 ] x 2.00 = 7.02 T= 2.60
C. Acian Plesteran
= 39.95 = 39.95 39.95 M2
D. Plesteran 1:4, Opening Kusen + Acian
PJ1 [ 0.79 x 1.00 ] x 1.00 = 0.79 x 1.00 Bh = 0.79
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 1.00 Bh = 4.29
[ 0.55 x 2.00 ] x 1.00 = 1.09 x 1.00 Bh = 1.09
J1K [ 1.54 x 2.00 ] x 1.00 = 3.07 x 2.00 Bh = 6.14
[ 1.19 x 2.00 ] x 1.00 = 2.38 x 2.00 Bh = 4.76
J2K [ 1.34 x 2.00 ] x 1.00 = 2.67 x 1.00 Bh = 2.67
[ 1.19 x 2.00 ] x 1.00 = 2.38 x 1.00 Bh = 2.38
= 22.12 = 22.12 22.12 M'
Pekerjaan Pengecatan
G. Pengecatan dinding Exterior Ex. Propan
Dinding = 39.95 x 0.60 = 23.97
= 23.97 = 23.97 23.97 M2
H. Pengecatan dinding Interior Ex. Propan
Dinding = 39.95 x 0.40 = 15.98
= 15.98 = 15.98 15.98 M2
Pembesian
Tul- utama [ 4.00 x 12.00 ] x 42.00 x 0.89 = 149.14
Begel [ 241.00 x 8.00 ] x 0.74 x 0.39 = 70.37 = 219.51 219.51 Kg
B. Pek. Kolom Praktis Kp Uk. 130 x 130 mm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Beton
[ 0.13 x 0.13 ] x 3.25 = 0.05 x 19.00 = 1.04
= 1.04 1.04 M3
Pembesian
Tul- utama [ 4.00 x 12.00 ] x 61.75 x 0.89 = 219.28
Begel [ 353.86 x 8.00 ] x 0.46 x 0.39 = 64.22 = 283.50 283.50 Kg
C. Pek. Balok Beton Type rb uk. 13 x 20 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 42.00 x 0.62 = 103.57
Begel [ 241.00 x 8.00 ] x 0.60 x 0.39 = 57.05 = 160.63 160.63 Kg
D. Pek. Balok Beton Type BL uk. 11 x 15 cm,Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 42.00 x 0.62 = 103.57
Begel [ 241.00 x 8.00 ] x 0.46 x 0.39 = 43.74 = 147.31 147.31 Kg
Pekerjaan pasangan bata ringan dan bata merah alat bantu, perapian dan tenaga kerja.
A. Pasangan Batu Bata 1 : 4
Luas Bidang Kozen Bata
P1 [ 0.99 x 2.15 ] x 1.00 = 2.12 x 1.00 Bh = 2.12
P1' [ 0.99 x 2.15 ] x 1.00 = 2.12 x 1.00 Bh = 2.12
P3 [ 0.69 x 2.15 ] x 1.00 = 1.48 x 1.00 Bh = 1.48
J2K [ 1.49 x 1.19 ] x 1.00 = 1.77 x 2.00 Bh = 3.53
J3K [ 2.24 x 1.19 ] x 1.00 = 2.66 x 1.00 Bh = 2.66
BV1 [ 0.79 x 0.49 ] x 1.00 = 0.39 x 1.00 Bh = 0.39
BV2 [ 1.34 x 0.49 ] x 1.00 = 0.65 x 1.00 Bh = 0.65
KR4 [ 1.60 x 1.20 ] x 1.00 = 1.92 x 2.00 Bh = 3.84
KR5 [ 2.40 x 1.20 ] x 1.00 = 2.88 x 2.00 Bh = 5.76
Pintu Tanpa Kusen [ 1.85 x 2.20 ] x 1.00 = 4.07 x 1.00 Bh = 4.07
= 26.63
Luas Pas. Bata
[ 11.00 x 3.20 ] x 2.00 = 70.40 T= 3.20
[ 6.00 x 3.20 ] x 4.00 = 76.80 T= 3.20
[ 2.00 x 3.20 ] x 1.00 = 6.40 T= 3.55
C. Plesteran 1 : 4
= 126.97 x 2.00 = 253.94 - 11.42 = 242.52 = 242.52 242.52 M2
D. Acian Plesteran
= 242.52 = 242.52 242.52 M2
E. Plesteran 1:4, Opening Kusen + Acian
P1 [ 0.99 x 1.00 ] x 1.00 = 0.99 x 1.00 Bh = 0.99
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 1.00 Bh = 4.29
P1' [ 0.99 x 1.00 ] x 1.00 = 0.99 x 1.00 Bh = 0.99
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 1.00 Bh = 4.29
P3 [ 0.69 x 1.00 ] x 1.00 = 0.69 x 1.00 Bh = 0.69
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 1.00 Bh = 4.29
J2K [ 1.49 x 2.00 ] x 1.00 = 2.97 x 2.00 Bh = 5.94
[ 1.19 x 2.00 ] x 1.00 = 2.38 x 2.00 Bh = 4.76
J3K [ 2.24 x 2.00 ] x 1.00 = 4.47 x 1.00 Bh = 4.47
[ 1.19 x 2.00 ] x 1.00 = 2.38 x 1.00 Bh = 2.38
BV1 [ 0.79 x 2.00 ] x 1.00 = 1.58 x 1.00 Bh = 1.58
[ 0.49 x 2.00 ] x 1.00 = 0.98 x 1.00 Bh = 0.98
BV2 [ 1.34 x 2.00 ] x 1.00 = 2.67 x 1.00 Bh = 2.67
[ 0.49 x 2.00 ] x 1.00 = 0.98 x 1.00 Bh = 0.98
Pintu Tanpa Kusen [ 1.85 x 1.00 ] x 1.00 = 1.85 x 1.00 Bh = 1.85
[ 2.20 x 2.00 ] x 1.00 = 4.40 x 1.00 Bh = 4.40
= 45.55 = 45.55 45.55 M'
Pekerjaan Keramik 400x400mm (Unpolished) Ex.Ikad , include material, adukan dan tenaga kerja.
C. Keramik Area Toilet
Tioliet [ 1.85 x 1.35 ] x 1.00 = 2.50
= 2.50 x 1.00 = 2.50 = 2.50 2.50 M2
4.3 RUMAH GENSET, RUANG POMPA, RUANG TANGKI BAHAN BAKAR DAN FIRE WATER TANK
Pembesian
Tul- utama [ 6.00 x 16.00 ] x 38.00 x 1.58 = 359.84
Begel [ 305.00 x 8.00 ] x 1.14 x 0.39 = 137.19 = 497.03 497.03 Kg
B. Pek. Sloof Beton Type S2 uk. 150 x 250 mm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Beton [ 0.15 x 0.25 ] x 12.00 = 0.45 = 0.45 0.45 M3
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 12.00 x 0.62 = 29.59
Begel [ 69.57 x 8.00 ] x 0.74 x 0.39 = 20.31 = 49.91 49.91 Kg
D. Pek. Kolom Praktis Kp Uk. 130 x 130 mm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Beton
[ 0.13 x 0.13 ] x 3.05 = 0.05 x 3.00 = 0.15
[ 0.13 x 0.13 ] x 1.05 = 0.02 x 4.00 = 0.07
= 0.23 0.23 M3
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 13.35 x 0.62 = 32.92
Begel [ 77.29 x 8.00 ] x 0.46 x 0.39 = 14.03 = 46.95 46.95 Kg
E. Pek. Balok Beton Type RB1 uk. 20 x 40 cm , Besi 6 Ø16 (Tump) Besi 5 Ø16 (Lap), Sengkang Ø8-100 mm (Tump), Ø8-150 mm (Lap)
Beton [ 0.20 x 0.40 ] x 57.00 = 4.56 - 1.37 = 3.19 3.19 M3
Pembesian
Tul- utama [ 5.50 x 16.00 ] x 57.00 x 1.58 = 494.78
Begel [ 457.00 x 8.00 ] x 1.14 x 0.39 = 205.56 = 700.34 700.34 Kg
F. Pek. Balok Beton Type BL uk. 11 x 15 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Beton [ 0.11 x 0.15 ] x 29.90 = 0.49 = 0.49 0.49 M3
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 29.90 x 0.62 = 73.73
Begel [ 171.86 x 8.00 ] x 0.46 x 0.39 = 31.19 = 104.93 104.93 Kg
Melintang
Tul- utama [ 11.50 x 51.00 ] x 2.00 = 1,173.00
[ 7.50 x 77.67 ] x 2.00 = 1,165.00
= 2,338.00 x 0.62 = 1,441.38 = 1,441.38 1,441.38 Kg
Melintang
Tul- utama [ 38.00 x 4.00 ] x 1.00 = 152.00
[ 0.55 x 253.33 ] x 1.00 = 139.33
= 291.33 x 0.62 = 179.61 = 179.61 179.61 Kg
K. Pek. Rabat Beton K-175, Lantai Genset Dan Rumah Pompa T=10 Cm
Rumah Genset [ 5.85 x 5.85 ] x 0.10 = 3.42 - 0.34 = 3.09
[ 1.60 x 9.10 ] x 0.10 = 1.46 x 1.00 = 1.46
Rumah Pompa [ 3.85 x 5.85 ] x 0.10 = 2.25 x 1.00 = 2.25 = 6.79 6.79 M3
M. Pek. Beton Dinding Fire Water Tank T=25 Cm & T=20 Cm, Besi Ø13-15 (vertikal), Besi Ø10-15 (Horizontal)
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
Beton
Dinding T=25 Cm [ 6.20 x 2.85 ] x 0.25 x 1.00 = 4.42 x 2.00 = 8.84
[ 5.45 x 2.85 ] x 0.25 x 1.00 = 3.88 x 2.00 = 7.77
Dinding T=20 Cm [ 5.45 x 2.85 ] x 0.20 x 1.00 = 3.11 x 1.00 = 3.11
Sudut T=25 Cm [ 5.45 x 0.23 ] x 0.46 x 1.00 = 0.57 x 4.00 = 2.30
[ 5.70 x 0.23 ] x 0.46 x 1.00 = 0.60 x 4.00 = 2.40
Sudut T=25 Cm [ 5.45 x 0.10 ] x 0.20 x 1.00 = 0.11 x 4.00 = 0.44
= 24.84 = 24.84 24.84 M3
Pembesian
Vertikal T=25 [ 40.00 x 13.00 ] x 7.00 x 1.04 = 291.73 x 1.00 = 291.73
[ 42.00 x 13.00 ] x 7.00 x 1.04 = 306.31 x 1.00 = 306.31
Melintang
Tul- utama [ 45.00 x 5.95 ] x 2.00 = 535.50
[ 41.00 x 6.55 ] x 2.00 = 537.10
= 1,072.60 x 1.04 = 1,117.53 = 1,117.53 1,117.53 Kg
C. Plesteran 1 : 4
Plesteran Beton
Kolom [ 1.05 x 42.35 ] x 1.00 = 44.47
Balok [ 0.85 x 57.00 ] x 1.00 = 48.45
Listpalnk [ 0.90 x 38.00 ] x 1.00 = 34.20
Pekerjaan Pengecatan
G. Pengecatan dinding Exterior Ex. Propan
Dinding = 354.28 x 0.40 = 141.71
= 141.71 = 141.71 141.71 M2
H. Pengecatan dinding Interior Ex. Propan
Dinding = 354.28 x 0.60 = 212.57
= 212.57 = 212.57 212.57 M2
4.3.4 Pekerjaan Atap
Pekerjaan atap, termasuk biaya mob de mobilisasi alat bantu, material dan jasa pemasangan.
A. Pek. Tiang Kuda-Kuda Besi Pipa Dia-3" T=3 MMFin. Cat, Rg Tangki Bahan Bakar
Tiang = 1.73 x 2.00 x 1.00 = 3.46
= 1.48 x 1.00 x 1.00 = 1.48
= 1.23 x 2.00 x 1.00 = 2.46
Kuda-Kuda = 7.20 x 2.00 x 1.00 = 14.40
= 2.85 x 3.00 x 1.00 = 8.55
= 30.35 x 6.72 = 203.95 203.95 Kg
B. Pek. Gording CNP 150.65.20.3,2
= 3.38 x 7.00 x 1.00 = 23.63
= 7.20 x 1.00 x 1.00 = 7.20
= 30.83 x 7.52 = 231.70 231.70 Kg
C. Atap Zincalum 0,40 TCT Klip lock tanpa sambungan (roll on side)
= 7.38 x 3.53 x 1.00 = 26.00
= 26.00 = 26.00 26.00 M2
4.3.5 Pekerjaan Finishing Lantai
Finish lantai super flat Floor hardener 3kg/m2 ex Besroc (Type 10)
A. Beton Plat Area Rg. Genset Dan Rumah Pompa
Genset [ 5.85 x 5.85 ] x 1.00 = 34.22
Rumah Pompa [ 3.85 x 5.85 ] x 1.00 = 22.52
= 56.75 x 1.00 = 56.75 = 56.75 56.75 M2
4.3.6 Pekerjaan Arsitek Pintu dan Jendela
Pekerjaan Pintu Besi
A. Pintu Besi Type PB1 (1000x2100mm) = 1.00 1.00 Unit
B. Pintu Besi Type PB5 (2200x2100mm) = 1.00 1.00 Unit
C. Pintu Besi Type PB4 (800x1900mm) = 1.00 1.00 Unit
Pembesian
Tul- utama [ 4.00 x 12.00 ] x 102.00 x 0.89 = 362.21
Begel [ 583.86 x 8.00 ] x 0.74 x 0.39 = 170.47 = 532.68 532.68 Kg
B. Pek. Kolom Praktis Kp Uk. 130 x 130 mm,Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Beton
[ 0.13 x 0.13 ] x 3.25 = 0.05 x 40.00 = 2.20
= 2.20 2.20 M3
Pembesian
Tul- utama [ 4.00 x 12.00 ] x 130.00 x 0.89 = 461.64
Begel [ 743.86 x 8.00 ] x 0.46 x 0.39 = 135.01 = 596.64 596.64 Kg
C. Pek. Balok Beton Type rb uk. 13 x 20 cm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 102.00 x 0.62 = 251.53
Begel [ 583.86 x 8.00 ] x 0.60 x 0.39 = 138.22 = 389.75 389.75 Kg
D. Pek. Balok Beton Type BL uk. 11 x 15 cm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 54.30 x 0.62 = 133.90
Begel [ 311.29 x 8.00 ] x 0.46 x 0.39 = 56.50 = 190.40 190.40 Kg
Pekerjaan pasangan bata ringan dan bata merah alat bantu, perapian dan tenaga kerja.
A. Pasangan Batu Bata 1 : 4
Luas Bidang Kozen Bata
P1 [ 0.99 x 2.15 ] x 1.00 = 2.12 x 1.00 Bh = 2.12
P2 [ 0.84 x 2.15 ] x 1.00 = 1.80 x 1.00 Bh = 1.80
P3 [ 0.69 x 2.15 ] x 1.00 = 1.48 x 3.00 Bh = 4.44
J1K [ 1.34 x 1.19 ] x 1.00 = 1.59 x 1.00 Bh = 1.59
BV1 [ 0.79 x 0.49 ] x 1.00 = 0.39 x 4.00 Bh = 1.55
BV1' [ 0.79 x 0.49 ] x 1.00 = 0.39 x 1.00 Bh = 0.39
KR1 [ 1.35 x 1.80 ] x 1.00 = 2.43 x 8.00 Bh = 19.44
KR2 [ 1.60 x 0.60 ] x 1.00 = 0.96 x 3.00 Bh = 2.88
KR3 [ 0.20 x 0.30 ] x 1.00 = 0.06 x 10.00 Bh = 0.60
Pintu Tanpa Kusen [ 1.50 x 2.20 ] x 1.00 = 3.30 x 1.00 Bh = 3.30
[ 1.35 x 2.20 ] x 1.00 = 2.97 x 1.00 Bh = 2.97
[ 0.85 x 2.20 ] x 1.00 = 1.87 x 1.00 Bh = 1.87
[ 1.00 x 2.20 ] x 1.00 = 2.20 x 2.00 Bh = 4.40
= 47.35 = 47.35 47.35 M2
Luas Pas. Bata
[ 24.00 x 3.20 ] x 1.00 = 76.80 T= 3.20
[ 6.00 x 3.20 ] x 6.00 = 115.20 T= 3.20
[ 3.50 x 3.20 ] x 1.00 = 11.20 T= 3.55
[ 5.00 x 2.15 ] x 1.00 = 10.75 T= 2.15
[ 3.00 x 3.20 ] x 1.00 = 9.60 T= 3.20
[ 6.50 x 2.15 ] x 1.00 = 13.98 T= 2.15
D. Plesteran 1 : 4
= 190.18 x 2.00 = 380.35 - 81.99 = 298.36 = 298.36 298.36 M2
E. Acian Plesteran
= 298.36 = 298.36 298.36 M2
F. Plesteran 1:4, Opening Kusen + Acian
P1 [ 0.99 x 1.00 ] x 1.00 = 0.99 x 1.00 Bh = 0.99
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 1.00 Bh = 4.29
P2 [ 0.84 x 1.00 ] x 1.00 = 0.84 x 1.00 Bh = 0.84
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 1.00 Bh = 4.29
P3 [ 0.69 x 1.00 ] x 1.00 = 0.69 x 1.00 Bh = 0.69
[ 2.15 x 2.00 ] x 1.00 = 4.29 x 1.00 Bh = 4.29
J1K [ 1.34 x 2.00 ] x 1.00 = 2.67 x 1.00 Bh = 2.67
[ 1.19 x 2.00 ] x 1.00 = 2.38 x 1.00 Bh = 2.38
BV1 [ 0.79 x 2.00 ] x 1.00 = 1.58 x 4.00 Bh = 6.32
[ 0.49 x 2.00 ] x 1.00 = 0.98 x 4.00 Bh = 3.92
BV1' [ 0.79 x 2.00 ] x 1.00 = 1.58 x 1.00 Bh = 1.58
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
[ 0.49 x 2.00 ] x 1.00 = 0.98 x 1.00 Bh = 0.98
Pintu Tanpa Kusen [ 1.50 x 1.00 ] x 1.00 = 1.50 x 1.00 Bh = 1.50
[ 2.20 x 2.00 ] x 1.00 = 4.40 x 1.00 Bh = 4.40
[ 1.35 x 1.00 ] x 1.00 = 1.35 x 1.00 Bh = 1.35
[ 2.20 x 2.00 ] x 1.00 = 4.40 x 1.00 Bh = 4.40
[ 0.85 x 1.00 ] x 1.00 = 0.85 x 1.00 Bh = 0.85
[ 2.20 x 2.00 ] x 1.00 = 4.40 x 1.00 Bh = 4.40
[ 1.00 x 1.00 ] x 1.00 = 1.00 x 2.00 Bh = 2.00
[ 2.20 x 2.00 ] x 1.00 = 4.40 x 2.00 Bh = 8.80
= 60.94 = 60.94 60.94 M'
I. Pekerjaan Naad dan Pearapian Dinding Atas Keramik Termasuk pada Plin Dinding
[ 13.55 x 1.00 ] - 1.38 = 12.17 x 1.00 = 12.17
[ 5.40 x 1.00 ] - 1.38 = 4.02 x 1.00 = 4.02
[ 6.40 x 1.00 ] - 3.06 = 3.34 x 4.00 = 13.36
[
[ 8.05 x 1.00 ] = 8.05 x 1.00 = 8.05
[ 5.40 x 1.00 ] = 5.40 x 1.00 = 5.40
Plin Keramik = 69.80
= 112.80 = 112.80 112.80 M'
Pekerjaan Keramik 400x400mm (Unpolished) Ex.Ikad , include material, adukan dan tenaga kerja.
C. Keramik Area Toilet, tempat Wudhuk
Wuduk [ 1.35 x 3.85 ] x 1.00 = 5.20
[ 1.35 x 1.85 ] x 1.00 = 2.50
Tiolet [ 0.85 x 3.00 ] x 1.00 = 2.55
[ 1.85 x 1.35 ] x 2.00 = 5.00
[ 2.85 x 1.35 ] x 1.00 = 3.85
[ 1.35 x 1.35 ] x 2.00 = 3.65
= 22.73 x 1.00 = 22.73 = 22.73 22.73 M2
Pekerjaan Pengecatan
C. Pekerjaan cat plafond gypsum board & beton exposed dibawah tangga
Pekerjaan cat include material, tenaga kerja, alat bantu dan perapian)
Plafond Gipsum = 134.18
Plafond Kalsi = 80.87
= 215.04 = 215.04 215.04 M2
B. Pek. Kolom KP Uk. 130 x 130 mm, Besi 4 Ø12, Sengkang Ø8-150 mm, Ø8-200 mm
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
Beton
[ 0.13 x 0.13 ] x 1.70 = 0.03 x 1.00 = 0.03
[ 0.13 x 0.13 ] x 1.20 = 0.02 x 4.00 = 0.08
= 0.03 0.03 M3
Pembesian
Tul- utama [ 6.00 x 12.00 ] x 1.70 x 0.89 = 9.06
Begel [ 18.00 x 8.00 ] x 0.46 x 0.39 = 3.27 = 12.32 12.32 Kg
C. Pek. Balok Beton Type BL uk. 11 x 15 cm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 11.00 x 0.62 = 27.13
Begel [ 63.86 x 8.00 ] x 0.46 x 0.39 = 11.59 = 38.72 38.72 Kg
Pekerjaan pasangan bata ringan dan bata merah alat bantu, perapian dan tenaga kerja.
A. Pasangan Batu Bata 1 : 4
Luas Pas. Bata
[ 4.80 x 1.70 ] x 1.00 = 8.16 T= 1.70
[ 6.00 x 1.20 ] x 1.00 = 7.20 T= 1.20
C. Acian Plesteran
= 8.16 = 8.16 8.16 M2
D. Pas. Keramik Dinding Uk. 200x400 MM (Dinding Belakang Dan Bak Air)
Dinding Belakan[ 5.00 x 1.70 ] = 8.50 x 1.00 = 8.50
Bak Air [ 6.00 x 1.20 ] = 7.20 x 2.00 = 14.40
= 22.90 = 22.90 22.90 M2
Pekerjaan Pengecatan
E. Pengecatan dinding Exterior Ex. Propan
Dinding = 8.16 x 1.00 = 8.16
= 8.16 = 8.16 8.16 M2
4.5.4 Pekerjaan Atap
Pekerjaan atap, termasuk biaya mob de mobilisasi alat bantu, material dan jasa pemasangan.
A. Pek. Tiang Besi Pipa Dia-3" T=3 MM Fin. Cat
Tiang = 3.30 x 2.00 x 1.00 = 6.60
= 1.60 x 2.00 x 1.00 = 3.20
= 9.80 x 6.72 = 65.86 = 65.86 65.86 Kg
B. Pek. Kuda Besi Pipa Dia-3" T=3 MM dan Skor Pipa Besi Dia 2"T=2.8 MM Fin. Cat
Kuda-Kuda 3" = 7.20 x 2.00 x 1.00 = 14.40
= 5.96 x 2.00 x 1.00 = 11.92
= 26.32 x 6.72 = 176.87
Kuda-Kuda 2" = 0.45 x 2.00 x 2.00 = 1.80
= 0.45 x 3.00 x 2.00 = 2.70
= 1.95 x 3.00 x 2.00 = 11.70
= 1.25 x 4.00 x 2.00 = 10.00
= 26.20 x 4.08 = 106.90
= 283.77 = 283.77 283.77 Kg
Pembesian
Tul- utama [ 4.00 x 12.00 ] x 50.00 x 0.89 = 177.55
Begel [ 286.71 x 8.00 ] x 0.74 x 0.39 = 83.71 = 261.27 261.27 Kg
B. Pek. Kolom Praktis Kp Uk. 130 x 130 mm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Beton
[ 0.13 x 0.13 ] x 3.10 = 0.05 x 10.00 = 0.52
[ 0.13 x 0.13 ] x 2.85 = 0.05 x 6.00 = 0.29
[ 0.13 x 0.13 ] x 1.60 = 0.03 x 4.00 = 0.11
= 0.52 0.52 M3
Pembesian
Tul- utama [ 4.00 x 12.00 ] x 54.50 x 0.89 = 193.53
Begel [ 312.43 x 8.00 ] x 0.46 x 0.39 = 56.71 = 250.24 250.24 Kg
C. Pek. Balok Beton Type rb uk. 13 x 20 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 50.00 x 0.62 = 123.30
Begel [ 286.71 x 8.00 ] x 0.60 x 0.39 = 67.88 = 191.18 191.18 Kg
D. Pek. Balok Beton Type BL uk. 11 x 15 cm,Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 25.00 x 0.62 = 61.65
Begel [ 143.86 x 8.00 ] x 0.46 x 0.39 = 26.11 = 87.76 87.76 Kg
Pekerjaan pasangan bata ringan dan bata merah alat bantu, perapian dan tenaga kerja.
A. Pasangan Batu Bata 1 : 4
Luas Bidang Kozen Bata
PB7 [ 1.50 x 1.50 ] x 1.00 = 2.25 x 2.00 Bh = 4.50
PB7' [ 1.50 x 2.80 ] x 1.00 = 4.20 x 2.00 Bh = 8.40
JK1 [ 1.03 x 1.46 ] x 1.00 = 1.50 x 4.00 Bh = 5.99
= 18.89
Luas Pas. Bata
[ 8.00 x 1.60 ] x 2.00 = 25.60 T= 1.60
[ 4.00 x 1.60 ] x 3.00 = 19.20 T= 1.60
[ 8.00 x 3.10 ] x 1.00 = 24.80 T= 3.10
[ 8.00 x 2.85 ] x 1.00 = 22.80 T= 2.85
[ 3.00 x 2.98 ] x 3.00 = 26.78 T= 2.98
= 119.18 - 18.89 = 100.29 = 100.29 100.29 M2
B. Plesteran 1 : 4
= 100.29 x 2.00 = 200.58 = 200.58 = 200.58 200.58 M2
C. Acian Plesteran
= 200.58 = 200.58 200.58 M2
D. Plesteran 1:4, Opening Kusen + Acian
PB7 [ 1.50 x 2.00 ] x 1.00 = 3.00 x 2.00 Bh = 6.00
PB7' [ 1.50 x 1.00 ] x 1.00 = 1.50 x 2.00 Bh = 3.00
[ 2.80 x 2.00 ] x 1.00 = 5.60 x 2.00 Bh = 11.20
JK1 [ 1.03 x 2.00 ] x 1.00 = 2.05 x 4.00 Bh = 8.20
[ 1.46 x 2.00 ] x 1.00 = 2.92 x 4.00 Bh = 11.68
= 40.08 = 40.08 40.08 M'
Pekerjaan Pengecatan
E. Pengecatan dinding Exterior Ex. Propan
Dinding = 200.58 x 0.45 = 90.26
= 90.26 = 90.26 90.26 M2
F Pengecatan dinding Interior Ex. Propan
Dinding = 200.58 x 0.55 = 110.32
= 110.32 = 110.32 110.32 M2
4.6.4 Pekerjaan Atap
Pekerjaan atap, termasuk biaya mob de mobilisasi alat bantu, material dan jasa pemasangan.
A. Pek. Tiang Besi Pipa Dia-3" T=3 MM Fin. Cat
Tiang = 0.10 x 15.00 x 1.00 = 1.50
= 1.50 x 6.72 = 10.08 = 10.08 10.08 Kg
B. Pek. Kuda Besi Pipa Dia-3" T=3 MM Fin. Cat
Kuda-Kuda 3" = 4.60 x 3.00 x 1.00 = 13.80
= 5.69 x 3.00 x 1.00 = 17.07
= 30.87 x 6.72 = 207.45
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
= 207.45 = 207.45 207.45 Kg
Melintang
Tul- utama [ 22.00 x 2.15 ] x 2.00 = 94.60
[ 15.33 x 3.15 ] x 2.00 = 96.60
= 191.20 x 0.62 = 117.87 = 117.87 117.87 Kg
Pembesian
Tul- utama [ 4.00 x 12.00 ] x 44.00 x 0.89 = 156.25
Begel [ 252.43 x 8.00 ] x 0.74 x 0.39 = 73.70 = 229.95 229.95 Kg
B. Pek. Kolom Praktis Kp Uk. 130 x 130 mm,Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Beton
[ 0.13 x 0.13 ] x 3.25 = 0.05 x 14.00 = 0.77
= 0.77 0.77 M3
Pembesian
Tul- utama [ 4.00 x 12.00 ] x 45.50 x 0.89 = 161.57
Begel [ 261.00 x 8.00 ] x 0.46 x 0.39 = 47.37 = 208.94 208.94 Kg
C. Pek. Balok Beton Type rb uk. 13 x 20 cm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 44.00 x 0.62 = 108.50
Begel [ 252.43 x 8.00 ] x 0.60 x 0.39 = 59.76 = 168.26 168.26 Kg
D. Pek. Balok Beton Type BL uk. 11 x 15 cm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 16.00 x 0.62 = 39.46
Begel [ 92.43 x 8.00 ] x 0.46 x 0.39 = 16.78 = 56.23 56.23 Kg
Pekerjaan pasangan bata ringan dan bata merah alat bantu, perapian dan tenaga kerja.
A. Pasangan Batu Bata 1 : 4
Luas Bidang Kozen Bata
PB3 [ 1.60 x 2.40 ] x 1.00 = 3.84 x 1.00 Bh = 3.84
JK2 [ 1.50 x 1.30 ] x 1.00 = 1.95 x 4.00 Bh = 7.80
= 11.64
Luas Pas. Bata
[ 16.00 x 3.20 ] x 2.00 = 102.40 T= 3.20
[ 6.00 x 3.20 ] x 2.00 = 38.40 T= 3.20
[ 3.00 x 0.72 ] x 2.00 = 4.32 T= 0.72
= 145.12 - 11.64 = 133.48 = 133.48 133.48 M2
B. Plesteran 1 : 4
= 133.48 x 2.00 = 266.96 = 266.96 = 266.96 266.96 M2
C. Acian Plesteran
= 266.96 = 266.96 266.96 M2
D. Plesteran 1:4, Opening Kusen + Acian
PB3 [ 1.60 x 1.00 ] x 1.00 = 1.60 x 1.00 Bh = 1.60
[ 2.40 x 2.00 ] x 1.00 = 4.80 x 1.00 Bh = 4.80
JK2 [ 1.50 x 2.00 ] x 1.00 = 3.00 x 4.00 Bh = 12.00
[ 1.30 x 2.00 ] x 1.00 = 2.60 x 4.00 Bh = 10.40
= 28.80 = 28.80 28.80 M'
Pekerjaan Pengecatan
E. Pengecatan dinding Exterior Ex. Propan
Dinding = 266.96 x 0.50 = 133.48
= 133.48 = 133.48 133.48 M2
F. Pengecatan dinding Interior Ex. Propan
Dinding = 266.96 x 0.50 = 133.48
= 133.48 = 133.48 133.48 M2
Pekerjaan Pintu & Jendela Kawat Harmonika, detail lihat digambar. Pekerjaan include accesories.
B. Jendela JK2 (Area Gudang Arsip) = 4.00 4.00 Unit
Pembesian
Tul- utama [ 6.00 x 16.00 ] x 20.00 x 1.58 = 189.39
Begel [ 161.00 x 8.00 ] x 1.14 x 0.39 = 72.42 = 261.81 261.81 Kg
B. Pek. Kolom Praktis K1 Uk. 300 x 300 mm, Besi 6 Ø16, Sengkang Ø8-100 mm (Tump), Ø8-150 mm (Lap)
Beton
[ 0.30 x 0.30 ] x 3.65 = 0.33 x 6.00 = 1.97
= 1.97 1.97 M3
Pembesian
Tul- utama [ 6.00 x 16.00 ] x 21.90 x 1.58 = 207.38
Begel [ 176.20 x 8.00 ] x 1.14 x 0.39 = 79.25 = 286.64 286.64 Kg
C. Pek. Kolom Praktis Kp Uk. 130 x 130 mm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Beton
[ 0.13 x 0.13 ] x 2.85 = 0.05 x 3.00 = 0.14
= 0.14 0.14 M3
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 8.55 x 0.62 = 21.08
Begel [ 49.86 x 8.00 ] x 0.46 x 0.39 = 9.05 = 30.13 30.13 Kg
D. Pek. Balok Beton Type RB1 uk. 20 x 40 cm , Besi 6 Ø16 (Tump) Besi 5 Ø16 (Lap), Sengkang Ø8-100 mm (Tump), Ø8-150 mm (Lap)
Beton [ 0.20 x 0.40 ] x 27.30 = 2.18 - 0.66 = 1.53 1.53 M3
Pembesian
Tul- utama [ 5.50 x 16.00 ] x 30.00 x 1.58 = 260.41
Begel [ 241.00 x 8.00 ] x 1.14 x 0.39 = 108.40 = 368.81 368.81 Kg
E. Pek. Balok Beton Type BL uk. 11 x 15 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
Beton [ 0.11 x 0.15 ] x 14.50 = 0.24 = 0.24 0.24 M3
Pembesian
Tul- utama [ 4.00 x 10.00 ] x 14.50 x 0.62 = 35.76
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
Begel [ 83.86 x 8.00 ] x 0.46 x 0.39 = 15.22 = 50.98 50.98 Kg
Melintang
Tul- utama [ 7.50 x 37.67 ] x 2.00 = 565.00
[ 5.50 x 51.00 ] x 2.00 = 561.00
= 1,126.00 x 0.62 = 694.18 = 694.18 694.18 Kg
Melintang
Tul- utama [ 26.00 x 4.00 ] x 1.00 = 104.00
[ 0.55 x 173.33 ] x 1.00 = 95.33
= 199.33 x 0.62 = 122.89 = 122.89 122.89 Kg
B. Plesteran 1 : 4
Plesteran Beton
Kolom [ 1.05 x 21.90 ] x 1.00 = 23.00
Balok [ 0.85 x 27.30 ] x 1.00 = 23.21
Listpalnk [ 0.90 x 26.00 ] x 1.00 = 23.40
= 69.60
Plesteran Dinding
= 42.35 x 2.00 = 84.71
Pekerjaan Pengecatan
E. Pengecatan dinding Exterior Ex. Propan
Dinding = 154.31 x 0.50 = 77.15
= 77.15 = 77.15 77.15 M2
F. Pengecatan dinding Interior Ex. Propan
Dinding = 154.31 x 0.50 = 77.15
= 77.15 = 77.15 77.15 M2
4.8.4 Pekerjaan Arsitek Pintu dan Jendela
Pekerjaan Pintu Besi
A. Pintu Besi Type PV1 (1350x2850mm) = 1.00 1.00 Unit
-, Pembesian
Tulangan Bawah[ 28.00 x 16.00 ] x 1.36 x 1.58 = 60.10
[ 28.00 x 16.00 ] x 1.36 x 1.58 = 60.10
Tulangan Atas [ 28.00 x 13.00 ] x 1.36 x 1.04 = 39.67
[ 28.00 x 13.00 ] x 1.36 x 1.04 = 39.67
199.55 = 199.55 199.55 Kg
-, Bekisting
[ 4.00 x 1.00 ] x 0.30 x 4.00 = 4.80 = 4.80 4.80 M2
-, Pembesian
Tul- utama [ 32.00 x 13.00 ] x 1.72 x 1.04 = 57.18
Begel [ 36.00 x 8.00 ] x 0.94 x 0.39 = 13.35
= 70.53 = 70.53 70.53 Kg
-, Bekisting
[ 4.00 x 0.25 ] x 1.30 x 4.00 = 5.20 = 5.20 5.20 M2
-, Pembesian
Tul- utama [ 16.00 x 13.00 ] x 2.27 x 1.04 = 37.84
Begel [ 48.00 x 10.00 ] x 0.56 x 0.62 = 16.57
= 54.41 = 54.41 54.41 Kg
-, Bekisting
[ 2.00 x 0.20 ] x 1.75 x 4.00 = 2.80 = 2.80 2.80 M2
C. Baut Dia 20 mm
3.00 x 2.00 = 6.00 = 6.00 6.00 Bh
D. Tiang Bendera Pipa Besi Dia 4" panjang 6 m + Dia 3" panjang 3 m include Katrol dan Besi Ka 1.00 = 1.00 1.00 Unit
E. Tiang Bendera Pipa Besi Dia 4" panjang 5 m + Dia 3" panjang 3 m include Katrol dan Besi Ka 2.00 = 2.00 2.00 Unit
5 EXTERNAL
5.1 PAGAR
5.1.1 Pekerjaan Tanah dan Pondasi
A. Pek. Galian Tanah Pondasi
Depan
Type VIII [ 1.10 x 0.40 ] x 22.99 = 10.12
[ 1.10 x 0.40 ] x 22.50 = 9.90
Type VA [ 1.50 x 0.50 ] x 2.50 = 1.88
[ 2.00 x 0.70 ] x 2.50 = 3.50
[ 2.00 x 0.70 ] x 2.00 = 2.80
Type V [ 2.00 x 0.70 ] x 9.87 = 13.82
[ 2.00 x 0.70 ] x 9.84 = 13.78
[ 2.00 x 0.70 ] x 12.50 = 17.50
[ 2.00 x 0.70 ] x 19.73 = 27.62
Type VI [ 2.00 x 0.70 ] x 61.15 = 85.61
[ 2.00 x 0.70 ] x 8.80 = 12.32
[ 2.00 x 0.70 ] x 30.40 = 42.56
Samping Kiri
Type IX [ 2.00 x 0.80 ] x 22.50 = 36.00
Type IIIA [ 2.50 x 0.90 ] x 2.50 = 5.63
[ 2.00 x 0.80 ] x 2.50 = 4.00
[ 2.00 x 0.80 ] x 2.50 = 4.00
Type III [ 2.75 x 0.90 ] x 32.50 = 80.44
Type I [ 3.00 x 0.90 ] x 80.00 = 216.00
Type II [ 3.00 x 0.90 ] x 22.50 = 60.75
Type III [ 2.75 x 0.90 ] x 21.64 = 53.56
Samping Kanan
Type VII [ 1.50 x 0.50 ] x 143.05 = 107.29
Belakang
Type VII [ 1.50 x 0.50 ] x 15.00 = 11.25
Type VI [ 2.00 x 0.70 ] x 27.50 = 38.50
Type V [ 2.00 x 0.70 ] x 40.00 = 56.00
Type IV [ 2.50 x 0.90 ] x 57.45 = 129.26
= 1,044.07 = 1,044.07 1,044.07 M3
Samping Kiri
Type IX [ 2.00 x 4.00 ] x 45.00 = 360.00
Type IIIA [ 2.00 x 5.00 ] x 5.00 = 50.00
[ 2.00 x 4.00 ] x 5.00 = 40.00
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
[ 2.00 x 4.00 ] x 5.00 = 40.00
Type III [ 2.00 x 5.00 ] x 65.00 = 650.00
Type I [ 2.00 x 6.00 ] x 160.00 = 1,920.00
Type II [ 2.00 x 6.00 ] x 45.00 = 540.00
Type III [ 2.00 x 6.00 ] x 44.00 = 528.00
Samping Kanan
Type VII [ 2.00 x 3.00 ] x 287.00 = 1,722.00
Belakang
Type VII [ 2.00 x 3.00 ] x 30.00 = 180.00
Type VI [ 2.00 x 4.00 ] x 55.00 = 440.00
Type V [ 2.00 x 4.00 ] x 80.00 = 640.00
Type IV [ 2.00 x 5.00 ] x 115.00 = 1,150.00
= 11,192.00 = 11,192.00 11,192.00 M'
Samping Kiri
Type IX [ 2.00 x 0.10 ] x 22.50 = 4.50
Type IIIA [ 2.50 x 0.10 ] x 2.50 = 0.63
[ 2.00 x 0.10 ] x 2.50 = 0.50
[ 2.00 x 0.10 ] x 2.50 = 0.50
Type III [ 2.75 x 0.10 ] x 32.50 = 8.94
Type I [ 3.00 x 0.10 ] x 80.00 = 24.00
Type II [ 3.00 x 0.10 ] x 22.50 = 6.75
Type III [ 2.75 x 0.10 ] x 21.64 = 5.95
Samping Kanan
Type VII [ 1.50 x 0.10 ] x 143.05 = 21.46
Belakang
Type VII [ 1.50 x 0.10 ] x 15.00 = 2.25
Type VI [ 2.00 x 0.10 ] x 27.50 = 5.50
Type V [ 2.00 x 0.10 ] x 40.00 = 8.00
Type IV [ 2.50 x 0.10 ] x 57.45 = 14.36
= 140.07 = 140.07 140.07 M3
Samping Kiri
Type IX 2.00 x 0.70 x 22.50 = 31.50
[ 0.35 + 1.40 ] : 2.00 = 0.88 x 2.30 x 22.50 = 45.28
Type IIIA 2.50 x 0.80 x 2.50 = 5.00
[ 0.35 + 1.70 ] : 2.00 = 1.03 x 3.30 x 2.50 = 8.46
2.00 x 0.70 x 2.50 = 3.50
[ 0.35 + 1.40 ] : 2.00 = 0.88 x 3.10 x 2.50 = 6.78
2.00 x 0.70 x 2.50 = 3.50
[ 0.35 + 1.40 ] : 2.00 = 0.88 x 2.70 x 2.50 = 5.91
Type III 2.75 x 0.80 x 32.50 = 71.50
[ 0.35 + 1.95 ] : 2.00 = 1.15 x 3.70 x 32.50 = 138.29
Type I 3.00 x 0.80 x 80.00 = 192.00
[ 0.35 + 2.20 ] : 2.00 = 1.28 x 4.70 x 80.00 = 479.40
Type II 3.00 x 0.80 x 22.50 = 54.00
[ 0.35 + 2.20 ] : 2.00 = 1.28 x 4.20 x 22.50 = 120.49
Type III 2.75 x 0.80 x 21.64 = 47.61
[ 0.35 + 1.95 ] : 2.00 = 1.15 x 3.70 x 21.64 = 92.08
Samping Kanan
Type VII 1.50 x 0.40 x 143.05 = 85.83
[ 0.35 + 1.10 ] : 2.00 = 0.73 x 2.10 x 143.05 = 217.79
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
Belakang
Type VII 1.50 x 0.40 x 15.00 = 9.00
[ 0.35 + 1.10 ] : 2.00 = 0.73 x 2.10 x 15.00 = 22.84
Type VI 2.00 x 0.60 x 27.50 = 33.00
[ 0.35 + 1.40 ] : 2.00 = 0.88 x 2.40 x 27.50 = 57.75
Type V 2.00 x 0.60 x 40.00 = 48.00
[ 0.35 + 1.40 ] : 2.00 = 0.88 x 2.90 x 40.00 = 101.50
Type IV 2.50 x 0.80 x 57.45 = 114.90
[ 0.35 + 1.40 ] : 2.00 = 0.88 x 3.20 x 57.45 = 160.86
= 2,758.62 = 2,758.62 2,758.62 M3
Samping Kiri
Type IX 2.78 x 9.00 = 25.02
Type IIIA 4.20 x 1.00 = 4.20
2.97 x 1.00 = 2.97
2.97 x 1.00 = 2.97
Type III 5.12 x 13.00 = 66.56
Type I 7.71 x 32.00 = 246.72
Type II 6.66 x 9.00 = 59.94
Type III 5.12 x 9.00 = 46.08
Samping Kanan
Type VII 1.77 x 58.00 = 102.66
Belakang
Type VII 1.77 x 6.00 = 10.62
Type VI 2.79 x 11.00 = 30.69
Type V 3.07 x 16.00 = 49.12
Type IV 4.27 x 23.00 = 98.21
= 959.00 = 959.00 959.00 M'
Samping Kiri
Type IX [ 2.70 + 0.60 ] : 2.00 = 1.65 x 2.30 x 22.50 = 85.39
Type IIIA [ 3.50 + 0.80 ] : 2.00 = 2.15 x 3.30 x 2.50 = 17.74
[ 2.70 + 0.60 ] : 2.00 = 1.65 x 3.10 x 2.50 = 12.79
[ 2.70 + 0.60 ] : 2.00 = 1.65 x 2.70 x 2.50 = 11.14
Type III [ 4.25 + 0.80 ] : 2.00 = 2.53 x 3.70 x 32.50 = 303.63
Type I [ 4.50 + 0.80 ] : 2.00 = 2.65 x 4.70 x 80.00 = 996.40
Type II [ 4.50 + 0.80 ] : 2.00 = 2.65 x 4.20 x 22.50 = 250.43
Type III [ 4.25 + 0.80 ] : 2.00 = 2.53 x 3.70 x 21.64 = 202.17
Samping Kanan
Type VII [ 1.90 + 0.40 ] : 2.00 = 1.15 x 2.10 x 143.05 = 345.47
Belakang
Type VII [ 1.90 + 0.40 ] : 2.00 = 1.15 x 2.10 x 15.00 = 36.23
Type VI [ 2.70 + 0.60 ] : 2.00 = 1.65 x 2.40 x 27.50 = 108.90
Type V [ 2.70 + 0.60 ] : 2.00 = 1.65 x 2.90 x 40.00 = 191.40
Type IV [ 4.00 + 0.80 ] : 2.00 = 2.40 x 3.20 x 57.45 = 441.22
= 3,752.21 = 3,752.21 3,752.21 M3
Samping Kiri
[ 6.00 x 2.40 ] x 9.00 = 21.60
[ 6.00 x 2.40 ] x 1.00 = 2.40
[ 6.00 x 2.40 ] x 1.00 = 2.40
[ 6.00 x 2.40 ] x 1.00 = 2.40
[ 6.00 x 2.40 ] x 13.00 = 31.20
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
[ 6.00 x 2.40 ] x 32.00 = 76.80
[ 6.00 x 2.40 ] x 9.00 = 21.60
[ 6.00 x 2.40 ] x 8.66 = 20.78
Samping Kanan
[ 6.00 x 2.40 ] x 57.22 = 137.33
Belakang
[ 6.00 x 2.40 ] x 6.00 = 14.40
[ 6.00 x 2.40 ] x 11.00 = 26.40
[ 6.00 x 2.40 ] x 16.00 = 38.40
[ 6.00 x 2.40 ] x 22.98 = 55.15
= 551.16 = 551.16 551.16 M'
Samping Kiri
3.70 x 9.00 = 33.30
3.70 x 1.00 = 3.70
3.70 x 1.00 = 3.70
3.70 x 1.00 = 3.70
3.70 x 13.00 = 48.10
3.70 x 32.00 = 118.40
3.70 x 9.00 = 33.30
3.70 x 9.00 = 33.30
Samping Kanan
3.70 x 58.00 = 214.60
Belakang
3.70 x 6.00 = 22.20
3.70 x 11.00 = 40.70
3.70 x 16.00 = 59.20
3.70 x 23.00 = 85.10
= 858.40 = 858.40 858.40 M'
C. Pek. Ring Balok Beton Type BL uk. 15 x 15 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225
Depan
[ 0.15 x 0.15 ] x 22.99 = 3.45
[ 0.15 x 0.15 ] x 22.50 = 3.38
[ 0.15 x 0.15 ] x 2.50 = 0.38
[ 0.15 x 0.15 ] x 2.50 = 0.38
[ 0.15 x 0.15 ] x 2.00 = 0.30
[ 0.15 x 0.15 ] x 9.87 = 1.48
[ 0.15 x 0.15 ] x 9.84 = 1.48
[ 0.15 x 0.15 ] x 12.50 = 1.88
[ 0.15 x 0.15 ] x 19.73 = 2.96
Samping Kiri
[ 0.15 x 0.15 ] x 22.50 = 3.38
[ 0.15 x 0.15 ] x 2.50 = 0.38
[ 0.15 x 0.15 ] x 2.50 = 0.38
[ 0.15 x 0.15 ] x 2.50 = 0.38
[ 0.15 x 0.15 ] x 32.50 = 4.88
[ 0.15 x 0.15 ] x 80.00 = 12.00
[ 0.15 x 0.15 ] x 22.50 = 3.38
[ 0.15 x 0.15 ] x 21.64 = 3.25
Samping Kanan
[ 0.15 x 0.15 ] x 143.05 = 21.46
Belakang
[ 0.15 x 0.15 ] x 15.00 = 2.25
[ 0.15 x 0.15 ] x 27.50 = 4.13
[ 0.15 x 0.15 ] x 40.00 = 6.00
[ 0.15 x 0.15 ] x 57.45 = 8.62
= 86.11 = 86.11 86.11 M3
-, Pembesian
Tul- utama
Depan
[ 4.00 x 10.00 ] x 22.99 x 0.62 = 56.69
[ 4.00 x 10.00 ] x 22.50 x 0.62 = 55.49
[ 4.00 x 10.00 ] x 2.50 x 0.62 = 6.17
[ 4.00 x 10.00 ] x 2.50 x 0.62 = 6.17
[ 4.00 x 10.00 ] x 2.00 x 0.62 = 4.93
[ 4.00 x 10.00 ] x 9.87 x 0.62 = 24.34
[ 4.00 x 10.00 ] x 9.84 x 0.62 = 24.27
[ 4.00 x 10.00 ] x 12.50 x 0.62 = 30.83
[ 4.00 x 10.00 ] x 19.73 x 0.62 = 48.65
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
Samping Kiri
[ 4.00 x 10.00 ] x 22.50 x 0.62 = 55.49
[ 4.00 x 10.00 ] x 2.50 x 0.62 = 6.17
[ 4.00 x 10.00 ] x 2.50 x 0.62 = 6.17
[ 4.00 x 10.00 ] x 2.50 x 0.62 = 6.17
[ 4.00 x 10.00 ] x 32.50 x 0.62 = 80.15
[ 4.00 x 10.00 ] x 80.00 x 0.62 = 197.28
[ 4.00 x 10.00 ] x 22.50 x 0.62 = 55.49
[ 4.00 x 10.00 ] x 21.64 x 0.62 = 53.36
Samping Kanan
[ 4.00 x 10.00 ] x 143.05 x 0.62 = 352.76
Belakang
[ 4.00 x 10.00 ] x 15.00 x 0.62 = 36.99
[ 4.00 x 10.00 ] x 27.50 x 0.62 = 67.82
[ 4.00 x 10.00 ] x 40.00 x 0.62 = 98.64
[ 4.00 x 10.00 ] x 57.45 x 0.62 = 141.67
= 1,415.66
Begel
Depan
[ 155.00 x 8.00 ] x 0.54 x 0.39 = 33.02
[ 151.00 x 8.00 ] x 0.54 x 0.39 = 32.17
[ 18.00 x 8.00 ] x 0.54 x 0.39 = 3.84
[ 18.00 x 8.00 ] x 0.54 x 0.39 = 3.84
[ 15.00 x 8.00 ] x 0.54 x 0.39 = 3.20
[ 67.00 x 8.00 ] x 0.54 x 0.39 = 14.28
[ 67.00 x 8.00 ] x 0.54 x 0.39 = 14.28
[ 85.00 x 8.00 ] x 0.54 x 0.39 = 18.11
[ 133.00 x 8.00 ] x 0.54 x 0.39 = 28.34
Samping Kiri
[ 151.00 x 8.00 ] x 0.54 x 0.39 = 32.17
[ 18.00 x 8.00 ] x 0.54 x 0.39 = 3.84
[ 18.00 x 8.00 ] x 0.54 x 0.39 = 3.84
[ 18.00 x 8.00 ] x 0.54 x 0.39 = 3.84
[ 218.00 x 8.00 ] x 0.54 x 0.39 = 46.45
[ 535.00 x 8.00 ] x 0.54 x 0.39 = 113.99
[ 151.00 x 8.00 ] x 0.54 x 0.39 = 32.17
[ 146.00 x 8.00 ] x 0.54 x 0.39 = 31.11
Samping Kanan
[ 955.00 x 8.00 ] x 0.54 x 0.39 = 203.47
Belakang
[ 101.00 x 8.00 ] x 0.54 x 0.39 = 21.52
[ 185.00 x 8.00 ] x 0.54 x 0.39 = 39.42
[ 268.00 x 8.00 ] x 0.54 x 0.39 = 57.10
[ 384.00 x 8.00 ] x 0.54 x 0.39 = 81.82
= 821.78
-, Bekisting
Depan
[ 2.00 x 0.15 ] x 22.99 = 3.45
[ 2.00 x 0.15 ] x 22.50 = 3.38
[ 2.00 x 0.15 ] x 2.50 = 0.38
[ 2.00 x 0.15 ] x 2.50 = 0.38
[ 2.00 x 0.15 ] x 2.00 = 0.30
[ 2.00 x 0.15 ] x 9.87 = 1.48
[ 2.00 x 0.15 ] x 9.84 = 1.48
[ 2.00 x 0.15 ] x 12.50 = 1.88
[ 2.00 x 0.15 ] x 19.73 = 2.96
Samping Kiri
[ 2.00 x 0.15 ] x 22.50 = 3.38
[ 2.00 x 0.15 ] x 2.50 = 0.38
[ 2.00 x 0.15 ] x 2.50 = 0.38
[ 2.00 x 0.15 ] x 2.50 = 0.38
[ 2.00 x 0.15 ] x 32.50 = 4.88
[ 2.00 x 0.15 ] x 80.00 = 12.00
[ 2.00 x 0.15 ] x 22.50 = 3.38
[ 2.00 x 0.15 ] x 21.64 = 3.25
Samping Kanan
[ 2.00 x 0.15 ] x 143.05 = 21.46
Belakang
[ 2.00 x 0.15 ] x 15.00 = 2.25
[ 2.00 x 0.15 ] x 27.50 = 4.13
[ 2.00 x 0.15 ] x 40.00 = 6.00
[ 2.00 x 0.15 ] x 57.45 = 8.62
= 86.11 = 86.11 86.11 M2
Depan
[ 0.50 x 0.50 ] x 0.20 x 3.00 = 0.15
[ 0.50 x 0.50 ] x 0.20 x 3.00 = 0.15
[ 0.50 x 0.50 ] x 0.20 x 1.00 = 0.05
[ 0.50 x 0.50 ] x 0.20 x 1.00 = 0.05
[ 0.50 x 0.50 ] x 0.20 x 2.00 = 0.10
[ 0.50 x 0.50 ] x 0.20 x 3.00 = 0.15
Samping Kiri
[ 0.50 x 0.50 ] x 0.20 x 3.00 = 0.15
[ 0.50 x 0.50 ] x 0.20 x 4.00 = 0.20
[ 0.50 x 0.50 ] x 0.20 x 11.00 = 0.55
[ 0.50 x 0.50 ] x 0.20 x 3.00 = 0.15
[ 0.50 x 0.50 ] x 0.20 x 3.00 = 0.15
Samping Kanan
[ 0.50 x 0.50 ] x 0.20 x 19.00 = 0.95
Belakang
[ 0.50 x 0.50 ] x 0.20 x 2.00 = 0.10
[ 0.50 x 0.50 ] x 0.20 x 4.00 = 0.20
[ 0.50 x 0.50 ] x 0.20 x 5.00 = 0.25
[ 0.50 x 0.50 ] x 0.20 x 8.00 = 0.40
= 3.75 = 3.75 3.75 M3
-, Pembesian
Depan
[ 24.00 x 12.00 ] x 1.26 x 0.89 = 26.85
[ 24.00 x 12.00 ] x 1.26 x 0.89 = 26.85
[ 8.00 x 12.00 ] x 1.26 x 0.89 = 8.95
[ 8.00 x 12.00 ] x 1.26 x 0.89 = 8.95
[ 16.00 x 12.00 ] x 1.26 x 0.89 = 17.90
[ 24.00 x 12.00 ] x 1.26 x 0.89 = 26.85
Samping Kiri
[ 24.00 x 12.00 ] x 1.26 x 0.89 = 26.85
[ 32.00 x 12.00 ] x 1.26 x 0.89 = 35.79
[ 88.00 x 12.00 ] x 1.26 x 0.89 = 98.43
[ 24.00 x 12.00 ] x 1.26 x 0.89 = 26.85
[ 24.00 x 12.00 ] x 1.26 x 0.89 = 26.85
Samping Kanan
[ 152.00 x 12.00 ] x 1.26 x 0.89 = 170.02
Belakang
[ 16.00 x 12.00 ] x 1.26 x 0.89 = 17.90
[ 32.00 x 12.00 ] x 1.26 x 0.89 = 35.79
[ 40.00 x 12.00 ] x 1.26 x 0.89 = 44.74
[ 64.00 x 12.00 ] x 1.26 x 0.89 = 71.59
= 671.15 = 671.15 671.15 Kg
-, Bekisting
Depan
[ 4.00 x 0.50 ] x 0.20 x 3.00 = 1.20
[ 4.00 x 0.50 ] x 0.20 x 3.00 = 1.20
[ 4.00 x 0.50 ] x 0.20 x 1.00 = 0.40
[ 4.00 x 0.50 ] x 0.20 x 1.00 = 0.40
[ 4.00 x 0.50 ] x 0.20 x 2.00 = 0.80
[ 4.00 x 0.50 ] x 0.20 x 3.00 = 1.20
Samping Kiri
[ 4.00 x 0.50 ] x 0.20 x 3.00 = 1.20
[ 4.00 x 0.50 ] x 0.20 x 4.00 = 1.60
[ 4.00 x 0.50 ] x 0.20 x 11.00 = 4.40
[ 4.00 x 0.50 ] x 0.20 x 3.00 = 1.20
[ 4.00 x 0.50 ] x 0.20 x 3.00 = 1.20
Samping Kanan
[ 4.00 x 0.50 ] x 0.20 x 19.00 = 7.60
Belakang
[ 4.00 x 0.50 ] x 0.20 x 2.00 = 0.80
[ 4.00 x 0.50 ] x 0.20 x 4.00 = 1.60
[ 4.00 x 0.50 ] x 0.20 x 5.00 = 2.00
[ 4.00 x 0.50 ] x 0.20 x 8.00 = 3.20
= 30.00 = 30.00 30.00 M2
E. Pek. Kolom Pedestal Beton Type KP uk. 20 x 20 cm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225
Depan
[ 0.20 x 0.20 ] x 0.85 x 3.00 = 0.10
[ 0.20 x 0.20 ] x 0.85 x 3.00 = 0.10
[ 0.20 x 0.20 ] x 0.85 x 1.00 = 0.03
[ 0.20 x 0.20 ] x 0.85 x 1.00 = 0.03
[ 0.20 x 0.20 ] x 0.85 x 2.00 = 0.07
[ 0.20 x 0.20 ] x 0.85 x 3.00 = 0.10
Samping Kiri
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
Samping Kanan
[ 0.20 x 0.20 ] x 0.85 x 19.00 = 0.65
Belakang
[ 0.20 x 0.20 ] x 0.85 x 2.00 = 0.07
[ 0.20 x 0.20 ] x 0.85 x 4.00 = 0.14
[ 0.20 x 0.20 ] x 0.85 x 5.00 = 0.17
[ 0.20 x 0.20 ] x 0.85 x 8.00 = 0.27
= 2.55 = 2.55 2.55 M3
-, Pembesian
Tul- utama
Depan
[ 12.00 x 12.00 ] x 1.20 x 0.89 = 12.78
[ 12.00 x 12.00 ] x 1.20 x 0.89 = 12.78
[ 4.00 x 12.00 ] x 1.20 x 0.89 = 4.26
[ 4.00 x 12.00 ] x 1.20 x 0.89 = 4.26
[ 8.00 x 12.00 ] x 1.20 x 0.89 = 8.52
[ 12.00 x 12.00 ] x 1.20 x 0.89 = 12.78
Samping Kiri
[ 12.00 x 12.00 ] x 1.20 x 0.89 = 12.78
[ 16.00 x 12.00 ] x 1.20 x 0.89 = 17.04
[ 44.00 x 12.00 ] x 1.20 x 0.89 = 46.87
[ 12.00 x 12.00 ] x 1.20 x 0.89 = 12.78
[ 12.00 x 12.00 ] x 1.20 x 0.89 = 12.78
Samping Kanan
[ 76.00 x 12.00 ] x 1.20 x 0.89 = 80.96
Belakang
[ 8.00 x 12.00 ] x 1.20 x 0.89 = 8.52
[ 16.00 x 12.00 ] x 1.20 x 0.89 = 17.04
[ 20.00 x 12.00 ] x 1.20 x 0.89 = 21.31
[ 32.00 x 12.00 ] x 1.20 x 0.89 = 34.09
= 319.59
Begel
Depan
[ 18.00 x 8.00 ] x 0.74 x 0.39 = 5.26
[ 18.00 x 8.00 ] x 0.74 x 0.39 = 5.26
[ 6.00 x 8.00 ] x 0.74 x 0.39 = 1.75
[ 6.00 x 8.00 ] x 0.74 x 0.39 = 1.75
[ 12.00 x 8.00 ] x 0.74 x 0.39 = 3.50
[ 18.00 x 8.00 ] x 0.74 x 0.39 = 5.26
Samping Kiri
[ 18.00 x 8.00 ] x 0.74 x 0.39 = 5.26
[ 24.00 x 8.00 ] x 0.74 x 0.39 = 7.01
[ 66.00 x 8.00 ] x 0.74 x 0.39 = 19.27
[ 18.00 x 8.00 ] x 0.74 x 0.39 = 5.26
[ 18.00 x 8.00 ] x 0.74 x 0.39 = 5.26
Samping Kanan
[ 114.00 x 8.00 ] x 0.74 x 0.39 = 33.29
Belakang
[ 12.00 x 8.00 ] x 0.74 x 0.39 = 3.50
[ 24.00 x 8.00 ] x 0.74 x 0.39 = 7.01
[ 30.00 x 8.00 ] x 0.74 x 0.39 = 8.76
[ 48.00 x 8.00 ] x 0.74 x 0.39 = 14.01
= 131.39
-, Bekisting
Depan
[ 4.00 x 0.20 ] x 0.85 x 3.00 = 2.04
[ 4.00 x 0.20 ] x 0.85 x 3.00 = 2.04
[ 4.00 x 0.20 ] x 0.85 x 1.00 = 0.68
[ 4.00 x 0.20 ] x 0.85 x 1.00 = 0.68
[ 4.00 x 0.20 ] x 0.85 x 2.00 = 1.36
[ 4.00 x 0.20 ] x 0.85 x 3.00 = 2.04
Samping Kiri
[ 4.00 x 0.20 ] x 0.85 x 3.00 = 2.04
[ 4.00 x 0.20 ] x 0.85 x 4.00 = 2.72
[ 4.00 x 0.20 ] x 0.85 x 11.00 = 7.48
[ 4.00 x 0.20 ] x 0.85 x 3.00 = 2.04
[ 4.00 x 0.20 ] x 0.85 x 3.00 = 2.04
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
Samping Kanan
[ 4.00 x 0.20 ] x 0.85 x 19.00 = 12.92
Belakang
[ 4.00 x 0.20 ] x 0.85 x 2.00 = 1.36
[ 4.00 x 0.20 ] x 0.85 x 4.00 = 2.72
[ 4.00 x 0.20 ] x 0.85 x 5.00 = 3.40
[ 4.00 x 0.20 ] x 0.85 x 8.00 = 5.44
= 51.00 = 51.00 51.00 M2
Samping Kiri
1.97 x 3.00 x 9.66 = 57.09
1.97 x 4.00 x 9.66 = 76.12
1.97 x 11.00 x 9.66 = 209.33
1.97 x 3.00 x 9.66 = 57.09
1.97 x 3.00 x 9.66 = 57.09
Samping Kanan
1.97 x 19.00 x 9.66 = 361.57
Belakang
1.97 x 2.00 x 9.66 = 38.06
1.97 x 4.00 x 9.66 = 76.12
1.97 x 5.00 x 9.66 = 95.15
1.97 x 8.00 x 9.66 = 152.24
= 1,427.27 = 1,427.27 1,427.27 Kg
G. Pek. Plat T = 8 mm
Depan
[ 0.13 x 0.13 ] x 3.00 x 62.80 = 2.94
[ 0.13 x 0.13 ] x 3.00 x 62.80 = 2.94
[ 0.13 x 0.13 ] x 1.00 x 62.80 = 0.98
[ 0.13 x 0.13 ] x 1.00 x 62.80 = 0.98
[ 0.13 x 0.13 ] x 2.00 x 62.80 = 1.96
[ 0.13 x 0.13 ] x 3.00 x 62.80 = 2.94
Samping Kiri
[ 0.13 x 0.13 ] x 3.00 x 62.80 = 2.94
[ 0.13 x 0.13 ] x 4.00 x 62.80 = 3.93
[ 0.13 x 0.13 ] x 11.00 x 62.80 = 10.79
[ 0.13 x 0.13 ] x 3.00 x 62.80 = 2.94
[ 0.13 x 0.13 ] x 3.00 x 62.80 = 2.94
Samping Kanan
[ 0.13 x 0.13 ] x 19.00 x 62.80 = 18.64
Belakang
[ 0.13 x 0.13 ] x 2.00 x 62.80 = 1.96
[ 0.13 x 0.13 ] x 4.00 x 62.80 = 3.93
[ 0.13 x 0.13 ] x 5.00 x 62.80 = 4.91
[ 0.13 x 0.13 ] x 8.00 x 62.80 = 7.85
= 73.59 = 73.59 73.59 Kg
Samping Kiri
4.00 x 3.00 = 12.00
4.00 x 4.00 = 16.00
4.00 x 11.00 = 44.00
4.00 x 3.00 = 12.00
4.00 x 3.00 = 12.00
Samping Kanan
4.00 x 19.00 = 76.00
Belakang
4.00 x 2.00 = 8.00
4.00 x 4.00 = 16.00
4.00 x 5.00 = 20.00
4.00 x 8.00 = 32.00
= 300.00 = 300.00 300.00 Bh
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
Samping Kiri
2.00 x 3.00 = 6.00
2.00 x 4.00 = 8.00
2.00 x 11.00 = 22.00
2.00 x 3.00 = 6.00
2.00 x 3.00 = 6.00
Samping Kanan
2.00 x 19.00 = 38.00
Belakang
2.00 x 2.00 = 4.00
2.00 x 4.00 = 8.00
2.00 x 5.00 = 10.00
2.00 x 8.00 = 16.00
= 150.00 = 150.00 150.00 Bh
Samping Kiri
0.65 x 9.00 x 3.77 = 22.04
0.65 x 1.00 x 3.77 = 2.45
0.65 x 1.00 x 3.77 = 2.45
0.65 x 1.00 x 3.77 = 2.45
0.65 x 13.00 x 3.77 = 31.83
0.65 x 32.00 x 3.77 = 78.35
0.65 x 9.00 x 3.77 = 22.04
0.65 x 9.00 x 3.77 = 22.04
Samping Kanan
0.65 x 58.00 x 3.77 = 142.00
Belakang
0.65 x 6.00 x 3.77 = 14.69
0.65 x 11.00 x 3.77 = 26.93
0.65 x 16.00 x 3.77 = 39.17
0.65 x 23.00 x 3.77 = 56.31
= 568.01 = 568.01 568.01 Kg
Samping Kiri
5.00 x 22.50 = 112.50
5.00 x 2.50 = 12.50
5.00 x 2.50 = 12.50
5.00 x 2.50 = 12.50
5.00 x 32.50 = 162.50
5.00 x 80.00 = 400.00
5.00 x 22.50 = 112.50
5.00 x 21.64 = 108.20
Samping Kanan
5.00 x 143.05 = 715.25
Belakang
5.00 x 15.00 = 75.00
5.00 x 27.50 = 137.50
5.00 x 40.00 = 200.00
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
-, Pembesian
Tul- utama [ 4.00 x 12.00 ] x 96.20 x 0.89 = 341.61
Begel [ 642.00 x 8.00 ] x 0.94 x 0.39 = 238.11
= 579.72 = 579.72 579.72 Kg
-, Bekisting
[ 2.00 x 0.25 ] x 2.60 x 37.00 = 48.10 = 48.10 48.10 M2
B. Pek. Balok Beton Type BL uk. 15 x 15 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225
[ 0.15 x 0.15 ] x 2.40 x 26.00 = 1.40
[ 0.15 x 0.15 ] x 2.50 x 2.00 = 0.11
[ 0.15 x 0.15 ] x 1.95 x 4.00 = 0.18
[ 0.15 x 0.15 ] x 1.65 x 3.00 = 0.11
= 1.80 = 1.80 1.80 M3
-, Pembesian
Tul- utama [ 4.00 x 10.00 ] x 65.00 x 0.62 = 160.29
[ 4.00 x 10.00 ] x 5.20 x 0.62 = 12.82
[ 4.00 x 10.00 ] x 8.20 x 0.62 = 20.22
[ 4.00 x 10.00 ] x 5.25 x 0.62 = 12.95
Begel [ 416.00 x 8.00 ] x 0.54 x 0.39 = 88.63
[ 34.00 x 8.00 ] x 0.54 x 0.39 = 7.24
[ 52.00 x 8.00 ] x 0.54 x 0.39 = 11.08
[ 33.00 x 8.00 ] x 0.54 x 0.39 = 7.03
= 320.27 = 320.27 320.27 Kg
-, Bekisting
[ 2.00 x 0.15 ] x 2.40 x 26.00 = 18.72
[ 2.00 x 0.15 ] x 2.50 x 2.00 = 1.50
[ 2.00 x 0.15 ] x 1.95 x 4.00 = 2.34
[ 2.00 x 0.15 ] x 1.65 x 3.00 = 1.48
= 24.04 = 24.04 24.05 M2
D. Pek. Plesteran 1 : 4
[ 1.05 x 2.40 ] x 26.00 x 2.00 = 131.04
[ 1.05 x 2.50 ] x 2.00 x 2.00 = 10.50
[ 1.05 x 1.95 ] x 4.00 x 2.00 = 16.38
[ 1.05 x 1.65 ] x 3.00 x 2.00 = 10.40
= 168.32 = 168.32 168.32 M2
5.2 DRAINASE
5.2.1 Pekerjaan Saluran Tipe I Uk. 40x40 (Terbuka)
A. Pekerjaan Galian
1-2 [ 0.45 + 0.52 ] : 2.00 = 0.49 x 0.76 x 33.67 = 12.41
9-7 [ 0.65 + 0.76 ] : 2.00 = 0.71 x 0.76 x 7.80 = 4.18
14 - 5 [ 0.77 + 0.80 ] : 2.00 = 0.78 x 0.76 x 7.35 = 4.39
1 - 15 [ 0.45 + 0.54 ] : 2.00 = 0.50 x 0.76 x 17.73 = 6.67
24a - 24b [ 0.60 + 0.55 ] : 2.00 = 0.58 x 0.76 x 10.00 = 4.37
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
C. Pas. Batako
1-2 [ 0.50 + 0.15 ] = 0.65 x 33.67 = 21.89
9-7 [ 0.50 + 0.15 ] = 0.65 x 7.80 = 5.07
14 - 5 [ 0.50 + 0.15 ] = 0.65 x 7.35 = 4.78
1 - 15 [ 0.50 + 0.15 ] = 0.65 x 17.73 = 11.52
24a - 24b [ 0.50 + 0.15 ] = 0.65 x 10.00 = 6.50
23 - 24 [ 0.50 + 0.15 ] = 0.65 x 35.82 = 23.28
25 - 25a [ 0.50 + 0.15 ] = 0.65 x 18.66 = 12.13
25 - 35 [ 0.50 + 0.15 ] = 0.65 x 19.65 = 12.77
27 - 27a [ 0.50 + 0.15 ] = 0.65 x 20.09 = 13.06
28 - 29 [ 0.50 + 0.15 ] = 0.65 x 8.90 = 5.79
27 - 36 [ 0.50 + 0.15 ] = 0.65 x 21.90 = 14.24
31 - 32 [ 0.50 + 0.15 ] = 0.65 x 5.95 = 3.87
32 - 33 [ 0.50 + 0.15 ] = 0.65 x 10.43 = 6.78
33 - 34 [ 0.50 + 0.15 ] = 0.65 x 12.71 = 8.26
31 - 38 [ 0.50 + 0.15 ] = 0.65 x 5.95 = 3.87
38 - 39 [ 0.50 + 0.15 ] = 0.65 x 33.60 = 21.84
= 175.64 = 175.64 175.64 M2
-, Pembesian
Tul. U
1-2 [ 225.00 x 12.00 ] x 1.50 x 0.89 = 299.62
9-7 [ 53.00 x 12.00 ] x 1.50 x 0.89 = 70.58
14 - 5 [ 50.00 x 12.00 ] x 1.50 x 0.89 = 66.58
1 - 15 [ 119.00 x 12.00 ] x 1.50 x 0.89 = 158.47
24a - 24b [ 68.00 x 12.00 ] x 1.50 x 0.89 = 90.55
23 - 24 [ 240.00 x 12.00 ] x 1.50 x 0.89 = 319.59
25 - 25a [ 125.00 x 12.00 ] x 1.50 x 0.89 = 166.46
25 - 35 [ 132.00 x 12.00 ] x 1.50 x 0.89 = 175.78
27 - 27a [ 135.00 x 12.00 ] x 1.50 x 0.89 = 179.77
28 - 29 [ 60.00 x 12.00 ] x 1.50 x 0.89 = 79.90
27 - 36 [ 147.00 x 12.00 ] x 1.50 x 0.89 = 195.75
31 - 32 [ 41.00 x 12.00 ] x 1.50 x 0.89 = 54.60
32 - 33 [ 71.00 x 12.00 ] x 1.50 x 0.89 = 94.55
33 - 34 [ 86.00 x 12.00 ] x 1.50 x 0.89 = 114.52
31 - 38 [ 41.00 x 12.00 ] x 1.50 x 0.89 = 54.60
38 - 39 [ 225.00 x 12.00 ] x 1.50 x 0.89 = 299.62
2,420.92
Tul. Memanjang
1-2 [ 10.00 x 12.00 ] x 33.67 x 0.89 = 298.91
9-7 [ 10.00 x 12.00 ] x 7.80 x 0.89 = 69.25
14 - 5 [ 10.00 x 12.00 ] x 7.35 x 0.89 = 65.25
1 - 15 [ 10.00 x 12.00 ] x 17.73 x 0.89 = 157.40
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
-, Bekisting
1-2 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 33.67 = 34.88
9-7 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 7.80 = 9.01
14 - 5 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 7.35 = 8.56
1 - 15 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 17.73 = 18.94
24a - 24b [ 0.43 x 2.00 ] + 0.35 = 1.21 x 10.00 = 11.21
23 - 24 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 35.82 = 37.03
25 - 25a [ 0.43 x 2.00 ] + 0.35 = 1.21 x 18.66 = 19.87
25 - 35 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 19.65 = 20.86
27 - 27a [ 0.43 x 2.00 ] + 0.35 = 1.21 x 20.09 = 21.30
28 - 29 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 8.90 = 10.11
27 - 36 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 21.90 = 23.11
31 - 32 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 5.95 = 7.16
32 - 33 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 10.43 = 11.64
33 - 34 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 12.71 = 13.92
31 - 38 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 5.95 = 7.16
38 - 39 [ 0.43 x 2.00 ] + 0.35 = 1.21 x 33.60 = 34.81
289.54 = 289.54 289.54 M2
C. Pas. Batako
10 - 11 [ 0.33 + 0.33 ] = 0.66 x 14.71 = 9.71
12 - 11 [ 0.33 + 0.33 ] = 0.66 x 8.45 = 5.58
13a - 13b [ 0.33 + 0.33 ] = 0.66 x 4.17 = 2.75
13 - 14 [ 0.33 + 0.33 ] = 0.66 x 41.58 = 27.44
20 - 18 [ 0.33 + 0.33 ] = 0.66 x 44.16 = 29.15
21 - 22 [ 0.33 + 0.33 ] = 0.66 x 31.18 = 20.58
22 - 30 [ 0.33 + 0.33 ] = 0.66 x 41.59 = 27.45
22a - 24a [ 0.33 + 0.33 ] = 0.66 x 15.40 = 10.16
26a - 26 [ 0.33 + 0.33 ] = 0.66 x 5.35 = 3.53
25 - 35 [ 0.33 + 0.33 ] = 0.66 x 3.41 = 2.25
= 138.60 = 138.60 138.60 M2
-, Pembesian
Tul. U
10 - 11 [ 99.00 x 12.00 ] x 1.50 x 0.89 = 131.83
12 - 11 [ 57.00 x 12.00 ] x 1.50 x 0.89 = 75.90
13a - 13b [ 29.00 x 12.00 ] x 1.50 x 0.89 = 38.62
13 - 14 [ 278.00 x 12.00 ] x 1.50 x 0.89 = 370.20
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
-, Bekisting
10 - 11 [ 0.43 x 2.00 ] + 0.34 = 1.20 x 14.71 = 15.91
12 - 11 [ 0.43 x 2.00 ] + 0.34 = 1.20 x 8.45 = 9.65
13a - 13b [ 0.43 x 2.00 ] + 0.34 = 1.20 x 4.17 = 5.37
13 - 14 [ 0.43 x 2.00 ] + 0.34 = 1.20 x 41.58 = 42.78
20 - 18 [ 0.43 x 2.00 ] + 0.34 = 1.20 x 44.16 = 45.36
21 - 22 [ 0.43 x 2.00 ] + 0.34 = 1.20 x 31.18 = 32.38
22 - 30 [ 0.43 x 2.00 ] + 0.34 = 1.20 x 41.59 = 42.79
22a - 24a [ 0.43 x 2.00 ] + 0.34 = 1.20 x 15.40 = 16.60
26a - 26 [ 0.43 x 2.00 ] + 0.34 = 1.20 x 5.35 = 6.55
25 - 35 [ 0.43 x 2.00 ] + 0.34 = 1.20 x 3.41 = 4.61
221.98 = 221.98 221.98 M2
C. Pas. Batako
9-7 [ 0.33 + 0.33 ] = 0.66 x 14.10 = 9.31 = 9.31 9.31 M2
-, Pembesian
Tul. U
9-7 [ 95.00 x 12.00 ] x 1.50 x 0.89 = 126.51
Tul. Memanjang
9-7 [ 10.00 x 12.00 ] x 14.10 x 0.89 = 125.17
-, Bekisting
9-7 [ 0.43 x 2.00 ] + 0.34 = 1.20 x 14.10 = 15.30 = 15.30 15.30 M2
C. Pas. Batako
2-3 [ 0.70 + 0.35 ] = 1.05 x 29.65 = 31.13
15 - 16 [ 0.70 + 0.35 ] = 1.05 x 47.85 = 50.24
16 - 17 [ 0.70 + 0.35 ] = 1.05 x 31.05 = 32.60
= 113.98 = 113.98 113.98 M2
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
-, Pembesian
Tul. U
2-3 [ 199.00 x 12.00 ] x 1.90 x 0.89 = 335.66
15 - 16 [ 320.00 x 12.00 ] x 1.90 x 0.89 = 539.76
16 - 17 [ 208.00 x 12.00 ] x 1.90 x 0.89 = 350.84
1,226.26
Tul. Memanjang
2-3 [ 12.00 x 12.00 ] x 29.65 x 0.89 = 315.87
15 - 16 [ 12.00 x 12.00 ] x 47.85 x 0.89 = 509.75
16 - 17 [ 12.00 x 12.00 ] x 31.05 x 0.89 = 330.78
1,156.40
-, Bekisting
2-3 [ 0.63 x 2.00 ] + 0.35 = 1.61 x 29.65 = 31.26
15 - 16 [ 0.63 x 2.00 ] + 0.35 = 1.61 x 47.85 = 49.46
16 - 17 [ 0.63 x 2.00 ] + 0.35 = 1.61 x 31.05 = 32.66
113.37 = 113.37 113.37 M2
C. Pas. Batako
11 - 6 [ 0.53 + 0.53 ] = 1.06 x 7.90 = 8.37 = 8.37 8.37 M2
-, Pembesian
Tul. U
11 - 6 [ 54.00 x 12.00 ] x 1.90 x 0.89 = 91.08
Tul. Memanjang
11 - 6 [ 12.00 x 12.00 ] x 7.90 x 0.89 = 84.16
-, Bekisting
11 - 6 [ 0.63 x 2.00 ] + 0.34 = 1.60 x 7.90 = 9.50 = 9.50 9.50 M2
C. Pas. Batako
3a - 4 [ 0.70 + 0.35 ] = 1.05 x 39.69 = 41.67
4-5 [ 0.70 + 0.35 ] = 1.05 x 10.82 = 11.36
17 - 18 [ 0.70 + 0.35 ] = 1.05 x 108.78 = 114.22
= 167.25 = 167.25 167.25 M2
-, Pembesian
Tul. U
3a - 4 [ 266.00 x 12.00 ] x 2.10 x 0.89 = 495.90
4-5 [ 73.00 x 12.00 ] x 2.10 x 0.89 = 136.09
17 - 18 [ 726.00 x 12.00 ] x 2.10 x 0.89 = 1,353.48
1,985.48
Tul. Memanjang
3a - 4 [ 13.00 x 12.00 ] x 39.69 x 0.89 = 458.06
4-5 [ 13.00 x 12.00 ] x 10.82 x 0.89 = 124.87
17 - 18 [ 13.00 x 12.00 ] x 108.78 x 0.89 = 1,255.42
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
1,838.35
-, Bekisting
3a - 4 [ 0.63 x 2.00 ] + 0.35 = 1.61 x 39.69 = 41.30
4-5 [ 0.63 x 2.00 ] + 0.35 = 1.61 x 10.82 = 12.43
17 - 18 [ 0.63 x 2.00 ] + 0.35 = 1.61 x 108.78 = 110.39
164.11 = 164.11 164.11 M2
5.2.7 Pekerjaan Saluran Tipe IIIA Uk. 60x60 (Tertutup)
A. Pekerjaan Galian
3 - 3a [ 0.67 + 0.72 ] : 2.00 = 0.70 x 0.96 x 21.40 = 14.28 = 14.28 14.28 M3
C. Pas. Batako
3 - 3a [ 0.58 + 0.58 ] = 1.16 x 21.40 = 24.82 = 24.82 24.82 M2
-, Pembesian
Tul. U
3 - 3a [ 144.00 x 12.00 ] x 2.10 x 0.89 = 268.46
Tul. Memanjang
3 - 3a [ 13.00 x 12.00 ] x 21.40 x 0.89 = 246.97
-, Bekisting
3 - 3a [ 0.63 x 2.00 ] + 0.34 = 1.60 x 21.40 = 23.00 = 23.00 23.00 M2
C. Pas. Batako
18 - 19 [ 0.90 + 0.55 ] = 1.45 x 44.47 = 64.48 = 64.48 64.48 M2
-, Pembesian
Tul. U
18 - 19 [ 297.00 x 13.00 ] x 2.50 x 1.04 = 773.60
Tul. Memanjang
18 - 19 [ 15.00 x 12.00 ] x 44.47 x 0.89 = 592.18
-, Bekisting
18 - 19 [ 0.83 x 2.00 ] + 0.35 = 2.02 x 44.47 = 46.49 = 46.49 46.49 M2
C. Pas. Batako
5-6 [ 0.80 + 0.55 ] = 1.35 x 53.95 = 72.83
6-7 [ 0.80 + 0.55 ] = 1.35 x 19.87 = 26.82
7-8 [ 0.80 + 0.55 ] = 1.35 x 19.87 = 26.82
= 126.48 = 126.48 126.48 M2
-, Pembesian
Tul. U
5-6 [ 361.00 x 13.00 ] x 2.70 x 1.04 = 1,015.53
6-7 [ 133.00 x 13.00 ] x 2.70 x 1.04 = 374.14
7-8 [ 133.00 x 13.00 ] x 2.70 x 1.04 = 374.14
1,763.81
VOLUME
NO. SKETSA URAIAN PERHITUNGAN VOL DECIMAL STN
Tul. Memanjang
5-6 [ 17.00 x 12.00 ] x 53.95 x 0.89 = 814.21
6-7 [ 17.00 x 12.00 ] x 19.87 x 0.89 = 299.88
7-8 [ 17.00 x 12.00 ] x 19.87 x 0.89 = 299.88
1,413.96
-, Bekisting
5-6 [ 0.84 x 2.00 ] + 0.35 = 2.03 x 53.95 = 55.98
6-7 [ 0.84 x 2.00 ] + 0.35 = 2.03 x 19.87 = 21.90
7-8 [ 0.84 x 2.00 ] + 0.35 = 2.03 x 19.87 = 21.90
99.79 = 99.79 99.79 M2
-, Pembesian
Melintang [ 305.00 x 13.00 ] x 3.20 x 1.04 = 1,016.88
[ 610.00 x 13.00 ] x 2.04 x 1.04 = 1,296.52
[ 305.00 x 13.00 ] x 2.10 x 1.04 = 667.33
[ 305.00 x 13.00 ] x 3.20 x 1.04 = 1,016.88
Memanjang [ 56.00 x 13.00 ] x 36.61 x 1.04 = 2,136.03
[ 24.00 x 13.00 ] x 36.61 x 1.04 = 915.44
7,049.08 = 7,049.08 7,049.08 Kg
-, Bekisting
Pelat Alas [ 2.00 x 0.15 ] x 36.55 x 1.00 = 10.96
Pelat Dinding [ 2.00 x 0.55 ] x 36.55 x 2.00 = 80.41
[ 2.00 x 0.15 ] x 35.55 x 1.00 = 10.67
Pelat Penutup [ 2.00 x 0.15 ] x 36.55 x 1.00 = 10.96
[ 1.00 x 0.40 ] x 35.55 x 1.00 = 14.22
[ 1.00 x 0.60 ] x 34.55 x 1.00 = 20.73
[ 1.00 x 1.18 ] x 1.00 x 1.00 = 1.18
149.14 = 149.14 149.14 M2
HARGA
NO. URAIAN PEKERJAAN STN VOLUME SATUAN JUMLAH TOTAL (Rp)
(Rp)
Catatan :
Sebelum mengisi harga, pemborong wajib membaca dokumen tender dan
catatan harga dengan seksama agar sudah mengetahui kondisi yang
diminta.
HARGA
NO. URAIAN PEKERJAAN STN VOLUME SATUAN JUMLAH TOTAL (Rp)
(Rp)
b. Penyediaan tempat cuci (cleaning pit / washing bay) sebelum kendaraan
keluar Proyek termasuk peralatan dan fasilitasnya disediakan Pemborong.
HARGA
NO. URAIAN PEKERJAAN STN VOLUME SATUAN JUMLAH TOTAL (Rp)
(Rp)
15.0 Pengadaan Tenaga Listrik Ls 1.00
a. Pengadaan Penerangan sementara/buatan yang dipergunakan oleh
Pemborong untuk penerangan dalam bekerja dan lalu lintas umum di
Proyek termasuk pemindahan & perijinan meteran PLN (bila digunakan)/
Genset disediakan oleh Pemborong Utama. Pengadaan daya listrik dan
panel-panel sementara di tiap-tiap lantai di shaft-shaft Bangunan.
HARGA
NO. URAIAN PEKERJAAN STN VOLUME SATUAN JUMLAH TOTAL (Rp)
Biaya untuk menyiapkan dokumen termasuk gambar-gambar, instruksi (Rp)
operasi dan pemeliharaan dari semua peralatan yang dipasangkan.
24.0 Biaya pengetesan, commissioning dan star-up termasuk operasi lengkap Ls 1.00
dengan instalasi dan penyediaan tenaga listrik, sarana lain yang diperlukan
dan sesuai kondisi Spesifikasi Teknis dan petunjuk dari Pabrik.
BILL OF QUANTITY
PEKERJAAN : PEMBANGUNAN DC MADIUN ALFA MART
LOKASI : KOTA MADIUN JAWA TIMUR
a b c d e f=dxe g
2.0 WIREHOUSE
2.3 Pekerjaan Architech
2.3.1 Pekerjaan Pas. Bata 1 : 4, Wire House Dan Gudang Kardus
A. Pasangan Batu Bata 1 : 4 M2 999.02 -
B. Pasangan Bata Roster, (Area Charger forklif) M2 9.60 -
C. Pek. Kolom Praktis Kp Uk. 130 x 130 MM
-, Beton Site MIx K-175 M3 4.56 -
-, Pembesian Kg 946.38 -
-, Bekisting M2 70.23 -
D. Pek. Balok Beton Type rb uk. 13 x 20 cm
-, Beton Site MIx K-175 M3 3.31 -
-, Pembesian Kg 475.24 -
-, Bekisting M2 38.22 -
E. Pek. Balok Beton rbt Uk. 13x20
-, Beton Site MIx K-175 M3 7.66 -
-, Pembesian Kg 997.59 -
-, Bekisting M2 101.20 -
Jumlah -
2.3.2 Pekerjaan Finishing Lantai
Finish lantai gudang super flat Floor hardener 3kg/m2 ex Besroc (Type 10)
A. Beton Plat Area Gudang As-1-15/As-A-Q' M2 7,597.25 -
B. Beton Plat Area Loading Dock Include Area Kantor As-15-16/As-A-T M2 374.50 -
C. Beton Plat Area Gudang Kardus As-1-8/As-A'-A M2 168.00 -
Finish lantai gudang flat Flowfresh MF T=3 mm Ex Flow Creed (type 11) Aplicator bebas
D. Super Flat Flowcreed u/ Parkir Forklif M2 87.68 -
E. Super Flat Flowcreed u/ Charger Forklif M2 44.40 -
Pekerjaan Pengecatan
C. Pengecatan dinding Exterior Ex. Propan M2 1,648.10 -
D. Pengecatan dinding Interior Ex. Propan M2 1,541.73 -
a b c d e f=dxe g
2.3.5. Pekerjaan Arsitek Protektor & Stopper
Pekerjaan Protektor & stoper include pengadaan, installing dan accessories.
A. Pekerjaan Protector Type 1, Detail Lihat Gambar (''Provesional Sum'') Unit 13.00 -
B. Pekerjaan Protector Type 2, Detail Lihat Gambar (''Provesional Sum'') Unit 1.00 -
C. Pekerjaan Protector Type 2A, Detail Lihat Gambar (''Provesional Sum'' Unit 1.00 -
D. Pekerjaan Protector Type 3, Detail Lihat Gambar (''Provesional Sum'') Unit 1.00 -
E. Pekerjaan Protector Type 4, Detail Lihat Gambar (''Provesional Sum'') Unit 13.00 -
F. Pekerjaan Protector Type 5, Detail Lihat Gambar (''Provesional Sum'') Unit 17.00 -
G. Pekerjaan Stoper Type A Black PIPE Dia 2,5'' T: 3,6 mm M' 25.45 -
Jumlah -
2.3.6. Pekerjaan Atap
Pekerjaan atap, termasuk biaya mob de mobilisasi alat bantu, material dan jasa pemasangan.
A. Atap Zincalum 0,45 TCT klip lock tanpa sambungan (roll on side) M2 8,076.68 -
E. Sky light t:1,2mm ex Intec, warna putih susu. (lebar efektif 633.3 mm M' 923.93 -
H. Pek. Bak Kontrol Saluran Air Hujan Uk. 30x30x30CM Unit 17.00 -
Jumlah -
2.3.7. Pekerjaan Bumper
A. Bumper Solid Rubber 80 x10x8 cm, Unit 30.00 -
B. Siku 70.70.7 Galvanised u/bibir loading dock termasuk pekerjaan angk M' 107.20 -
Jumlah -
2.4 Pekerjaan lain-lain
A. Corner Dinding RG. Obat, Finish Alumunium Curve, include perapian d M' 70.35 -
B. List Plafond Model Curve Material Gypsum. Include perapian dan alat M' 38.95 -
Corner Guard Pintu Rolling Door, pekerjaan include pemasangan, material, alat bantu dan material bantu
C. Besi Siku 50.50.3,8 Termasuk Pengecatan Warna Kuning Dan Hitam M' 90.00 -
Jumlah -
3 OFFICE
3.5 Pekerjaan Arsitek Lantai I
3.5.1. Pekerjaan Pasangan Brick Wall
Pekerjaan pasangan bata ringan dan bata merah alat bantu, perapian dan tenaga kerja.
A. Pasangan Batu Bata 1 : 4 0 1,592.46 -
B. Pasangan Batu Bata 1 : 4 (Area Shaft) 0 45.73 -
C. Pasangan Glass Block Uk. 20x20 Cm, GB1 M2 19.20 -
D. Pek. Kolom Praktis Kp1 Uk. 130 x 130 MM
-, Beton Site MIx K-175 M3 10.99 -
-, Pembesian Kg 2,278.97 -
-, Bekisting M2 169.13 -
E. Pek. Balok Beton Type rb uk. 13 x 20 cm
-, Beton Site MIx K-175 M3 507.68 -
-, Pembesian Kg ### -
-, Bekisting M2 78.11 -
a b c d e f=dxe g
3.5.2. Pekerjaan Finishing Lantai
Pekerjaan Homogenius tile 600x600mm type Antique White Ex.Sandimas, include material, adukan dan tenaga kerja.
A. Homogenius tile Area Office M2 722.54 -
B. Homogenius tile Area Tangga Utama + Stopnozing M2 16.66 -
C. Plin Dinding Homogenius Tile M' 352.63 -
Pekerjaan Homogenius tile 600x600mm Type Salsa Crystal Black , include material, adukan dan tenaga kerja.
D. Homogenius tile Area Entrance Depan M2 11.18 -
E. Homogenius tile Area Tangga Entrance Depan + Stopnozing M2 15.36 -
Pekerjaan Keramik 400x400mm (polished) Ex.Ikad , include material, adukan dan tenaga kerja.
F. Keramik Area Lobby Samping + Tangga M2 18.30 -
G. Keramik Area Tangga Samping + Stopnozing M2 16.66 -
H. Plin Dinding Keramik M' 9.70 -
Pekerjaan Keramik 400x400mm (Unpolished) Ex.Ikad , include material, adukan dan tenaga kerja.
I. Keramik Area Toilet, Pantry dan Janitor M2 69.58 -
Lantai finish Floor hardener, include material, tenaga kerja dan alat bantu
J. Finishing floor hardener area G. MKT, G.GA, G.COKELAT, R. ATK Da M2 409.31 -
Jumlah -
Pekerjaan Pengecatan
F. Pengecatan dinding Exterior Ex. Propan M2 1,302.99 -
G. Pengecatan dinding Interior Ex. Propan M2 1,954.49 -
H. Pekerjaan Naad dan Perapian Dinding Atas Keramik Termasuk Plin Di M' 464.07 -
I. Pekerjaan Naad dan Pearapian Dinding Luar M' 292.70 -
Jumlah -
3.5.4. Pekerjaan Dinding Partisi
Pekerjaan Dinding Partisi Gypsum Termasuk Rangka dan Pengecatan
A. Pek. Partisi gypsum Dua Sisi H: 3.700 MM, include rangka dan finishin M2 213.36 -
B Pek. Partisi gypsum Dua Sisi H: 2.700 MM, include rangka dan finishin M2 70.94 -
C Pek. Partisi gypsum Dua Sisi H: 1.200 MM, include rangka dan finishin M2 26.70 -
D. Pek. Partisi Ruang Lobby Multiplek Fin. HPL dan Kalsi Part T=8 MM F M2 15.80 -
E. Plin Bawah Dinding Partisi Multiplek T=18 MM Uk. 18x100 MM, Fin. H M' 152.66 -
F. Profil U Dinding Partisi Multiplek T=18 MM Uk. 5 x10 Cm, Fin. HPL M' 11.13 -
Jumlah -
3.5.5. Pekerjaan Arsitek Pintu
Pekerjaan Pintu include pengadaan, installing dan accessories(ironmongery ex Dekkson).
Pintu Enginering Door, finish HPL, kusen alumunium
A. Pintu Type P1 Unit 2.00 -
B. Pintu Type P2 Unit 14.00 -
C. Pintu Type P2' Unit 1.00 -
D. Pintu Type P3 Unit 2.00 -
E. Pintu Type P4 Unit 5.00 -
F. Pintu Type P5 Unit 8.00 -
G. Pintu Type PS Unit 3.00 -
Pekerjaan Pintu Rolling Door, Material dan pemasangan Supplay By Owner. Perapian openingan include kontraktor
J. Pintu Rolling Door Type RD1 Unit 1.00 -
a b c d e f=dxe g
S. Jendela Kawat harmonika Type JK7 Unit 1.00 -
Jumlah -
Pekerjaan Pengecatan
F. Pekerjaan cat plafond gypsum board & beton exposed dibawah tangga M2 933.91 -
Pekerjaan cat include material, tenaga kerja, alat bantu dan perapian)
Jumlah -
3.5.8. Pekerjaan Arsitek Sanitary
Pekerjaan Sanitary include material , installing dan accessories. Unit Ex TOTO . ''Provesional Sum''
A. Closed Jongkok Type CE6 Ex TOTO hanya pemasangan dan instalas Unit 3.00 -
B. Partition Urinal A100 Ex Toto Unit 8.00 -
C. Wall Hung Lavatory Type LW240CJ inc keran lavatory Ex. TOTO hany Unit 5.00 -
D. Kran Dinding Type Y 20JC Ex San Ei Unit 5.00 -
E. Floor Drain Dia 4" Type H51 Ex SAN EI Unit 9.00 -
F. Shower Spray S403SBW Ex. TOTO hanya pemasangan dan instalasi Unit 5.00 -
G. Closet Duduk Type CW 421 J/SW 420 JP Ex. TOTO hanya pemasangan Unit 5.00 -
H. Urinoir type U57M Ex TOTO Unit 5.00 -
I. Kaca Cermin Tebal 5mm + Bevel Ex. Asahimas by maincon. (ukuran Unit 5.00 -
J. Kitchen zick Single Bowl Ex Royal Unit 2.00 -
K. Kran Pantry Model Leher Angsa A10C Ex SAN EI Unit 2.00 -
Jumlah -
3.5.9. Pekerjaan Entrance
Pas. Alumunium Composite panel Ex. Alucopan, Untuk Kanopi Entrance Depan
A. Pas. Alumunium Composite panel Ex. Alucopan, Untuk Kanopi Entran M2 55.49 -
B. Pek. Ramp Teras Lobby Include Grove (Pekerjaan Beton T=70 MM, Ls 2.00 -
C. Pek. Planter Box + Batu Alam Dinding, (include pekerjaan struktural pl Ls 2.00 -
Jumlah -
3.5.10. Pekerjaan Lain-Lain
A. Pek. Hand Railling Tangga Lobby (Pipa Stainlesstell 2,5'' Dan 2") M' 12.90 -
B. Pek. Hand Railling Tangga Lobby Samping (Pipa Stainlesstell 2,5'' Da M' 8.40 -
C. Pek. Hand Railling Tangga Samping (Pipa Stainlesstell 2") M' 7.30 -
D Pekerjaan Meja Beton Watafel dan Pantry T= 100mm, include pas. ke M2 3.09 -
E. Tanggulan Janitor dan Tempat Wudhu, include pasangan bata, pasang M' 5.55 -
F. Dudukan Closet Jongkok, Pas. Bata H: 200mm, termasuk alat bantu d M2 2.66 -
Corner Guard Pintu Rolling Door RD1, pekerjaan include pemasangan, material, alat bantu dan material bantu
G. Besi Siku 50.50.3.8 Termasuk Pengecatan (dua warna Kuning dan Hit M' 3.00 -
a b c d e f=dxe g
-, Pembesian Kg 1,192.30 -
-, Bekisting M2 88.48 -
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
E. Pek. Balok Beton Type rb uk. 13 x 20 cm
-, Beton Site MIx K-175 M3 7.74 -
-, Pembesian Kg 1,136.42 -
-, Bekisting M2 119.01 -
Pekerjaan Keramik 400x400mm (Unpolished) Ex.Ikad , include material, adukan dan tenaga kerja.
C. Keramik Area Toilet, Pantry dan Janitor M2 69.83 -
D. Screed Waterproofing, M2 93.63 -
E. Waterproofing Liquid Membrant Include Overlap ke Dinding 30 Cm M2 93.63 -
Jumlah -
3.6.3. Pekerjaan Finishing Dinding
A. Plesteran 1 : 4 Dinding Bata, Termasuk Plesteran Kolom, dan Balok M2 1,167.93 -
B. Acian Plesteran M2 1,167.93 -
C. Plesteran 1:4, Opening Kusen + Acian M' 398.61 -
D. Pas. Keramik Dinding Uk. 200x400 MM (Toilet dan Janitor) M2 248.20 -
E. Pas. Keramik Dinding Uk. 300x300 MM (Pantry) M2 1.80 -
Pekerjaan Pengecatan
F. Pengecatan dinding Exterior Ex. Propan M2 467.17 -
G. Pengecatan dinding Interior Ex. Propan M2 700.76 -
H. Pekerjaan Naad dan Pearapian Dinding Atas Keramik M' 95.65 -
I. Pekerjaan Naad dan Pearapian Dinding Luar M' 222.50 -
Jumlah -
3.6.4. Pekerjaan Dinding Partisi
Pekerjaan Dinding Partisi Gypsum Termasuk Rangka dan Pengecatan
A. Pek. Partisi gypsum Dua Sisi H: 2.700 MM, include rangka dan finishin M2 559.21 -
B. Pek. Partisi gypsum Dua Sisi H: 1.200 MM, include rangka dan finishin M2 243.23 -
C. Plin Bawah Dinding Partisi Multiplek T=18 MM Uk. 18x100 MM, Fin. H M' 401.42 -
D. Profil U Dinding Partisi Multiplek T=18 MM Uk. 5 x10 Cm, Fin. HPL M' 101.35 -
Jumlah -
3.6.5. Pekerjaan Arsitek Pintu
Pekerjaan Pintu include pengadaan, installing dan accessories(ironmongery ex Dekkson).
Pintu Enginering Door, finish HPL, kusen alumunium
A. Pintu Type P1 Unit 1.00 -
B. Pintu Type P2 Unit 11.00 -
C. Pintu Type P3 Unit 3.00 -
D. Pintu Type P4 Unit 5.00 -
E. Pintu Type P5 Unit 8.00 -
F. Pintu Type PS Unit 2.00 -
Pintu dan Jendela alumunium Pekerjaan pintu jendela, detail accessories Lihat Di DWS
G. Pintu Dan Jendela Type PJ5 Unit 1.00 -
Pintu Lipat, detail accessories Lihat Di DWS
H. Pintu Lipat M2 44.04 -
Pekerjaan Pengecatan
C. Pekerjaan cat plafond gypsum board M2 206.20 -
Pekerjaan cat include material, tenaga kerja, alat bantu dan perapian)
Jumlah -
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
3.6.8. Pekerjaan Arsitek Sanitary
Pekerjaan Sanitary include material , installing dan accessories. Unit Ex TOTO . ''Provesional Sum''
A. Closed Jongkok Type CE6 Ex TOTO hanya pemasangan dan instalas Unit 4.00 -
B. Partition Urinal A100 Ex Toto Unit 2.00 -
C. Wall Hung Lavatory Type LW240CJ inc keran lavatory Ex. TOTO hany Unit 4.00 -
D. Kran Dinding Type Y 20JC Ex San Ei Unit 10.00 -
E. Floor Drain Dia 4" Type H51 Ex SAN EI Unit 10.00 -
F. Shower Spray S403SBW Ex. TOTO hanya pemasangan dan instalasi Unit 4.00 -
G. Closet Duduk Type CW 421 J/SW 420 JP Ex. TOTO hanya pemasangan Unit 4.00 -
H. Urinoir type U57M Ex TOTO Unit 4.00 -
I. Kaca Cermin Tebal 5mm + Bevel Ex. Asahimas by maincon. (ukuran Unit 4.00 -
J. Kitchen zick Single Bowl Ex Royal Unit 1.00 -
K. Kran Pantry Model Leher Angsa A10C Ex SAN EI Unit 1.00 -
B. Tanggulan Janitor dan Tempat Wudhu, include pasangan bata, pasang M' 5.55 -
C. Dudukan Closet Jongkok, Pas. Bata H: 200mm, termasuk alat bantu d M2 4.05 -
D. Tangga maintenance include pekerjaan pipa baja dia 5'' + siku 50.50.5 Unit 1.00 -
Reilling Pipa 1"pengecatan, alat bantu dan material bantu.
Jumlah -
3.7 Pekerjaan Arsitek Atap
3.7.1. Pekerjaan Pasangan Brick Wall
Pekerjaan pasangan bata ringan dan bata merah alat bantu, perapian dan tenaga kerja.
A. Pasangan Batu Bata 1 : 4 M2 46.36 -
B. Pek. Kolom Praktis Kp1 Uk. 130 x 130 MM
-, Beton Site MIx K-175 M3 0.42 -
-, Pembesian Kg 87.41 -
-, Bekisting M2 6.47 -
a b c d e f=dxe g
4 SUPPORTING BUILDING
4.1 POS JAGA
4.1.1 Pekerjaan Tanah dan Pondasi
Pekerjaan tanah menyangkut semua pekerjaan galian dan urugan, penawaran include dengan jasa tenaga kerja, alat bantu dan materil.
A. Pek. Galian Tanah Pondasi M3 4.48 -
B. Urugan Kembali Bekas Galian Tanah M3 1.12 -
C. Urugan Tanah Bawah Lantai T=35 cm Pakai Bekas Galian M3 1.11 -
D. Urugan Pasir Bawah Pondasi Batu Kali M3 0.32 -
E. Pek. Pondasi Batu Kali, 1 Pc : 4 Ps M3 3.66 -
F. Pek. Stek Pondasi Dia-10-1000 MM, L= 500MM Kg 2.47 -
Jumlah -
4.1.2 Pekerjaan Beton
A. Pek. Sloof Beton Type S1 uk. 150 x 250 mm , Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.30 -
-, Pembesian Kg 42.05 -
-, Bekisting M2 4.00 -
B. Pek. Kolom Praktis K1 Uk. 200 x 200 mm, Besi 6 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.50 -
-, Pembesian Kg 87.03 -
-, Bekisting M2 9.92 -
C. Pek. Balok Beton Type RB uk. 15 x 25 cm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.30 -
-, Pembesian Kg 42.05 -
-, Bekisting M2 4.00 -
D. Pek. Balok Beton Type BL uk. 11 x 15 cm,Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.13 -
-, Pembesian Kg 28.21 -
-, Bekisting M2 2.40 -
Pekerjaan Pengecatan
G. Pengecatan dinding Exterior Ex. Propan M2 23.97 -
H. Pengecatan dinding Interior Ex. Propan M2 15.98 -
Jumlah -
4.1.4 Pekerjaan Finishing Lantai
Pekerjaan Keramik 400x400mm (polished) Ex.Ikad , include material, adukan dan tenaga kerja.
A. Keramik Pos Jaga M2 3.17 -
B. Plin Dinidng Keramik M' 6.66 -
Jumlah -
4.1.5 Pekerjaan Arsitek Pintu dan Jendela
Pekerjaan Pintu include pengadaan, installing dan accessories(ironmongery ex Dekkson).
Pintu Kaca Rangka dan Kusen alumunium
A. Pintu Type PJ1 Unit 1.00 -
a b c d e f=dxe g
4.1.6 Pekerjaan Lain-Lain
Pekerjaan Waterproofing LantaI Dak Atap
A. Screed Waterproofing, M2 11.65 -
B. Waterproofing Liquid Membrant Include Overlap ke Dinding 30 Cm M2 11.65 -
C. Pek. Pengecatan Plafon Beton Expose M2 11.65 -
D. Pek. Saluran Vertikal Air Hujan Pipa Dia-2" M' 2.00 -
E. Pas. Roof Drain Dia 2" Unit 2.00 -
Jumlah -
B. Pek. Kolom Praktis Kp Uk. 130 x 130 mm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 1.04 -
-, Pembesian Kg 283.50 -
-, Bekisting M2 32.11 -
C. Pek. Balok Beton Type rb uk. 13 x 20 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 1.09 -
-, Pembesian Kg 160.63 -
-, Bekisting M2 16.80 -
D. Pek. Balok Beton Type BL uk. 11 x 15 cm,Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.69 -
-, Pembesian Kg 147.31 -
-, Bekisting M2 12.60 -
Pekerjaan Pengecatan
I. Pengecatan dinding Exterior Ex. Propan M2 0.40 -
J. Pengecatan dinding Interior Ex. Propan M2 0.59 -
Jumlah -
4.2.4 Pekerjaan Atap
Pekerjaan atap, termasuk biaya mob de mobilisasi alat bantu, material dan jasa pemasangan.
A. Pek. Rangka Atap Baja Ringan M2 131.60 -
B. Atap Zincalum 0,40 TCT Klip lock M2 131.60 -
C. Lisplank Zincalumn T: 0,4 TCT MP Deck M2 23.45 -
D. Flasing Zincalum 0,4 TCT M' 18.60 -
E. Nok Atap Zincalum 0,40 TCT M' 14.15 -
Jumlah -
4.2.5 Pekerjaan Finishing Lantai
Pekerjaan Keramik 400x400mm (polished) Ex.Ikad , include material, adukan dan tenaga kerja.
A. Keramik Pos Security, Locker dan Rg, tunggu Sopir M2 58.02 -
B. Plin Keramik Dinding M' 47.85 -
Pekerjaan Keramik 400x400mm (Unpolished) Ex.Ikad , include material, adukan dan tenaga kerja.
B. Keramik Area Toilet M2 2.50 -
Jumlah -
4.2.6 Pekerjaan Arsitek Pintu dan Jendela
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
Pekerjaan Pintu include pengadaan, installing dan accessories(ironmongery ex Dekkson).
Pintu Enginering Door, finish HPL, kusen alumunium Dan Pintu Kaca
A. Pintu Type P1 Unit 1.00 -
Pekerjaan Pengecatan
C. Pekerjaan cat plafond gypsum board & Palfon Kalsi Link M2 83.49 -
Pekerjaan cat include material, tenaga kerja, alat bantu dan perapian)
Jumlah -
4.3 RUMAH GENSET, RUANG POMPA, RUANG TANGKI BAHAN BAKAR DAN FIRE WATER TANK
4.3.1 Pekerjaan Tanah dan Pondasi
Pekerjaan tanah menyangkut semua pekerjaan galian dan urugan, penawaran include dengan jasa tenaga kerja, alat bantu dan materil.
Pondasi Plat Setempat
A. Galian Tanah Pondasi M3 13.20 -
B. Urugan Bekas galian M3 7.70 -
C. Urugan Pasir Alas Pondasi M3 0.55 -
D. Pek. Lantai Kerja pondasi M3 0.55 -
E. Pek. Pondasi Plat Tapak P1
-, Beton Site MIx K-225 M3 3.30 -
-, Pembesian Kg 559.01 -
-, Bekisting M2 13.20 -
B. Pek. Sloof Beton Type S2 uk. 150 x 250 mm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-225 M3 0.45 -
-, Pembesian Kg 49.91 -
-, Bekisting M2 6.00 -
C. Pek. Kolom Praktis K1 Uk. 300 x 300 mm, Besi 6 Ø16, Sengkang Ø8-100 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225 M3 3.81 -
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
-, Pembesian Kg 553.87 -
-, Bekisting M2 50.82 -
D. Pek. Kolom Praktis Kp Uk. 130 x 130 mm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-225 M3 0.23 -
-, Pembesian Kg 46.95 -
-, Bekisting M2 6.94 -
E. Pek. Balok Beton Type RB1 uk. 20 x 40 cm , Besi 6 Ø16 (Tump) Besi 5 Ø16 (Lap), Sengkang Ø8-100 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225 M3 3.19 -
-, Pembesian Kg 700.34 -
-, Bekisting M2 57.00 -
F. Pek. Balok Beton Type BL uk. 11 x 15 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-225 M3 0.49 -
-, Pembesian Kg 104.93 -
-, Bekisting M2 8.97 -
K. Pek. Rabat Beton K-175, Lantai Genset Dan Rumah Pompa T=10 Cm M3 6.79 -
M. Pek. Beton Dinding Fire Water Tank T=25 Cm & T=20 Cm, Besi Ø13-15 (vertikal), Besi Ø10-15 (Horizontal)
-, Beton Site MIx K-300 M3 24.84 -
-, Pembesian Kg 2,184.97 -
-, Bekisting M2 161.60 -
Pekerjaan Pengecatan
G. Pengecatan dinding Exterior Ex. Propan M2 141.71 -
H. Pengecatan dinding Interior Ex. Propan M2 212.57 -
Jumlah -
4.3.4 Pekerjaan Atap
Pekerjaan atap, termasuk biaya mob de mobilisasi alat bantu, material dan jasa pemasangan.
A. Pek. Tiang Kuda-Kuda Besi Pipa Dia-3" T=3 MMFin. Cat, Rg Tangki Kg 203.95 -
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
B. Pek. Gording CNP 150.65.20.3,2 Kg 231.70 -
C. Atap Zincalum 0,40 TCT Klip lock tanpa sambungan (roll on side) M2 26.00 -
Jumlah -
4.3.5 Pekerjaan Finishing Lantai
Finish lantai super flat Floor hardener 3kg/m2 ex Besroc (Type 10)
A. Beton Plat Area Rg. Genset Dan Rumah Pompa M2 56.75 -
Jumlah -
4.3.6 Pekerjaan Arsitek Pintu dan Jendela
Pekerjaan Pintu Besi
A. Pintu Besi Type PB1 (1000x2100mm) Unit 1.00 -
B. Pintu Besi Type PB5 (2200x2100mm) Unit 1.00 -
C. Pintu Besi Type PB4 (800x1900mm) Unit 1.00 -
B. Pek. Kolom Praktis Kp Uk. 130 x 130 mm,Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 2.20 -
-, Pembesian Kg 596.64 -
-, Bekisting M2 67.60 -
C. Pek. Balok Beton Type rb uk. 13 x 20 cm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 2.65 -
-, Pembesian Kg 389.75 -
-, Bekisting M2 40.80 -
D. Pek. Balok Beton Type BL uk. 11 x 15 cm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.90 -
-, Pembesian Kg 190.40 -
-, Bekisting M2 16.29 -
a b c d e f=dxe g
F. Plesteran 1:4, Opening Kusen + Acian M' 60.94 -
G. Pas. Keramik Dinding Uk. 200x400 MM (Toilet dan T. Wudhuk) M2 78.66 -
H. Pas. Keramik Dinding Uk. 300x300 MM (Pantry) M2 3.33 -
I. Pekerjaan Naad dan Pearapian Dinding Atas Keramik Termasuk pada M' 112.80 -
J. Pekerjaan Profil Beton Dinding Luar M' 116.26 -
Pekerjaan Pengecatan
I. Pengecatan dinding Exterior Ex. Propan M2 0.40 -
J. Pengecatan dinding Interior Ex. Propan M2 0.59 -
Jumlah -
4.4.4 Pekerjaan Atap
Pekerjaan atap, termasuk biaya mob de mobilisasi alat bantu, material dan jasa pemasangan.
A. Pek. Rangka Atap Baja Ringan M2 252.50 -
B. Atap Zincalum 0,40 TCT Klip lock M2 252.50 -
C. Lisplank Zincalumn T: 0,4 TCT MP Deck M2 31.80 -
D. Flasing Zincalum 0,4 TCT M' 9.30 -
E. Nok Atap Zincalum 0,40 TCT M' 27.15 -
Jumlah -
4.4.5 Pekerjaan Finishing Lantai
Pekerjaan Keramik 400x400mm (polished) Ex.Ikad , include material, adukan dan tenaga kerja.
A. Keramik Mushalla, Kantin Dan Kantor trac M2 111.44 -
B. Plin Lantai Keramik M' 69.80
Pekerjaan Keramik 400x400mm (Unpolished) Ex.Ikad , include material, adukan dan tenaga kerja.
C. Keramik Area Toilet, tempat Wudhuk M2 22.73 -
Jumlah -
4.4.6 Pekerjaan Arsitek Pintu dan Jendela
Pekerjaan Pintu include pengadaan, installing dan accessories(ironmongery ex Dekkson).
Pintu Kaca Rangka Dan Kusen Alumunium
A. Pintu Type P1 Unit 1.00 -
Pekerjaan Pengecatan
C. Pekerjaan cat plafond gypsum board & beton exposed dibawah tangga M2 215.04 -
Jumlah -
a b c d e f=dxe g
C. Urugan Tanah Bawah Lantai T=35 cm Pakai Bekas Galian M3 10.50 -
D. Urugan Pasir Bawah Lantai T=10 cm M3 3.00 -
E. Pek. Pondasi Batu Kali, 1 Pc : 4 Ps M3 5.18 -
F. Pek. Stek Pondasi Dia-10-1000 MM, L= 500MM Kg 3.08 -
Jumlah -
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
4.5.2 Pekerjaan Beton
A. Pek. Kolom K1 Uk. 200 x 200 mm, Besi 6 Ø12, Sengkang Ø8-100 mm
-, Beton Site MIx K-175 M3 0.18 -
-, Pembesian Kg 36.58 -
-, Bekisting M2 3.52 -
B. Pek. Kolom KP Uk. 130 x 130 mm, Besi 4 Ø12, Sengkang Ø8-150 mm, Ø8-200 mm
-, Beton Site MIx K-175 M3 0.03 -
-, Pembesian Kg 12.32 -
-, Bekisting M2 0.88 -
C. Pek. Balok Beton Type BL uk. 11 x 15 cm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.18 -
-, Pembesian Kg 38.72 -
-, Bekisting M2 3.30 -
B. Pek. Kolom Praktis Kp Uk. 130 x 130 mm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.52 -
-, Pembesian Kg 250.24 -
-, Bekisting M2 28.34 -
C. Pek. Balok Beton Type rb uk. 13 x 20 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 1.30 -
-, Pembesian Kg 191.18 -
-, Bekisting M2 20.00 -
D. Pek. Balok Beton Type BL uk. 11 x 15 cm,Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.41 -
-, Pembesian Kg 87.76 -
-, Bekisting M2 7.50 -
a b c d e f=dxe g
Jumlah -
4.6.3 Pekerjaan Pasangan dan Finishing Dinding
Pekerjaan pasangan bata ringan dan bata merah alat bantu, perapian dan tenaga kerja.
A. Pasangan Batu Bata 1 : 4 M2 100.29 -
B. Plesteran 1 : 4 M2 200.58 -
C. Acian Plesteran M2 200.58 -
D. Plesteran 1:4, Opening Kusen + Acian M' 40.08 -
Pekerjaan Pengecatan
E. Pengecatan dinding Exterior Ex. Propan M2 90.26 -
F. Pengecatan dinding Interior Ex. Propan M2 110.32 -
Jumlah -
4.6.4 Pekerjaan Atap
Pekerjaan atap, termasuk biaya mob de mobilisasi alat bantu, material dan jasa pemasangan.
A. Pek. Tiang Besi Pipa Dia-3" T=3 MM Fin. Cat Kg 10.08 -
B. Pek. Kuda Besi Pipa Dia-3" T=3 MM Fin. Cat Kg 207.45 -
C. Pek. Gording CNP 150.65.20.3,2 Kg 936.05 -
D. Atap Zincalum 0,40 TCT Klip lock M2 97.01 -
Jumlah -
4.6.5 Pekerjaan Arsitek Pintu
Pekerjaan Pintu Besi
A. Pintu Type PB7, (1500x1500mm) Unit 2.00 -
B. Pintu Type PB7', (1500x2100mm) Unit 2.00 -
Pekerjaan Pintu & Jendela Kawat Harmonika, detail lihat digambar. Pekerjaan include accesories.
C. Jendela JK1 (Area Limbab B3) Unit 4.00 -
Jumlah -
4.6.6 Pekerjaan Tempat Sampah Cair
Beton Struktur Limbah Cair
A. Pek. Beton Lantai T=15 Cm, Besi Ø10-15.
-, Beton Site MIx K-300 M3 1.02 -
-, Pembesian Kg 133.00 -
-, Bekisting M2 1.59 -
B. Pek. Kolom Praktis Kp Uk. 130 x 130 mm,Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.77 -
-, Pembesian Kg 208.94 -
-, Bekisting M2 23.66 -
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
C. Pek. Balok Beton Type rb uk. 13 x 20 cm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 1.14 -
-, Pembesian Kg 168.26 -
-, Bekisting M2 17.60 -
D. Pek. Balok Beton Type BL uk. 11 x 15 cm , Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-175 M3 0.26 -
-, Pembesian Kg 56.23 -
-, Bekisting M2 4.80 -
Pekerjaan Pengecatan
E. Pengecatan dinding Exterior Ex. Propan M2 133.48 -
F. Pengecatan dinding Interior Ex. Propan M2 133.48 -
Jumlah -
4.7.4 Pekerjaan Atap
Pekerjaan atap, termasuk biaya mob de mobilisasi alat bantu, material dan jasa pemasangan.
A. Atap Zincalum 0,40 TCT klip lock M2 168.80 -
B. Lisplank Zincalumn T: 0,4 TCT MP Deck M2 22.80 -
C. Flasing Zincalum 0,4 TCT M' 9.30 -
D. Nok Atap Zincalum 0,40 TCT M' 18.15 -
Jumlah -
4.7.5 Pekerjaan Finishing Lantai
Finish lantai Floor hardener 3kg/m2 ex Besroc
A. Beton Plat Lantai Gudang Arsip M2 92.72 -
Jumlah -
4.7.6 Pekerjaan Arsitek Pintu dan Jendela
Pekerjaan Pintu Besi
A. Pintu Type PB3, (1600x2400mm) Unit 1.00 -
Pekerjaan Pintu & Jendela Kawat Harmonika, detail lihat digambar. Pekerjaan include accesories.
B. Jendela JK2 (Area Gudang Arsip) Unit 4.00 -
Jumlah -
B. Pek. Kolom Praktis K1 Uk. 300 x 300 mm, Besi 6 Ø16, Sengkang Ø8-100 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225 M3 1.97 -
-, Pembesian Kg 286.64 -
-, Bekisting M2 26.28 -
C. Pek. Kolom Praktis Kp Uk. 130 x 130 mm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-225 M3 0.14 -
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
-, Pembesian Kg 30.13 -
-, Bekisting M2 2.22 -
D. Pek. Balok Beton Type RB1 uk. 20 x 40 cm , Besi 6 Ø16 (Tump) Besi 5 Ø16 (Lap), Sengkang Ø8-100 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225 M3 1.53 -
-, Pembesian Kg 368.81 -
-, Bekisting M2 27.30 -
E. Pek. Balok Beton Type BL uk. 11 x 15 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-200 mm (Lap)
-, Beton Site MIx K-225 M3 0.24 -
-, Pembesian Kg 50.98 -
-, Bekisting M2 4.35 -
Pekerjaan Pengecatan
E. Pengecatan dinding Exterior Ex. Propan M2 77.15 -
F. Pengecatan dinding Interior Ex. Propan M2 77.15 -
Jumlah -
4.8.4 Pekerjaan Arsitek Pintu dan Jendela
Pekerjaan Pintu Besi
A. Pintu Besi Type PV1 (1350x2850mm) Unit 1.00 -
Pekerjaan Ventilasi include pengadaan, installing dan accessories.
B. Pekerjaan Ventilasi detail accessories lihat di DWS u/ Jendela Type B Unit 3.00 -
C. Pekerjaan Ventilasi detail accessories lihat di DWS u/ Jendela Type B Unit 4.00 -
Jumlah -
4.8.5 Pekerjaan Lain-Lain
Pekerjaan Waterproofing Lantai, Dinding dan Dak Atap Fire Water tank, Dak Atap Ruang Genset dan Rumah Pompa
A. Screed Waterproofing, M2 41.25 -
B. Waterproofing Liquid Membrant Include Overlap ke Dinding 30 Cm M2 41.25 -
C. Pas. Tutup Menhole Dengan Besi Plat T= 2 MM rangka Siku 50.50.5 Unit 4.00 -
D. Pek. Saluran Vertikal Air Hujan Pipa Dia-2.5" M' 9.10 -
E. Pas. Roof Drain Dia 2.5" Unit 2.00 -
F. Pek. Rabat Dan Saluran Keliling M' 26.70 -
Jumlah -
a b c d e f=dxe g
4.9.2. Pekerjaan Konstruksi Baja
A. Pek. Base Plat T = 15 mm Kg 29.44 -
B. Pas. Angkur + baut dia. 16 mm Bh 16.00 -
C. Pek. Besi Siku L 60.60.6 Kg 870.45 -
D. Pek. Plat Buhul T = 6 mm Kg 81.31 -
E. Pek. Plat Baja T = 3 mm Kg 1.00 -
Jumlah -
4.9.3 Water Tank Atas
A. Pas. Water Tank Kap. 1000 Liter Unit 1.00 -
Jumlah -
5 EXTERNAL
5.1 PAGAR
5.1.1 Pekerjaan Tanah dan Pondasi
A. Pek. Galian Tanah Pondasi M3 1,044.07 -
B. Pas. Cerucuk Kayu Dolken dia. 10 cm P = 2 m M' ### -
C. Pek. Urugan tebal 10 cm M3 140.07 -
D. Pas. Pondasi Batukali 1 : 4 M3 2,758.62 -
E. Pas. Pipa Suling PVC dia. 2" + Ijuk M' 959.00 -
F. Pek. Urugan Tanah M3 3,752.21 -
Jumlah -
5.1.2 Pekerjaan Pagar Panel Precast
A. Pek. Panel Precast uk. 5x40x240 cm M' 551.16 -
B. Pek. Tiang Panel Precast uk. 18x19x370 cm M' 858.40 -
C. Pek. Ring Balok Beton Type BL uk. 15 x 15 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225 M3 86.11 -
-, Pembesian Kg 2,237.44 -
-, Bekisting M2 86.11 -
D. Pondasi Tapak Beton uk. 50x50x20 cm, Besi Ø12-150 mm (2 Lapis)
-, Beton Site MIx K-225 M3 3.75 -
-, Pembesian Kg 671.15 -
-, Bekisting M2 30.00 -
E. Pek. Kolom Pedestal Beton Type KP uk. 20 x 20 cm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225 M3 2.55 -
-, Pembesian Kg 450.98 -
-, Bekisting M2 51.00 -
F. Pek. Besi Siku L 80.80.8 Kg 1,427.27 -
G. Pek. Plat T = 8 mm Kg 73.59 -
H. Pas. Angkur + baut dia. 16 mm Bh 300.00 -
I. Pas. Angkur U + baut dia. 16 mm Bh 150.00 -
J. Pek. Besi Siku L 50.50.5 Kg 568.01 -
K. Pas. Kawat Berduri M' 2,870.35 -
Jumlah -
5.1.3 Pekerjaan Pagar BRC
A. Pek. Kolom Beton Type KB uk. 25 x 25 cm, Besi 4 Ø12, Sengkang Ø8-150 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225 M3 6.01 -
-, Pembesian Kg 579.72 -
-, Bekisting M2 48.10 -
B. Pek. Balok Beton Type BL uk. 15 x 15 cm, Besi 4 Ø10, Sengkang Ø8-150 mm (Tump), Ø8-150 mm (Lap)
-, Beton Site MIx K-225 M3 1.80 -
-, Pembesian Kg 320.27 -
-, Bekisting M2 24.05 -
C. Pas. Batu Bata 1 : 4 M2 84.16 -
D. Pek. Plesteran 1 : 4 M2 168.32 -
E. Pek. Acian Plesteran M2 168.32 -
F. Pengecatan dinding Exterior Ex. Propan M2 168.32 -
G. Pas. Pagar BRC M2 96.18 -
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
Jumlah -
5.1.4 Pekerjaan Gerbang Pagar
A. Pintu Pagar Dorong Besi uk. 6000 x 2260 MM Unit 2.00 -
B. Pintu Pagar Besi uk. 1500 x 2260 MM Unit 1.00 -
Jumlah -
5.2 DRAINASE
5.2.1 Pekerjaan Saluran Tipe I Uk. 40x40 (Terbuka)
A. Pekerjaan Galian M3 121.35 -
B. Lantai Kerja Tebal 5 cm M3 10.27 -
C. Pas. Batako M2 175.64 -
D. Saluran Beton Berulang
- Beton Site MIx K-250 M3 39.15 -
-, Pembesian Kg 4,819.74 -
-, Bekisting M2 289.54 -
Jumlah -
5.2.2Pekerjaan Saluran Tipe IA Uk. 40x40 (Tertutup)
A.Pekerjaan Galian M3 124.17 -
B.Lantai Kerja Tebal 5 cm M3 7.98 -
C.Pas. Batako M2 138.60 -
D.Saluran Beton Berulang
- Beton Site MIx K-250 M3 30.43 -
-, Pembesian Kg 3,741.91 -
-, Bekisting M2 221.98 -
E. Tutup Saluran Heavy Duty Uk. 600x530x100 MM M' 210.00 -
Jumlah -
5.2.3Pekerjaan Saluran Tipe IB Uk. 40x40 (Tertutup Gril)
A.Pekerjaan Galian M3 7.55 -
B.Lantai Kerja Tebal 5 cm M3 0.54 -
C.Pas. Batako M2 9.31 -
D.Saluran Beton Berulang
- Beton Site MIx K-250 M3 2.04 -
-, Pembesian Kg 251.68 -
-, Bekisting M2 15.30 -
E. Tutup Saluran Besi Gril M' 14.10 -
Jumlah -
5.2.4 Pekerjaan Saluran Tipe II Uk. 40x60 (Terbuka)
A. Pekerjaan Galian M3 69.51 -
B. Lantai Kerja Tebal 5 cm M3 4.12 -
C. Pas. Batako M2 113.98 -
D. Saluran Beton Berulang
- Beton Site MIx K-250 M3 20.07 -
-, Pembesian Kg 2,382.66 -
-, Bekisting M2 113.37 -
Jumlah -
5.2.5Pekerjaan Saluran Tipe IIA Uk. 40x60 (Tertutup)
A.Pekerjaan Galian M3 5.22 -
B.Lantai Kerja Tebal 5 cm M3 0.30 -
C.Pas. Batako M2 8.37 -
D.Saluran Beton Berulang
- Beton Site MIx K-250 M3 1.46 -
-, Pembesian Kg 175.24 -
-, Bekisting M2 9.50 -
E. Tutup Saluran Heavy Duty Uk. 600x530x100 MM M' 7.90 -
Jumlah -
5.2.6 Pekerjaan Saluran Tipe III Uk. 60x60 (Terbuka)
A. Pekerjaan Galian M3 182.65 -
B. Lantai Kerja Tebal 5 cm M3 7.65 -
C. Pas. Batako M2 167.25 -
D. Saluran Beton Berulang
- Beton Site MIx K-250 M3 32.64 -
-, Pembesian Kg 3,823.82 -
-, Bekisting M2 164.11 -
Jumlah -
5.2.7Pekerjaan Saluran Tipe IIIA Uk. 60x60 (Tertutup)
A.Pekerjaan Galian M3 14.28 -
B.Lantai Kerja Tebal 5 cm M3 1.03 -
C.Pas. Batako M2 24.82 -
D.Saluran Beton Berulang
- Beton Site MIx K-250 M3 4.38 -
-, Pembesian Kg 515.43 -
-, Bekisting M2 23.00 -
E. Tutup Saluran Heavy Duty Uk. 600x730x140 MM M' 21.40 -
Jumlah -
HARGA SATUAN SUB TOTAL TOTAL
NO. URAIAN PEKERJAAN STN VOLUME
(Rp) (Rp) (Rp)
a b c d e f=dxe g
5.2.8 Pekerjaan Saluran Tipe IV Uk. 60x80 (Terbuka)
A. Pekerjaan Galian M3 67.88 -
B. Lantai Kerja Tebal 5 cm M3 2.13 -
C. Pas. Batako M2 64.48 -
D. Saluran Beton Berulang
- Beton Site MIx K-250 M3 10.96 -
-, Pembesian Kg 1,365.78 -
-, Bekisting M2 46.49 -
Jumlah -
5.2.9 Pekerjaan Saluran Tipe V Uk. 80x80 (Terbuka)
A. Pekerjaan Galian M3 128.92 -
B. Lantai Kerja Tebal 5 cm M3 5.43 -
C. Pas. Batako M2 126.48 -
D. Saluran Beton Berulang
- Beton Site MIx K-250 M3 25.30 -
-, Pembesian Kg 3,177.77 -
-, Bekisting M2 99.79 -
Jumlah -
5.2.10 Pekerjaan Saluran Tipe IA x 2 (Tertutup)
A. Pekerjaan Galian M3 42.68 -
B. Lantai Kerja Tebal 5 cm M3 2.88 -
C. Saluran Beton Bertulang
- Beton Site MIx K-250 M3 25.88 -
-, Pembesian Kg 7,049.08 -
-, Bekisting M2 149.14 -
Jumlah -
I Gedung Kantor
A Pekerjaan Pondasi
1 Pengadaan Tiang Pancang □ 25x25 (L.6M + 3M) 1044 M¹
2 Pemancangan Tiang Pancang (HSPD) 1044 M¹
3 Penyambungan Tiang Pancang 116 Titik
4 Bobok Kepala Tiang Pancang 116 Titik
5 PDA Tes 1 Titik
B Pekerjaan Tanah
1 Galian Pondasi 35.36 M³
2 Urug Basecorse 1,057.21 M³
3 Pekerjaan Pemadatan Tanah CBR 90% 1,321.51 M²
C Pekerjaan Beton
Pekerjaan Lantai 1
1 Pek. Lantai Kerja 65.63 M³
2 Pondasi PC-1
a Beton K.300 2.54 M³
b Pembesian 498.04 Kg
c Bekisting Dengan Batako 18.48 M²
2 Pondasi PC-2
a Beton K.300 23.02 M³
b Pembesian 5,847.84 Kg
c Bekisting Dengan Batako 119.14 M²
3 Pondasi PC-3
a Beton K.300 4.15 M³
b Pembesian 813.54 Kg
c Bekisting Dengan Batako 14.20 M²
8 Kolom K1 40/40
a Beton K.300 47.01 M³
b Pembesian 14,437.39 Kg
c Bekisting 485.34 M²
9 Kolom K2 40/60
a Beton K.300 5.02 M³
b Pembesian 1,315.13 Kg
c Bekisting 41.84 M²
10 Kolom K3 15/40
a Beton K.300 0.31 M³
b Pembesian 58.03 Kg
c Bekisting 5.75 M²
11 Balok B1 30/50
a Beton K.300 60.24 M³
b Pembesian 21,518.49 Kg
c Bekisting 414.98 M²
12 Balok B2 20/30
a Beton K.300 15.80 M³
b Pembesian 6,489.18 Kg
c Bekisting 157.87 M²
13 Perkerasan Lantai
a Lantai Type L2
- Beton K.300 107.89 M³
- Pembesian 11,328.90 Kg
b Lantai Type L3
- Beton K.300 73.24 M³
- Pembesian 4,760.44 Kg
15 Tangga Samping
a Beton K.300 0.86 M³
b Pembesian 81.92 Kg
c Bekisting 3.57 M²
Pekerjaan Lantai 2
1 Kolom K1 40/40
a Beton K.300 22.98 M³
b Pembesian 7,535.24 Kg
c Bekisting 229.82 M²
2 Kolom K2 40/60
BILL OF QUANTITY
PEKERJAAN : PEMBANGUNAN DC MADIUN ALFA MART
LOKASI : KOTA MADIUN JAWA TIMUR
KELOMPOK KERJA : STRUKTUR
3 Balok B1 30/50
a Beton K.300 32.31 M³
b Pembesian 11,525.20 Kg
c Bekisting 300.40 M²
4 Balok B2 20/30
a Beton K.300 7.70 M³
b Pembesian 3,911.04 Kg
c Bekisting 119.84 M²
5 Plat Lantai
a Beton K.300 149.89 M³
b Pembesian 20,984.72 Kg
c Bekisting 1,249.04 M²
6 Tangga Utama
a Beton K.300 3.10 M³
b Pembesian 433.67 Kg
c Bekisting 25.81 M²
7 Tangga Samping
a Beton K.300 2.77 M³
b Pembesian 388.40 Kg
c Bekisting 23.12 M²
BILL OF QUANTITY
PEKERJAAN : PEMBANGUNAN DC MADIUN ALFA MART
LOKASI : KOTA MADIUN JAWA TIMUR
KELOMPOK KERJA : STRUKTUR
D Pekerjaan Atap
1 Pekerjaan Plat Atap
a Beton K.300 42.43 M³
b Pembesian 5,939.77 Kg
c Bekisting 353.54 M²
2 Pekerjaan Dinding Parapet
a Beton K.30 17.61 M³
b Pembesian 2,025.15 Kg
c Bekisting 63.40 M²
3 Siku 90.90.7 20,103.13 Kg
4 Siku 60.60.6 4,754.27 Kg
5 Plate t.10 105.15 Kg
6 CNP 150.65.20.3,2 4,880.94 Kg
7 Trekstank ∅12 642.32 Kg
8 Ikatan Angin ∅22 820.68 Kg
9 Zincromate 1 x 35 Microne + 2 x 40 Microne 31,306.49 Kg
10 Teras
a IWF 300.150.6,5.9 447.74 Kg
b Plate t.10 42.34 Kg
c Angkur ∅22 24 Bh
d CNP 150.65.20.3,2 300.68 Kg
e Trekstank ∅12 34.09 Kg
f Pipa Ø 2,5" 65.20 Kg
g Zincromate 1 x 35 Microne + 2 x 40 Microne 890.05 Kg
II Warehouse
A Pekerjaan Pondasi
1 Pengadaan Tiang Pancang □ 25x25 (L.6M + 3M) 1,710.00 M¹
2 Pemancangan Tiang Pancang (HSPD) 1,710.00 M¹
3 Penyambungan Tiang Pancang 190.00 Titik
4 Bobok Kepala Tiang Pancang 190.00 Titik
5 PDA Tes 2.00 Titik
B Pekerjaan Tanah
1 Galian Pondasi 33.92 M³
2 Urug Basecorse 6,433.00 M³
3 Pekerjaan Pemadatan Tanah CBR 90% 8,041.25 M²
C Pekerjaan Beton
1 Pek. Lantai Kerja 401.77 M³
2 Pondasi PC-2
a Beton K.300 47.55 M³
b Pembesian 12,077.07 Kg
c Bekisting Dengan Batako 246.06 M²
3 Pondasi PC-4
a Beton K.300 19.95 M³
b Pembesian 3,012.45 Kg
c Bekisting Dengan Batako 113.99 M²
BILL OF QUANTITY
PEKERJAAN : PEMBANGUNAN DC MADIUN ALFA MART
LOKASI : KOTA MADIUN JAWA TIMUR
KELOMPOK KERJA : STRUKTUR
5 Balok B3
a Beton K.300 2.74 M³
b Pembesian 489.74 Kg
c Bekisting 45.60 M²
D Pekerjaan Baja
1 Portal A dan Q
a Base Plate 296.25 Kg
b Angkur Ø 22 180.00 Bh
c Kolom IWF 350.175.7.11 19,376.74 Kg
d Sambungan Kolom
- Plate 1,680.42 Kg
- Baut HTB Ø 16 1,920.00 Bh
e Rafter IWF 350.175.7.11 10,148.66 Kg
f Sambungan Rafter
- IWF 350.175.7.11 87.30 Kg
- Plate 617.25 Kg
- Baut HTB Ø 16 832.00 Bh
g Stiffener 5,914.83 Kg
h Pipa Ø 2,5" 108.10 Kg
i Zincromate 1 x 35 Microne + 2 x 40 Microne 38,229.53 Kg
2 Portal B, D, F, H, J, L, N, P
a Base Plate 158.00 Kg
b Angkur Ø 22 96.00 Bh
c Kolom IWF 350.175.7.11 9,174.02 Kg
d Rafter IWF 350.175.7.11 38,947.90 Kg
BILL OF QUANTITY
PEKERJAAN : PEMBANGUNAN DC MADIUN ALFA MART
LOKASI : KOTA MADIUN JAWA TIMUR
KELOMPOK KERJA : STRUKTUR
e Sambungan Rafter
- Plate 4,461.27 Kg
- Baut HTB Ø 16 5,472.00 Bh
- IWF 350.175.7.11 69.84 Kg
f Stiffener 36,281.30 Kg
g Pipa Ø 2,5" 432.41 Kg
h Zincromate 1 x 35 Microne + 2 x 40 Microne 89,524.74 Kg
3 Portal C, E, G, I, K, M, O
a Base Plate 954.18 Kg
b Angkur Ø 22 84.00 Bh
c Angkur Ø 32 140.00 Bh
d Kolom IWF 400.200.8.13 4,145.57 Kg
e Kolom KWF 400.200.8.13 24,769.25 Kg
f Kolom IWF 350.175.7.11 2,701.22 Kg
BILL OF QUANTITY
PEKERJAAN : PEMBANGUNAN DC MADIUN ALFA MART
LOKASI : KOTA MADIUN JAWA TIMUR
KELOMPOK KERJA : STRUKTUR
g Sambungan Kolom
- Plate 3,798.75 Kg
- Baut HTB Ø 19 1,792.00 Bh
h Rafter IWF 400.200.8.13 32,663.40 Kg
i Rafter IWF 350.175.7.11 13,105.06 Kg
j Sambungan Rafter
- Plate 2,739.52 Kg
- Baut HTB Ø 19 2,240.00 Bh
- Baut HTB Ø 16 420.00 Bh
k Stiffener 18,894.51 Kg
l Pipa Ø 2,5" 378.36 Kg
m Zincromate 1 x 35 Microne + 2 x 40 Microne 63,574.29 Kg
4 Portal T, S, R
a IWF 350.175.7.11 836.75 Kg
b Plate 15.80 Kg
c Angkur Ø 22 32.00 Bh
d Pipa Ø 2,5" 108.10 Kg
e Zincromate 1 x 35 Microne + 2 x 40 Microne 960.65 Kg
5 Balok
a Elevasi + 7.00
- IWF 200.100.5,5.8 722.07 Kg
b Elevasi + 8.00
- IWF 200.100.5,5.8 1,823.28 Kg
c Elevasi + 10.50 - 0
- IWF 350.175.7.11 4,348.93 Kg
d Elevasi + 12.50
- IWF 350.175.7.11 4,348.93 Kg
- IWF 200.100.5,5.8 1,823.28 Kg
e Elevasi + 14.28
- IWF 350.175.7.11 8,697.86 Kg
f Elevasi + 15.76
- IWF 350.175.7.11 8,697.86 Kg
g Elevasi + 16.45
- IWF 200.100.5,5.8 3,871.49 Kg
h Elevasi + 17.72
- IWF 200.100.5,5.8 2,903.62 Kg
h Stiffener 8,120.79 Kg
i Zincromate 1 x 35 Microne + 2 x 40 Microne 42,225.63 Kg
6 Bracing
a Siku 90.90.7 6,548.82 Kg
b Plate t.10 322.88 Kg
c Zincromate 1 x 35 Microne + 2 x 40 Microne 6,871.70 Kg
E Pekerjaan Atap
1 Kolom IWF 200.150.6.9 1,177.49 Kg
2 Rafter IWF 200.100.5,5.8 3,228.65 Kg
3 Base Plate 101.92 Kg
BILL OF QUANTITY
PEKERJAAN : PEMBANGUNAN DC MADIUN ALFA MART
LOKASI : KOTA MADIUN JAWA TIMUR
KELOMPOK KERJA : STRUKTUR
4 Plate 303.11 Kg
5 Baut HTB Ø 16 1,196.00 Bh
6 CNP 150.65.20.3,2 57,929.01 Kg
7 Trekstank ∅12 4,772.60 Kg
8 Ikatan Angin 4,595.44 Kg
9 Zincromate 1 x 35 Microne + 2 x 40 Microne 72,108.22 Kg