Professional Documents
Culture Documents
Scope of Worked:
Data:
3-LAYER CANAL w/ COVER RCCP DRAINAGE CANAL
Length = 340.00 lm Length = 15.00 lm
Depth = 0.70 m Diameter = 600.00 mm
Length = 0.40 m
A. Flooring
Volume = 100.00 x 0.70 x 0.10 = 7.00 cu.m
Cement = 7.00 x 9.50 = 66.50 bags
Sand = 7.00 x 0.53 = 3.71 cu.m
Gravel = 7.00 x 0.85 = 5.95 cu.m
10mm Rebar = 4.00 x 100.00 = 400.00 l.m. 66.67 say
67.00 pcs
TieWires #16 = 30.00 pcs
B. Wall
no. of CHB = 100.00 x 0.60 x 13.00 x 2.00 = 1,560.00 pcs
vol. of Mortar = 1,560.00 x 0.0045 = 7.02 cu.m
Cement = 7.02 x 11.00 = 77.22 cu.m
Sand = 7.02 x 1.00 = 7.02 cu.m
10mm Rebar = [( 100 / 0.30) + 1 ](1.5) + 4.00 x 100.00 = 901.50 l.m. 150.25 say
151.00 pcs
TieWires #16 = 15.00 pcs
C. Plastering
Volume = 100.00 x 0.60 x 0.03 x 2.00 = 3.00 cu.m
Cement = 3.00 x 11.00 = 33.00 cu.m
Sand = 3.00 x 1.00 = 3.00 cu.m
D. Cover
Volume = 100.00 x 0.70 x 0.10 = 7.00 cu.m
Cement = 7.00 x 9.50 = 66.50 bags
Sand = 7.00 x 0.53 = 3.71 cu.m
Gravel = 7.00 x 0.85 = 5.95 cu.m
10mm Rebar = [ ( 100 / 0.20) + 1 ](.7) + 4.00 x 100.00 = 750.70 l.m. 125.12 say
126.00 pcs
TieWires #16 = 30.00 pcs
Materials
Description Unit Qty Unit Cost Amount
6" CHB thk pcs 1,560.00 16.00 24,960.00
Cement bags 212.00 235.00 49,820.00
Sand cu.m 16.00 850.00 13,600.00
Gravel cu.m 12.00 900.00 10,800.00
10mm dia x 6m pcs 344.00 200.00 68,800.00
TieWires #16 kgs 75.00 90.00 6,750.00
174,730.00
Labor
Pouring of Concrete
Capacity of 1 gang = 7.50 cu.m / day
No. of days = 7.00
= 0.93 say 1 day
7.50
1 Construction Foreman
1 Mason
4 Laborers
Installation of CHB, of Mortar & Installation of Rebars
Capacity of 1 gang = 116.00 pcs / day
No. of days = 1,560.00
= 13.45 say 14 day
116.00
1 Construction Foreman
1 Mason
4 Laborers
Materials 174,730.00
Labor 60,000.00
Equipment 6,000.00
Direct Cost 240,730.00
Say 2,407.00
818,380.00
SPL CHB CANAL (2 LAYER) w/ cover
L 30.00 L.M.
A. Flooring
Volume = 30.00 x 0.70 x 0.10 = 2.10 cu.m
Cement = 2.10 x 9.50 = 19.95 bags
Sand = 2.10 x 0.53 = 1.11 cu.m
Gravel = 2.10 x 0.85 = 3.57 cu.m
10mm Rebar = 4.00 x 30.00 + (100/6) (.35) (4) = 120.00 l.m. 26.00 say
26.00 pcs
TieWires #16 = 2.00 kgs
B. Wall
no. of CHB = 30.00 x 0.40 x 13.00 x 2.00 = 312.00 pcs
vol. of Mortar = 312.00 x 0.0045 = 1.40 cu.m
Cement = 1.40 x 11.00 = 15.44 cu.m
Sand = 1.40 x 1.00 = 1.40 cu.m
10mm Rebar = [( 100 / 0.60) + 1 ](1.7) + 4.00 x 100.00 = 705.03 l.m. 117.51 say
118.00 pcs
TieWires #16 = 9.00 kgs
C. Plastering
Volume = 30.00 x 0.60 x 0.03 x 2.00 = 0.90 cu.m
Cement = 0.90 x 11.00 = 9.90 cu.m
Sand = 0.90 x 1.00 = 0.90 cu.m
D. Cover
Volume = 30.00 x 1.30 x 0.10 = 3.90 cu.m
Cement = 3.90 x 9.50 = 37.05 bags
Sand = 3.90 x 0.53 = 2.07 cu.m
Gravel = 3.90 x 0.85 = 6.63 cu.m
10mm Rebar = 4.00 x 30.00 + (100/6) (.35) (4) = 595.70 l.m. 106.78 say
107.00 pcs
TieWires #16 = 8.00 kgs
Materials
Description Unit Qty Unit Cost Amount
6" CHB thk pcs 312.00 16.00 4,992.00
Cement bags 84.00 235.00 19,740.00
Sand cu.m 8.00 850.00 6,800.00
Gravel cu.m 11.00 900.00 9,900.00
12mm dia x 6m pcs 251.00 220.00 55,220.00
TieWires #16 kgs 19.00 90.00 1,710.00
Total Material Cost 98,362.00
Labor
Pouring of Concrete
Capacity of 1 gang = 7.50 cu.m / day
No. of days = 2.10
= 0.28 say 2 day
7.50
1 Construction Foreman
1 Mason
4 Laborers
1 Construction Foreman
1 Mason
4 Laborers
Materials 98,362.00
Labor 64,000.00
Equipment 6,400.00
Direct Cost 168,762.00
Say 1,688.00
1,688.00
500(1) PIPE CULVERT (24")
L 16.00 L.M.
MATERIALS
Joint Collar
Cement = 16.00 x 0.35 = 5.60 bags
say 6.00 bags
Sand = 16.00 x 0.79 = 12.64 cu.m
say 13.00 bags
Sand Bedding
Materials
Description Unit Qty Unit Cost Amount
RCCP 24" pcs 16.00 1,500.00 24,000.00
Portland Cement bags 6.00 235.00 1,410.00
Sand cu.m 17.00 850.00 14,450.00
Total Material Cost 39,860.00
LABOR
Designation Number No. of Hours Rate/Hour Amount
Const. Foreman 1 8 75 600.00
Mason 2 8 62.5 1,000.00
Laborers 6 8 37.5 1,800.00
Total Labor Cost 3,400.00
Minor Tools 340.00
Materials 39,860.00
Labor 3,400.00
Equipment 340.00
Direct Cost 43,600.00
Say 2,725.00
For Length l.m. 15.00
Total Cost 40,875.00
Mark Up 10,464.00
VAT 6,487.68
Total Cost 60,551.68
2,725.00
Unit Cost 3,784.48
40,875.00
Say 3,785.00
Length l.m. 35.00
Total Cost 132,475.00
SPL CHB CANAL (2 LAYER) w/ cover
L 100.00 L.M.
A. Flooring
Volume = 100.00 x 0.70 x 0.10 = 7.00 cu.m
Cement = 7.00 x 9.50 = 67.00 bags
Sand = 7.00 x 0.53 = 3.71 cu.m
Gravel = 7.00 x 0.85 = 5.95 cu.m
10mm Rebar = 4.00 x 100.00 = 400.00 l.m. 67.00 pcs
B. Wall
no. of CHB = 100.00 x 0.40 x 13.00 x 2.00 = 1,040.00 pcs
vol. of Mortar = 1,040.00 x 0.0045 = 4.68 cu.m
Cement = 4.68 x 11.00 = 51.00 cu.m
Sand = 4.68 x 1.00 = 4.68 cu.m
10mm Rebar = [( 100 / 0.30) + 1 ](1.5) + 4.00 x 100.00 = 901.50 l.m. 151.00 pcs
C. Plastering
Volume = 100.00 x 0.40 x 0.03 x 2.00 = 2.00 cu.m
Cement = 2.00 x 11.00 = 22.00 cu.m
Sand = 2.00 x 1.00 = 2.00 cu.m
D. Cover
Volume = 100.00 x 0.70 x 0.10 = 7.00 cu.m
Cement = 7.00 x 9.50 = 67.00 bags
Sand = 7.00 x 0.53 = 3.71 cu.m
Gravel = 7.00 x 0.85 = 5.95 cu.m
10mm Rebar = [ ( 100 / 0.20) + 1 ](.7) + 4.00 x 100.00 = 750.70 l.m. 126.00 pcs
Materials
Description Unit Qty Unit Cost Amount
6" CHB thk pcs 1,040.00 16.00 16,640.00
Cement bags 140.00 235.00 32,900.00
Sand cu.m 10.39 850.00 8,831.50
Gravel cu.m 5.95 900.00 5,355.00
10mm dia x 6m pcs 218.00 200.00 43,600.00
TieWires #16 kgs 50.00 90.00 4,500.00
Total Material Cost 111,826.50
Labor
Pouring of Concrete
Capacity of 1 gang = 7.50 cu.m / day
No. of days = 14.00
= 1.87 say 2 day
7.50
1 Construction Foreman
1 Mason
4 Laborers
1 Construction Foreman
1 Mason
4 Laborers
Materials 111,826.50
Labor 44,000.00
Equipment 4,400.00
Direct Cost 160,226.50
Say 1,602.00
For Length l.m. 42.00
Total Cost 67,284.00
Mark Up 32,045.30
VAT 23,072.62
Total Cost 215,344.42
1,602.00
32,045.30
23,072.62
215,344.42
MANHOLE WITH COVER