01 Project Description:

The goal of this design is to build a synchronous twin-tub washing machine (TTWM)
drive with a 340 Watt load capacity. The load and the majority of the design
parameters were drawn from a real twin-tub washing machine, the Toshiba VH-
H80WPH, whose technical data was acquired from its brochure and was used as a
guide when calculating the initial design parameters.
A. Driven Load

Calculating Design Torque:


135
τ S= =1.2 N . m
1070
2π x
60
N W DS 1070 x 62
= ; NW = =345.5 rpm
N S DW 192

340
τW = =9.4 N .m
345.5
2π x
60
03Shafting:
A. Calculations
Calculating The Shaft Weight:

(( ) )
2
π x 0.02 3 kg
W shaft= (0.25) m x 7830 3 x 9.81=6 N
4 m

Calculating pulley weights:

m pulley = [ π x 0.0622
4 ]
3 kg
x 0.025 m x 1300 3 =0.016 kg
m

m drive= [
π x 0.1922
4 ] kg
x 0.025 m3 x 1300 3 =0.94 kg
m
Gear weight ¿ brochure=2.54 kg

Balancing the vertical forces:


F y =W sℎaft +W load +W pulley
S

F y =6+ ( 4.6 x 9.81 )+ ( 0.016 x 9.81 )=51.3 N


S

F y =W sℎaft +W load + W drive +W gear


W

F y =6|7|60 x 9.81|0.94 x 9.81|2.54 x 9.81=697.4 N


W

The Bending Load:


120+22.6 x cos 10.1=141 N

Free Body Diagram(FBD):

F x =F B − F x 0 − F xL
F 0+ F L=141
By conservation of movement:
τ =τ L − τ B
0=0.25 F x L − ( 0.2 x 141 )
F xL=112.8 N ; F x0 =28.2 N
Bending load:
141 x 0.2=28.2 N . m

Calculating Torque:

( )
2 2
m D ¿ + D out ω max − ω min
τ= x
2 t
τ S=1.2 N . m
τ W =9.4 N . m

τ pulley =
0.016 x 0.022 +0.0622 1070 − 0
2
x
1 (
=0.012 N . m )
( )
2 2
0.94 x 0.02 +0.192 345.5− 0
τ drive= x =6 N . m
2 1

τ g ear =
2 .54 x 0.022+0.15 2 345.5 −0
2
x
1 (
=10 N . m )
τ S=1.2+0.012=1.212 N . m
τ W =9.4 +6+10=25.4 N . m

Spinner shaft design stress:


16
x [ 1.5 x 28.2+ 1.5 x 1.212 +1.5 x 28.2 ]=53.88 MPa
2 2
Sdesign , S = 2
π x 0.02
16
Sdesign , W = 2
x [ 1.5 x 28.2+1.5 x 25.4 2 +1.5 x 28.22 ] =63.17 MPa
π x 0.02

05Bearings:
A. Calculations:
Calculate load for ball bearing:

W aS =

3 0.2 n x 6.16 3+ 0.8 n x 51.33
n
=47.63 N

W aW =
√ 3 0.2 n x 628.7 3+ 0.8 n x 697 .43
n
=684.74 N

Calculate load for thrust roller bearing:


[ ]
10 10 3
3 3 10
0.2 n x 6.16 +0.8 n x 51.3
W aS = =48 N
n

[ ]
10 10 3
3 3 10
0.2 n x 628.7 +0.8 n x 697 .4
W aW = =685 N
n

Calculate Bearing A Dynamic Equivalent Load:


W A =1 x 1 x 141+2.1 x 684.74=1579 N
Calculate Bearing B Dynamic Equivalent Load:
W B=1 x 1 x 141+2.1 x 47.63=241 N
SUC 204 C=12300 N

LA=( ) 12300 3
1579
6 6
x 10 =472.68 x 10 rev

L =(
241 )
3
12300 6 11
B x 10 =1.33 x 10 rev

Time to replace bearing A:


472.68 x 106 rev 3 day yr
L HA= =(22.8 x 10 ℎrs )x x =2.6 yrs
min 24 ℎrs 365 days
60 x 345.5 rev
ℎr
Time to replace bearing B:
11
1.33 x 10 rev day yr
L HB= =(2 x 106 ℎrs) x x =236.5 yrs
min 24 ℎrs 365 days
60 x 1070 rev
ℎr
SKF K − 81103− TN C=12200 N

( )
LC =
12200 3
1579
6 6
x 10 =461.25 x 10 rev

L =(
241 )
3
12200 6 11
D x 10 =1.33 x 10 rev

Time to replace bearing C:


461.25 x 106 rev day yr
L HC = =(22.25 x 103 ℎrs ) x x =2.54 yrs
min 24 ℎrs 365 days
60 x 345.5 rev
ℎr
Time to replace bearing D:
11
1.33 x 10 rev 6 day yr
L HD= =(2 x 10 ℎrs) x x =236.5 yrs
min 24 ℎrs 365 days
60 x 1070 rev
ℎr