PERHITUNGAN KEBUTUHAN BAHAN DAN HOK

1.5

3 3

PERHITUNGAN VOLUME

Volume Galian
Panjang = = 6.00 M

0.5 Volume = 0.5 x 0.5 x 6.00 = 1.50 M3

0.5

Volume Urugan dan Pondasi


Volume 1 = Urugan kembali pondasi
0.25 0.15 = (0,15 + 0.05) / 2 x 0,5 x 6 x 2 = 0.6 M3
Volume 2 = Urugan lantai, dari tanah asli ke permukaan lantai, tinggi = 0.2 M
= ((3 x 1,5) x 0,2 = 0.9 M3
0.5 = 1.5 M3

0.05 Volume Pondasi = (0,25 + 0,5) / 2 x 0,5 x 6 = 1.13 M3


0.5 V.Urugan Pasir = 0.05 x 0.6 x 6.00 = 0.18 M3
0.6
Volume Plat tutup Resapan
1 Volume = 1.00 x 1.00 x 0.10 = 0.10 m3
Jumlah besi Ø8 = 1.00 / 0.15 + 0 = 6.666667 bh
1 = 7 x 1.00 x 1.10 = 7.33 m
Ø8- 0.15 = 7.33 / 12.00 = 0.61 ≈ 1.00 btg
= 1.00 / 0.15 = 7.67 bh
= 7.67 x 1.00 x 1.10 = 8.43 m
Ø 8 - 0.15 = 8.43 / 12.00 = 0.70 ≈ 1.00 btg

Volume Plat tutup Septictank


0.6 Volume = 0.60 x 0.60 x 0.10 = 0.04 m3
Jumlah besi Ø8 = 0.60 / 0.15 + 0 = 4 bh
0.6 = 4 x 0.60 x 1.10 = 2.64 m
Ø8- 0.15 = 2.64 / 12.00 = 0.22 ≈ 1.00 btg
= 0.60 / 0.15 = 5.00 bh
= 5.00 x 0.60 x 1.10 = 3.30 m
Ø 8 - 0.15 = 3.30 / 12.00 = 0.28 ≈ 0.00 btg

Jml Pintu P1 = 1.00 bh


Jml Pintu P2 = bh
Volume 3 = 1.0 x 2.00 x 0.0 = 0.01 m2
2

0.9

Volume a
= -0.01 = -0.01 m2
Dinding Belakang
3.0
Volume 2 = 3.0 x 3.00 x = 9.00 m2
3.00

Dinding Samping

3.20 Volume 3 = 1/2 x 3.20 + 3.00 x 1.50 x = 4.65 m2


3.00
1.5

Total Luas Dinding Bata = -0.01 + 9.00 + 4.65 = 13.64 m2


Batu Bata untuk Resapan dan Septiktang = 7.44 m3
Luas Lantai
Luas Lantai Gedung
Luas Lantai = 3.00 x 1.50 = 4.50 m2
Luas Dinding Keramik
= 3.00 x 3 + 2.00 = 11 m2

Luas Atap
Luas a = 2.5 x 4.0 = 10.00 m2
3.00
1
4.0

Luas Plafon Luas 1 = 1.50 x 3.00 = 4.50 m2


Luas Total = = 4.50 m2
ANALISA
No. Kode Koefisien Volume
2a
b

5. SNI-6897-2008 - 6.9 1 m2 pasangan bata = 21.08 M2


6.9 - Batu Bata 85 x 21.08 = 1,791.80 ≈ 1,792 bh
- Semen 0.23 x 21.08 = 4.85 ≈ 5.00 zak
- Pasir 0.043 x 21.08 = 0.91 ≈ 1.00 m3
- Pekerja 0.3 x 21.08 = 6.32 ≈ 6.00 hok
- Tukang 0.1 x 21.08 = 2.11 ≈ 2.00 hok

6. SNI DT-91-0010-2007 1 m2 plesteran dinding tebal 15 mm 1:4 = 42.16 M2


6.4 - Semen 0.125 x 42.16 = 5.26 ≈ 5.00 zak
- Pasir 0.024 x 42.16 = 1.01 ≈ 1.00 m3
- Pekerja 0.2 x 42.16 = 8.43 ≈ 8.00 hok
- Tukang 0.15 x 42.16 = 6.32 ≈ 6.00 hok

7. SNI DT-91-0010-2007 1 m2 acian = 42.16 M2


6.27 - Semen 0.065 x 42.16 = 2.74 ≈ 3.00 zak
- Pekerja 0.15 x 42.16 = 6.32 ≈ 6.00 hok
- Tukang 0.1 x 42.16 = 4.22 ≈ 4.00 hok
13. SNI DT-91-00078-2007 1 m3 beton bertulang 1:2:3 (balok dan plat) = 0.14 M3
6.31 - Semen 6.72 x 0.14 = 0.91 ≈ 1.00 zak
- Pasir 0.54 x 0.14 = 0.07 ≈ 0.10 m3
- Split 0.81 x 0.14 = 0.11 ≈ 0.11 m3
- Bekisting 0.32 x 0.14 = 0.04 ≈ 0.04 m3
- Bendrat 3 x 0.14 = 0.41 ≈ 0.00 kg
- Paku 3.2 x 0.14 = 0.44 ≈ 0.00 kg
- Besi Ø10 mm 1.05 x 0.00 = 0.00 ≈ 0.00 btg
- Besi Ø8 mm 1.05 x 1.00 = 1.05 ≈ 1.00 btg
- Besi Ø6 mm 1.05 x 1.00 = 1.05 ≈ 1.00 btg
- Pekerja 7.05 x 0.14 = 0.96 ≈ 0.00 hok
- Tukang 0.275 x 0.14 = 0.04 ≈ 0.00 hok

16. SNI-2836-2008 - 6.4 1 m3 pasangan batu belah 1:4 = 1.13 M3


- Batu Belah 1.2 x 1.13 = 1.35 ≈ 1.00 m3
- Semen 3.26 x 1.13 = 3.67 ≈ 4.00 zak
- Pasir 0.52 x 1.13 = 0.59 ≈ 1.00 m3
- Pekerja 1.5 x 1.13 = 1.69 ≈ 2.00 hok
- Tukang 0.75 x 1.13 = 0.84 ≈ 1.00 hok

17. SNI DT-91-0006-2007 1 m3 galian biasa = 3.22 M3


6.1 - Pekerja 0.75 x 3.22 = 2.41 ≈ 2.00 hok
- Tukang 0.025 x 3.22 = 0.08 ≈ 1.00 hok

18. SNI DT-91-0006-2007 1 m3 urugan biasa = 1.50 M3


6.10 - Pekera 0.5 x 1.50 = 0.75 ≈ 1.00 hok

19. SNI PT T38-2000 1 m2 cat tembok = 31.78 M2


- Plamir 0.1 x 31.78 = 3.18 ≈ 3.00 kg
- Cat tembok 0.35 x 31.78 = 11.12 ≈ 11.00 kg
- Kuas 0.015 x 31.78 = 0.48 ≈ 0.00 bh
- Pekerja 0.08 x 31.78 = 2.54 ≈ 3.00 hok
- Tukang 0.08 x 31.78 = 2.54 ≈ 3.00 hok
22. SNI DT-91-0012-2007 1 m2 lantai keramik 20 x 20 (KM/WC) = 4.50 M2
6.36 - Keramik 26.50 x 4.50 = 119.25 ≈ 119.00 Buah
- Semen 0.208 x 4.50 = 0.94 ≈ 1.00 zak
- Semen Warna 1.62 x 4.50 = 7.29 ≈ 7.00 kg
- Pasir 0.045 x 4.50 = 0.20 ≈ 0.20 m3
- Pekerja 0.62 x 4.50 = 2.79 ≈ 3.00 hok
- Tukang 0.35 x 4.50 = 1.58 ≈ 2.00 hok

23. SNI DT-91-0012-2007 1 m2 dinding keramik 20 x 25 (KM/WC) = 11.00 M2


6.54 - Keramik 26.50 x 11.00 = 291.50 ≈ 292.00 Buah
- Semen 0.186 x 11.00 = 2.05 ≈ 2.00 zak
- Semen Warna 1.94 x 11.00 = 21.34 ≈ 21.00 kg
- Pasir 0.018 x 11.00 = 0.20 ≈ 0.20 m3
- Pekerja 0.60 x 11.00 = 6.60 ≈ 7.00 hok
- Tukang 0.45 x 11.00 = 4.95 ≈ 5.00 hok