NO NAMA PEKERJAAN PERHITUNGAN VOLUME PEKERJAAN

1 2 3
1 PEKERJAAN GALIAN TANAH PONDASI V1 = 0.30 x 0.50 = 0.15 M²
P = 2.00 + 3.00 + 2.00 + 3.00
= 10.00 M'
TOTAL = 0.15 x 10.00 = 1.50 M³
2 PEKERJAAN LANTAI
PAS. BATU 5/7 V1 = 2.00 X 3.00 X 0.07 = 0.42 M²
V2 = 6.00 X 0.07 = 0.42 M²
TOTAL = 0.84 M²
PASTERAN LANTAI V1 = 12.00 X 0.02 = 0.18 M²
3 PEKERJAAN PAS. PONDASI V1 = 0.30 x 0.50 = 0.15 M²

TOTAL = 0.15 x 10.00 = 1.50 M²


4 BETON BERTULANG
a RING BALOK 12/12
1. BETON P = 2.00 + 3.00 + 2.00 + 3.00
= 10.00 M'
V1 = 0.12 x 0.12 x 10.00
= 0.14 M³ -
2. BEKISTING V1 = 0.12 x 10.00 x 2
= 2.40 M²

3. PEMBESIAN CINCIN = 0.09 + 0.09 + 0.9 + 0.9 + 0.03


+ 0.03
= 2.04 M'
Ø6 - 15 CM = 67.67 x 2.04 = 138.04 M' 12 btg
= 138.04 x 0.22 = 30.37 Kg
POKOK Ø 10 = 10.00 x 4 = 40 M' 3.33 btg
= 40 x 0.62 = 24.8 Kg

TOTAL = 30.3688 + 24.8 = 55.1688 Kg


b KOLOM PRAKTIS 12/12
1. BETON V1 = 0.12 x 0.12 x 1.00
= 0.014 x 4 = 0.06 M³

TOTAL = 0.058 M³

2. BEKISTING V1 = 0.12 x 1.00 x 2 sisi


= 0.24 x 4 = 0.96 M²

TOTAL = 0.960 M³
3. PEMBESIAN CINCIN = 0.09 + 0.09 + 0.09 + 0.09 + 0.03
0.03
= 0.51 M'
Ø6 - 15 CM = 27.67 x 0.51 = 14.11 M' 1.18 btg
= 14.11 x 0.22 = 3.10 Kg
POKOK Ø 10 = 4.80 x 4 = 19.2 M' 1.6 btg
= 19.2 x 0.62 = 11.904 Kg
TOTAL = 3.10 + 11.90 = 15.01 Kg

TOTAL BESI = 15.01 Kg


5 PAS. BATA MERAH dan PLASTERAN
V1 = 1.00 x 8.80 = 8.8 M²

6. KERANGKA BAJA RINGAN C.75.75 TIANG = 2.00 x 2x 4= 16.00


= 16.00 + 1.00 = 17.00 M'
SKOR ATAS = 3.12 x 4= 12.48 M'
SKOR BAWAH = 1.88 x 4= 7.52 M'
= 12.48 + 7.52 + 1.00 = 21.00 M'
TOTAL = 38.00 M'
7 RANGKA ATAP BAJA RINGAN COS 25 ͦ = 0.91
V.bangunan = 3.60 x 4.60 = 16.56 M²
TOTAL = 16.56 / 0.91 = 18.27 M²
8 SENG SUPERDEX COS 25 ͦ = 0.91
V.bangunan = 3.60 x 4.60 = 16.56 M²
TOTAL = 16.56 / 0.91 = 18.27 M²
9 NOK SUPERDEX V1 = 0.25 x 0.91 = 0.23 M²
10 PAPAN LISTPLANK V1 = 16.40 M'
11 PINTU PLAT V1 = 2.00 X 1.20 = 2.40 M²