DETAILED COMPUTATION
SPL-8 SITEWORKS
Excavation
C1F1 : 1.30 x 0.80 x 1.175 = 1.222 x 48.00 = 58.66 m³
C2F2 : 0.70 x 0.70 x 1.075 = 0.527 x 48.00 = 25.28 m³
WF : 0.40 x 0.825 x 2.30 = 0.759 x 95.00 = 72.11 m³
Sub-total = 156.05 m³
Backfill
C1F1 : 1.30 x 0.80 x 0.85 = 0.884 x 48.00 = 42.43 m³ = 37.74 m³
less 0.20 x 0.20 x 0.85 = 0.034 x 48.00 = 1.63 m³
less 0.50 x 0.85 x 0.15 = 0.064 x 48.00 = 3.06 m³
C2F2 : 0.70 x 0.70 x 0.75 = 0.368 x 48.00 = 17.64 m³ = 16.20 m³
less 0.20 x 0.20 x 0.75 = 0.030 x 48.00 = 1.44 m³
WF : 0.40 x 0.50 x 2.30 = 0.460 x 95.00 = 43.70 m³ = 27.31 m³
less 0.15 x 0.50 x 2.30 = 0.173 x 95.00 = 16.39 m³
Sub-total = 81.25 m³
Gravel base
C1F1 : 1.30 x 0.80 x 0.075 = 0.078 x 48.00 = 3.74 m³
C2F2 : 0.70 x 0.70 x 0.075 = 0.037 x 48.00 = 1.76 m³
WF : 0.40 x 2.30 x 0.075 = 0.069 x 95.00 = 6.56 m³
Sub-total = 12.06 m³
Batterboard
2" x 2" Formlumber : 384.00 + 153.60 = 537.60 m. = 587.78 bdft.
L1 : 1.20 x 4.00 x 32.00 = 153.60 m.
L2 : 1.50 x 8.00 x 32.00 = 384.00 m.
CWN assorted : 587.78 / 2500.00 x 45.00 = 10.58 kgs.
Nylon spool : = 1.30 rolls
Summary
Excavation : 157.00 m³
Backfill : 82.00 m³
Gravel base : 12.50 m³
2" x 2" Formlumber : 588.00 bdft.
CWN assorted : 11.00 kgs.
Nylon spool : 2.00 rolls
1 of 3
LC1F1 : 1.46 x 14.00 x 48.00 = 981.12 m.
LC2F2 : 2.95 x 4.00 x 48.00 = 566.40 m.
10 mm Ø x 6m DRSB : 2198.40 x 1.10 / 6.00 = 404.00 pcs. = 1,493.18 kgs.
LC1F1 : 0.80 x 14.00 x 48.00 = 537.60 m.
: 1.30 x 18.00 x 48.00 = 1123.20 m.
LC2F2 : 0.80 x 14.00 x 48.00 = 537.60 m.
Tiewires : 4029.52 / 3000.00 x 45.00 = 60.44 kgs.
Formlumber : 332.76 = 332.76 m² x 33.00 / 3.00 = 3,660.36 bdft.
AC1F1 : 0.80 x 2.55 x 48.00 = 97.92 m²
: 1.15 x 2.55 x 48.00 = 140.76 m²
AC2F2 : 0.80 x 2.45 x 48.00 = 94.08 m²
½" x 4' x 8' Ord. Plywood : 332.76 / 2.88 / 3.00 = 38.51 pcs.
CWN assorted : 3660.36 / 2500.00 x 45.00 = 65.89 kgs.
Summary
Portland cement : 638.00 bags Volume 63.74
Sand : 32.00 m³
Gravel : 64.00 m³
16 mm Ø x 6m DRSB : 1024.00 kgs.
12 mm Ø x 6m DRSB : 3399.50 kgs.
10 mm Ø x 6m DRSB : 1778.00 kgs.
Tiewires : 93.00 kgs.
Formlumber : 3661.00 bdft.
½" x 4' x 8' Ord. Plywood : 39.00 pcs.
CWN assorted : 66.00 kgs.
Summary
6" CHB : 7,315.00 pcs.
Portland cement : 416.00 bags
Sand : 34.00 m³
16 mm Ø x 6m DRSB : 1592.00 kgs.
12 mm Ø x 6m DRSB : 2062.00 kgs.
Tiewires : 55.00 kgs.
2 of 3
Welding Rod : 876.96 x 0.025 / 20.00 = 1.10 boxes
Summary
2 "Ø G.I. Pipe, Sch. 40 : 24.00 pcs.
10 mm Ø x 6m DRSB : 74.00 kgs.
Barbed Wire (100m. Length) : 15.00 rolls
Welding Rod : 2.00 boxes
Oxygen & Acetylene : 1.00 set
Galvawash : 1.00 gals
Red Oxide : 3.00 gals
Aluminum Paint : 4.00 gals
Paint Brush #2 : 48.00 pcs.