1 RUANG TAMU A 2.88 X 4.15 = 11.95 LUAS TOTAL 1. RUANG TAMU 43.54 M2 X 20,000.00 = 870,780.00
DIKURANGI :
- 0.5 X 1.78 = 0.89
- 0.5 X 0.25 = 0.13
- 1.55 X 1.78 = 2.76
- 1.2 X 0.23 = 0.28
- 1.55 X 0.6 = 0.93
4.98
LUAS A = 6.97 M2
C 4.15 X 2 = 8.30
2.15 X 0.88 = 1.89
10.19 M2
2 RUANG KELUARGA A 3.65 X 2.1 = 7.67 LUAS TOTAL 2 RUANG KELUARGA 88.39 M2 X 20,000.00 = 1,767,700.00
1.7 X 0.85 = 1.45
9.11 M2
B 3.65 X 2 = 7.30 M2
K 1 X 3.65 = 3.65 M2
3 RUANG TIDUR 1 A 3.65 X 2.9 = 10.59 LUAS TOTAL 3 RUANG TIDUR 1 39.57 M2 X 20,000.00 = 791,388.00
DIKURANGI :
- 0.5 X 1.48 = 0.74
- 0.5 X 0.25 = 0.13
- 0.026 X 4 = 0.11
0.97
LUAS A = 9.61 M2
B 2.9 X 3.65 = 10.59 M2
4 KM/WC 1 A 1.65 X 0.95 = 1.57 LUAS TOTAL 4 KM/WC 1 4.61 M2 X 20,000.00 = 92,280.00
B 1.65 X 0.95 = 1.57
C 1.02 X 0.95 = 0.97
D 1.02 X 0.5 = 0.51
4.61 M2
5 KM/WC 2 A 1.65 X 0.95 = 1.57 LUAS TOTAL 5 KM/WC 2 4.95 M2 X 20,000.00 = 98,950.00
B 1.65 X 0.95 = 1.57
C 1.25 X 0.95 = 1.19
D 1.25 X 0.5 = 0.63
4.95 M2
6 RUANG KERJA A 1 X 1.8 = 1.80 LUAS TOTAL 6 RUANG KERJA 6.00 M2 X 20,000.00 = 120,000.00
B 1 X 1.8 = 1.80
C 1 X 2.4 = 2.40
6.00 M2
7 KAMAR TIDUR UTAMA A 2.9 X 3.65 = 10.59 LUAS TOTAL 7 KAMAR TIDUR UTAMA 44.79 M2 X 20,000.00 = 895,810.00
DIKURANGI :
0.7 X 1.8 = 1.26
LUAS A = 9.33 M2
8 KAMAR TIDUR 2 A 2.7 X 3.65 = 9.86 LUAS TOTAL 8 KAMAR TIDUR 2 40.20 M2 X 20,000.00 = 803,980.00
DIKURANGI :
0.9 X 2 = 1.80
LUAS B = 8.06 M2
9 KM/WC 3 A 1.36 X 1.1 = 1.50 LUAS TOTAL 9 KM/WC 3 6.91 M2 X 20,000.00 = 138,160.00
B 1.1 X 1.1 = 1.21
C 1.1 X 1.1 = 1.21
D 1.36 X 1.1 = 1.50
F 1.36 X 1.1 = 1.50
6.91 M2
10 RUANG DAPUR A 2.65 X 3.65 = 9.67 LUAS TOTAL 10 RUANG DAPUR 43.30 M2 X 20,000.00 = 865,950.00
DIKURANGI :
0.6 X 1.5 = 0.90
LUAS A = 8.77 M2
11 KM/WC 4 A 1.36 X 1.1 = 1.50 LUAS TOTAL 11 KM/WC 4 6.37 M2 X 20,000.00 = 127,480.00
B 1.36 X 1.1 = 1.50
C 0.95 X 1.1 = 1.05
D 0.95 X 1.1 = 1.05
F 0.95 X 1.36 = 1.292
6.37 M2