You are on page 1of 15

URAIAN PEKERJAAN ANALISA PERHITUNGAN

Galian Tanah Biasa P Vol Total


Type a b1 = lbr atas = 1.25 25.00 1.50 37.50
b2 = lbr bwh = 1.25 37.50 m3
h = tggi = 1.20

Urugan Pasir bawah Pondasi P Vol Total


Type a b = lebar = 1.25 25.00 0.06 1.56
t = tebal = 0.05 1.56 m3

Pas Bt Kosong P Vol Total


Type a b = lebar = 1.25 25.00 0.25 6.25
t = tebal = 0.20 6.25 m3
P Vol
Type b b = lebar = 0.00 9.00 0.00 0.00
t = tebal = 0.20

Pas Pond bt Gunung P Vol Total


Type a b1 = lbr atas = 0.40 25.00 1.40 35.00
b2 = lbr bwh = 1.00
h = tggi = 2.00 271.25 m3
Type b p = panjang = 25.00 9.00 26.25 236.25
b = lebar = 1.25
h = tggi = 2.00
URAIAN PEKERJAAN ANALISA PERHITUNGAN

sloef 40/50 P Vol Total


beton b = lebar = 0.40 m 25.00 0.20 5.00 5.00 m3
t = tebal = 0.50 m

besi Ø 12 P berat (kg)


n = 10.00 btg 25.00 221.94
netto = 0.89 kg
net/M1 = 8.88 kg 281.12 kg

besi Ø6 P berat (kg)


n = 6.67 btg 25.00 59.18
pjg = 1.60 m
netto = 0.22 kg
net/M1 = 2.37 kg
pake 2x
bekisting b = lebar = 0.40 m 25.00 1.00 25.00 12.50 m2
t = tebal = 0.50 m
kolom 40/40 P L V Total
beton b = lebar = 0.40 m 12.00 0.16 1.92 1.92 m3
t = tebal = 0.40 m
n = jmlh = 6.00 bh
h = tnggi = 2.00 m

besi Ø 12 P berat (kg)


n = 8.00 btg 12.00 85.22496
netto = 0.89 kg
net/M1 = 7.10 kg 110.08 kg

besi Ø6 P berat (kg)


n = 6.67 btg 12.00 24.86
pjg = 1.40 m
netto = 0.22 kg
net/M1 = 2.07 kg
pake 3x
bekisting b = 0.40 m 12.00 0.80 9.60 3.20 m2
t = 0.40 m

URAIAN PEKERJAAN ANALISA PERHITUNGAN

dinding tembok P L Total


type 1
1 t = 3.35 m 33.30 111.56 111.56
111.56

luas lubang kolom 0 0 0


0
0 0.8 0
4 0
j1 2.189 13.134
j2 0.96 1.92
j3 3.136 6.272
j4 0.77 0.77
p1 2.665 2.665
p1 1.845 1.845
p2 1.64 3.28
La 0.08 3.76
33.646 77.91 m2

PLASTERAN 25.00 0 0 155.82 m2


69.00 0 0
0 PLS
CAT 155.82 m2

URAIAN PEKERJAAN ANALISA PERHITUNGAN

kusen kayu 5/15 P L V Total


J2 b = 0.15 m 3.80 0.01 0.03 0.06
t = 0.05 m
2 Bh
P2 b = 0.15 m 5.10 0.01 0.04 0.08
t = 0.05 m
2 Bh
P3 b = 0.15 m 5.00 0.008 0.04 0.11
t = 0.05 m
3 Bh
0.25

Pintu L Total
PJ1 p = 0.00 m 0.00 6.19 M2
l = 0.00 m
n = 1.00 bh
P2 p = 2.01 m 3.30
l = 0.82 m
n = 2.00 bh
P3 p = 2.01 m 2.89
l = 0.72 m
n = 2.00 bh

DAUN JENDELA P L Total


J l = 0.82 m 1.000 0.080 0.64 M2
t = 1.22 M
8.00
V l = 0.00 m 3.00 - - - M2
t = 0.86 m
13.00
KACA
1 l = 0.64 m 0.00 0.538 4.301 4.30 M2
t = 0.84 m
8.00
2 l = 1.52 m 0.00 0.486 -
t = 0.32 m
0.00
3 l = 1.12 m 0.00 0.829 -
t = 0.74 m
0.00

URAIAN PEKERJAAN ANALISA PERHITUNGAN


Kuda-Kuda L Total
KD1 p = 0.06 m 32.40 0.01 0.23
l = 0.12 m 0.47
2.00

Kd2 p = 0.06 m 21.30 0.01 0.15


l = 0.12 m 0.61
4.00

p = 0.05 m 0.00 0.01 -


l = 0.10 m -
4.00
1.08
10% 1.08

GORDING
p = 0.04 m 144.48 0.00 0.35
l = 0.06 m 0.69
2.00

p = 0.05 m 202.44 0.00 0.61


l = 0.06 m 1.21
2.00
1.91

BALOK ANGIN
p = 0.05 m 2.71 0.01 0.01
l = 0.10 m 0.05
4.00

Atap L Total
1 p = lbr atas = 1.80 m 7.98 48.57 97.14 97.14 m2
l = lbr bawah = 12.35 m
t = tnggi = 6.09 m
2.00 pias
2 p = lbr atas = 1.00 m 6.28 38.21 -
l = lbr bawah = 10.55 m
t = tnggi = 6.09 m
0.00

bubungan 1.80 m 7.20 7.20 7.20 m1


4.00 bh

Listplank P Total
p = 10.55 m 22.90 45.80 m1
l = 12.35 m
l = 2.00 m
URAIAN PEKERJAAN ANALISA PERHITUNGAN

Rangka lafond L Total


r1 p = 12.15 m 123.32 123.32 123.32
l = 10.15 m
1.00
R2 p = 6.75 m 25.65
l = 3.80 m
1.00
luar p = 0.00 m 0.00 0.00
l = 0.00 m
2.00
Samp. Bang
n = 0.00 bh
p = 10.50 m 0.00
l = 0.80 m 148.97 m2

Eternit L Total
Kelas p = 0.00 m 0.00
l = 10.15 m

Teras p = 0.00 m 0.00


l = 0.00 m

Samp. Bang
n = 1.00 bh
p = 40.00 m 48.00
l = 1.20 m 48.00 m2

42 84
lantai keramik P L

Type 1 b = 8.20 10.00 82.00 82.00


t = 1.00 109.70 m2
40 b = 3.80 6.50 24.70 24.70
t = 1.00
40 b = 3.00 TERAS 1.00 3.00 3.00
109.70

20 b = 0.00 1.50 0.00 0.00


2.00 0.00
20 b = 0.00 2.35 0.00 0.00
1.00
20 b = 0.00 1.50 0.00 0.00
2.00
PLINT b = 0.00 22.08 0.00 0.00 0.00
1.00

Pengecatan Plafon L Total


Kelas p = 0.00 m 0.00
l = 10.15 m
1.00
Teras p = 0.00 m 0.00
l = 2.85 m

wc p = 0.00 m 0.00
l = 1.85 m

Samp. Bang
n = 1.00 bh
p = 0.00 m 0.00
l = 1.20 m - m2

List Plafon P Total


Kelas p = 12.15 m 44.60
l = 10.15 m
1.00
Teras p = 6.75 m 21.10
l = 3.80 m
wc p = 1.00 m 2.00
l = 0.00 m

Samp. Bang
n = 0.00 bh
p = 0.00 m 0.00
l = 0.80 m 67.70 m1

Pengecat Listplank P L Total


p = 9.46 m 45.80 13.74 13.74 m2
l = 11.46 m
b = 0.30 m

BT. TEMPEL 1.65 m 4.87


2.95 m

0.50 m 1.48
2.95 m 6.34
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1 PEKERJAAN PERSIAPAN
a. Mobilisasi Ls 1.00 2,000,000.00 2,000,000.00
b. Pembersihan Lokasi Ls 1.00 1,500,000.00 1,500,000.00
SUB TOTAL 3,500,000.00
2 PEKERJAAN PONDASI
a. Galian Pondasi m3 37.50 89,766.60 3,366,247.50
b. Urugan Pasir m3 15.63 118,063.44 1,844,741.25
c. Pasangan Batu Kosong m3 1,931.25 423,165.86 817,239,074.85
d. Pasangan Batu gunung m3 271.25 818,463.20 222,008,143.00
d. Pekerjaan Sloft
- Beton K 250 m3 5.00 1,019,558.70 5,097,793.48
- Pembesian Kg 281.12 18,845.57 5,297,941.91
- Bekisting m2 12.50 232,609.34 2,907,616.80
e. Pekerjaan Kolom
- Beton K250 m3 1.92 1,019,558.70 1,957,552.69
- Pembesian Kg 110.08 18,845.57 2,074,562.52
- Bekisting m2 3.20 431,765.75 1,381,650.41
f. Pekerjaan Plasteran m 49.00 72,092.33 3,532,524.07
g. Pasangan Bata Mereh m 12.50 251,129.03 3,139,112.90
SUB TOTAL 1,069,846,961.37
3 PEKERJAAN RAILING PAGAR
a. Pekerjaan Railing Hollow m2 110,413.52 -
SUB TOTAL -
NO URAIAN PEKERJAAN JUMLAH HARGA

1 PEKERJAAN PERSIAPAN 3,500,000.00


2 PEKERJAAN PONDASI 1,069,846,961.37
3 PEKERJAAN RAILING PAGAR -
JUMLAH 1,073,346,961.37
PPN 10% 107,334,696.14
JUMLAH TOTAL 1,180,681,657.51
Terbilang:
Satu milyar seratus delapan puluh juta enam ratus
delapan puluh satu ribu enam ratus lima puluh tujuh
koma lima puluh satu
DAFTAR HARGA SATUAN BARANG DAN UPAH KERJA

No. Nama Barang Merk / Ukuran Satuan Harga Satuan


1 2 3 4 5
1 SUB BIDANG BAHAN DAN PERALATAN BANGUNAN
a. BAHAN DASAR
1 Air Kerja Kg 50
2 Batu Gunung M³ 181,920
3 Kerikil M³ 190,640
4 Sirtu
Sirtu (Quary) M³ 164,480
Sirtu Olahan M³ 129,120
5 Batu Bata -
* Batu Merah Ukuran Besar Buah 560
* Batu Merah Ukuran Kecil Buah 400
6 Cipping
* Spilit 7-10 cm 7-10 cm M³ 206,560
* spilit 5-7 cm 5-7 cm M³ 206,560
* Spilit 3-5 cm 3-5 cm M³ 224,480
* Spilit 2-3 cm 2-3 cm M³ 274,880
* Spilit 1-2 cm 1-2 cm M³ 295,360
* Spilit 0.5-1 0.5-1 M³ 296,000
7 Timbunan -
* Tanah Biasa M³ 50,560
* Tanah Pilihan M³ 66,720
* Tanah Humus M³ 111,440
* Tanah (Quarry) M³ 24,560
* Pilihan (Quarry) M³ 25,920
8 Pasir -
* Pasir Timbunan/Urugan M³ 62,240
* Pasir Pasangan M³ 161,840
* Pasir Saringan M³ 142,960
* Pasir Beton M³ 134,640
* Pasir Quary M³ 100,560
9 Semen PC -
* Portlan Cemen (Tonasa) 50 Kg Zak 62,720
* Portlan Cemen (Tonasa) 40 Kg Zak 54,480
* Portlan Cemen (Bosowa) 40 Kg Zak 50,880
-
b. BAHAN KAYU -
1 Kayu Kelas II -
* Balok M³ 3,757,600
* Papan M³ 3,757,600
2 Kayu Kelas III -
* Balok M³ 2,488,800
* Papan M³ 2,488,800
3 Tripleks -
* 0.2 cm 122 x 244 cm Lembar 44,080
* 0.3 cm 122 x 244 cm Lembar 52,480
* 0.4 cm 122 x 244 cm Lembar 69,600
* 0.6 cm 122 x 244 cm Lembar 72,480
* 0.9 cm 122 x 244 cm Lembar 103,440
* 1.2 cm 122 x 244 cm Lembar 158,080
4 Bambu Btg 26,460
5 Rotan Pengikat Ikat 29,280
6 Dolken Kayu galang d=8 - 10 / 4 m Btg 36,480
No. Nama Barang Merk / Ukuran Satuan Harga Satuan
-
No. Nama Barang Merk / Ukuran Satuan Harga Satuan

c. BAHAN BESI / BAJA -


1 Besi Beton SNI -
* d = 5 mm Btg 27,520
* d = 6 mm (0.22 kg/m) Btg 32,640
* d = 8 mm (0.39 kg/m) Btg 51,520
* d = 10 mm (0.62 kg/m) Btg 75,600
* d = 12 mm (0.89 kg/m) Btg 112,880
2 kawat -
* Licin 4 mm Kg 22,000
* Beton kg 18,720
3 Paku -
* Biasa Kg 17,680
* Asbes kg 41,120
-
d. BAHAN SANITASI -
Bahan Pipa -
1 Pipa Superalon PVC AW -
Φ 3/4 inci - 4 m Maspion Btg 31,680
Φ 1 inci - 4m Maspion Btg 49,040
Φ 2 inci - 4 m Btg 80,960
Φ 2 1/2 inci - 4 m Btg 96,400
Φ 3 inci - 4 m Btg 159,360

e. BAHAN FINISHING CAT -


1 Minyak Bekisting Ltr 11,600
-
f. DAFTAR SATUAN HARGA UPAH -
1 Pekerja O/H 103,440
2 Tukang O/H 120,960
3 Kepala Tukang O/H 137,600
4 Mandor Lapangan O/H 161,040

Pangkajene Sidenreng,………….. 2019

Dibuat oleh :
Konsultan Perencana
CV. KARYA MANDIRI CONSULTAN

KHAERUDDIN RH, ST
SINARDIN SALENG, ST
Direktur Utama Team Leader
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
BIDANG CIPTA KARYA
A.2.2.1 ANALISA HARGA SATUAN PEKERJAAN BANGUNAN SEMENTARA

A.2.3.1 ANALISA HARGA SATUAN PEKERJAAN TANAH DAN GALIAN

A.2.3.1.1 Penggalian 1 m3 Menggali tanah biasa sedalam 1 meter Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien (Rp.) (Rp.)
A. TENAGA
Pekerja L.01 Oh 0.750 103,440.00 77,580.00
Mandor L.04 Oh 0.025 161,040.00 4,026.00
JUMLAH TENAGA KERJA 81,606.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT -
D. Jumlah ( A + B + C ) 81,606.00
E. Overhead & Profit 10% 8,160.60
F. Harga Satuan Pekerjaan 89,766.60

A.2.3.1.11 Pengurukan 1 m3 dengan pasir urug Harga Satuan Jumlah Harga


No. Uraian Kode Satuan Koefisien (Rp.) (Rp.)
A. TENAGA
Pekerja L.01 Oh 0.300 103,440.00 31,032.00
Mandor L.04 Oh 0.010 161,040.00 1,610.40
JUMLAH TENAGA KERJA 32,642.40
B. BAHAN
Pasir Urug m3 1.200 62,240.00 74,688.00
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT -
D. Jumlah ( A + B + C ) 107,330.40
E. Overheead & Profit 10% 10,733.04
F. Harga Satuan Pekerjaan dengan Pasir Urug 118,063.44
A.3.2.1 ANALISA HARGA SATUAN PEKERJAAN PONDASI

A.3.2.1.1 pemasangan 1 m3 pondasi batu belah, campuran 1 SP : 3 PP Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien (Rp.) (Rp.)
A TENAGA
Pekerja Oh 1.5000 103,440.00 155,160.00
Tukang batu Oh 0.7500 120,960.00 90,720.00
Kepala tukang Oh 0.0750 137,600.00 10,320.00
Mandor Oh 0.0750 161,040.00 12,078.00
JUMLAH TENAGA KERJA 268,278.00
B BAHAN
Batu gunung 15/20 m3 1.2000 181,920.00 218,304.00
Semen PC kg 202.0000 1,254.40 253,388.80
Pasir Pasang m3 0.4850 161,840.00 78,492.40
JUMLAH HARGA BAHAN 550,185.20
C PERALATAN

JUMLAH HARGA PERALATAN


D. Jumlah ( A + B + C ) 818,463.20
E. Overhead & Profit 10% 81,846.32
F. Harga Satuan Pekerjaan 818,463.20

A.3.2.1.9 (K3) Memasang 1m3 batu kosong (aanstamping) Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien (Rp.) (Rp.)
A TENAGA
Pekerja Oh 0.7800 103,440.00 80,683.20
Tukang batu Oh 0.3900 120,960.00 47,174.40
Kepala tukang Oh 0.0390 137,600.00 5,366.40
Mandor Oh 0.0390 161,040.00 6,280.56
JUMLAH TENAGA KERJA 139,504.56
B BAHAN
Batu gunung m3 1.2000 181,920.00 218,304.00
Pasir Urug m3 0.4320 62,240.00 26,887.68
JUMLAH HARGA BAHAN 245,191.68
C PERALATAN

JUMLAH HARGA PERALATAN


D. Jumlah ( A + B + C ) 384,696.24
E. Overhead & Profit 10% 38,469.62
F. Harga Satuan Pekerjaan 423,165.86

A.4.1.1.8 Membuat 1 m3 beton mutu f' c = 21,7 Mpa ( K 250 ), slump ( 12 ± 2 ) cm, w/c Harga
= 0,56Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien (Rp.) (Rp.)
A TENAGA
Pekerja L.01 Oh 1.650 103,440.00 170,676.00
Tukang batu L.02 Oh 0.275 120,960.00 33,264.00
Kepala tukang L.03 Oh 0.028 137,600.00 3,852.80
Mandor L.04 Oh 0.083 161,040.00 13,366.32
JUMLAH TENAGA KERJA 221,159.12
B BAHAN
Semen PC kg 384.000 1,254.40 481,689.60
Pasir beton kg 692.000 96.17 66,550.63
Krikil (max. 30 mm ) kg 1,039.000 141.21 146,722.19
Air ltr 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 705,712.42
C PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah ( A + B + C ) 926,871.54
E. Overheead & Profit 10% 92,687.15
F. Harga Satuan Pekerjaan 1,019,558.70

A.4.1.1.17 Pembesian 10 Kg dengan besi polos atau besi ulir Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien (Rp.) (Rp.)
A TENAGA
Pekerja L.01 Oh 0.070 103,440.00 7,240.80
Tukang batu L.02 Oh 0.070 120,960.00 8,467.20
Kepala tukang L.03 Oh 0.007 137,600.00 963.20
Mandor L.04 Oh 0.004 161,040.00 644.16
RENCANA ANGGARAN BIAYA (RAB)
Instansi : DINAS PEKERJAAN UMUM, PENATAAN RUANG DAN PERHUBUNGAN KAB. SIDRAP
Kegiatan : Pembangunan Gedung Kantor (Bidang Permukiman)
Pekerjaan : Pembangunan/Rehabilitasi Masjid At Tauhid Lagalumpang Desa Kalosi
Lokasi : Kecamatan Dua Pitue
Tahun Anggaran : 2019

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN SAT. VOLUME
(Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN 1,300,000.00
1 Papan nama proyek Ls 1.00 300,000.00 300,000.00
2 Pek. Bongkaran Ls 1.00 1,000,000.00 1,000,000.00

II PEKERJAAN TANAH 1,046,505.68


1 Galian Tanah M3 6.63 89,766.60 595,152.56
2 Urugan Pasir Bawah Pondasi M3 0.55 118,063.44 65,230.05
3 Urugan Tanah Kembali M3 1.66 65,749.20 108,979.30
4 Urugan Tanah Didatangkan M3 2.70 102,645.84 277,143.77

III PEKERJAAN BATU DAN STRUKTUR 11,940,242.96


1 Pek. Pondasi 4,234,883.27
a Pas. Batu Kosong M3 1.66 423,165.86 701,397.42
b Pas. Batu Gunung (1Pc : 5ps) M3 4.14 852,726.60 3,533,485.85

2 Pek. Rabat Beton Bawah Lantai 454,117.47


a Urugan Pasir Bawah Lantai M3 0.47 118,063.44 55,784.98
b Rabat Beton Lantai (Mutu K 100), T. 5 Cm M3 0.47 843,031.74 398,332.50

3 Pek. Sloef 15/20 (SL) 2,571,104.02


a Beton Bertulang ( Mutu K 175 ) M3 0.56 945,168.24 527,403.88
b Besi Beton Kg 62.53 18,845.57 1,178,393.39
c Bekesting (2 x pakai) M2 7.44 116,304.67 865,306.76

4 Pek. Kolom Praktis 15/15 (KP) 3,711,381.36


a Beton Bertulang ( Mutu K 175 ) M3 0.57 945,168.24 535,910.39
b Besi Beton Kg 81.90 18,845.57 1,543,396.43
c Bekesting (2 x pakai) M2 7.56 215,882.88 1,632,074.54

5 Pek. Kolom 25/25 968,756.84


a Beton Bertulang ( Mutu K 175 ) M3 0.18 945,168.24 165,404.44
b Besi Beton Kg 20.18 18,845.57 380,221.96
c Bekesting (2 x pakai) M2 1.96 215,882.88 423,130.44

IV PEKERJAAN DINDING 5,375,861.03


1 Pas. Batu Bata ( 1/2 batu 1pc : 4 ps ) M2 45.46 118,254.75 5,375,861.03

V PEKERJAAN SANITASI 1,155,728.11


1 Pas. Pipa 3/4" (Saluran Air Bersih) M1 8.00 25,583.18 204,665.47
2 Pas. Pipa 3" (Saluran Air Kotor) M' 4.00 95,106.26 380,425.06
3 Pas. Pipa 3" (Saluran Kotoran Padat) M' 6.00 95,106.26 570,637.58
REKAPITULASI RAB

Instansi : DINAS PEKERJAAN UMUM, PENATAAN RUANG DAN PERHUBUNGAN KAB. SIDRAP
Kegiatan : Pembangunan Gedung Kantor (Bidang Permukiman)
Pekerjaan : Pembangunan/Rehabilitasi Masjid At Tauhid Lagalumpang Desa Kalosi
Lokasi : Kecamatan Dua Pitue
Tahun Anggaran : 2019

JUMLAH HARGA
NO. JENIS PEKERJAAN
(Rp)
1 2 3
I PEKERJAAN PERSIAPAN 1,300,000.00
II PEKERJAAN TANAH 1,046,505.68
III PEKERJAAN BATU DAN STRUKTUR 11,940,242.96
IV PEKERJAAN DINDING 5,375,861.03
V PEKERJAAN SANITASI 1,155,728.11

JUMLAH BIAYA (A) 20,818,337.77


Ppn 10 % (B) 2,081,833.78
TOTAL (A) + (B) 22,900,171.55
DIBULATKAN 22,900,000.00

TERBILANG : Dua Puluh Dua Juta Sembilan Ratus Ribu Rupiah

Pangkajene Sidenreng,………….. 2019

Dibuat oleh :
Konsultan Perencana
CV. KARYA MANDIRI CONSULTAN

KHAERUDDIN RH, ST SINARDIN SALENG, ST


Direktur Utama Team Leader

You might also like