You are on page 1of 885

DAFTAR BANYAK 2012

KEGIATAN : UPTD WILAYAH II


PAKET : PENGECATAN JEMBATAN SAMARINDA SEBERANG
LOKASI : KEC. SAMARINDA SEBERANG
SUMBER DANA : APBD 2012

NO. MT URAIAN PEKERJAAN PE


PEMB.

I. PEKERJAAN PERSIAPAN

1.1 Papan Nama Kegiatan

II PEKERJAAN PENGECATAN

7.1.(5) JBT PANGERAN BENDAHARA 1. PIPA 3,5 " 6.80 m x 0.28


Dinding 11.00 m x 1.07
Lening 4.00 m x 1.70
Hand Rilling 1.20 m x 0.40
Potok Pengaman 0.80 m x 0.20
Dinding Bawah 11.00 m x 2.50

2. Lening 4.00 m x 0.90


Dinding 6.20 m x 0.20

3. PIPA 3,5 " 3.70 m x 0.28


Dinding 6.30 m x 0.35
Hand Rilling 0.80 m x 0.20
Potok Pengaman 1.50 m x 0.28
Dinding Bawah 3.70 m x 0.20

4. Lening 1.80 m x 0.50

5. PIPA 3,5 " 3.70 m x 0.28


Dinding 3.70 m x 0.20
Hand Rilling 0.70 m x 0.20
Dinding Bawah 9.50 m x 0.60

6. PIPA 3,5 " 2.60 m x 0.28


Dinding 5.40 m x 0.20
Hand Rilling 0.70 m x 0.20
Dinding Bawah 6.00 m x 0.30

7. PIPA 3,5 " 9.60 m x 0.28


Dinding 9.60 m x 0.20
Lening 2.60 m x 1.40
Hand Rilling 9.60 m x 0.40
Potok Pengaman 0.80 m x 0.20
Dinding Bawah 9.60 m x 2.50
NYAK 2012

PERHITUNGAN VOLUME

= 1.00 Ls

11.1

m x 4.00 Bh = 7.62 m2
m x 2.00 R/L = 23.54 m2
m x 4.00 R/L = 27.20 m2
m x 2.00 Bh x 2.0 R/L = 1.92 m2
m x 4.00 Bh x 2.0 R/L = 1.28 m2
m x 2.00 R/L = 55.00 m2
total 116.56 m2

m x 2.00 R/L = 7.20 m2


m x 2.00 R/L = 2.48 m2
total 9.68 m2

m x 4.00 Bh = 4.14 m2 6.3


m x 2.00 R/L = 4.41 m2
m x 2.00 Bh x 2.0 R/L = 0.64 m2
m x 6.00 Bh x 2.0 R/L = 5.04 m2
m x 2.00 R/L = 1.48 m2
total 15.71 m2

m x 2.00 R/L = 1.80 m2


total 1.80 m2

m x 4.00 Bh = 4.14 m2
m x 2.00 R/L = 1.48 m2
m x 3.00 Bh x 2.0 R/L = 0.84 m2
m x 2.00 R/L = 11.40 m2 9.5
total 17.86 m 2

m x 4.00 Bh = 2.91 m2 5.4


m x 2.00 R/L = 2.16 m2
m x 3.00 Bh x 2.0 R/L = 0.84 m2
m x 2.00 R/L = 3.60 m2
total 9.51 m2

m x 4.00 Bh = 10.75 m2
m x 2.00 R/L = 3.84 m2
m x 4.00 R/L = 14.56 m2
m x 2.00 Bh x 2.0 R/L = 15.36 m2
m x 4.00 Bh x 2.0 R/L = 1.28 m2
m x 2.00 R/L = 48.00 m2
total 93.79 m2

TOTAL CAT JBT 1,2,3 = 264.92 m2


4.78
DAFTAR KUANTITAS DAN HARGA

KEGIATAN : UPTD WILAYAH II


PAKET : PENGECATAN JEMBATAN SAMARINDA SEBERANG
LOKASI : KEC. SAMARINDA SEBERANG
SUMBER DANA : APBD 2012

Perkiraan Harga Jumlah


NO Uraian Satuan
Kuantitas Satuan Harga-Harga
(Rupiah) (Rupiah)
a b c d e f = (d x e)

I UMUM

1 Papan Nama Kegiatan Set 1.0 500,000 500,000.00

JUMLAH HARGA A 500,000.00

VII PEKERJAAN STRUKTUR DAN LAINNYA

1 Beton K - 300 M3
2 Beton K - 225 M3
3 Baja Tulangan Kg
4 Pasangan Batu dengan mortar M3
5 Pemancangan kayu ulin uk. 10 /10 M'
6 Pasangan Kerb Beton / Kansteen PU : 15 x 20 x 30 x 50 M1
7 Plesteran 1: 2 Tebal 15 mm M2
8 Pengecatan ( Cat Minyak ) M2 264.92 91,190.00 24,157,872.42

JUMLAH HARGA E 24,157,872.42


FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

Kegiatan : UPTD WILAYAH II


Item Pembayaran : 7.8
Jenis Kegiatan : Pengecatan
Satuan Pembayaran : M2

NO KOMPONEN SATUAN PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Tidak Terlatih L.101 Jam 3.0000 7,800.00 23,400.00
2 Pekerjan Terlatih L.106 Jam 0.3000 10,000.00 3,000.00
3 Mandor L.061 Jam 0.0300 15,000.00 450.00

JUMLAH HARGA TENAGA 26,850.00

B. BAHAN
1 Cat Anti Korosit Mutu Tinggi Kg 0.3000 150,000.00 45,000.00
2 Thinner Liter 0.0900 45,000.00 4,050.00

JUMLAH HARGA BAHAN 49,050.00

C. PERALATAN

1 Alat Bantu Ls 1.0000 7,000.00 7,000.00

JUMLAH HARGA PERALATAN 7,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN(A + B + C) 82,900.00


E. BIAYA UMUM DAN KEUNTUNGAN 10 % x D 8,290.00
F. HARGA SATUAN KEGIATAN (D + E) 91,190.00
REKAPITULASI ( OE )
DAFTAR KUANTITAS DAN HARGA

PROGRAM : UPTD WILAYAH II


NAMA KEGIATAN : PENGECATAN JEMBATAN SAMARINDA SEBERANG
LOKASI : KEC. SAMARINDA SEBERANG
KOTA : SAMARINDA
SUMBER DANA : APBD 2012

Jumlah Harga
No Uraian Pekerjaan
(Rupiah)

I Pekerjaan Pendahuluan 500,000.00

II Pekerjaan Drainase

III Pekerjaan Tanah

IV Perkerasan Berbutir

VII Pekerjaan Struktur dan Lainnya 24,157,872.42

(I) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 24,657,872.42
(II) Pajak Pertambahan Nilai ( PPN ) = 10% x ( I ) 2,465,787.24
(III) JUMLAH TOTAL HARGA PEKERJAAN = ( I ) + ( II ) 27,123,659.66
(IV) PEMBULATAN 27,123,000.00
Terbilang "Dua Puluh Tujuh Juta Seratus Dua Puluh Tiga Ribu Rupiah"

Pejabat Pembuat Komitmen Pejabat Pengadaan Barang dan Jasa

DI SAHKAN OLEH, PANITIA


PELAKSANA KEGIATAN, KETUA,

Ir. EKO RESTUMINTO. MMT Budi Santoso, ST


NIP. 19591009 199303 1 003 NIP. 19770327 200901 1 002
DAFTAR KUANTITAS DAN HARGA

KEGIATAN : UPTD WILAYAH II


PAKET : PENGECATAN JEMBATAN SAMARINDA SEBERANG
LOKASI : KEC. SAMARINDA SEBERANG
SUMBER DANA : APBD 2012

Perkiraan Harga Jumlah


NO Uraian Satuan
Kuantitas Satuan Harga-Harga
(Rupiah) (Rupiah)
a b c d e f = (d x e)

A UMUM

1 Papan Nama Kegiatan Set 1.0 550,000 550,000.00

JUMLAH HARGA A 550,000.00

B PEKERJAAN DRAINASE

1 Pekerjaan Galian Untuk Selokan Drainase dan Saluran A M3


2 Pekerjaan Pasangan Batu Dengan Mortar M3
3 Pipa Pvc 2 " M1
4 Pipa Pvc 4" M1

JUMLAH HARGA B -

C PEKERJAAN TANAH

1 Galian biasa M3
2 Galian Keras M3
3 Urugan Biasa M3
4 Urugan Pilihan M3
5 Urugan Pasir M3

JUMLAH HARGA C

D PERKERASAN BERBUTIR

1 Lapis Pondasi Agregat Kelas A M3


2 Lapis Pondasi Agregat Kelas B M3
3 Telford Batu Gunung M3

JUMLAH HARGA D

E PEKERJAAN STRUKTUR DAN LAINNYA

1 Beton K - 300 M3
2 Beton K - 225 M3
3 Baja Tulangan Kg
4 Pasangan Batu dengan mortar M3
5 Pemancangan kayu ulin uk. 10 /10 M'
6 Pasangan Kerb Beton / Kansteen PU : 15 x 20 x 30 x 50 M1
7 Plesteran 1: 2 Tebal 15 mm M2
8 Pengecatan ( Cat Minyak ) M2 264.92 89,540.00 23,720,757.72
JUMLAH HARGA E 23,720,757.72
REKAPITULASI
DAFTAR KUANTITAS DAN HARGA

PROGRAM : UPTD WILAYAH II


NAMA KEGIATAN : PENGECATAN JEMBATAN SAMARINDA SEBERANG
LOKASI : KEC. SAMARINDA SEBERANG
KOTA : SAMARINDA
SUMBER DANA : APBD 2012

Jumlah Harga
No Uraian Pekerjaan
(Rupiah)

A Pekerjaan Pendahuluan 550,000.00

B Pekerjaan Drainase

C Pekerjaan Tanah

D Perkerasan Berbutir

E Pekerjaan Struktur dan Lainnya 23,720,757.72

(I) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 24,270,757.72
(II) Pajak Pertambahan Nilai ( PPN ) = 10% x ( I ) 2,427,075.77
(III) JUMLAH TOTAL HARGA PEKERJAAN = ( I ) + ( II ) 26,697,833.49
(IV) PEMBULATAN 26,697,000.00
Terbilang "Dua Puluh Enam Juta Enam Ratus Sembilan Puluh Tujuh Ribu Rupiah"

Samarinda 30 Maret 2012


CV. CREMONA PROFESIONAL ENGINEERING

PANITIA
KETUA,

HARUDI AS, ST.


Direktur
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

Kegiatan : UPTD WILAYAH II


Item Pembayaran : 7.8
Jenis Kegiatan : Pengecatan
Satuan Pembayaran : M2

NO KOMPONEN SATUAN PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Tidak Terlatih L.101 Jam 3.0000 7,800.00 23,400.00
2 Pekerjan Terlatih L.106 Jam 0.3000 10,000.00 3,000.00
3 Mandor L.061 Jam 0.0300 15,000.00 450.00

JUMLAH HARGA TENAGA 26,850.00

B. BAHAN
1 Cat Anti Korosit Mutu Tinggi Kg 0.2900 150,000.00 43,500.00
2 Thinner Liter 0.0900 45,000.00 4,050.00

JUMLAH HARGA BAHAN 47,550.00

C. PERALATAN

1 Alat Bantu Ls 1.0000 7,000.00 7,000.00

JUMLAH HARGA PERALATAN 7,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 81,400.00


E. BIAYA UMUM DAN KEUNTUNGAN 10 % x D 8,140.00
F. HARGA SATUAN KEGIATAN (D + E) 89,540.00
LAMPIRAN BERITA ACARA HASIL EVALUSI DAN NEGOSIASI PENAWARAN HARGA

NAMA KEGIATAN : UPTD WILAYAH II KOTA SAMARINDA


NAMA PAKET : PENGECATAN JEMBATAN SAMARINDA SEBERANG
WILAYAH : KECAMATAN SAMARINDA SEBERANG
SUMBER DANA : TAHUN ANGGARAN 2012

Perkiraan CV. CREMONA PROFESIONAL ENGINEERING HPS / OE NEGOSIASI


Mata Pemb URAIAN Satuan Kuantitas Harga Satuan Total Harga Harga Satuan Total Harga Harga Satuan Total Harga KET
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
1 2 3 4 7 8 9 10 11

A PEKERJAAN UMUM

1 Papan Nama Kegiatan Ls 1.00 550,000.00 550,000.00 500,000.00 500,000.00 500,000.00 500,000.00 Nego

550,000.00 500,000.00 500,000.00

B STRUKTUR

1 Pengecatan ( Cat Minyak ) M2 264.92 89,540.00 23,720,757.72 91,190.00 24,157,872.42 89,540.00 23,720,757.72 Tetap

23,720,757.72 24,157,872.42 23,720,757.72


A JUMLAH 24,270,758 24,657,872 24,220,758
B PPN 10% 2,427,076 2,465,787 2,422,076
C TOTAL 26,697,833 27,123,660 26,642,833
D DIBULATKAN 26,697,000 27,123,000 26,642,000

MENGETAHUI, PANITIA UNIT LAYANAN PENGADAAAN


CV. CREMONA PROFESIONAL ENGINEERING

1. BUDI SANTOSO, ST : .....................


Pejabat Pengadaan Barang dan Jasa

HARUDI AS, ST.


Direktur
JADWAL PELAKSANAAN PEKERJAAN (TIME SCHEDULLE)

NAMA KEGIATAN : UPTD WILAYAH II KOTA SAMARINDA


NAMA PAKET : PENURAPAN DAN NORMALISASI JL. PANG. BENDAHARA
WILAYAH : KECAMATAN SAMARINDA SEBERANG

No. JUMLAH HARGA APRIL MEI


URAIAN VOLUME SATUAN ( Rp ) BOBOT KETERANGAN
DIV. Minggu Ke-2 Minggu Ke-3 Minggu Ke-4 Minggu Ke-1
(%)
1 DIVISI I UMUM
100%
Papan Nama Kegiatan 1.00 LS 500,000.00 2.06% 2.06%
50%
2 STRUKTUR
Pengecatan ( Cat Minyak ) 264.92 M2 23,720,757.72 97.94% 24.48% 24.48% 24.48% 24.48% 0%

Jumlah Nilai Pekerjaan 100%

Kemajuan Pekerjaan Bulanan (%) 26.55% 24.48% 24.48% 24.48%

Kemajuan Pekerjaan Kumulatif (%) 0.00% 26.55% 51.03% 75.52% 100%

MENGETAHUI,
KONTRAKTOR
CV. CREMONA PROFESIONAL ENGINEERING

HARUDI AS, ST.


KEGIATAN : UPTD WILAYAH II KOTA SAMARINDA
PEKERJAAN : PENURAPAN DAN NORMALISASI JL. PANG. BENDAHARA
LOKASI : KECAMATAN SAMARINDA SEBERANG
PAGU DANA Rp 26,697,000.00

Evaluasi harga dilakukan terhadap Penawaran yang memenuhi Persyaratan (Evaluasi) Administrasi dan Teknis, dengan penilaian terhadap Harga Penawaran
meliputi :
a. Koreksi Aritmatika
b. Kewajaran Harga

Adalah sebagai berikut :


a. Koreksi Aritmatika

1. CV. BAMBU BORNEO


PENAWARAN PENAWARAN TERKOREKSI
NO. URAIAN PEKERJAAN KODE SAT. VOLUME HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH SELISIH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) (%)

I UMUM
1 Papan Nama Kegiatan Ls 1.00 500,000.00 500,000.00 500,000.00 500,000.00 0.00

II STRUKTUR
1 Pengecatan ( Cat Minyak ) M2 264.92 89,540.00 23,720,757.72 89,540.00 23,720,757.72 0.00

JUMLAH HARGA 24,220,757.72 24,220,757.72 0.00


PPN 10 % 2,422,075.77 2,422,075.77 0.00
JUMLAH TERMASUK PPN 10 % 26,642,833.49 26,642,833.49 0.00
DIBULATKAN 26,642,000.00 26,642,000.00 0.00

b. Kewajaran harga

NO. NAMA PENAWAR HARGA PENAWARAN PROSENTASE THD KETERANGAN


PAGU DANA

1 CV. CREMONA PROFESIONAL ENGINEERING Rp. 26,642,000.00 99.79 Wajar

UNIT LAYANAN PENGADAAN :

NO. NAMA PANITIA Tanda Tangan

1 BUDI SANTOSO,ST Pejabat Pengadaan Barang dan Jasa ……………………………


DAFTAR BANYAK TAHUN 2009

KEGIATAN : UPTD WILAYAH II KOTA SAMARINDA


PAKET : PENURAPAN DAN NORMALISASI JL. PANG. BENDAHARA
LOKASI : KECAMATAN SAMARINDA SEBERANG
SUMBER DANA : TAHUN 2012

NO. MT URAIAN PEKERJAAN PERHITUNGA


PEMB.

I. PEKERJAAN PERSIAPAN

1 Papan Nama Kegiatan

II. PEKERJAAN TANAH

1 Galian Lumpur dan Pembuangan Sta 0+000 s/d 0+040 150.00 m x 2.00 m

III. PEKERJAAN STRUKTUR

1 Pengadaan dan Pemancangan ka 1 (40/1)+1 m x


ukuran 10/10

2 Papan Dinding 2/20 - 4M 1 (40 x 1,5) m x

3 Struktur Kayu Ulin 1 0.46 + 3.00

Suai 5/10 a 28.00 x 3m x

Slop 10/10 - 2M b (0,1 x 0,1) 40 x 4 m + (0,1 x 0,1) 35 x4

1.6

0.03

13.3333333333333
UN 2009

PERHITUNGAN VOLUME

6.25
3.125

1.00 Ls

0.7
0.35
x 1.00 m = 300.00 m³ 254.56
300.00 m³

6.8
3.4

3 = 123.00 M1 123

2 ki/ka = 120 M2 160

= 3.46 M3 60

0x 0.1 x 1.10 = 0.462 M3

(0,1 x 0,1) 35 x4 = 3 M3 320

13.33333 11.666666667
26.66667 23.333333333
1 60
41
50
0.01

0.7 0.8

56
DAFTAR KUANTITAS DAN HARGA

KEGIATAN : UPTD WILAYAH II KOTA SAMARINDA


PAKET : PENURAPAN DAN NORMALISASI JL. PANG. BENDAHARA
LOKASI : KECAMATAN SAMARINDA SEBERANG
SUMBER DANA : TAHUN 2012

Perkiraan Harga Jumlah


No Pembayaran Uraian Satuan
Kuantitas Satuan Harga-Harga
(Rupiah) (Rupiah)
a b c d e f = (d x e)

I UMUM

1 Papan Nama Kegiatan Set 1.0 500,000 500,000.00

JUMLAH HARGA DIVISI I 500,000.00

II PEKERJAAN DRAINASE

2.2 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air M3 300.0 82,106.00 24,631,799.69

JUMLAH HARGA II 24,631,799.69

VII PEKERJAAN STRUKTUR DAN LAINNYA

1 Pemancangan kayu ulin uk. 10 /10 M1 123.00 76,254.44 9,379,296.67


2 Papan Dinding 2/20 - 4M M2 120.00 134,004.44 16,080,533.33
3 Struktur Kayu Ulin M3 3.46 6,433,753.33 22,273,654.04

JUMLAH HARGA VII 47,733,484.04


REKAPITULASI ( OE )
DAFTAR KUANTITAS DAN HARGA

PROGRAM : UPTD WILAYAH II


NAMA KEGIATAN : : PENURAPAN DAN NORMALISASI JL. PANG. BENDAHARA
LOKASI : KEC. SAMARINDA SEBERANG
KOTA : SAMARINDA
SUMBER DANA : APBD 2012

Jumlah Harga
No Uraian Pekerjaan
(Rupiah)

i Pekerjaan Pendahuluan 500,000.00

ii Pekerjaan Drainase 24,631,799.69

iii Pekerjaan Tanah

iV Perkerasan Berbutir

VII Pekerjaan Struktur dan Lainnya 47,733,484.04

(I) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 72,865,283.73
(II) Pajak Pertambahan Nilai ( PPN ) = 10% x ( I ) 7,286,528.37
(III) JUMLAH TOTAL HARGA PEKERJAAN = ( I ) + ( II ) 80,151,812.10
(IV) PEMBULATAN 80,151,000.00
Terbilang : "Delapan Puluh Juta Seratus Lima Puluh Satu Ribu Rupiah"

Samarinda, 05 Februari 2012

Pejabat Pembuat Komitmen Pejabat Pengadaan Barang dan Jasa

DI SAHKAN OLEH, PANITIA


PELAKSANA KEGIATAN, KETUA,

Ir. EKO RESTU MINTO. MMT Budi Santoso, ST


NIP. 19591009 199303 1 003 NIP. 19770327 200901 1 002
H. THAMRIN. B, ST
FORMULIR STANDAR UNTUK
REKAMAN ANALISA HARGA SATUAN

Kegiatan : UPTD WILAYAH II


Item Pembayaran : 2.1
Jenis Kegiatan : Galian Manual
Satuan Pembayaran : M3

NO KOMPONEN SATUAN PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Tidak Terlatih L.101 Jam 0.8000 7,800.00 6,240.00
2 Mandor L.061 Jam 0.2000 15,000.00 3,000.00

JUMLAH HARGA TENAGA 9,240.00

JUMLAH HARGA BAHAN

1 Flet Bed Truck Jam 0.3443 189,640.54 65,301.82


2 Alat Bantu Ls 1.0000 100.00 100.00

JUMLAH HARGA PERALATAN 65,401.82

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 74,641.82


E. BIAYA UMUM DAN KEUNTUNGAN 10 % x D 7,464.18
F. HARGA SATUAN KEGIATAN (D + E) 82,106.00
DAFTAR KUANTITAS DAN HARGA

KEGIATAN : UPTD WILAYAH II KOTA SAMARINDA


PAKET : PENURAPAN DAN NORMALISASI JL. PANG. BENDAHARA
LOKASI : KECAMATAN SAMARINDA SEBERANG
SUMBER DANA : TAHUN 2012

Perkiraan Harga Jumlah


NO Uraian Satuan
Kuantitas Satuan Harga-Harga
(Rupiah) (Rupiah)
a b c d e f = (d x e)

A UMUM

1 Papan Nama Kegiatan Set 1.0 500,000 500,000.00

JUMLAH HARGA A 500,000.00

B PEKERJAAN DRAINASE

1 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air M3 300.0 81,432.20 24,429,660.53

JUMLAH HARGA B 24,429,660.53

C PEKERJAAN STRUKTUR DAN LAINNYA

1 Pemancangan kayu ulin uk. 10 /10 M1 123.00 79,071.67 9,725,815.00


2 Papan Dinding 2/20 - 4M M 2
120.00 132,336.11 15,880,333.33
3 Struktur Kayu Ulin M3 3.46 6,375,233.33 22,071,057.80

JUMLAH HARGA E 47,677,206.13


REKAPITULASI
DAFTAR KUANTITAS DAN HARGA

PROGRAM : UPTD WILAYAH II


NAMA KEGIATAN : PENURAPAN DAN NORMALISASI JL. P. BENDAHARA
LOKASI : KEC. SAMARINDA SEBERANG
KOTA : SAMARINDA
SUMBER DANA : APBD 2012

Jumlah Harga
No Uraian Pekerjaan
(Rupiah)

A Pekerjaan Pendahuluan 500,000.00

B Pekerjaan Drainase 24,429,660.53

C Pekerjaan Tanah

D Perkerasan Berbutir

E Pekerjaan Struktur dan Lainnya 47,677,206.13

(I) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 72,606,866.67
(II) Pajak Pertambahan Nilai ( PPN ) = 10% x ( I ) 7,260,686.67
(III) JUMLAH TOTAL HARGA PEKERJAAN = ( I ) + ( II ) 79,867,553.33
(IV) PEMBULATAN 79,867,000.00
Terbilang : "Tujuh Puluh Sembilan Juta Delapan Ratus Enam Puluh Tujuh Ribu Rupiah"

Samarinda, 30 Maret 2012


CV. BAMBU BORNEO

ASNOPY PIRADE,SHut
Direktur

H. THAMRIN. B, ST
Alat - 1

TABEL DEPRESIASI NILAI ALAT

Kegiatan :
Kabupaten/Kota :
Lokasi :
Tahun Anggaran : 0

DECLINING 1 TAHUN 2 TAHUN 3 TAHUN 4 TAHUN 5 TAHUN


TAHUN 2003 1 1 1 1 1
TAHUN 2004 2 2 2 2
TAHUN 2005 3 3 3
TAHUN 2006 4 4
TAHUN 2007 5
TAHUN 2008

SUMARY 1 3 6 10 15
KOEFISIEN AWAL 1.000 1.000 1.000 1.000 1.000
DECLINING
TAHUN 2003 1.000 0.000 0.667 0.333 0.500 0.500 0.400 0.600 0.333 0.667
TAHUN 2004 AKHIR 0.333 0.000 0.333 0.167 0.300 0.300 0.267 0.400
TAHUN 2005 AKHIR 0.167 0.000 0.200 0.100 0.200 0.200
TAHUN 2006 AKHIR 0.100 0.000 0.133 0.067
TAHUN 2007 AKHIR 0.067 0.000
TAHUN 2008 AKHIR
Alat - 2

6 TAHUN 7 TAHUN 8 TAHUN 9 TAHUN 10 TAHUN


1 1 1 1 1 NO
2 2 2 2 2
3 3 3 3 3
4 4 4 4 4
5 5 5 5 5
6 6 6 6 6
7 7 7 7 1
8 8 8 2
9 9 3
10 4
21 28 36 45 55 5
1.000 1.000 1.000 1.000 1.000 6
7
0.286 0.714 0.250 0.750 0.222 0.778 0.200 0.800 0.182 0.818 8
0.238 0.476 0.214 0.536 0.194 0.583 0.178 0.622 0.164 0.655 9
0.190 0.286 0.179 0.357 0.167 0.417 0.156 0.467 0.145 0.509 10
0.143 0.143 0.143 0.214 0.139 0.278 0.133 0.333 0.127 0.382 11
0.095 0.048 0.107 0.107 0.111 0.167 0.111 0.222 0.109 0.273 12
0.048 0.000 0.071 0.036 0.083 0.083 0.089 0.133 0.091 0.182 13
AKHIR 0.036 0.000 0.056 0.028 0.067 0.067 0.073 0.109 14
AKHIR 0.028 0.000 0.044 0.022 0.055 0.055 15
AKHIR 0.022 0.000 0.036 0.018 16
AKHIR 0.018 0.000 17
AKHIR 18
19
Tenggarong, Juni 2007 20
Dibuat Oleh : 21
Konsultan Perencana 22
CV. KALTICON DESAIN 23
24
25
24
H A D R I Y A N I, ST
Direktur
Alat - 2

SUMBER DATA : UNITED TRACKTOR CABANG BALIKPAPAN


TAHUN 0

URAIAN KODE HP KAPASITAS HARGA ALAT HARGA ALAT


DI DI D
BALIKPAPAN SAMARINDA
140,792.20 2,5 % TA
(Rp.) (Rp.)

Asphat Mixing Plant E.010 150 50 Ton/Jam 1,150,000,000 1,178,750,000 =(


Asphalt Finisher E.020 47 6 Ton 650,000,000 666,250,000 =(
Asphalt Sprayer E.030 150 800 Liter 28,350,000 29,058,750 =(
Air Compressor 4000-6500 L/m3 E.040 50 --- 42,000,000 43,050,000 =(
Bulldozer 100-150 HP E.050 140 --- 274,490,000 281,352,250 =(
Concrete Mixer 0,3-0,6 m3 E.060 15 500 Liter 26,200,650 26,855,666 =(
Concrete Vibrator E.070 10 --- 2,610,000 2,675,250 =(
Dump Truck 3-4 m3 E.080 100 6 Ton 178,500,000 182,962,500 =(
Dump Truck E.090 125 8 Ton 103,217,000 105,797,425 =(
Excavator 80-140 HP E.100 90 0.5 m3 136,111,000 139,513,775 =(
Flat Bed Truck 3-4 m3 E.110 100 4 m3 139,650,000 143,141,250 =(
Generator Set E.120 175 125 KVA 89,250,000 91,481,250 =(
Jack Hammer E.130 3 --- 3,675,000 3,766,875 =(
Motor Grader > 100 HP E.140 125 --- 407,569,000 417,758,225 =(
Stone Crusher E.150 220 50 Ton/Jam 516,075,000 528,976,875 =(
Track Loader 75-100 HP E.160 90 1.6 m3 198,450,000 203,411,250 =(
Three Wheel Roller 6-8 Ton E.170 55 8 Ton 63,518,000 65,105,950 =(
Tandem Roller 6-8 Ton E.180 50 8 Ton 161,700,000 165,742,500 =(
Tire Roller 8-10 Ton E.190 50 10 Ton 115,500,000 118,387,500 =(
Tamper Vibrator Plate E.200 5 0.17 Ton 3,150,000 3,228,750 =(
Water Pump 70-100 mm E.210 6 --- 3,402,000 3,487,050 =(
Wheel Loader 1,0-1,6 m3 E.220 105 1.5 m3 371,700,000 380,992,500 =(
Water Tanker 3000-4500 Liter E.230 100 4000 Liter 131,250,000 134,531,250 =(
Vibratory Roller 5-8 Ton E.240 75 7 Ton 133,842,000 137,188,050 =(
Concrete Cuter
Fulvi Mixer E.250 75 --- 195,000,000
HARGA ALAT KET.
DEPRESIASI / DECLINING METHODE USIA
DARI USIA ALAT TERHADAP ALAT
TAHUN 2001 KE TAHUN TINJAUAN 2005
(Rp.)

0.382 ) x = Rp. 1,178,750,000.00 Nilai Buku = 450,068,181.82 10 Tahun


0.214 ) x = Rp. 666,250,000.00 Nilai Buku = 142,767,857.14 7 Tahun
0.214 ) x = Rp. 29,058,750.00 Nilai Buku = 6,226,875.00 7 Tahun
0.278 ) x = Rp. 43,050,000.00 Nilai Buku = 11,958,333.33 8 Tahun
0.278 ) x = Rp. 281,352,250.00 Nilai Buku = 78,153,402.78 8 Tahun
0.067 ) x = Rp. 26,855,666.25 Nilai Buku = 1,790,377.75 5 Tahun
0.067 ) x = Rp. 2,675,250.00 Nilai Buku = 178,350.00 5 Tahun
0.143 ) x = Rp. 182,962,500.00 Nilai Buku = 26,137,500.00 6 Tahun
0.143 ) x = Rp. 105,797,425.00 Nilai Buku = 15,113,917.86 6 Tahun
0.278 ) x = Rp. 139,513,775.00 Nilai Buku = 38,753,826.39 5 Tahun
0.143 ) x = Rp. 143,141,250.00 Nilai Buku = 20,448,750.00 6 Tahun
0.278 ) x = Rp. 91,481,250.00 Nilai Buku = 25,411,458.33 8 Tahun
0.067 ) x = Rp. 3,766,875.00 Nilai Buku = 251,125.00 5 Tahun
0.278 ) x = Rp. 417,758,225.00 Nilai Buku = 116,043,951.39 8 Tahun
0.382 ) x = Rp. 528,976,875.00 Nilai Buku = 201,972,988.64 10 Tahun
0.382 ) x = Rp. 203,411,250.00 Nilai Buku = 77,666,113.64 10 Tahun
0.382 ) x = Rp. 65,105,950.00 Nilai Buku = 24,858,635.45 10 Tahun
0.382 ) x = Rp. 165,742,500.00 Nilai Buku = 63,283,500.00 10 Tahun
0.382 ) x = Rp. 118,387,500.00 Nilai Buku = 45,202,500.00 10 Tahun
0.143 ) x = Rp. 3,228,750.00 Nilai Buku = 461,250.00 6 Tahun
0.067 ) x = Rp. 3,487,050.00 Nilai Buku = 232,470.00 5 Tahun
0.278 ) x = Rp. 380,992,500.00 Nilai Buku = 105,831,250.00 8 Tahun
0.143 ) x = Rp. 134,531,250.00 Nilai Buku = 19,218,750.00 6 Tahun
0.143 ) x = Rp. 137,188,050.00 Nilai Buku = 19,598,292.86 6 Tahun
Tenggarong 2008
Dibuat Oleh :
Konsultan Perencana
CV.MITRA JASA BINA PRATAMA

ISKANDAR, ST
Direktur
BINA MARGA DAN PENGAIRAN KOTA SAMARINDA

Kegiatan : Pembangunan Jalan Dalam Kota Samarind


Lokasi : Samarinda
Tahun Anggaran : 2011

KODE TENA- KAPASITAS


NO URAIAN ALAT GA TENAGA
DI PERGUNAKAN ALAT
HARGA ALAT
DMB MAKSIMUM
1 - (200 %) ÷ (n-ni) HP ---
(Rp.) Pw Cp

1,139,458,333.33
621,833,333.33
27,121,500.00 1 2 3 4 5
40,897,500.00 1 Asphat Mixing Plant E.010 150 50 Ton/Jam
267,284,637.50 2 Batcing Plant E.020 150 150 Ton
21,484,533.00 3 Asphalt Finisher E.020 47 6 Ton
2,140,200.00 4 Concret Finisher 30 6 Ton
164,666,250.00 5 Asphalt Sprayer E.030 150 800 Liter
95,217,682.50 6 Air Compressor 4000-6500 L/m3 E.040 50 ---
111,611,020.00 7 Bulldozer 100-150 HP E.050 150 ---
128,827,125.00 8 Concrete Mixer 0,3-0,6 m3 E.060 15 500 Liter
86,907,187.50 9 Concrete Vibrator E.070 30 ---
3,013,500.00 10 Dump Truck 3-4 m3 E.080 100 6 Ton
396,870,313.75 11 Dump Truck 3-4 m3 E.080 100 6 Ton
511,344,312.50 12 Dump Truck Mixer E.090 100 6 Ton
196,630,875.00 13 Excavator 80-140 HP E.100 50 0.5 m3
62,935,751.67 14 Flat Bed Truck 3-4 m3 E.110 100 4 m3
160,217,750.00 15 Generator Set E.120 175 125 KVA
114,441,250.00 16 Jack Hammer E.130 3 ---
2,905,875.00 17 Motor Grader > 100 HP E.140 125 ---
2,789,640.00 18 Stone Crusher E.150 220 50 Ton/Jam
361,942,875.00 19 Track Loader 75-100 HP E.160 90 2 m3
121,078,125.00 20 Three Wheel Roller 6-8 Ton E.170 55 8 Ton
123,469,245.00 21 Tandem Roller 6-8 Ton E.180 50 8 Ton
22 Tire Roller 8-10 Ton E.190 50 10 Ton
23 Tamper Vibrator Plate E.200 5 0 Ton
116,590.62 24 Water Pump 70-100 mm E.210 6 ---
25 Wheel Loader 1,0-1,6 m3 E.220 105 2 m3
26 Water Tanker 3000-4500 Liter E.230 100 4,000 Liter
INA PRATAMA 27 Vibratory Roller 5-8 Ton E.240 75 7 Ton
28 Concrete Cuter E.250 2
29 Fulvi Mixer E.250 75 ---
30 Concrete Pump E.260 125 ---
31 Mesin Pancang E.270 100 ---

KETERANGAN
Tingkat Suku Bunga i = 20 %
Upah Operator / Sopir U1
Upah Pembantu Operator / Sopir U2
Bahan Bakar Bensin Mb
Bahan Bakar Solar Ms
Minyak Pelumas Mp
ANALISA BIAYA SEWA

alam Kota Samarinda

PERALATAN ALAT YANG DI PAKAI NILAI


UMUR JAM HARGA UMUR JAM HARGA SISA
EKO- KERJA ALAT EKO- KERJA ALAT ALAT
NOMIS 1 TH NOMIS 1 TH NILAI SUSUT
ALAT (PEMBULATAN) ALAT PER TAHUN
Tahun Jam Rp. Tahun Jam Rp. Rp.
A W B A' W' B' C
7 Jam (W' ÷ W) 4 Jam B x (1 - A'/A) 10 % x B
Efektif x xA Efektif x
300 Hari 300 Hari
6 7 8 9 10 11 12
5 2,100 1,700,000,000.00 3 1,200 728,571,428.57 170,000,000.00
10 2,100 800,000,000.00 6 1,200 342,857,142.86 80,000,000.00
6 2,100 600,000,000.00 3 1,200 257,142,857.14 60,000,000.00
8 2,100 625,000,000.00 5 1,200 267,857,142.86 62,500,000.00
8 2,100 5,500,000.00 5 1,200 2,357,142.86 550,000.00
8 2,100 95,000,000.00 5 1,200 40,714,285.71 9,500,000.00
6 2,100 1,200,000,000.00 3 1,200 514,285,714.29 120,000,000.00
5 2,100 5,000,000.00 3 1,200 2,142,857.14 500,000.00
6 2,100 60,000,000.00 3 1,200 25,714,285.71 6,000,000.00
10 2,000 202,000,000.00 6 1,200 80,793,939.70 20,200,000.00
10 2,000 202,000,000.00 6 1,200 80,793,939.70 20,200,000.00
5 2,100 325,000,000.00 3 1,200 139,285,714.29 32,500,000.00
4 2,100 950,000,000.00 2 1,200 407,142,857.14 95,000,000.00
5 2,100 325,000,000.00 3 1,200 139,285,714.29 32,500,000.00
10 2,100 222,000,000.00 6 1,200 95,142,857.14 22,200,000.00
4 2,100 27,000,000.00 2 1,200 11,571,428.57 2,700,000.00
5 2,100 1,150,000,000.00 3 1,200 492,857,142.86 115,000,000.00
8 2,100 1,010,000,000.00 5 1,200 432,857,142.86 101,000,000.00
7 2,100 504,000,000.00 4 1,200 216,000,000.00 50,400,000.00
7 2,100 765,000,000.00 4 1,200 327,857,142.86 76,500,000.00
8 2,100 890,000,000.00 5 1,200 381,428,571.43 89,000,000.00
7 2,100 665,000,000.00 4 1,200 285,000,000.00 66,500,000.00
3 2,100 6,700,000.00 2 1,200 2,871,428.57 670,000.00
5 2,100 9,450,000.00 3 1,200 4,050,000.00 945,000.00
6 2,100 1,012,000,000.00 3 1,200 433,714,285.71 101,200,000.00
5 2,100 320,000,000.00 3 1,200 137,142,857.14 32,000,000.00
7 2,100 900,000,000.00 4 1,200 385,714,285.71 90,000,000.00
4 2,100 15,000,000.00 2 1,200 6,428,571.43 1,500,000.00
5 2,100 150,000,000.00 3 1,200 64,285,714.29 15,000,000.00
5 2,100 950,000,000.00 3 1,200 407,142,857.14 95,000,000.00
5 2,100 500,000,000.00 3 1,200 214,285,714.29 50,000,000.00

= 0.20 / Tahun
= Rp. 1,400.00 Rp. / Jam
= Rp. 10,000.00 Rp. / Jam
= Rp. 6,000.00 Liter
= Rp. 8,500.00 Liter
= Rp. 3,045,230.68 Liter
A BIAYA SEWA PERALATAN PER JAM KERJA

FAKTOR BIAYA PASTI PER JAM BI


PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR DAN PELUMAS
BALIAN PENGEM- DAN BIAYA BAHAN BAHAN
MODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR BAKAR
MODAL AMP
--- Rp. Rp. Rp. Lt/HP/Jam Lt/HP/Jam
D E F G H1 H2
i x (1+i)^A' (B'-C) x D 0,2 x C E+F (0,125-0,175) 12 x 0,7 Cp x Ms
(1+i)^A'-1 W' W' Lt/HP/Jam
x Pw x Ms
13 14 15 16 17 18
0.00000 0.00 28,333.33 28,333.33 4,200,000.00
0.00000 0.00 13,333.33 13,333.33 232,500.00
0.00000 0.00 10,000.00 10,000.00 72,850.00
0.00000 0.00 10,416.67 10,416.67 46,500.00
0.00000 0.00 91.67 91.67 187,500.00
0.00000 0.00 1,583.33 1,583.33 77,500.00
0.00000 0.00 20,000.00 20,000.00 232,500.00
0.00000 0.00 83.33 83.33 23,250.00
0.00000 0.00 1,000.00 1,000.00 46,500.00
0.00000 0.00 3,366.67 3,366.67 155,000.00
0.00000 0.00 3,366.67 3,366.67 165,000.00
0.00000 0.00 5,416.67 5,416.67 155,000.00
0.00000 0.00 15,833.33 15,833.33 77,500.00
0.00000 0.00 5,416.67 5,416.67 155,000.00
0.00000 0.00 3,700.00 3,700.00 271,250.00
0.00000 0.00 450.00 450.00 4,650.00
0.00000 0.00 19,166.67 19,166.67 206,250.00
0.00000 0.00 16,833.33 16,833.33 341,000.00
0.00000 0.00 8,400.00 8,400.00 139,500.00
0.00000 0.00 12,750.00 12,750.00 90,750.00
0.00000 0.00 14,833.33 14,833.33 77,500.00
0.00000 0.00 11,083.33 11,083.33 77,500.00
0.00000 0.00 111.67 111.67 7,750.00
0.00000 0.00 157.50 157.50 9,300.00
0.00000 0.00 16,866.67 16,866.67 173,250.00
0.00000 0.00 5,333.33 5,333.33 165,000.00
0.00000 0.00 15,000.00 15,000.00 123,750.00
0.00000 0.00 250.00 250.00 3,100.00
0.00000 0.00 2,500.00 2,500.00 93,750.00
0.00000 0.00 15,833.33 15,833.33 193,750.00
0.00000 0.00 8,333.33 8,333.33 155,000.00
BIAYA OPERASI PER JAM
R DAN PELUMAS WORKSHOP SPAREPART UPAH TOTAL
MINYAK KOEFISIEN KOEFISIEN OPERATOR PEMBANTU BIAYA
PELUMAS SOPIR OPERATOR OPERASI / JAM
SOPIR
Lt/HP/Jam --- --- Rp. Rp. Rp.
I J K L M N
(0,0035-0,0060) (6,25%-8,75%) x B' (12,5%-17,5%) x B' 1 Orang 1 Orang H+I+J+K+L+M
Lt/HP/Jam W' W' x U1 x U2
x Pw x Mp AMP = 3 Orang
19 20 21 22 23 24
5,400.00 53,125.00 106,250.00 0.00 0.60 4,364,775.60
5,400.00 25,000.00 50,000.00 0.00 0.20 312,900.20
1,692.00 18,750.00 37,500.00 0.00 0.20 130,792.20
1,080.00 19,531.25 39,062.50 0.00 0.20 106,173.95
3,150.00 171.88 343.75 0.00 0.20 191,165.83
1,800.00 2,968.75 5,937.50 0.00 0.20 88,206.45
5,400.00 37,500.00 75,000.00 0.00 0.20 350,400.20
540.00 156.25 312.50 0.00 0.20 24,258.95
1,080.00 1,875.00 3,750.00 0.00 0.20 53,205.20
3,600.00 5,891.22 11,782.45 0.00 0.20 176,273.87
3,600.00 5,891.22 11,782.45 0.00 0.20 186,273.87
3,600.00 10,156.25 20,312.50 0.00 0.20 189,068.95
1,800.00 29,687.50 59,375.00 0.00 0.20 168,362.70
3,600.00 10,156.25 20,312.50 0.00 0.20 189,068.95
6,300.00 6,937.50 13,875.00 0.00 0.20 298,362.70
108.00 843.75 1,687.50 0.00 0.20 7,289.45
4,500.00 35,937.50 71,875.00 0.00 0.20 318,562.70
7,920.00 31,562.50 63,125.00 0.00 0.20 443,607.70
3,240.00 15,750.00 31,500.00 0.00 0.20 189,990.20
1,980.00 23,906.25 47,812.50 0.00 0.20 164,448.95
1,800.00 27,812.50 55,625.00 0.00 0.20 162,737.70
1,800.00 20,781.25 41,562.50 0.00 0.20 141,643.95
180.00 209.38 418.75 0.00 0.20 8,558.33
216.00 295.31 590.63 0.00 0.20 10,402.14
3,780.00 31,625.00 63,250.00 0.00 0.20 271,905.20
3,600.00 10,000.00 20,000.00 0.00 0.20 198,600.20
2,700.00 28,125.00 56,250.00 0.00 0.20 210,825.20
72.00 468.75 937.50 0.00 0.20 4,578.45
1,575.00 4,687.50 9,375.00 0.00 0.20 109,387.70
4,500.00 29,687.50 59,375.00 0.00 0.20 287,312.70
3,600.00 15,625.00 31,250.00 0.00 0.20 205,475.20
BINA MARGA DAN PENGAIRAN KOTA SAMARINDA

DAFTAR ANALISA HARGA SATUAN DASA

Kegiatan : Pembangunan Jalan Dalam Kota Samarinda


Lokasi : Samarinda
Tahun Anggaran : 2011
TOTAL
BIAYA KET.
SEWA ALAT USIA NO TENAGA KERJA KODE
PER JAM KERJA ALAT

Rp.
O P A B C
G+N
1 Mandor Lapangan L.061
2 Mekanik L.071
25 26 3 Mekanik Pembantu L.072
4,393,108.93 5 Tahun 4 Kepala Tukang L.073
326,233.53 10 Tahun 5 Tukang L.079
140,792.20 6 Tahun 6 Operator Terlatih L.081
116,590.62 8 Tahun 7 Operator Semi Terlatih L.082
191,257.49 8 Tahun 8 Pembantu Operator L.089
89,789.78 8 Tahun 9 Sopir Truck L.091
370,400.20 6 Tahun 10 Sopir Personil L.092
24,342.28 5 Tahun 11 Pembantu Sopir L.099
54,205.20 6 Tahun 12 Pekerja Tak Terlatih L.101
179,640.54 10 Tahun 13 Pekerja Semi Terlatih L.103
189,640.54 10 Tahun 14 Pekerja Terlatih L.106
194,485.62 5 Tahun
184,196.03 4 Tahun
194,485.62 5 Tahun
302,062.70 10 Tahun
7,739.45 4 Tahun
337,729.37 5 Tahun
460,441.03 8 Tahun
198,390.20 7 Tahun
177,198.95 7 Tahun
177,571.03 8 Tahun
152,727.28 7 Tahun
8,669.99 3 Tahun
10,559.64 5 Tahun
288,771.87 6 Tahun
203,933.53 5 Tahun
225,825.20 7 Tahun
4,828.45 4 Tahun DAFTAR ANALISA HARGA SATUAN DAS
111,887.70 5 Tahun
303,146.03 5 Tahun
213,808.53 5 Tahun Kegiatan : Pembangunan Jalan Dalam Kota Samarinda
Lokasi : Samarinda
Tahun Anggaran : 2011

NO BAHAN / MATERIAL

A B

1 Agregat Kasar Pondasi Kelas A (P)


2 Agregat Halus Pondasi Kelas A (P)
3 Agregat Kasar Pondasi Kelas B (P)
4 Agregat Halus Pondasi Kelas B (P)
5 Agregat Kasar Untuk Hotmix (P)
6 Agregat Halus Untuk Hotmix (P)
7 Agregat Untuk Beton (P)
8 Aspal Bitumen
9 Batu Pecah 15 - 20 cm (L)
10 Batu Pecah 10 - 15 cm (L)
11 Batu Pecah 5 - 7 cm (L)
12 Batu Pecah 3 - 5 cm (L)
13 Batu Pecah 2 - 3 cm (L)
14 Batu Pecah 1 - 2 cm (L)
15 Batu Pecah 0,5 - 1 cm (L)
16 Batu Gunung (L)
17 Batu Padas (L)
18 Besi Galvanis
19 Baja Konstruksi
21 Besi Tulangan Beton
21 Filler / Debu Batu (P)
22 Kayu Ulin 10/10-4 (L)
23 Kawat Bronjong (Gabions)
24 Kawat Beton
25 Kayu Perancah / Bekisting (L)
26 Kayu Ulin Konstruksi Jembatan (L)
27 Kerikil / Sirtu (L)
28 Kerikil Sungai (L)
29 Pasir Ayak Untuk Beton (P)
30 Pasir Pasangan (L)
31 Pasir Urug / Timbunan (L)
32 Paku Biasa
33 Paku Ulin
35 Baut
36 Plat Beugel
37 Semen PC
39 Tanah Urug (L)
40 Minyak Flux / Kerosene
41 Minyak Tanah
42 Minyak Diesel / Solar
43 Minyak Pelumas
44 Bensin / Premium
45 Besi Wearmes Diameter 10 mm
46 Agregat Kelas C (L)
47 Joint Sealent
48 Diamond Blade
49 Plastik Sheet
50 Kayu Segitiga
51 Karung Goni
52 Beton Ready Mix K 2350
52 Beton Ready Mix K 300

DAFTAR ANALISA HARGA SATUAN DAS

Kegiatan : Pembangunan Jalan Dalam Kota Samarinda


Lokasi : Samarinda
Tahun Anggaran : 2011

NO PERALATAN

A B

1 Asphat Mixing Plant


2 Asphalt Finisher
3 Asphalt Sprayer
4 Air Compressor 4000-6500 L/m3
5 Bulldozer 100-150 HP
6 Concrete Mixer 0,3-0,6 m3
7 Concrete Vibrator
8 Dump Truck 3-4 m3
9 Dump Truck Mixer
10 Excavator 80-140 HP
11 Flat Bed Truck 3-4 m3
12 Generator Set
13 Jack Hammer
14 Motor Grader > 100 HP
15 Stone Crusher
16 Track Loader 75-100 HP
17 Three Wheel Roller 6-8 Ton
18 Tandem Roller 6-8 Ton
19 Pneumatic Tire Roller 8-10 Ton
20 Tamper Vibrator Plate
21 Water Pump 70-100 mm
22 Wheel Loader 1,0-1,6 m3
23 Water Tanker 3000-4500 Liter
24 Vibratory Roller 6-8 Ton
25 Concrete Cutter
25 Concrete Pump
26 Mesin Pancang
BINA MARGA DAN PENGAIRA

A HARGA SATUAN DASAR UPAH TENAGA KERJA

m Kota Samarinda

NO TENAGA

HARGA HARGA
SAT SATUAN SATUAN DASAR UPAH 1 Mandor Lapangan
DASAR TENAGA KERJA 2 Mekanik
PER HARI PER JAM PEMBULATAN 3 Mekanik Pembantu
Rp. Rp. Rp. 4 Kepala Tukang
D E F=E÷7 G 5 Tukang
6 Operator Terlatih
Jam 84,000.00 12,000.00 12,000.00 7 Operator Semi Terlatih
Jam 76,000.00 10,857.14 10,800.00
Jam 70,000.00 10,000.00 10,000.00 NO MATERIAL
Jam 75,000.00 10,714.29 10,700.00
Jam 91,000.00 13,000.00 13,000.00
Jam 91,000.00 13,000.00 13,000.00
Jam 67,000.00 9,571.43 9,500.00 A B
Jam 10,000.00 1,428.57 1,400.00 1 Agregat Kasar Pondasi Kela
Jam 70,000.00 10,000.00 10,000.00 2 Agregat Halus Pondasi Kela
Jam 70,000.00 10,000.00 10,000.00 3 Agregat Kasar Pondasi Kela
Jam 65,000.00 9,285.71 9,200.00 4 Agregat Halus Pondasi Kela
Jam 52,500.00 7,500.00 7,500.00 5 Agregat Kasar Untuk Hotm
Jam 70,000.00 10,000.00 10,000.00 6 Agregat Halus Untuk Hotm
Jam 70,000.00 10,000.00 10,000.00 7 Agregat Untuk Beton (P)
8 Aspal Bitumen
9 Batu Pecah 15 - 20 cm (L)
10 Batu Pecah 10 - 15 cm (L)
Dibuat Oleh, 11 Batu Pecah 5 - 7 cm (L)
Konsultan Perencana 12 Batu Pecah 3 - 5 cm (L)
CV. KALTIKONS DESAIN 13 Batu Pecah 2 - 3 cm (L)
289,920.00 14 Batu Pecah 1 - 2 cm (L)
15 Batu Pecah 0,5 - 1 cm (L)
0.00 16 Batu Gunung (L)
1368431.98 17 Batu Padas (L)
HADRIYANI, ST 18 Besi Galvanis
Direktur 19 Baja Konstruksi
869559 20 Besi Tulangan Beton
21 Filler / Debu Batu (P)
22 Beton Ready Mix K-350
#DIV/0! 23 Kayu Ulin 10/10-4 (L)
SA HARGA SATUAN DASAR BAHAN / MATERIAL 24 Kawat Bronjong (Gabions)
25 Kawat Beton
26 Kayu Perancah / Bekisting
m Kota Samarinda 27 Kayu Ulin Konstruksi Jemb
28 Kerikil / Sirtu (L)
29 Kerikil Sungai (L)
30 Pasir Ayak Untuk Beton (P)
HARGA 31 Pasir Pasangan (L)
KODE SAT SATUAN DASAR 32 Tanah Urug (L)
BAHAN / MATERIAL 33 Paku Biasa
PEMBULATAN 34 Paku Ulin
Rp. Rp. 35 Baut
C D E F 36 Plat Beugel
37 Semen PC
M.031 M3 340,000.00 340,000.00 38 Tanah Pilihan (L)
M.033 M3 340,000.00 340,000.00 39 Minyak Flux / Kerosene
M.035 M3 286,000.00 286,000.00 40 Minyak Tanah
M.036 M3 286,000.00 286,000.00 41 Minyak Diesel / Solar
M.090 M3 302,000.00 302,000.00 42 Minyak Pelumas
M.161 M3 286,000.00 286,000.00 43 Bensin / Premium
M.082 M3 364,477.27 364,477.27 44 Besi Wearmes Diameter 10 m
M.061 Kg 8,604.43 8,604.43 45 Agregat Kelas C (L)
M.020 M3 246,120.45 246,120.45 46 Joint Sealent
M.021 M3 261,720.45 261,720.45 47 Diamond Blade
M.022 M3 269,000.45 269,000.45 48 Plastik Sheet
M.023 M3 303,320.45 303,320.45 49 Kayu Segitiga
M.024 M3 313,720.45 313,720.45 50 Pipa PVC 1"
M.025 M3 331,920.45 331,920.45 51 Karung Goni
M.026 M3 334,520.45 334,520.45 52 Beton Ready Mix K-250
M.010 M3 227,627.27 227,627.27 53 Beton Ready Mix K-300
M.011 Kg 106,575.00 106,575.00
M.164 Kg 99,193.18 99,193.18 Beton Ready Mix K-175
M.165 Kg 19,515.68 19,515.68
M.167 Kg 7,285.99 7,285.99
M.062 Kg 821.23 821.23
M.070 Titik 145,692.27 145,692.27
M.162 Kg 27,635.68 27,635.68
M.170 Kg 14,672.73 14,672.73
M.180 M3 2,342,306.82 2,342,306.82
M.181 M3 3,642,306.82 3,642,306.82
M.011 M3 261,720.45 261,720.45
M.012 M3 282,520.45 282,520.45
M.041 M3 344,177.27 344,177.27
M.040 M3 130,000.00 130,000.00
M.050 M3 37,606.25 37,606.25
M.166 Kg 15,455.68 15,455.68
M.167 Kg 24,590.68 24,590.68
M.168 Buah 4,290.68 4,290.68
M.169 Buah 25,605.68 25,605.68
M.080 Kg 1,420.77 1,420.77
M.081 M3 37,606.25 37,606.25
M.063 Liter < ---------------- > 6,000.00
M.065 Liter < ---------------- > 3,000.00
M.183 Liter < ---------------- > 7,527.50
M.185 Liter < ---------------- > 26,000.00
M.184 Liter < ---------------- > 6,000.00
M.186 M2 3,045,230.68 3,045,230.68
M.187 M3 141,177.27 141,177.27
M.189 Kg 9,349.40 9,349.40
M.190 Buah 862,750.00 862,750.00
M.191 M2 8,627.50 8,627.50
M.192 M1 3,552.50 3,552.50
Lbr 5,075.00 5,075.00
M.195 M3 1,007,133.75 1,007,133.75
M.196 M3 1,205,820.00 1,205,820.00
Dibuat Oleh,
Konsultan Perencana
CV. KALTIKONS DESAIN

HADRIYANI, ST
Direktur

SA HARGA SATUAN DASAR SEWA PERALATAN

m Kota Samarinda
HARGA SATUAN
KODE SAT PERALATAN
HARGA BELI HARGA SEWA
SESUAI TAHUN ALAT PER JAM
Rp. Rp.
C D E F

E.010 Jam 1,700,000,000.00 4,393,108.93


E.020 Jam 600,000,000.00 140,792.20
E.030 Jam 5,500,000.00 191,257.49
E.040 Jam 95,000,000.00 89,789.78
E.050 Jam 1,200,000,000.00 370,400.20
E.060 Jam 5,000,000.00 24,342.28
E.070 Jam 60,000,000.00 54,205.20
E.080 Jam 202,000,000.00 189,640.54
E.090 Jam 325,000,000.00 194,485.62
E.100 Jam 950,000,000.00 184,196.03
E.110 Jam 325,000,000.00 194,485.62
E.120 Jam 222,000,000.00 302,062.70
E.130 Jam 27,000,000.00 7,739.45
E.140 Jam 1,150,000,000.00 337,729.37
E.150 Jam 1,010,000,000.00 460,441.03
E.160 Jam 504,000,000.00 198,390.20
E.170 Jam 765,000,000.00 177,198.95
E.180 Jam 890,000,000.00 177,571.03
E.190 Jam 665,000,000.00 152,727.28
E.200 Jam 6,700,000.00 8,669.99
E.210 Jam 9,450,000.00 10,559.64
E.220 Jam 1,012,000,000.00 288,771.87
E.230 Jam 320,000,000.00 203,933.53
E.240 Jam 900,000,000.00 225,825.20
E.250 Jam 150,000,000.00 111,887.70
E.260 Jam 950,000,000.00 303,146.03
E.270 Jam 500,000,000.00 213,808.53

Dibuat Oleh,
Konsultan Perencana
CV. KALTIKONS DESAIN
HADRIYANI, ST
Direktur
MARGA DAN PENGAIRAN KOTA SAMARINDA

DAFTAR UPAH TENAGA KERJA DAN HARGA SATUAN BAHAN / MATERI

TENAGA KERJA KODE HARGA NO


UPAH
(Rp. / HARI)
Mandor Lapangan L.061 84,000.00 8
L.071 84,000.00 9
Mekanik Pembantu L.072 70,000.00 10
Kepala Tukang L.073 70,000.00 11
L.079 91,000.00 12
Operator Terlatih L.081 91,000.00 13
Operator Semi Terlatih L.082 67,000.00 14

MATERIAL SAT KODE HARGA JARAK ONGKOS


QUARRY RATA² ANGKUT
RATA-RATA
(Rp.) (Km) (Rp.)
B C D E F G
Agregat Kasar Pondasi Kelas A (P) M3 M.031 290,000.00 20 9,090.91 / M3
Agregat Halus Pondasi Kelas A (P) M3 M.033 305,000.00 20 9,090.91 / M3
Agregat Kasar Pondasi Kelas B (P) M3 M.035 245,000.00 20 9,090.91 / M3
Agregat Halus Pondasi Kelas B (P) M3 M.036 255,000.00 20 9,090.91 / M3
Agregat Kasar Untuk Hotmix (P) M3 M.090 315,000.00 20 9,090.91 / M3
Agregat Halus Untuk Hotmix (P) M3 M.161 335,000.00 20 9,090.91 / M3
Agregat Untuk Beton (P) M3 M.082 350,000.00 20 9,090.91 / M3
Aspal Bitumen Kg M.061 8,250.00 5 227.27 / Kg
Batu Pecah 15 - 20 cm (L) M3 M.020 230,000.00 15 6,818.18 / M3
Batu Pecah 10 - 15 cm (L) M3 M.021 245,000.00 15 6,818.18 / M3
Batu Pecah 5 - 7 cm (L) M3 M.022 252,000.00 15 6,818.18 / M3
Batu Pecah 3 - 5 cm (L) M3 M.023 285,000.00 15 6,818.18 / M3
Batu Pecah 2 - 3 cm (L) M3 M.024 295,000.00 15 6,818.18 / M3
Batu Pecah 1 - 2 cm (L) M3 M.025 312,500.00 15 6,818.18 / M3
Batu Pecah 0,5 - 1 cm (L) M3 M.026 315,000.00 15 6,818.18 / M3
Batu Gunung (L) M3 M.010 210,000.00 20 9,090.91 / M3
Batu Padas (L) M3 M.011 100,000.00 20 5,000.00 / M3
Besi Galvanis Kg M.164 97,500.00 5 227.27 / Kg
Baja Konstruksi Kg M.165 19,000.00 5 227.27 / Kg
Besi Tulangan Beton Kg M.167 8,000.00 5 227.27 / Kg
Filler / Debu Batu (P) Kg M.062 800.00 20 9.09 / Kg
Beton Ready Mix K-350 M3 M555 1,302,000.00 20 9,090.91 / M3
Kayu Ulin 10/10-4 (L) Btg M.070 140,000.00 5 90.91 / Ttk
Kawat Bronjong (Gabions) Kg M.162 27,000.00 5 227.27 / Kg
Kawat Beton Kg M.170 12,000.00 5 227.27 / M3
Kayu Perancah / Bekisting (L) M3 M.180 2,250,000.00 5 2,272.73 / M3
Kayu Ulin Konstruksi Jembatan (L) M3 M.181 3,500,000.00 5 2,272.73 / M3
Kerikil / Sirtu (L) M3 M.011 245,000.00 15 6,818.18 / M3
Kerikil Sungai (L) M3 M.012 265,000.00 15 6,818.18 / M3
Pasir Ayak Untuk Beton (P) M3 M.041 330,000.00 20 9,090.91 / M3
Pasir Pasangan (L) M3 M.040 100,000.00 15 6,818.18 / M3
Tanah Urug (L) M3 M.050 32,500.00 15 3,750.00 / M3
Kg M.166 15,000.00 5 227.27 / Kg
Kg M.167 24,000.00 5 227.27 / Kg
Buah M.168 4,000.00 5 227.27 / Kg
Buah M.169 25,000.00 5 227.27 / Bh
Kg M.080 1,190.00 40 45.45 / Kg
Tanah Pilihan (L) M3 M.081 45,000.00 15 3,750.00 / M3
Minyak Flux / Kerosene Lt M.063 6,000.00
Minyak Tanah Lt M.065 3,000.00
Minyak Diesel / Solar Lt M.183 7,277.50 5.00 250.00
Minyak Pelumas Lt M.185 26,000.00
Bensin / Premium Lt M.184 6,000.00
Besi Wearmes Diameter 10 mm Roll M.186 3,000,000.00 5 227.27 / Roll
Agregat Kelas C (L) M3 M.187 130,000.00 20 9,090.91 / M3
Joint Sealent Kg M.189 17,000.00 0.00 / Kg
Diamond Blade Buah M.190 850,000.00 0.00 / Buah
Plastik Sheet M2 M.191 8,500.00 0.00 / Buah
Kayu Segitiga M1 M.192 3,500.00 0.00 / Buah
Pipa PVC 1" M1 M.193 12,500.00 0.00 / Buah
Karung Goni Lbr M.194 5,000.00 0.00 / Buah
Beton Ready Mix K-250 Lbr M.195 992,250.00 0.00 / Buah
Beton Ready Mix K-300 Lbr M.196 1,188,000.00 0.00 / Buah

Beton Ready Mix K-175 950,250


GA SATUAN BAHAN / MATERIAL

Kegiatan
Item Pembayaran
Jenis Kegiatan
TENAGA KERJA KODE HARGA Satuan Pembayaran
UPAH
(Rp. / HARI)
Pembantu Operator L.089 10,000.00 NO
Sopir Truck L.091 60,000.00
Sopir Personil L.092 60,000.00
Pembantu Sopir L.099 10,000.00 I
Pekerja Tak Terlatih L.101 52,500.00 1
Pekerja Semi Terlatih L.103 70,000.00 2
Pekerja Terlatih L.106 70,000.00 3
4
JUMLAH PROFIT PAJAK JUMLAH 5
HARGA 1,5 % 2,5 % HARGA
TANPA PAJAK / SATUAN 20 x E / SATUAN PASARAN II
(Rp.) (Rp.) (Rp.) (Rp.) 1
H I J K 2
299,090.91 4,486.36 303,577.27
314,090.91 4,711.36 318,802.27 3
254,090.91 3,811.36 257,902.27
264,090.91 3,961.36 268,052.27 4
324,090.91 4,861.36 328,952.27
344,090.91 5,161.36 349,252.27 III
359,090.91 5,386.36 364,477.27 1
8,477.27 127.16 8,604.43
236,818.18 3,552.27 5,750.00 Galian C 246,120.45 2
251,818.18 3,777.27 6,125.00 Galian C 261,720.45 2.a.
258,818.18 3,882.27 6,300.00 Galian C 269,000.45
291,818.18 4,377.27 7,125.00 Galian C 303,320.45
301,818.18 4,527.27 7,375.00 Galian C 313,720.45
319,318.18 4,789.77 7,812.50 Galian C 331,920.45
321,818.18 4,827.27 7,875.00 Galian C 334,520.45
219,090.91 3,286.36 5,250.00 Galian C 227,627.27
105,000.00 1,575.00 106,575.00
97,727.27 1,465.91 99,193.18
19,227.27 288.41 19,515.68
8,227.27 123.41 8,350.68
809.09 12.14 821.23
1,311,090.91 19,666.36 1,330,757.27 2.b.
140,090.91 2,101.36 3,500.00 SAKO 145,692.27
27,227.27 408.41 27,635.68
12,227.27 2,445.45 14,672.73
2,252,272.73 33,784.09 56,250.00 SAKO 2,342,306.82
3,502,272.73 52,534.09 87,500.00 SAKO 3,642,306.82
251,818.18 3,777.27 6,125.00 Galian C 261,720.45
271,818.18 4,077.27 6,625.00 Galian C 282,520.45
339,090.91 5,086.36 344,177.27
106,818.18 1,602.27 2,500.00 Galian C 110,920.45
36,250.00 543.75 812.50 Galian C 37,606.25
15,227.27 228.41 15,455.68
24,227.27 363.41 24,590.68
4,227.27 63.41 4,290.68
25,227.27 378.41 25,605.68
1,235.45 185.32 1,420.77 Catatan = Lr di sesuaikan dengan kondis
48,750.00 731.25 1,125.00 Galian C 50,606.25
6,000.00
3,000.00
7,527.50 Kegiatan
26,000.00 Item Pembayaran
6,000.00 Jenis Kegiatan
3,000,227.27 45,003.41 3,045,230.68 Satuan Pembayaran
139,090.91 2,086.36 141,177.27
17,000.00 255.00 17,255.00
850,000.00 12,750.00 862,750.00 NO
8,500.00 127.50 8,627.50
3,500.00 52.50 3,552.50
12,500.00 187.50 12,687.50 2.c.
5,000.00 75.00 5,075.00
992,250.00 14,883.75 1,007,133.75
1,188,000.00 17,820.00 1,205,820.00
75115
23 3
ilir
sambutan permai
cf 16
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3

4
5
6

II
1

III
1
1.a.
1.b.

1.c.
2
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5

II
1
2
3

III
1

2
2.a.
2.b.

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

II
1
2
3
4

5
III
1
1.a.
2
2.a.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO
2.b.

2.c.

2.d.

2.e.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

II
1
2
3
4

III
1
1.a.
2
2.a.
2.b.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.
2.d.

2.e.

2.f.

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5

II
1
2
3

III
1

2
2.c.
2.d.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.e.

2.f.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7
8

II
1
2
3
4
5

III
1
1.a.
2
2.a.

2.b.
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.

2.d.
2.e.

2.f.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO
I
1
2
3
4
5
6
7
8

II
1
2
3
4
5

III
1
1.a.
2
2.a.

2.b.
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.

2.d.

2.e.
2.f.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7

II
1
2
3
4
5

III
1
1.a.

2
2.a.

2.b.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.

2.d.

2.e.

2.f.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7

II
1
2
3
4
5

III
1
1.a.
2
2.a.

2.b.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.
2.d.

2.e.

2.f.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7

II
1
2
3
4
5

III
1
1.a.

2
2.a.
2.b.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.

2.g.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO
I
1
2
3
4
5
6

II
1

III
1

1.a.
1.b.
2
2.a.

2.b.
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

7
8

II
1
2

III
1
1.a.
1.b.
1.c.
1.d.
2
2.a.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.b.

2.c.
2.d.

2.e.

2.f.
2.g.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4

II
1

2
3
III
1
1.a
1.b.
1.c.
1.d.

5 2
11.2 2.a.
2.24

2.b.

2.c

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4

II
1

2
3
III
1
1.a
1.b.
1.c.
1.d.

2
2.a.
2,b

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

7
8

II
1

2
3

III
1
1.a.
1.b.
1.c.
1.d.

2
2.a.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.b.

2.c.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

II
1

2
3

III
1
1.1.
1.2.
2
2.a.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO
I
1
2
3
4
5
6

II
1
2

III
1
1.1.
1.2
2

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

II
1

2
3

III
1
1.1.
1.2.
2
2.a.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7

II
1
2

III
1
1.a.
1.b.
1.d.

2
2.a.

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.b.

2.c.

2.d.

2.e.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3

4
5
6

8
9

II
1

III
1
1.a.
1.b.

1.c.
2
3

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

II
1
2
3
5

III
1
1.a.
2
2.a.

2.b.
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.

2.f.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

7
8

II
1

III
1
1

2.a.
2.b.
2
2.a.

2.b.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
NO

2.c.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7
8
9

II
1

2
III
1
1

2
2.a.

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7
8
9

II
1
2
3
4

III
1
1.a.

2
2.a.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.b.

2.c.
2.d.

2.e.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.f
2.g

2.f.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7

II
1
2

III
1
1.a
1.b
1.c
1.d
2

2.a.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.b.
2.c.

2.d

2.e.

2.f.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO
2.g

2.h.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
NO

I
1
2
3
4
5
6

7
8

II
1

2
3

III
1
1.a.
1.b.
1.c.
1.d.

2
2.a.
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.b.

2.c.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5

II
1
2
3

III
1

2
2.a.

2.b.

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5

II
1
3
III
1

2
2.c.

2.d.

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

II
1

III
1
1.b.
1.c.

2
3
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

II
1
2

III
1
1.1.
1.2.
2

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
II
1
2

III
1
1.1.
1.2.
1.3.
2

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

7
8

II
1

2
3

III
1
1.a.
1.b.
1.c.
1.d.
1.e.

2
2.a.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Kegiatan

NO

2.b.

2.c.
3

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7

II
1
2
3
4
5

III
1
1.a.

2
2.a.

2.b.
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.

2.d.
2.e.

2.f.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO
I
1
2
3
4
5
6

II

1
2
3

III
1
1.a.

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7

II
1
2
3
4
5

III
1
1.a.

2
2.a.
2.b.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.c.

2.g.
3

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7
8
9

II
1

III
1
1

2
2.a.
3

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
7
8
9

II
1
2
3
4

III
1
1.a.

2
2.a.

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.b.

2.c.

2.d.
2.e.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.f

2.g
2.f.

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5

II
1

III
1
1.a.
1.b.

2
3
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

II
1
2
3
4
5

III
1
1.a.

2
2.a.
2.b.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6
II
1
2
3
4

III
1
1.a.

2.a.

2.b.

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5

II
1

III
1
1.a.
1.b.
1.c.

2
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3

4
5
6

II
1

III
1
1.a.
1.b.

1.c.
2
Catatan = Lr di sesuaikan dengan kondis
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

II

1
2
3

III
1
1.a.
1.b.
1.c.
2

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5

II
1

III
1
1.a.
1.b.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
NO

I
1
2
3
4
5
6

II
1
2

III
1
1.a.
1.b.
1.d.

2
2.a.
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

2.b.

2.c.

2.d.
2.e.

Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

I
1
2
3
4
5
6

7
8

II
1

2
3

III
1
1.a.
1.b.

2
2.a.

Catatan = Lr di sesuaikan dengan kondis


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

3
Catatan = Lr di sesuaikan dengan kondis

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO

1
2
3
4
5
6

II
1

2
III
1
1.a.

2.
2.a.

3.

Catatan = Lr di sesuaikan dengan kondis


METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 2.1
Jenis Kegiatan : Galian Parit
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk

METODE PELAKSANAAN
Penggalian di lakukan dengan menggunakan Excavator
Selanjutnya Excavator menuangkan material hasil galian
ke dalam Dump Truck
Dump Truck membuang hasil galian keluar lokasi jalan
sejauh Lpmb
Sekelompok pekerjan akan merapikan hasil galian

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Tidak Ada Bahan Yang Di Pergunakan
ALAT
EXCAVATOR E.10
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Berat Isi Material Bim
Waktu Siklus Ts1
- Menggali / Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fb x Fa x Bim x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Waktu Memuat = (V : Q1) x 60 T3
- Lain-Lain T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 2.1
Jenis Kegiatan : Galian Parit
Satuan Pembayaran : M3

URAIAN KODE

ALAT BANTU
Di Perlukan Alat-Alat Bantu Kecil

- Sekop
- Keranjang + Sapu
TENAGA
Produksi Menentukan = EXCAVATOR Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.9
Jenis Kegiatan : Pasangan Batu + Adukan
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan buruh (cara manual)
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (batu gunung, semen, pasir pasangan) di terima
seluruhnya di lokasi Kegiatan
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Perbandingan pasir & semen - Volume pasir Ps
- Volume semen Sm
Perbandingan batu & mortar
- Batu gunung Bt
- Mortar (campuran pasir & semen) Mr
Berat jenis bahan
- Pasangan batu dengan mortar D1
- Batu gunung D2
- Adukan (mortar) D3
- Pasir D4
- Semen PC D5
Faktor kehilangan bahan - Batu Fh1
- Pasir / Semen Fh2

METODE PELAKSANAAN
Semen, pasir dan air di campur dan di aduk menjadi mortar
dengan menggunakan alat bantu
Batu di bersihkan dan di basahi seluruh permukaannya
sebelum di pasang
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Batu Gunung [(Bt x D1 x 1 M3) : D2] x Fh1 M.010
Semen PC Sm x [(Mr x D1 x 1 M3) : D3] x Fh2 M.080
x [D5 x (1000)]
Pasir Pasangan Ps x [(Mr x D1 x 1 M3) : D4] x Fh2 M.040
ALAT
Produksi Per Hari = MORTAR Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih Pt
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Pt) : Qt L.106
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 3.1.(1)
Jenis Kegiatan : Galian Biasa
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk

METODE PELAKSANAAN
Tanah yang di potong umumnya berada di sisi jalan
Penggalian di lakukan dengan menggunakan Excavator
Selanjutnya Excavator menuangkan material hasil galian
ke dalam Dump Truck
Dump Truck membuang material hasil galian keluar lokasi
jalan sejauh Lpmb

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Tidak Ada Bahan Yang Di Pergunakan
ALAT
EXCAVATOR E.10
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Berat Isi Material Bim
Waktu Siklus Ts1
- Menggali / Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fb x Fa x Bim x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Waktu Memuat = (V : Q1) x 60 T3

Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN
Kegiatan : Pembangunan Jalan Dan Jembatan
Item Pembayaran : 3.1.(1)
Jenis Kegiatan : Galian Biasa
Satuan Pembayaran : M3

URAIAN KODE

ALAT BANTU
Di Perlukan Alat-Alat Bantu Kecil
- Sekop
- Keranjang + Sapu
TENAGA
Produksi Menentukan = EXCAVATOR Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 3.2.(1a)
Jenis Kegiatan : Urugan Biasa (Eks Galian)
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t

METODE PELAKSANAAN
Wheel Loader memuat ke dalam Dump Truck
Dump Truck mengangkut ke lapangan dengan jarak Lq
Material di hampar dengan menggunakan Motor Greader
Hamparan material di siram air dengan Water Tank Truck
(sebelum pemadatan) dan di padatkan dengan Vibratory Roller
Selama pemadatan sekelompok pekerja akan merapikan tepi
hamparan dan level permukaan dengan alat bantu
PEMAKAIAN BAHAN, ALAT DAN TENAGA
BAHAN
Tanah Urug = 1 x Fk M.081
ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 3.2.(1a)
Jenis Kegiatan : Urugan Biasa (Eks Galian)
Satuan Pembayaran : M3

URAIAN KODE
MOTOR GREADER E.140
Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts3
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1
- Lain-Lain T2
Ts3
Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3
Ts2 x n
Koefisien Alat / M3 = 1 : Q3
VIBRATORY ROLLER E.240
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q4
n
Koefisien Alat / M3 = 1 : Q4
WATER TANK TRUCK E.230
Volume Tangki Air V
Kebutuhan Air / M3 Material Padat Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q5
Wc
Koefisien Alat / M3 = 1 : Q5
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = WHEEL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 3.2.(1)
Jenis Kegiatan : Urugan Tanah Biasa
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t

METODE PELAKSANAAN
Wheel Loader memuat ke dalam Dump Truck
Dump Truck mengangkut ke lapangan dengan jarak Lq
Material di hampar dengan menggunakan Motor Greader
Hamparan material di siram air dengan Water Tank Truck
(sebelum pemadatan) dan di padatkan dengan Vibratory Roller
Selama pemadatan sekelompok pekerja akan merapikan tepi
hamparan dan level permukaan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Tanah Urug = 1 x Fk M.081
ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2

Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 3.2.(1)
Jenis Kegiatan : Urugan Tanah Biasa
Satuan Pembayaran : M3

URAIAN KODE

MOTOR GREADER E.140


Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts3
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1
- Lain-Lain T2
Ts3
Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3
Ts2 x n
Koefisien Alat / M3 = 1 : Q3
VIBRATORY ROLLER E.240
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q4
n
Koefisien Alat / M3 = 1 : Q4
WATER TANK TRUCK E.230
Volume Tangki Air V
Kebutuhan Air / M3 Material Padat Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q5
Wc
Koefisien Alat / M3 = 1 : Q5
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = WHEEL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN
Kegiatan : Pembangunan Jalan Dan Jembatan
Item Pembayaran : 3.3
Jenis Kegiatan : Penyiapan Badan Jalan
Satuan Pembayaran : M2

URAIAN KODE

ASUMSI
Kegiatan di laksanakan hanya pada tanah galian
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Kegiatan di lakukan secara mekanis

METODE PELAKSANAAN
Motor Greader meratakan permukaan hasil galian
Vibratory Roller memadatkan permukaan yang telah rata
Sekelompok pekerja akan membantu meratakan badan jalan
dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Tidak Di Perlukan Bahan / Material
ALAT
MOTOR GREADER E.140
Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts1
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = Lh x b x Fa x 60 Q1
Ts1 x n
Koefisien Alat / M3 = 1 : Q1
VIBRATORY ROLLER E.240
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x Fa Q2
n
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 3.3
Jenis Kegiatan : Penyiapan Badan Jalan
Satuan Pembayaran : M2

URAIAN KODE

WATER TANK TRUCK E.230


Volume Tangki Air V
Kebutuhan Air / M3 Material Padat Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q3
Wc
Koefisien Alat / M3 = 1 : Q3
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = VIBRATORY ROLLER Q2
Produksi Per Hari = Tk x Q2 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 3.2.(2)
Jenis Kegiatan : Timbunan Tanah Pilihan
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t
Jarak rata-rata ke Base Camp Lr
Lebar bahu jalan Lb

METODE PELAKSANAAN
Wheel Loader memuat timbunan ke dalam Dump Truck
Timbunan kemudian di hampar dengan Motor Greader
Hamparan timbunan di basahi dengan Water Tank Truck
Pemadatan di laksanakan dengan Vibratory Roller
Sekelompok pekerja merapikan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Tanah Urug = 1 x Fk M.081
ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 3.2.(2)
Jenis Kegiatan : Timbunan Tanah Pilihan
Satuan Pembayaran : M3

URAIAN KODE

MOTOR GREADER E.140


Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts3
- Perataan 1 kali lintasan = (Lh x 60) : (v x 1000) T1
- Lain-Lain T2
Ts3
Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3
Ts2 x n
Koefisien Alat / M3 = 1 : Q3
TANDEM ROLLER E.180
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q4
n
Koefisien Alat / M3 = 1 : Q4
WATER TANK TRUCK E.230
Volume Tangki Air V
Kebutuhan Air / M3 Material Padat Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q5
Wc
Koefisien Alat / M3 = 1 : Q5
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = WHEEL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 2.4
Jenis Kegiatan : Bahu Agregat
Satuan Pembayaran : M3

URAIAN KODE
ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t
Jarak rata-rata ke Base Camp Lr
Lebar bahu jalan Lb

METODE PELAKSANAAN
Wheel Loader memuat agregat ke dalam Dump Truck
Aggregat kemudian di hampar dengan Motor Greader
Hamparan agregat di basahi dengan Water Tank Truck
Pemadatan di laksanakan dengan Vibratory Roller
Sekelompok pekerja merapikan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Agregat Kasar Kelas B = 1 x Fk M.035
ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 2.4
Jenis Kegiatan : Bahu Agregat
Satuan Pembayaran : M3

URAIAN KODE

MOTOR GREADER E.140


Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts3
- Perataan 1 kali lintasan = (Lh x 60) : (v x 1000) T1
- Lain-Lain T2
Ts3
Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3
Ts2 x n
Koefisien Alat / M3 = 1 : Q3
TANDEM ROLLER E.180
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q4
n
Koefisien Alat / M3 = 1 : Q4
WATER TANK TRUCK E.230
Volume Tangki Air V
Kebutuhan Air / M3 Material Padat Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q5
Wc
Koefisien Alat / M3 = 1 : Q5
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = WHEEL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.1.(1).
Jenis Kegiatan : Lapis Pondasi Klas A
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t
Jarak rata-rata ke Base Camp Lr

METODE PELAKSANAAN
Wheel Loader memuat agregat ke dalam Dump Truck
Aggregat kemudian di hampar dengan Motor Greader
Hamparan agregat di basahi dengan Water Tank Truck
Pemadatan di laksanakan dengan Vibratory Roller
Sekelompok pekerja merapikan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Agregat Kasar A 65 % Di produksi di base camp M.033
Agregat Halus A 35 % Di produksi di base camp M.031
ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.1.(1).
Jenis Kegiatan : Lapis Pondasi Klas A
Satuan Pembayaran : M3

URAIAN KODE

MOTOR GREADER E.140


Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts3
- Perataan 1 kali lintasan = (Lh x 60) : (v x 1000) T1
- Lain-Lain T2
Ts3
Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3
Ts2 x n
Koefisien Alat / M3 = 1 : Q3
VIBRATORY ROLLER E.240
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x Fa Q5
n
Koefisien Alat / M3 = 1 : Q5
WATER TANK TRUCK E.230
Volume Tangki Air V
Kebutuhan Air / M3 Material Padat Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q5
Wc
Koefisien Alat / M3 = 1 : Q5
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = WHEEL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.1.(2)
Jenis Kegiatan : Lapis Pondasi Klas B
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t
Jarak rata-rata ke Base Camp Lr

METODE PELAKSANAAN
Wheel Loader memuat agregat ke dalam Dump Truck
Aggregat kemudian di hampar dengan Motor Greader
Hamparan agregat di basahi dengan Water Tank Truck
Pemadatan di laksanakan dengan Vibratory Roller
Sekelompok pekerja merapikan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Agregat Kasar B 85 % Di produksi di base camp M.035
Agregat Halus B 15 % Di produksi di base camp M.040
ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2

- Waktu Tempuh Isi = (L : v1) x 60 T1


- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.1.(2).
Jenis Kegiatan : Lapis Pondasi Klas B
Satuan Pembayaran : M3

URAIAN KODE

MOTOR GREADER E.140


Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts3
- Perataan 1 kali lintasan = (Lh x 60) : (v x 1000) T1
- Lain-Lain T2
Ts3
Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3
Ts2 x n
Koefisien Alat / M3 = 1 : Q3
VIBRATORY ROLLER E.240
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x Fa Q5
n
Koefisien Alat / M3 = 1 : Q5
WATER TANK TRUCK E.230
Volume Tangki Air V
Kebutuhan Air / M3 Material Padat Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q5
Wc
Koefisien Alat / M3 = 1 : Q5
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = WHEEL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran 5.1.(3a)
Jenis Kegiatan : Telford Batu Gunung
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t
Jarak rata-rata ke Base Camp Lr

METODE PELAKSANAAN
Wheel Loader memuat agregat ke dalam Dump Truck
Aggregat kemudian di hampar dengan Tenaga Manusia
Hamparan agregat / Batu Disusun Bediri
Pemadatan di laksanakan dengan Three Whell Roller
Sekelompok pekerja merapikan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Material Batu Gunung Produksi Di Lokasi
Batu Gunung = 1 x Fk M.010
ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain T3
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.1.(3).
Jenis Kegiatan : Telford Batu Gunung
Satuan Pembayaran : M3

URAIAN KODE

THREE WHEEL ROLLER E.170


Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q3
n
Koefisien Alat / M3 = 1 : Q3
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = WHEEL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.1.(1)
Jenis Kegiatan : Lapis Resap Pengikat
Satuan Pembayaran : Liter

URAIAN KODE
ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Jarak rata-rata ke Base Camp Lr
Jam kerja efektif per hari Tk
Faktor kehilangan bahan Fh
Komposisi campuran
- Aspal AC-10 atau AC-20 As
- Minyak Flux / Pencair K
Berat jenis bahan
- Aspal AC-10 atau AC-20 D1
- Minyak Flux / Pencair D2
Bahan dasar (aspal & minyak pencair) semuanya di lokasi

METODE PELAKSANAAN
Aspal dan minyak flux di campur dan di panaskan sehingga
menjadi campuran aspal cair
Permukaan yang akan di lapis di bersihkan dari kotoran debu
dengan menggunakan Air Compressor
Campuran aspal cair di semprotkan dengan Asphalt Sprayer
ke atas permukaan yang akan di lapis
Angkutan aspal dan minyak flux menggunakan Dump Truck

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Untuk Mendapatkan 1 liter Lapis Resap Pengikat Di Perlukan
Campuran = 1 liter x Fh PC
Aspal = As x PC x D1 M.061
Kerosene = K x PC M.063
ALAT
ASPHALT SPRAYER E.030
Kapasitas Alat V
Faktor Efesiensi Alat Fa
Waktu Siklus (Termasuk Proses Pemanasan) Ts
Kap. Prod. / Jam = V x Fa Q1
Ts
Koefisien Alat / Liter = 1 : Q1

AIR COMPRESSOR E.040


Kapasitas ----------------------------> Alat Di Ambil V
Aplikasi Lapis Resap Pengikat Rata-Rata (Spesifikasi) Ap
Kap. Prod. / Jam = V x Ap Q2
Koefisien Alat / Liter = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.1.(1).
Jenis Kegiatan : Lapis Resap Pengikat
Satuan Pembayaran : Liter

URAIAN KODE

DUMP TRUCK E.080


Sebagai Alat Pengangkut Bahan Di Lokasi Kegiatan, Dump
Truck Melayani Alat Asphalt Sprayer
Kap. Prod. / Jam = Sama Dengan Asphalt Sprayer Q3
Koefisien Alat / Liter = 1 : Q3
TENAGA
Produksi Menentukan = ASPHALT SPRAYER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / Liter
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.3
Jenis Kegiatan : Lapis Aus Asphalt Beton (AC-BC)
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan, Kondisi : sedang
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Tebal Lapis Pengikat Aspal Beton (AC-BC) t
Jam kerja efektif per hari Tk
Faktor kehilangan material - Agregat Fh1
- Aspal Fh2
Komposisi campuran Lapis Pengikat Aspal Beton (Spesifikasi)
- Coarse agregat = 40,0 - 60,0 % CA
- Fine agregat = 26,0 - 49,5 % FA
- Fraksi filler = 4,5 - 7,5 % FF
- Asphalt = minimum 7,0 % AS
Berat jenis bahan
- Lapis Pengikat Aspal Beton (AC-BC) D1
- Coarse agregat & Fine agregat D2
- Fraksi filler D3
- Asphalt D4

METODE PELAKSANAAN
Wheel Loader memuat agregat + aspal ke dalam Cold Bin AMP
Agregat + aspal di campur dan di panaskan dengan AMP untuk
di muat langsung ke dalam Dump Truck dan di angkut ke lokasi
Campuran panas ATB di hampar dengan Asphalt Finisher dan
di padatkan dengan Tandem Roller & Pneumatic Tire Roller
Selama pemadatan sekelompok pekerja akan merapikan tepi
hamparan dengan menggunakan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Agregat Kasar Hotmix = [CA x (D1 x 1 M3) x Fh1] : D2 M.090
Agregat Halus Hotmix = [FA x (D1 x 1 M3) x Fh1] : D2 M.161
Filler = [FF x (D1 x 1 M3) x Fh1] x 1000 M.062
Aspal = [AS x (D1 x 1 M3) x Fh2] x 1000 M.061
ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = D2 x V x Fb x Fa x 60 Q1
Ts1 x D1
Koefisien Alat / M3 = 1 : Q1

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.3
Jenis Kegiatan : Lapis Aus Asphalt Beton (AC-BC)
Satuan Pembayaran : M3

URAIAN KODE

ASPHALT MIXING PLANT (AMP) E.010


Kapasitas Produksi V
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x Fa Q2
D1
Koefisien Alat / M3 = 1 : Q2
GENERATOR SET Koefisien Alat / M3, Sama dengan AMP E.120
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Kapasitas AMP / Bacth Q2b
Waktu Menyiapkan 1 Bacth ATB Tb
Waktu Siklus Ts2
- Waktu Mengisi Bak = (V : Q2b) x Tb T1
- Angkut = (L : v1) x 60 T2
- Tunggu + Dump + Putar = T3
- Kembali = (L : v2) x 60 T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q4
Ts2 x D1
Koefisien Alat / M3 = 1 : Q4
ASPHALT FINISHER E.030
Kapasitas Produksi V
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x Fa Q5
D1
Koefisien Alat / M3 = 1 : Q5
TANDEM ROLLER E.180
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q6
n
Koefisien Alat / M3 = 1 : Q6
TIRE ROLLER E.190
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q7
n
Koefisien Alat / M3 = 1 : Q7

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.3
Jenis Kegiatan : Lapis Aus Asphalt Beton (AC-BC)
Satuan Pembayaran : M3

URAIAN KODE

TENAGA
Produksi Menentukan = ASPHALT MIXING PLANT Q2
Produksi Per Hari = Tk x Q2 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.1 (5)
Jenis Kegiatan : Beton K-350
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Beton Redy Mix di terima di lokasi
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Tebal Beton t
Jam kerja efektif per hari Tk

METODE PELAKSANAAN
Semen, pasir, koral dan air di campur dan di aduk menjadi
beton dengan menggunakan Batching Plant dan diaduk dalam perjalanan ke lokasi
Beton di cor ke dalam perancah yang telah di siapkan
Penyelesaian dan perapian setelah selesai beton readimix dituang
PEMAKAIAN BAHAN, ALAT DAN TENAGA
BAHAN
Beton Ready Mix K- 350 M555
Plastik Sheet M.191
Paku
Karung

ALAT
CONCRETE VIBRATOR E.070
Kebutuhan alat penggetar beton (Concrte Vibrator) ini di
sesuaikan dengan kapasitas produksi dari Alat Pencampur
(Concrete Mixer)
Koefisien Alat / M3 = 1 : Q2
CONCRETE FINISHER E.070
Kebutuhan alat penghampar beton ini disesuaikan dengan kapasitas produksi
dari baching plant
Koefisien Alat / M3
Alat Bantu -

TENAGA
Produksi Menentukan = Ready Mix Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih Tb
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Tb) : Qt L.106
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.1 (6)
Jenis Kegiatan : Beton K-300
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Beton Redy Mix di terima di lokasi
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Tebal Beton t
Jam kerja efektif per hari Tk

METODE PELAKSANAAN
Semen, pasir, koral dan air di campur dan di aduk menjadi
beton dengan menggunakan Batching Plant dan diaduk dalam perjalanan ke lokasi
Beton di cor ke dalam perancah yang telah di siapkan
Penyelesaian dan perapian setelah selesai beton readimix dituang
PEMAKAIAN BAHAN, ALAT DAN TENAGA
BAHAN
Beton Ready Mix K- 300 M.196
Plastik Sheet M.191
Karung
Pipa PVC 1" 0.00

ALAT
CONCRETE VIBRATOR E.070
Kebutuhan alat penggetar beton (Concrte Vibrator) ini di
sesuaikan dengan kapasitas produksi dari Alat Pencampur
(Concrete Mixer)
Koefisien Alat / M3 = 1 : Q2
Alat Bantu -

TENAGA
Produksi Menentukan = Ready Mix Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih Tb
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Tb) : Qt L.106
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran ; 7.1.(8)
Jenis Kegiatan : Beton K-175
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (koral, pasir dan semen) di terima di lokasi
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Kadar semen (Spesifikasi) - Minimum Ks1
- Maksimum Ks2
Perbandingan air, semen maksimum (Spesifikasi) Wcr
Perbandingan campuran = 1 : Semen Sm
= 2.5 : Pasir beton Ps
= 3 : Koral Kr
Berat jenis material
- Beton D1
- Semen (PC) D2
- Pasir beton D3
- Koral D4

METODE PELAKSANAAN
Semen, pasir, koral dan air di campur dan di aduk menjadi
beton dengan menggunakan Concrete Mixer
Beton di cor ke dalam perancah yang telah di siapkan
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Semen (PC) = [Sm x D1 x 1000] x 1,05 M.080
Pasir Beton (Palu) = [(Ps x D1) : D3] x 1,05 M.041
Koral Palu = [(Kr x D1) : D4] x 1,10 M.082
Air -

ALAT
CONCRETE MIXER E.060
Kapasitas Alat V
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Mengaduk T2
- Menuang T3
- Menunggu, dll T4
Ts1

Kap. Prod. / Jam = V x Fa x 60 Q1


Ts1 x 1000
Koefisien Alat / M3 = 1 : Q1

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran ; 7.1.(8)
Jenis Kegiatan : Beton K-175
Satuan Pembayaran : M3

URAIAN KODE

CONCRETE VIBRATOR E.070


Kebutuhan alat penggetar beton (Concrte Vibrator) ini di
sesuaikan dengan kapasitas produksi dari Alat Pencampur
(Concrete Mixer)
Koefisien Alat / M3 = 1 : Q2
WATER TANK TRUCK E.230
Volume Tangki Air V
Kebutuhan Air / M3 beton Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q3
Wc
Koefisien Alat / M3 = 1 : Q3
TENAGA
Produksi Menentukan = CONCRETE MIXER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih Tb
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Tb) : Qt L.106
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.3.(1)
Jenis Kegiatan : Besi Tulangan
Satuan Pembayaran : Kg

URAIAN KODE

ASUMSI
Kegiatan di lakukan secara manual
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (besi dan kawat) di terima di lokasi
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Faktor kehilangan besi tulangan Fk

METODE PELAKSANAAN
Besi tulangan di potong dan di bengkokan sesuai dengan yang
di perlukan atau sesuai dengan gambar rencana
Batang tulangan di pasang / di sesuaikan dengan gambar
Sambungan di beri kekuatan pengikat dari kawat besi

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Besi Beton M.167
Kawat Beton 20 % dari material pengisi (besi tulangan) M.170
ALAT
Di Perlukan Untuk Alat Bantu, Yaitu Sebanyak :
- Gunting Beton = 2 buah
- Kunci Pembengkok Besi = 2 buah
- Alat Lainnya
TENAGA
Produksi Per Hari Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih (Tk x P) : Qt P
- Pekerja Terlatih (Tk x Tb) : Qt Tb
- Mandor (Tk x M) : Qt M
Koefisien Tenaga / Kg
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Tb) : Qt L.106
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.6.(7)
Jenis Kegiatan : Pancang Kayu Ulin
Satuan Pembayaran : Titik

URAIAN KODE
ASUMSI
Kegiatan di lakukan secara manual
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (kayu ulin 10/10) di terima di lokasi
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Faktor kehilangan bahan Fk

METODE PELAKSANAAN
Kayu ulin 10/10 di perlukan sesuai dengan gambar rencana
Pemancangan mempergunakan alat-alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Kayu Ulin 10/10 M.070
Kayu Ulin 5/10 M.181
ALAT
Alat-Alat Kerja Lainnya (@ 3 set)
TENAGA
Produksi Per Hari Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih (Tk x P) : Qt P
- Pekerja Terlatih (Tk x Tb) : Qt Tb
- Mandor (Tk x M) : Qt M
Koefisien Tenaga / Titik
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Tb) : Qt L.106
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.5.(3).
Jenis Kegiatan : Bronjong
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Kegiatan di lakukan secara manual
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (anyaman kawat danbatu) di terima di lokasi
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Faktor kehilangan bahan Fk

METODE PELAKSANAAN
Keranjang kawat bronjong di rentangkan dan di bentuk
sesuai dengan konstruksi yang di inginkan
Batu di tempatkan satu demi satu sehingga rongga tertutup
Anyaman kawat di tutup dan ikat

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Kawat Bronjong 35 % dari material pengisi (batu) M.162
Batu Gunung M.010
ALAT
Di Perlukan Untuk Alat Bantu, Yaitu Sebanyak :
- Pemotong Kawat = 2 buah
- Palu Pemecah Batu = 2 buah
TENAGA
Produksi Per Hari Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih (Tk x P) : Qt P
- Pekerja Terlatih (Tk x Tb) : Qt Tb
- Mandor (Tk x M) : Qt M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Tb) : Qt L.106
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.5.(1)
Jenis Kegiatan : Lapen Macadam
Satuan Pembayaran : M2

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan, Kondisi : sedang
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Tebal rata-rata Lapen Macadam t
Jam kerja efektif per hari Tk
Faktor kehilangan material - Agregat Fh1
- Aspal Fh2
Komposisi campuran ATB (Spesifikasi)
- Agregat Kasar (3-5 cm) Ak
- Agregat Pengunci (1-2 cm) Ap
- Aspal As1
As2
Berat jenis bahan
- Agregat D1
- Aspal D2

METODE PELAKSANAAN
mukaan dasar di bersihkan dan di semprot aspal cair
Agregat kasar di muat ke dalam Dump Truck menggunakan
Wheel Loader (di Base Camp)
Agregat kasar di tebarkan (manual) sesuai tebal yang di perlukan
dan di padatkan dengan Three Wheel Roller minimal 6 lintasan
Aspal di semprotkan di atas agregat kasar yang telah di ratakan
menggunakan Asphalt Sprayer (merata)
Agregat pengunci di tebarkan dan di padatkan dengan cara
yang sama dengan pemadatan agregat kasar

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Agregat 3-5 cm = [(Ak/1000 ÷ t M3) x Fh1] : D1 M.023
Agregat 1-2 cm = [(Ap/1000 ÷ t M3) x Fh1] : D1 M.025
Aspal = [(As ÷ t M3) x Fh2] M.061

ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fb x Fa x 60 Q1
Ts1
Koefisien Alat / M3 = 1 : Q1

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN
Kegiatan : Pembangunan Jalan Dan Jembatan
Item Pembayaran : 6.5.(1)
Jenis Kegiatan : Lapen Macadam
Satuan Pembayaran : M2

URAIAN KODE

DUMP TRUCK E.080


Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain (Tunggu + Dump + Putar + Mengisi) T3
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2
Koefisien Alat / M3 = 1 : Q2
ASPHALT SPRAYER E.030
Kapasitas Alat V
Faktor Efesiensi Alat Fa
Waktu Siklus (Termasuk Proses Pemanasan) Ts3
Kap. Prod. / Jam = V x Fa x D2 Q3
Ts3 x As2
Koefisien Alat / Liter = 1 : Q3
THREE WHEEL ROLLER E.170
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q4
n
Koefisien Alat / M3 = 1 : Q4
ALAT BANTU
Di perlukan Kereta Dorong, Sekop, Sapu, Karung, Cerek Aspal
TENAGA
Produksi Menentukan = WHELL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih M
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x M) : Qt L.061
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran 7.10.
Jenis Kegiatan : Pas. Batu Padas
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan buruh (cara manual)
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (batu padas, semen, pasir pasangan) di terima
seluruhnya di lokasi Kegiatan
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Perbandingan pasir & semen - Volume pasir Ps
- Volume semen Sm
Perbandingan batu & mortar
- Batu padas Bt
- Mortar (campuran pasir & semen) Mr
Berat jenis bahan
- Pasangan batu dengan mortar D1
- Batu padas D2
- Adukan (mortar) D3
- Pasir D4
- Semen PC D5
Faktor kehilangan bahan - Batu Fh1
- Pasir / Semen Fh2

METODE PELAKSANAAN
Semen, pasir dan air di campur dan di aduk menjadi mortar
dengan menggunakan alat bantu
Batu di bersihkan dan di basahi seluruh permukaannya
sebelum di pasang
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Batu Padas [(Bt x D1 x 1 M3) : D2] x Fh1 M.010
Semen PC Sm x [(Mr x D1 x 1 M3) : D3] x Fh2 M.080
x [D5 x (1000)]
Pasir Pasangan Ps x [(Mr x D1 x 1 M3) : D4] x Fh2 M.040
ALAT
TENAGA
Produksi Per Hari = MORTAR Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih Pt
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Pt) : Qt L.106
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 1.2 (3)
Jenis Kegiatan : Urugan Padas
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t

METODE PELAKSANAAN
Wheel Loader memuat ke dalam Dump Truck
Dump Truck mengangkut ke lapangan dengan jarak Lq
Hamparan material di padatkan dengan Vibratory Roller
Selama pemadatan sekelompok pekerja akan merapikan tepi
hamparan dan level permukaan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Batu Padas = 1 x Fk M.011
ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1

DUMP TRUCK E.080


Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 3.2.(3).
Jenis Kegiatan : Urugan Padas
Satuan Pembayaran : M3

URAIAN KODE

VIBRATORY ROLLER E.240


Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q3
n
Koefisien Alat / M3 = 1 : Q3
- Lain-Lain

ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = WHEEL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.1.(2)
Jenis Kegiatan : Lapis Perekat
Satuan Pembayaran : Liter

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Jarak rata-rata ke Base Camp Lr
Jam kerja efektif per hari Tk
Faktor kehilangan bahan Fh
Komposisi campuran
- Aspal AC-10 atau AC-20 As
- Minyak Flux / Pencair K
Berat jenis bahan
- Aspal AC-10 atau AC-20 D1
Err:509 D2
Bahan dasar (aspal & minyak pencair) semuanya di lokasi

METODE PELAKSANAAN
Aspal dan minyak flux di campur dan di panaskan sehingga
menjadi campuran aspal cair
Permukaan yang akan di lapis di bersihkan dari kotoran debu
dengan menggunakan Air Compressor
Campuran aspal cair di semprotkan dengan Asphalt Sprayer
ke atas permukaan yang akan di lapis
Angkutan aspal dan minyak flux menggunakan Dump Truck

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN

Campuran = 1 liter x Fh PC
Aspal = As x PC x D1 M.061
Gasoline = K x PC M.184
ALAT
ASPHALT SPRAYER E.030
Kapasitas Alat V
Faktor Efesiensi Alat Fa
Waktu Siklus (Termasuk Proses Pemanasan) Ts
Kap. Prod. / Jam = V x Fa Q1
Ts
Koefisien Alat / Liter = 1 : Q1

AIR COMPRESSOR E.040


Kapasitas ----------------------------> Alat Di Ambil V
Aplikasi Lapis Perekat Rata-Rata (Spesifikasi) Ap
Kap. Prod. / Jam = V x Ap Q2
Koefisien Alat / Liter = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.1.(2)
Jenis Kegiatan : Lapis Perekat
Satuan Pembayaran : Liter
URAIAN KODE

DUMP TRUCK E.080


Sebagai Alat Pengangkut Bahan Di Lokasi Kegiatan, Dump
Truck Melayani Alat Asphalt Sprayer
Kap. Prod. / Jam = Sama Dengan Asphalt Sprayer Q3
Koefisien Alat / Liter = 1 : Q3
TENAGA
Produksi Menentukan = ASPHALT SPRAYER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / Liter
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.5 (1)
Jenis Kegiatan : Semen Untuk Pondasi Tanah Semen
Satuan Pembayaran : Ton

URAIAN KODE

ASUMSI
Kegiatan dilakukan secaramanal
Lokasi Kegiatan : sepanjang jalan
Kondisi Jalan : sedang / baik
Jarak rata-rata ke Base Camp ke lokasi Kegiatan L
Jam kerja efektif per hari Tk
Semen diangkut dari Base Camp ke lapangan dengan menggunakan dump truck
Satu hari dapat diselesaikan hamparan Soil Cement Sepanjang Ls
Faktor hilang material Fh
Tebal hamparan t

METODE PELAKSANAAN
Dump truck mengangkut seen dari Base Camp
ke lokasi Kegiatan
Semen diatur/disusun di tempat hamparan
soil/tanah oleh tenaga manusia
PEMAKAIAN BAHAN, ALAT DAN TENAGA
BAHAN
Semen yang diperlukan /ton = (1 x Fh : 40) x 1000 M.12

ALAT
DUMP TRUCK E.080
Kapasitas bak V
Faktor Efesiensi Alat Fa
Kecepatan rata-rata bermuatan v1
Kecepatan rata-rata kosong v2
Waktu siklus Ts1
- Waktu tempuh isi T1
- Waktu tempuh kosong T2
- Waktu mengisi T3
- Waktu bongkar T4
- Lain-lain T5
Ts1
Kap. Prod. / Jam = V x Fa x 60
Fh x Ts1

Koefisien Alat / M3 = 1/Q1 E.080

TENAGA
Lebar Hamparan Soil Cement b
Kadar semen (3-12) % s
Berat jenis tanah = V x Ap BJ
Setiap hari dengan produksi = {(s:100) x t x b x Ls} x Bj Qt

Kebutuhan tenaga :
- Pekerja Tidak Terlatih P
- Mandor M

Koefisien Tenaga / Ton :


- Pekerja Tidak Terlatih = (Tk x P ) : Qt (L01)
- Mandor = (Tk x M ) : Qt (L03)

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.5 (2)
Jenis Kegiatan : Lapis Pondasi Tanah Semen
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Kegiatan dilakukan secara manual
Lokasi Kegiatan : sepanjang jalan
Kondisi Jalan : sedang / baik
Jarak rata-rata ke Base Camp ke lokasi Kegiatan L
Jam kerja efektif per hari Tk
Harga pembayaran tidak termasuk semen (semen dibayar dalam item tersendiri)
Satu hari dapat diselesaikan hamparan Soil Cement Sepanjang Ls
Faktor kembang material (padat-lepas) Fk
Tebal hamparan padat t

METODE PELAKSANAAN
Sheel loader memuat material ke dalam dump truck di lokasi sumber bahan
Dump truck menangkut material kelokasi Kegiatan
Motor Grader menghampar material di lokasi Kegiatan
Semen dan material tanah diaduk ditempat dengan
menggunakan Vulvi mixer
Sebelum pemadatan material dibasahi dengan
menggunakan water tank truck
Pemadatan dilakukan dengan menggunakan
Vibrator Roller dan pneumatic Tire Roller
Selama pelaksanaan Kegiatan sekelompok pekerja
akan merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Setiap M3 Soil Cement padat diperlukan = 1 x Fk M08

ALAT
WHEEL LOADER E220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1 E220

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.5 (2)
Jenis Kegiatan : Lapis Pondasi Tanah Semen
Satuan Pembayaran : M3

URAIAN KODE

DUMP TRUCK
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2
MOTOR GREADER
Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts3
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1
- Lain-Lain T2
Ts3
Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3
Ts3 x n
Koefisien Alat / M3 = 1 : Q3
TANDEM ROLLER
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q4
n
Koefisien Alat / M3 = 1 : Q4
PNEUMATIC TIRE ROLLER
Kecepatan rata-rata alat V
Lebar efektif pemadatan b
Jumlah lintasan n
Faktor efesiensi alat Fa

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.5 (2)
Jenis Kegiatan : Lapis Pondasi Tanah Semen
Satuan Pembayaran : M3

URAIAN KODE

Kap. Prod. / Jam = (V x 1000) x b x t x Fa Q5


n
Koefisien Alat / M3 = 1 : Q5

WATER TANK TRUCK


Volume Tangki Air V
Kebutuhan Air / M3 beton Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q6
Wc
Koefisien Alat / M3 = 1 : Q6

FULVI MIXER
Kecepatan rata-rata alat V
Lebar efektif pemadatan Wc
Jumlah lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (V x 1000 ) x b x t x Fa Q7
n
Koefisien Alat / M3 = 1 : Q7

ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Kereta dorong = 2 buah
- Sekop = 3 buah

TENAGA
Produksi Menentukan = VIBRATOR ROLLER Q4
Produksi Per Hari = Tk x Q4 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.3.(6)
Jenis Kegiatan : Lapis Aus Aspal Beton (AC-WC)
Satuan Pembayaran : M2

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi Jalan : sedang / baik
Jarak rata-rata ke Base Camp ke lokasi Kegiatan L
Tebal lapis (AC) padat t
Jam kerja efektif per hari T
Faktor kehilangan material : - Agregat Fh1
- Aspal Fh2
Komposisi campuran AC (spesifikasi) :
- Coarse Agregat 30 - 50 % CA
- Fine Agregat 39 - 59 % FA
- Fraksi Filler 4.5 - 7.5 % FF
- Asphalt minimum 6.7 % As
Berat jenis bahan :
- AC D1
- Coarse Agregat & Fine Agregat D2
- Fraksi Filler D3
- Asphalt D4

METODE PELAKSANAAN
Wheel loader memuat agregat dan asphalt ke dalam cold bin AMP
Agregat dan aspal dicampur dan dipanaskan dengan
AMP untuk dimuat langsung kedalam Dump truck dan
diangkut ke lokasi Kegiatan
Campuran panas AC dihampar dengan finisher dan dipadatkan
dengan Tandem & Pneumatic Tire Roller
Selama pemadatan, sekelompok pekerja akan
merapikan tepi hamparan degan menggunakan alat
bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Agregat Kasar = (CA x ( D1 x tM3) x Fh1) : D2
Agregat halus = (FA x ( D1 x tM3) x Fh1) : D2
Filer = (FF x ( D1 x tM3) x Fh1)
Aspal = (AS x ( D1 x tM3) x Fh2)
ALAT

WHEEL LOADER
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = D2 x V x Fb x Fa x 60 Q1
D1 x t x Ts1
Koefisien Alat / M3 = 1 : Q1 E220

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.3.(6)
Jenis Kegiatan : Lapis Aus Aspal Beton (AC-WC)
Satuan Pembayaran : M2

URAIAN KODE

DUMP TRUCK
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Kapasitas AMP / batch Q2b
Waktu menyiapkan 1 batch AC Tb
Waktu Siklus Ts2
- Mengisi bak = (V : Q2b) x Tb T1
- Angkut = (L : v1) x 60 menit T2
- Tunggu + dump + putar T3
- Kembali = (L : v2) x 60 menit T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk x D1
Koefisien Alat / M3 = 1 : Q2
Asphalt Mixing Plant (AMP)
Kapasitas produksi v
Faktor Efesiensi alat Fa
Kap. Prod. / Jam = V x Fa Q3
D1 x t
Koefisien Alat / M3 = 1 : Q3
GENERATOR SET
Kap. Prod. / Jam = Sama dengan AMP
Koefisien Alat / M3 = 1 : Q4 Q4

TANDEM ROLLER
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q5
nxt
Koefisien Alat / M3 = 1 : Q5
ASPHALT FINISHER
Kapasitas produksi V
Faktor efesiensi alat Fa
Kap. Prod. / Jam = V x Fa
D1 x t
Koefisien Alat / M3 = 1 : Q3 Q6
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.3.(6)
Jenis Kegiatan : Lapis Aus Aspal Beton (AC-WC)
Satuan Pembayaran : M2

URAIAN KODE
PNEUMATIC TIRE ROLLER
Kecepatan rata-rata alat V
Lebar efektif pemadatan b
Jumlah lintasan n
Faktor efesiensi alat Fa
Kap. Prod. / Jam = (V x 1000) x bx t x Fa Q7
nxt
Koefisien Alat / M3 = 1 : Q7

ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Rambu = 2 buah
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garfu = 2 buah
- Tongkat Kontrol Ketebalan hamparan

TENAGA
Produksi Menentukan = ASPHALT MIXING PLANT (AMP) Q4
Produksi Per Hari = Tk x Q2 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.1.(10)
Jenis Kegiatan : Beton Bo
Satuan Pembayaran : M3
URAIAN KODE

ASUMSI
Menggunakan alat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (koral, pasir dan semen) di terima di lokasi
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Kadar semen (Spesifikasi) - Minimum Ks1
- Maksimum Ks2
Perbandingan air, semen maksimum (Spesifikasi) Wcr
Perbandingan campuran = 1 : Semen Sm
= 3 : Pasir Ayak Ps
= 4.4 : Batu Kerikil Kr
Berat jenis material
- Beton D1
- Semen (PC) D2
- Pasir beton D3
- Koral D4

METODE PELAKSANAAN
Semen, pasir, koral dan air di campur dan di aduk menjadi
beton dengan menggunakan Concrete Mixer
Beton di cor ke dalam perancah yang telah di siapkan
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Semen PC @ 50 Kg = [Sm x D1 x 1000] x 1,05 M.080
Pasir Ayak = [(Ps x D1) : D3] x 1,05 M.041
Batu Kerikil = [(Kr x D1) : D4] x 1,02 M.082
Kayu Acuan = M.180

ALAT
CONCRETE MIXER E.060
Kapasitas Alat V
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Mengaduk T2
- Menuang T3
- Menunggu, dll T4
Ts1

Kap. Prod. / Jam = V x Fa x 60 Q1


Ts1 x 1000
Koefisien Alat / M3 = 1 : Q1

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.1.(10)
Jenis Kegiatan : Beton Bo
Satuan Pembayaran : M3

URAIAN KODE

CONCRETE VIBRATOR E.070


Kebutuhan alat penggetar beton (Concrte Vibrator) ini di
sesuaikan dengan kapasitas produksi dari Alat Pencampur
(Concrete Mixer)
Koefisien Alat / M3 = 1 : Q2
WATER PUMP E.230
Volume Tangki Air V
Kebutuhan Air / M3 beton Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q3
Wc
Koefisien Alat / M3 = 1 : Q3
TENAGA
Produksi Menentukan = CONCRETE MIXER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih Tb
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Tb) : Qt L.106
- Kepala Tukang = (Tk x M) : Qt L.073
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 2.1.(2)
Jenis Kegiatan : Galian Tanah Keras/Batu
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Kegiatan dilakukan secara manual
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk

METODE PELAKSANAAN
Tanah /batu yang dipotong umumnya berada disisi jalan
Penggalian di lakukan dengan menggunakan compressor dan jack hammer
Dump Truck membuang material hasil galian keluar lokasi
jalan sejauh

Lpmb

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Tidak Ada Bahan Yang Di Pergunakan
ALAT
COMPRESSOR DAN JACK HAMMER
Produksi Per jam Q1

Koefisien Alat / M3 = 1 : Q1

DUMP TRUCK E.080


Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Waktu Memuat = (V : Q1) x 60 T3
- Lain-Lain T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 2.1.(2)
Jenis Kegiatan : Galian Tanah Keras/Batu
Satuan Pembayaran : M3

URAIAN KODE

ALAT BANTU
Di Perlukan Alat-Alat Bantu Kecil
- Pahat / tatah = 2 Buah
- Palu Besar = 2 Buah
TENAGA
Produksi Menentukan = JACK HAMMER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 3.4.(1)
Jenis Kegiatan : Pembersihan Semak Damija
Satuan Pembayaran : M2

URAIAN KODE

ASUMSI
Kegiatan di laksanakan hanya pada tanah badan jalan
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Kegiatan di lakukan secara mekanis

METODE PELAKSANAAN
Motor Greader mengupas semak yang ada disepanjang jalan dan bahu jalan
Sekelompok pekerja akan membantu meratakan badan jalan dengan alat bantu
PEMAKAIAN BAHAN, ALAT DAN TENAGA
BAHAN
Tidak Di Perlukan Bahan / Material
ALAT
MOTOR GREADER E.140
Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts1
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = Lh x b x Fa x 60 Q1
Ts1 x n
Koefisien Alat / M3 = 1 : Q1

ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3
TENAGA = 3
Kebutuhan Tenaga
- Pekerja Tidak Terlatih L.101
- Mandor L.061
- Operator Terlatih L.081
- Pembantu Operator L.089
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061
- Operator Terlatih = (Tk x P) : Qt L.081
- Pembantu Operator = (Tk x M) : Qt L.089

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran :
Jenis Kegiatan : Kegiatan Plesteran
Satuan Pembayaran : M2

URAIAN KODE

ASUMSI
Menggunakan buruh (cara manual)
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (semen, pasir pasangan) di terima seluruhnya di lkasi Kegiatan
Jarak rata-rata Base Camp ke lokasi Kegiatan
Jam kerja efektif per hari
Perbandingan pasir & semen - Volume pasir Ps
- Volume semen Sm
Berat jenis bahan
- Pasir D1
- Semen PC D2
Faktor kehilangan bahan - Pasir / Semen Fh

METODE PELAKSANAAN
Semen, pasir dan air di campur dan di aduk menjadi mortar
dengan menggunakan alat bantu
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Semen PC M.080
Pasir Pasangan M.080

ALAT
TENAGA
Produksi Per Hari = MORTAR
Kebutuhan Tenaga
- Pekerja Tidak Terlatih L.101
- Pekerja Terlatih L.106
- Mandor L.061
METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran :-
Jenis Kegiatan : Bekisting
Satuan Pembayaran : M2

URAIAN KODE

ASUMSI
Kegiatan di lakukan secara manual
Lokasi Kegiatan : pada gorong-gorong, box culvert dan lain-lain Kegiatan struktur
Bahan dasar kayu meranti/bekisitng yang memenuhi syarat
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Faktor kehilangan bahan Fk

METODE PELAKSANAAN
Ukuran kayu di perlukan sesuai dengan gambar rencana
Pemasangan mempergunakan alat-alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Kayu Meranti /Perancah M.180
Paku Biasa M.166
ALAT
Alat-Alat Kerja Lainnya (@ 3 set)
TENAGA
Produksi Per Hari Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih (Tk x P) : Qt P
- Pekerja Terlatih (Tk x Tb) : Qt Tb
- Mandor (Tk x M) : Qt M
Koefisien Tenaga / Titik
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Tb) : Qt L.106
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.1.(6a)
Jenis Kegiatan : Joint Sealent + Kayu Segitiga
Satuan Pembayaran : M1

URAIAN KODE

ASUMSI
Kegiatan di lakukan secara manual
Lokasi Kegiatan : pada Kegiatan semennisasi/rijid
Bahan dasar sealent dan diamond blade
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Faktor kehilangan bahan Fk
METODE PELAKSANAAN
Kegiatan pemotongan dilaksanakan dengan cutter
Pemasangan mempergunakan alat-alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Sealent M.189
Diamnod Blade M.190
Kayu Segitiga M.191
ALAT
COMPRESSOR
Produksi Per jam Q1

Koefisien Alat / M3 = 1 : Q1
Alat-Alat Kerja Lainnya (@ 3 set)

TENAGA
Produksi Per Hari Qt
Kebutuhan Tenaga
- Pekerja Semi Terlatih (Tk x P) : Qt P
- Mandor (Tk x M) : Qt M

Koefisien Tenaga / Titik


- Pekerja Semi Terlatih = (Tk x P) : Qt L.103
- Mandor = (Tk x Tb) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.1.(7)
Jenis Kegiatan : Beton K 250
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (koral, pasir dan semen) di terima di lokasi
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Kadar semen (Spesifikasi) - Minimum Ks1
- Maksimum Ks2
Perbandingan air, semen maksimum (Spesifikasi) Wcr
Perbandingan campuran = 1 : Semen Sm
= 2.5 : Pasir beton Ps
= 3 : Koral Kr
Berat jenis material
- Beton D1
- Semen (PC) D2
- Pasir pasangan D3
- Kerikil sungai D4

METODE PELAKSANAAN
Semen, pasir, koral dan air di campur dan di aduk menjadi
beton dengan menggunakan Concrete Mixer
Beton di cor ke dalam perancah yang telah di siapkan
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Semen (PC) = [Sm x D1 x 1000] x 1,1 M.080
Pasir Beton (Palu) = [(Ps x D1) : D3] x 1,1 M.041
Koral Eks Palu = [(Ps x D1) : D3] x 1,15 M.082
Air -
Plastik Sheet M.191

ALAT
CONCRETE MIXER E.060
Kapasitas Alat V
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Mengaduk T2
- Menuang T3
- Menunggu, dll T4
Ts1
Kap. Prod. / Jam = V x Fa x 60 Q1
Ts1 x 1000
Koefisien Alat / M3 = 1 : Q1

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.1.(7)
Jenis Kegiatan : Beton K 250
Kegiatan : M3

URAIAN KODE

CONCRETE VIBRATOR E.070


Kebutuhan alat penggetar beton (Concrte Vibrator) ini di
sesuaikan dengan kapasitas produksi dari Alat Pencampur
(Concrete Mixer)
Koefisien Alat / M3 = 1 : Q2
WATER TANK TRUCK E.230
Volume Tangki Air V
Kebutuhan Air / M3 beton Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q3
Wc
Koefisien Alat / M3 = 1 : Q3
TENAGA
Produksi Menentukan = CONCRETE MIXER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih Tb
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Tb) : Qt L.106
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN
Kegiatan : Pembangunan Jalan Dan Jembatan
Item Pembayaran : 5.1.(2).
Jenis Kegiatan : Lapis Pondasi Kelas C
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t
Jarak rata-rata ke Base Camp Lr

METODE PELAKSANAAN
Wheel Loader memuat agregat ke dalam Dump Truck
Aggregat kemudian di hampar dengan Motor Greader
Hamparan agregat di basahi dengan Water Tank Truck
Pemadatan di laksanakan dengan Vibratory Roller
Sekelompok pekerja merapikan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Agregat Kelas C Di produksi di base camp M.035

ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.1.(3)
Jenis Kegiatan : Lapis Pondasi Klas C
Satuan Pembayaran : M3

URAIAN KODE

MOTOR GREADER E.140


Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts3
- Perataan 1 kali lintasan = (Lh x 60) : (v x 1000) T1
- Lain-Lain T2
Ts3
Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3
Ts2 x n
Koefisien Alat / M3 = 1 : Q3
VIBRATORY ROLLER E.240
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x Fa Q5
n
Koefisien Alat / M3 = 1 : Q5
WATER TANK TRUCK E.230
Volume Tangki Air V
Kebutuhan Air / M3 Material Padat Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q5
Wc
Koefisien Alat / M3 = 1 : Q5
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = WHEEL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran :
Jenis Kegiatan : Urugan Pasir
Satuan Pembayaran : M3

URAIAN KODE
ASUMSI
Menggunakan alat Manual
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t

METODE PELAKSANAAN

Dump Truck mengangkut ke lapangan dengan jarak Lq


Material di hampar dengan menggunakan tenaga manusia
Hamparan Pasir Urug di siram air dengan Water Tank Truck
(sebelum pemadatan) dan di padatkan dengan stamper
Selama pemadatan sekelompok pekerja akan merapikan tepi
hamparan dan level permukaan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Pasir = 1 x Fk M.081

ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = Pekerja Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.1(3b)
Jenis Kegiatan : Telford Batu Padas
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t
Jarak rata-rata ke Base Camp Lr

METODE PELAKSANAAN
Wheel Loader memuat agregat ke dalam Dump Truck
Aggregat kemudian di hampar dengan Tenaga Manusia
Hamparan Agregat/ Telford Dipasang Berdiri
Pemadatan di laksanakan dengan Three Whell Roller
Sekelompok pekerja merapikan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Material Batu Gunung Produksi Di Lokasi
Batu Padas = 1 x Fk M.010
ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1
DUMP TRUCK E.080
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain T3
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 5.1.(3).
Jenis Kegiatan : Telford Batu Padas
Satuan Pembayaran : M3

URAIAN KODE

THREE WHEEL ROLLER E.170


Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q3
n
Koefisien Alat / M3 = 1 : Q3
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = WHEEL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


METODE PELAKSANAAN
Kegiatan : Pembangunan Jalan Dan Jembatan
Item Pembayaran : 1.2
Jenis Kegiatan : Mobilisasi
Satuan Pembayaran : Unit

URAIAN KODE

ASUMSI
Kegiatan dilakukan secara manual
Lokasi Kegiatan : sepanjang jalan
Kondisi Jalan : sedang / baik
Jarak rata-rata ke Base Camp ke lokasi Kegiatan L
Jam kerja efektif per hari Tk
Semen diangkut dari Base Camp ke lapangan dengan menggunakan dump truck
Satu hari dapat diselesaikan hamparan Soil Stabilizer Ecomix Sepanjang Ls
Faktor hilang material Fh
Tebal hamparan t

METODE PELAKSANAAN
Dump truck mengangkut seen dari Base Camp
ke lokasi Kegiatan
Semen diatur/disusun di tempat hamparan
soil/tanah oleh tenaga manusia

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Semen yang diperlukan /ton = (1 x Fh : 40) x 1000 M.12

ALAT
DUMP TRUCK E.080
Kapasitas bak V
Faktor Efesiensi Alat Fa
Kecepatan rata-rata bermuatan v1
Kecepatan rata-rata kosong v2
Waktu siklus Ts1
- Waktu tempuh isi T1
- Waktu tempuh kosong T2
- Waktu mengisi T3
- Waktu bongkar T4
- Lain-lain T5
Ts1
Kap. Prod. / Jam = V x Fa x 60
Fh x Ts1

Koefisien Alat / M3 = 1/Q1 E.080

TENAGA
Lebar Hamparan Soil Cement b
Kadar semen (3-12) % s
Berat jenis tanah = V x Ap BJ
Setiap hari dengan produksi = {(s:100) x t x b x Ls} x Bj Qt

Kebutuhan tenaga :
- Pekerja Tidak Terlatih P
- Mandor M

Koefisien Tenaga / Ton :


- Pekerja Tidak Terlatih = (Tk x P ) : Qt (L01)
- Mandor = (Tk x M ) : Qt (L03)

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 1.2
Jenis Kegiatan : Mobilisasi
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Kegiatan dilakukan secara manual
Lokasi Kegiatan : sepanjang jalan
Kondisi Jalan : sedang / baik
Jarak rata-rata ke Base Camp ke lokasi Kegiatan L
Jam kerja efektif per hari Tk
Harga pembayaran tidak termasuk semen (semen dibayar dalam item tersendiri)
Satu hari dapat diselesaikan hamparan Soil Cement Sepanjang Ls
Faktor kembang material (padat-lepas) Fk
Tebal hamparan padat t

METODE PELAKSANAAN
Sheel loader memuat material ke dalam dump truck di lokasi sumber bahan
Dump truck menangkut material kelokasi Kegiatan
Motor Grader menghampar material di lokasi Kegiatan
Semen dan material tanah diaduk ditempat dengan
menggunakan Vulvi mixer
Sebelum pemadatan material dibasahi dengan
menggunakan water tank truck
Pemadatan dilakukan dengan menggunakan
Vibrator Roller dan pneumatic Tire Roller
Selama pelaksanaan Kegiatan sekelompok pekerja
akan merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Setiap M3 Soil Cement padat diperlukan = 1 x Fk M08

ALAT
WHEEL LOADER E220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fa x Fb x 60 Q1
Ts1 x Fk
Koefisien Alat / M3 = 1 : Q1 E220

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 1.2
Jenis Kegiatan : Mobilisasi
Satuan Pembayaran : M3

URAIAN KODE

DUMP TRUCK
Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain T4
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2 x Fk
Koefisien Alat / M3 = 1 : Q2
MOTOR GREADER
Panjang Hamparan Lh
Lebar Efektif Kerja Blade b
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Alat v
Jumlah Lintasan n
Waktu Siklus Ts3
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1
- Lain-Lain T2
Ts3
Kap. Prod. / Jam = Lh x b x t x Fa x 60 Q3
Ts3 x n
Koefisien Alat / M3 = 1 : Q3
TANDEM ROLLER
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q4
n
Koefisien Alat / M3 = 1 : Q4
PNEUMATIC TIRE ROLLER
Kecepatan rata-rata alat V
Lebar efektif pemadatan b
Jumlah lintasan n
Faktor efesiensi alat Fa

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 1.2
Jenis Kegiatan : Mobilisasi
Satuan Pembayaran : M3

URAIAN KODE

Kap. Prod. / Jam = (V x 1000) x b x t x Fa Q5


n
Koefisien Alat / M3 = 1 : Q5

WATER TANK TRUCK


Volume Tangki Air V
Kebutuhan Air / M3 beton Wc
Pengisian Tangki / Jam n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = V x n x Fa Q6
Wc
Koefisien Alat / M3 = 1 : Q6

FULVI MIXER
Kecepatan rata-rata alat V
Lebar efektif pemadatan Wc
Jumlah lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (V x 1000 ) x b x t x Fa Q7
n
Koefisien Alat / M3 = 1 : Q7
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Kereta dorong = 2 buah
- Sekop = 3 buah

TENAGA
Produksi Menentukan = VIBRATOR ROLLER Q4
Produksi Per Hari = Tk x Q4 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.12.(2)
Jenis Kegiatan : Bearing Pad (406 x 406 x 50)
Satuan Pembayaran : Buah

URAIAN KODE

ASUMSI
Menggunakan buruh (cara manual)
Lokasi Kegiatan : sepanjang jalan
Bahan Dasar Karet
Menggunakan alat bantu berupa lem/perekat/baut
Jam kerja efektif per hari

METODE PELAKSANAAN
Rubeering diletakan pada posisi sesuai gambar yang sebelumnya diberi lem atau
perekat yang kuat sehingga tidak mudah geser
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Bearing Pad Ukuran 406 x 406 50 M.202
Lem/Perekat/baut -

ALAT
TENAGA
Produksi Per Hari = Bearing Pad
Kebutuhan Tenaga
- Pekerja Tidak Terlatih L.101
- Pekerja Terlatih L.106
- Mandor L.061
METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.6.(8)
Jenis Kegiatan : Pemancangan Tiang Pancang Beton □ 30 x 30 Cm
Satuan Pembayaran :M

URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Jarak rata-rata ke Base Camp Lr

METODE PELAKSANAAN
Tiang Pancang Diangkat Dan Didirikan Oleh Crane
Kemudian Crane Memancang Dengan Diesel Hammer
Digunakan Las-lasan Untuk Penyambungan Tiang
Digunakan Driver Untuk Penyesuaian Kedalaman Pancang
Pekerja Merapikan Dengan Alat Bantu Dan Menghancurkan Kepala Pancang

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Material Pancang disediakan oleh supplier
Kawat Las E.197
Kapasitas Produkasi V
Kawat Las
Koefisien Bahan / Inch = 1 : Q1
ALAT
MESIN PANCANG E.270
Faktor Efesiensi Alat Fa
T1
Q1
Koefisien Alat / M3 = 1 : Q1
WELDING MACHINE E.280
- Produksi
- Waktu T3
Q2
Koefisien Alat / M3 = 1 : Q2

TENAGA
Kebutuhan Tenaga
Produksi Per Hari = Tk x Q1 Qt
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.12.(5)
Jenis Kegiatan : Expantion Joint
Satuan Pembayaran :M

URAIAN KODE

ASUMSI
Menggunakan mesin las, besi siku dan besi plat
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Jarak rata-rata ke Base Camp Lr
METODE PELAKSANAAN
Untuk pekerjaan las-lasan pada sambungan tiang pancang, sambungan dan sekur
Dikerjakan oleh tukang las yang sudah berpengalaman
Kawat Las 3 mm - 5 mm
Bagian permukan yang kurang baik harus dibevel terlebih dahulu sehingga mendapatkan
sambungan yang baik

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Material
Kapasitas Produkasi V
Kawat Las E.197
Besi Siku 100.100.10 mm V
Besi Plat
Koefisien Bahan / Inch = 1 : Q1

ALAT
WELDING MACHINE E.280
- Produksi
- Waktu T3
Q2
Koefisien Alat / M3 = 1 : Q2

TENAGA
Kebutuhan Tenaga
Produksi Per Hari = Tk x Q1 Qt
- Pekerja Tidak Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : -
Jenis Kegiatan : Pengecatan Besi Sekur
Satuan Pembayaran : M2

URAIAN KODE

ASUMSI
Menggunakan buruh (cara manual)
Lokasi Kegiatan : sepanjang jalan
Cat anti korosit mutu tinggi
Menggunakan alat bantu berupa kuas
Jam kerja efektif per hari

METODE PELAKSANAAN
Rubeering diletakan pada posisi sesuai gambar yang sebelumnya diberi lem atau
perekat yang kuat sehingga tidak mudah geser
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Cat Anti Korosit -
Thinner Special -
Alat Bantu -

TENAGA
Produksi Per Hari = Pengecatan
Kebutuhan Tenaga
- Pekerja Tidak Terlatih L.101
- Pekerja Terlatih L.106
- Mandor L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 2.2
Jenis Kegiatan : Pasangan Batu Dengan Mortar
Satuan Pembayaran : M3

URAIAN KODE

ASUMSI
Menggunakan buruh (cara manual)
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (batu gunung, semen, pasir pasangan) di terima
seluruhnya di lokasi Kegiatan
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Perbandingan pasir & semen - Volume pasir Ps
- Volume semen Sm
Perbandingan batu & mortar
- Batu gunung Bt
- Mortar (campuran pasir & semen) Mr
Berat jenis bahan
- Pasangan batu dengan mortar D1
- Batu gunung D2
- Adukan (mortar) D3
- Pasir D4
- Semen PC D5
Faktor kehilangan bahan - Batu Fh1
- Pasir / Semen Fh2

METODE PELAKSANAAN
Semen, pasir dan air di campur dan di aduk menjadi mortar
dengan menggunakan alat bantu
Batu di bersihkan dan di basahi seluruh permukaannya
sebelum di pasang
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Batu Gunung [(Bt x D1 x 1 M3) : D2] x Fh1 M.010
Semen PC Sm x [(Mr x D1 x 1 M3) : D3] x Fh2 M.080
x [D5 x (1000)]
Pasir Pasangan Ps x [(Mr x D1 x 1 M3) : D4] x Fh2 M.040
ALAT
Produksi Per Hari = MORTAR Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih Pt
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Pt) : Qt L.106
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 11.1
Jenis Kegiatan : Pekerjaan Paving
Satuan Pembayaran : M2

URAIAN KODE

ASUMSI
Menggunakan alat Manual
Lokasi Kegiatan : sepanjang jalan
Kondisi jalan : sedang / baik
Jam kerja efektif per hari Tk
Faktor pengembangan material Fk
Tebal hamparan padat t

METODE PELAKSANAAN

Dump Truck mengangkut ke lapangan dengan jarak Lq


Material di hampar dengan menggunakan tenaga manusia
Hamparan Pasir Urug di siram air dengan Water Tank Truck
(sebelum pemadatan) dan di padatkan dengan stamper
Selama pemadatan sekelompok pekerja akan merapikan tepi
hamparan dan level permukaan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Pasir Urug M.050
Tanah Urug M.081
Paving -
ALAT BANTU
Di perlukan Alat-Alat Bantu Kecil
- Sekop = 3 buah
TENAGA
Produksi Menentukan = Pekerja Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih P
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x M) : Qt L.106
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : -
Jenis Kegiatan : Pengecatan Lenning
Satuan Pembayaran : M2

URAIAN KODE

ASUMSI
Menggunakan buruh (cara manual)
Lokasi Kegiatan : sepanjang jalan
Cat tembok anti lumut
Menggunakan alat bantu berupa kuas
Jam kerja efektif per hari

METODE PELAKSANAAN
Rubeering diletakan pada posisi sesuai gambar yang sebelumnya diberi lem atau
perekat yang kuat sehingga tidak mudah geser
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Cat Tembok Anti Lumut -
Alat Bantu -

TENAGA
Produksi Per Hari = Pengecatan
Kebutuhan Tenaga
- Pekerja Tidak Terlatih L.101
- Pekerja Terlatih L.106
- Mandor L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.3.(2)
Jenis Kegiatan : Latasir (SS-B)
Satuan Pembayaran : M2
URAIAN KODE

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan, Kondisi : sedang
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Tebal rata-rata Lapen Macadam t
Jam kerja efektif per hari Tk
Faktor kehilangan material - Agregat Fh1
- Aspal Fh2
Komposisi campuran ATB (Spesifikasi)
- Agregat Kasar (1-2 cm) Ak
- Debu Batu Ap
- Aspal As1
As2
Berat jenis bahan
- Agregat D1
- Aspal D2

METODE PELAKSANAAN
mukaan dasar di bersihkan dan di semprot aspal cair
Agregat kasar di muat ke dalam Dump Truck menggunakan
Wheel Loader (di Base Camp)
Agregat kasar di tebarkan (manual) sesuai tebal yang di perlukan
dan di padatkan dengan Three Wheel Roller minimal 6 lintasan
Aspal di semprotkan di atas agregat kasar yang telah di ratakan
menggunakan Asphalt Sprayer (merata)
Agregat pengunci di tebarkan dan di padatkan dengan cara
yang sama dengan pemadatan agregat kasar

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
- Agregat Kasar (1-2 cm= [(Ak/1000 ÷ t M3) x Fh1] : D1 M.025
- Debu Batu = [(Ap/1000 ÷ t M3) x Fh1] : D1 M.026
- Aspal = [(As ÷ t M3) x Fh2] M.061

ALAT
WHEEL LOADER E.220
Kapasitas Bucket V
Faktor Bucket Fb
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Lain-Lain T2
Ts1
Kap. Prod. / Jam = V x Fb x Fa x 60 Q1
Ts1
Koefisien Alat / M3 = 1 : Q1

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 6.3.(2)
Jenis Kegiatan : Latasir (SS-B)
Satuan Pembayaran : M2

URAIAN KODE

DUMP TRUCK E.080


Kapasitas Bak V
Faktor Efesiensi Alat Fa
Kecepatan Rata-Rata Bermuatan v1
Kecepatan Rata-Rata Kosong v2
Waktu Siklus Ts2
- Waktu Tempuh Isi = (L : v1) x 60 T1
- Waktu Tempuh Kosong = (L : v2) x 60 T2
- Lain-Lain (Tunggu + Dump + Putar + Mengisi) T3
Ts2
Kap. Prod. / Jam = V x Fa x 60 Q2
Ts2
Koefisien Alat / M3 = 1 : Q2
ASPHALT SPRAYER E.030
Kapasitas Alat V
Faktor Efesiensi Alat Fa
Waktu Siklus (Termasuk Proses Pemanasan) Ts3
Kap. Prod. / Jam = V x Fa x D2 Q3
Ts3 x As2
Koefisien Alat / Liter = 1 : Q3
THREE WHEEL ROLLER E.170
Kecepatan Rata-Rata Alat v
Lebar Efektif Pemadatan b
Jumlah Lintasan n
Faktor Efesiensi Alat Fa
Kap. Prod. / Jam = (v x 1000) x b x t x Fa Q4
n
Koefisien Alat / M3 = 1 : Q4
ALAT BANTU
Di perlukan Kereta Dorong, Sekop, Sapu, Karung, Cerek Aspal
TENAGA
Produksi Menentukan = WHELL LOADER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih M
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x M) : Qt L.061
- Mandor = (Tk x M) : Qt L.061

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 11.2
Jenis Kegiatan : Kerb Beton K350
Satuan Pembayaran : M1

URAIAN KODE

ASUMSI
Menggunakan alat (cara mekanik)
Lokasi Kegiatan : sepanjang jalan
Bahan dasar (koral, pasir dan semen) di terima di lokasi
Jarak rata-rata Base Camp ke lokasi Kegiatan Lr
Jam kerja efektif per hari Tk
Kadar semen (Spesifikasi) - Minimum Ks1
- Maksimum Ks2
Perbandingan air, semen maksimum (Spesifikasi) Wcr
Perbandingan campuran = 1 : Semen Sm
= 3 : Pasir Ayak Ps

Berat jenis material


Kerb Beton K350 D1
- Semen (PC) D2
- Pasir beton D3

METODE PELAKSANAAN
Semen, pasir, koral dan air di campur dan di aduk menjadi
beton dengan menggunakan Concrete Mixer
Beton di cor ke dalam perancah yang telah di siapkan
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Semen PC @ 50 Kg = [Sm x D1 x 1000] x 1,05 M.080
Pasir Ayak = [(Ps x D1) : D3] x 1,05 M.041

ALAT
CONCRETE MIXER E.060
Kapasitas Alat V
Faktor Efesiensi Alat Fa
Waktu Siklus Ts1
- Memuat T1
- Mengaduk T2
- Menuang T3
- Menunggu, dll T4
Ts1

Kap. Prod. / Jam = V x Fa x 60 Q1


Ts1 x 1000
Koefisien Alat / M3 = 1 : Q1

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 11.2
Jenis Kegiatan : Kerb Beton K350
Satuan Pembayaran : M1

URAIAN KODE

TENAGA
Produksi Menentukan = CONCRETE MIXER Q1
Produksi Per Hari = Tk x Q1 Qt
Kebutuhan Tenaga
- Pekerja Tidak Terlatih P
- Pekerja Terlatih Tb
- Mandor M
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih = (Tk x P) : Qt L.101
- Pekerja Terlatih = (Tk x Tb) : Qt L.106
- Mandor = (Tk x M) : Qt L.061
Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)

METODE PELAKSANAAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 7.1(5b)
Jenis Kegiatan : Pipa PVC 1"
Satuan Pembayaran : M1

URAIAN KODE

ASUMSI

Pekerjaan dilakukan secara manual dengan gergaji


Lokasi Kegiatan : sepanjang jalan
Jam kerja efektif per hari Tk
Bahan dasar (Pipa PVC) diterima seluruhnya di lokasi pekerjaan Fk
Kondisi jalan : sedang / baik
Jarak rata-rata ke Base Camp Lr

METODE PELAKSANAAN
Dowel D 20 - 30 yang telah selesai dipabrikasi sebelah sisinya di cat dengan
cat anti karat
Kemudian dowel D 20 - 30 yang telah dicat anti karat sebelah sisinya di beri
atau dimasuki pipa PVC 1"
PEMAKAIAN BAHAN, ALAT DAN TENAGA
BAHAN
Pipa PVC 1"

ALAT
GERGAJI BESI
Kapasitas memotong V
Koefisine alat Fa
Kapasitas produksi / jam = V x Fa Q
Koefisine alat / M3 = 1 / Q

TENAGA
Produksi kerja satu hari Qt
dibutuhkan - Mandor M
- Pekerja Tidak Terlatih P
Koefisine tenaga kerja/kg :
- Mandor = ( M x Tk ) : Qt L101
- Pekerja = ( P x Tk ) : Qt L106

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor

B. BAHAN

1.00 Km

0.50 M3
0.90 ---
0.75 --- C. PERALATAN
0.85 --- 1 Dump Truck
2 Excavator Hydraulic
0.50 menit 3 Alat Bantu
0.50 menit
1.00 menit
14.34 M3/Jam

0.0697 Jam

4.00 M3
0.80 ---
40.00 Km/Jam D. JUMLAH HARGA TENAGA, BAHAN D
65.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan
1.50 menit
1.00 menit
10.00 menit
1.00 menit
13.50 menit
11.85 M3/Jam

0.0844 Jam

AN

KOEFISIEN SATUAN KET

14.34 M3/Jam
100.41 M3

3.00 orang
1.00 orang

0.2092 Jam
0.0697 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
1 Pekerja Tidak Terlatih
10.000 Km 2 Pekerja Terlatih
7.00 Jam 3 Mandor
0.72 72%
0.28 28%

0.72 72% B. BAHAN


0.28 28% 1 Batu Gunung
2 Semen (PC)
2.20 Ton/M3 3 Pasir Pasangan
2.00 Ton/M3
1.80 Ton/M3
1.67 Ton/M3
1.44 Ton/M3
1.20 ---
1.10 ---

C. PERALATAN
1 Alat Bantu

0.9504 M3
0.1054 M3
151.7824 Kg
0.2921 M3
D. JUMLAH HARGA TENAGA, BAHAN D
5.00 M3 E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan
10.00 orang
5.00 orang
1.00 orang

14.0000 Jam
7.0000 Jam
1.4000 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor

B. BAHAN

3.00 Km
0.50 M3
0.90 ---
0.75 --- C. PERALATAN
0.85 --- 1 Dump Truck
2 Excavator Hydraulic
0.50 menit 3 Alat Bantu
0.50 menit
1.00 menit
14.34 M3/Jam

0.0697 Jam

4.00 M3
0.80 ---
40.00 Km/Jam D. JUMLAH HARGA TENAGA, BAHAN D
65.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan
4.50 menit
2.77 menit
12.55 menit

19.82 menit
8.07 M3/Jam

0.1239 Jam

AN
KOEFISIEN SATUAN KET

14.34 M3/Jam
100.41 M3

4.00 orang
1.00 orang

0.2789 Jam
0.0697 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor
0.15 M

3.00 Km B. BAHAN
1.2000 M3

1.50 M3 C. PERALATAN
0.90 --- 1 Wheel Loader
0.83 --- 2 Motor Greader
3 Water Tank Truck
0.50 menit 4 Vibratory Roller
0.50 menit 5 Alat Bantu
1.00 menit
56.03 M3/Jam

0.0178 Jam

D. JUMLAH HARGA TENAGA, BAHAN D


E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

AN

KOEFISIEN SATUAN KET


30.00 M
3.00 M
0.70 ---
5.00 Km/Jam
5.00 lintasan

0.36 menit
0.50 menit
0.86 menit
131.86 M3/Jam

0.0076 Jam

4.00 Km/Jam
1.20 M
6.00 lintasan
0.80 ---
96.00 M3/Jam

0.0104 Jam

2.00 M3
0.07 M3
3.00 kali
0.75 ---
64.29 M3/Jam

0.0156 Jam

56.03 M3/Jam
392.18 M3

6.00 orang
1.00 orang

0.1071 Jam
0.0178 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor
0.15 M

2.50 Km B. BAHAN
1 Tanah Urug

1.2000 M3

3.50 M3 C. PERALATAN
0.90 --- 1 Dump Truck
0.75 --- 2 Water Tank Truck
3 Alat Bantu
0.50 menit
0.25 menit
0.75 menit
157.50 M3/Jam

0.0063 Jam

4.00 M3
0.85 --- D. JUMLAH HARGA TENAGA, BAHAN D
65.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
70.00 Km/Jam F. HARGA SATUAN Kegiatan

2.31 menit
2.14 menit

4.45 menit
38.20 M3/Jam

0.0262 Jam

AN

KOEFISIEN SATUAN KET

60.00 M
2.40 M
0.90 ---
5.00 Km/Jam
5.00 lintasan
0.72 menit
0.50 menit
1.22 menit
191.21 M3/Jam

0.0052 Jam

4.00 Km/Jam
1.20 M
4.00 lintasan
0.83 ---
149.40 M3/Jam

0.0067 Jam

4.00 M3
0.07 M3
3.00 kali
0.83 ---
142.29 M3/Jam

0.0070 Jam

157.50 M3/Jam
1,102.50 M3

4.00 orang
1.00 orang

0.0254 Jam
0.0063 Jam

AN
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
2 Mandor

B. BAHAN

40.00 M
2.40 M
0.70 ---
3.00 Km/Jam
4.00 lintasan C. PERALATAN
1 Motor Greader
0.80 menit 2 Water Tank Truck
1.00 menit 3 Vibratory Roller
1.80 menit 4 Alat Bantu
560.00 M3/Jam

0.0018 Jam
D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

3.00 Km/Jam
1.20 M
12.00 lintasan
0.75 ---
225.00 M3/Jam

0.0044 Jam

AN

KOEFISIEN SATUAN KET

3.00 M3
0.09 M3
2.00 kali
0.75 ---
50.00 M3/Jam

0.0200 Jam

225.00 M3/Jam
1,575.00 M3

4.00 orang
1.00 orang
0.0178 Jam
0.0044 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN
A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor
0.25 M
1.000 Km
1.00 M

B. BAHAN
1 Tanah Urug

1.2000 M3

3.50 M3 C. PERALATAN
0.85 --- 1 Dump Truck
0.85 --- 2 Motor Grader
3 Water Tank Truck
0.50 menit 4 Wheel Loader
0.25 menit 5 Tandem Roller
0.75 menit 6 Alat Bantu
168.58 M3/Jam

0.0059 Jam

6.00 M3
0.85 --- D. JUMLAH HARGA TENAGA, BAHAN D
40.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
65.00 Km/Jam F. HARGA SATUAN Kegiatan

1.50 menit
0.92 menit
2.00 menit
4.42 menit
57.65 M3/Jam
0.0173 Jam

AN

KOEFISIEN SATUAN KET

60.00 M
3.50 M
0.85 ---
4.00 Km/Jam
6.00 lintasan

0.90 menit
1.00 menit
1.90 menit
234.87 M3/Jam

0.0043 Jam

3.00 Km/Jam
1.20 M
8.00 lintasan
0.85 ---
95.63 M3/Jam

0.0105 Jam

5.00 M3
0.07 M3
1.00 kali
0.85 ---
60.71 M3/Jam

0.0165 Jam

168.58 M3/Jam
1,180.08 M3

7.00 orang
1.00 orang

0.0415 Jam
0.0059 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET
NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor
0.15 M
10.000 Km
1.00 M

B. BAHAN
1 Agregat Kasar Kelas B

1.2000 M3

1.50 M3 C. PERALATAN
0.90 --- 1 Dump Truck
0.72 --- 2 Motor Greader
3 Water Tank Truck
0.50 menit 4 Wheel Loader
0.50 menit 5 Tandem Roller
1.00 menit 6 Alat Bantu
48.60 M3/Jam

0.0206 Jam

6.00 M3
0.72 --- D. JUMLAH HARGA TENAGA, BAHAN D
45.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
60.00 Km/Jam F. HARGA SATUAN Kegiatan

13.33 menit
10.00 menit
3.00 menit
26.33 menit
8.20 M3/Jam

0.1219 Jam

AN

KOEFISIEN SATUAN KET

50.00 M
2.40 M
0.72 ---
4.00 Km/Jam
4.00 lintasan

0.75 menit
1.00 menit
1.75 menit
111.09 M3/Jam

0.0090 Jam

3.00 Km/Jam
1.20 M
6.00 lintasan
0.72 ---
64.80 M3/Jam

0.0154 Jam

4.00 M3
0.07 M3
1.00 kali
0.72 ---
41.14 M3/Jam

0.0243 Jam

48.60 M3/Jam
340.20 M3

4.00 orang
1.00 orang

0.0823 Jam
0.0206 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor
0.10 M
5.000 Km
B. BAHAN
1 Agregat Kasar Kelas A
2 Agregat Halus Kelas A

0.7800 M3
0.4200 M3

1.50 M3 C. PERALATAN
0.90 --- 1 Dump Truck
0.85 --- 2 Motor Greader
3 Water Tank Truck
0.50 menit 4 Wheel Loader
0.25 menit 5 Vibratory Roller
0.75 menit 6 Alat Bantu
76.50 M3/Jam

0.0131 Jam

4.00 M3
0.72 --- D. JUMLAH HARGA TENAGA, BAHAN D
60.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
65.00 Km/Jam F. HARGA SATUAN Kegiatan

5.00 menit
4.62 menit
1.00 menit
10.62 menit
13.57 M3/Jam

0.0737 Jam

AN
KOEFISIEN SATUAN KET

50.00 M
2.40 M
0.72 ---
4.00 Km/Jam
6.00 lintasan

0.75 menit
1.00 menit
1.75 menit
49.37 M3/Jam

0.0203 Jam

2.00 Km/Jam
1.20 M
8.00 lintasan
0.75 ---
225.00 M3/Jam

0.0044 Jam

4.00 M3
0.07 M3
1.00 kali
0.72 ---
41.14 M3/Jam

0.0243 Jam

76.50 M3/Jam
535.50 M3

3.00 orang
1.00 orang

0.0392 Jam
0.0131 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 3 Mandor
0.15 M
3.000 Km

B. BAHAN
1 Agregat Kasar Kelas B
2 Agregat Halus Kelas B

1.0200 M3
0.1800 M3
1.50 M3 C. PERALATAN
0.90 --- 1 Dump Truck
0.90 --- 2 Motor Greader
3 Water Tank Truck
0.25 menit 4 Wheel Loader
0.25 menit 5 Vibratory Roller
0.50 menit 6 Alat Bantu
121.50 M3/Jam

0.0082 Jam

4.00 M3
0.90 --- D. JUMLAH HARGA TENAGA, BAHAN D
60.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
65.00 Km/Jam F. HARGA SATUAN Kegiatan

3.00 menit
2.77 menit
0.25 menit
6.02 menit
29.90 M3/Jam

0.0334 Jam

AN

KOEFISIEN SATUAN KET

40.00 M
3.50 M
0.85 ---
4.00 Km/Jam
6.00 lintasan

0.60 menit
0.25 menit
0.85 menit
210.00 M3/Jam

0.0048 Jam

2.00 Km/Jam
1.20 M
8.00 lintasan
0.75 ---
225.00 M3/Jam

0.0044 Jam

5.00 M3
0.07 M3
1.00 kali
0.85 ---
60.71 M3/Jam

0.0165 Jam

121.50 M3/Jam
850.50 M3

8.00 orang
1.00 orang

0.0658 Jam
0.0082 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor
0.20 M3/M2
5.000 Km

B. BAHAN
1 Batu Gunung

1.2000 M3

1.50 M3 C. PERALATAN
0.95 --- 1 Dump Truck
0.83 --- 2 Wheel Loader
3 Three Wheel Roller
1.50 menit 4 Alat Bantu
0.50 menit
2.00 menit
177.41 M3/Jam
0.0056 Jam

4.00 M3
0.90 --- D. JUMLAH HARGA TENAGA, BAHAN D
65.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
70.00 Km/Jam F. HARGA SATUAN Kegiatan

4.62 menit
4.29 menit
0.25 menit
9.15 menit
19.67 M3/Jam

0.0508 Jam

AN

KOEFISIEN SATUAN KET

3.00 Km/Jam
1.20 M
6.00 lintasan
0.83 ---
99.60 M3/Jam

0.0100 Jam

177.41 M3/Jam
1,241.89 M3
20.00 orang
2.00 orang

0.1127 Jam
0.0113 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET
NO KOMPONEN

10.000 Km A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.10 --- 2 Mandor

0.56 56 %
0.44 44 %

1.05 Kg/Liter B. BAHAN


0.80 Kg/Liter 1 Aspal
2 Kerosene

C. PERALATAN
1 Asphalt Sprayer
2 Air Compressor
3 Dump Truck
1.10 Liter 4 Alat Bantu
0.6468 Kg
0.4840 Liter

700.00 Liter
0.75 ---
2.75 Jam
190.91 Liter/Jam D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
0.0052 Jam F. HARGA SATUAN Kegiatan
350.00 M2/Jam
0.80 Liter/M2
280.00 Liter/Jam
0.0036 Jam

AN

KOEFISIEN SATUAN KET

190.91 Liter

280.00 Liter/Jam
0.0036 Jam

190.91 Liter/Jam
1,336.36 Liter

12.00 orang
2.00 orang

0.0718 Jam
0.0120 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

30.000 Km A. TENAGA
0.05 M 1 Pekerja Tidak Terlatih
7.00 Jam 2 Mandor
1.20 ---
1.05 ---
0.600 50,0 %
0.440 40,0 % B. BAHAN
0.060 6,2 % 1 Agregat Kasar Hotmix
0.070 7,0 % 2 Agregat Halus Hotmix
3 Filler
2.40 Ton/M3 4 Aspal
1.80 Ton/M3
2.00 Ton/M3
1.05 Ton/M3

C. PERALATAN
1 Asphalt Mixing Plant
2 Asphalt Finisher
3 Dump Truck
4 Generator Set
5 Tandem Roller
6 Tire Pneumatic Roller
7 Wheel Loader
0.9600 M3 8 Alat Bantu
0.7040 M3
172.8000 Kg
176.4000 Kg
D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
1.70 M3 F. HARGA SATUAN Kegiatan
0.90 ---
0.85 ---

1.50 menit
0.50 menit
2.00 menit
29.26 M3/Jam

0.0342 Jam

AN
KOEFISIEN SATUAN KET

70.00 Ton/Jam
0.90 ---
26.25 M3/Jam

0.0381 Jam
0.0381 Jam

4.00 M3
0.90 ---
40.00 Km/Jam
50.00 Km/Jam
0.40 Ton
2.00 menit

20.00 menit
30.00 menit
17.00 menit
15.00 menit
82.00 menit
1.10 M3/Jam

0.9111 Jam

40.00 Ton/Jam
0.85 ---
14.17 M3/Jam

0.0706 Jam

4.00 Km/Jam
3.00 M
4.00 lintasan
0.75 ---
112.50 M3/Jam
0.0089 Jam

4.00 Km/Jam
2.00 M
4.00 lintasan
0.85 ---
85.00 M3/Jam

0.0118 Jam

AN

KOEFISIEN SATUAN KET

26.25 M3 /Jam
183.75 M3

7.00 orang
1.00 orang

0.2667 Jam
0.0381 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN
10.000 Km A. TENAGA
0.2 M 1 Pekerja Tidak Terlatih
7.00 Jam 2 Pekerja Terlatih
3 Mandor

B. BAHAN

1 Beton Ready Mix K- 350


2 Plastik Sheet
3 Karung
1.000 M3
5.000 M2
0.350 Kg
6.000 Lbr

C. PERALATAN
1 Concrete Wibrator
2 Concrete Finisher
0.3500 Jam 3 Alat Bantu

0.5000 Jam
1.00 Ls

8.00 M3 /Jam
56.00 M3 D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
29.00 orang F. HARGA SATUAN Kegiatan
12.00 orang
3.00 orang

3.6250 Jam
1.5000 Jam
0.3750 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

10.000 Km A. TENAGA
0.2 M 1 Pekerja Tidak Terlatih
7.00 Jam 2 Pekerja Terlatih
3 Mandor

B. BAHAN

1 Beton Ready Mix K- 300


2 Plastik Sheet
3 Karung
1.000 M3 4 Pipa PVC 1"
5.000 M2
6.000 Lbr
2.240 M1

C. PERALATAN
1 Concrete Wibrator
2 Alat Bantu

0.3500 Jam
1.00 Ls

8.00 M3 /Jam
56.00 M3
D. JUMLAH HARGA TENAGA, BAHAN D
40.00 orang E. BIAYA UMUM DAN KEUNTUNGAN
14.00 orang F. HARGA SATUAN Kegiatan
3.00 orang

5.0000 Jam
1.7500 Jam
0.3750 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
10.000 Km 1 Pekerja Tidak Terlatih
7.00 Jam 2 Pekerja Terlatih
1.10 --- 3 Mandor
1.05 ---
0.57
0.111 11,1 %
0.333 33,3 % B. BAHAN
0.556 55,6 % 1 Semen (PC)
2 Pasir Beton (Palu)
2.50 Ton/M3 3 Koral Palu
1.44 Ton/M3 4 Air
1.67 Ton/M3
1.80 Ton/M3

C. PERALATAN
1 Concrete Mixer
2 Concrete Vibrator
3 Water Tank Truck
305.2500 Kg 4 Alat Bantu
0.5484 M3
0.8494 M3
30.0000 Liter

350.00 Liter
0.75 --- D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
7.00 menit F. HARGA SATUAN Kegiatan
5.00 menit
4.00 menit
3.00 menit
19.00 menit

0.83 M3/Jam

1.2063 Jam

AN
KOEFISIEN SATUAN KET

1.2063 Jam

2.00 M3
0.16 M3
1.00 kali
0.75 ---
9.38 M3/Jam

0.1067 Jam

0.83 M3 /Jam
5.80 M3

10.00 orang
6.00 orang
1.00 orang

12.0635 Jam
7.2381 Jam
1.2063 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
10.000 Km 1 Pekerja Tidak Terlatih
7.00 Jam 2 Pekerja Terlatih
1.10 --- 3 Mandor

B. BAHAN
1 Besi Beton
2 Kawat Beton

1.1000 Kg
0.2200 Kg
C. PERALATAN
1 Alat Bantu
200.00 Kg

3.00 orang
1.00 orang
1.00 orang

0.1050 Jam
0.0350 Jam
0.0350 Jam

D. JUMLAH HARGA TENAGA, BAHAN D


E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN
A. TENAGA
10.000 Km 1 Pekerja Tidak Terlatih
7.00 Jam 2 Pekerja Terlatih
1.10 --- 3 Mandor

B. BAHAN
1 Kayu Ulin 10/10
2 Kayu Ulin 5/10

1.0000 Titik
0.0075 M3

12.00 Titik

3.00 orang
1.00 orang C. PERALATAN
1.00 orang 1 Alat Bantu

1.7500 Jam
0.5833 Jam
0.5833 Jam

D. JUMLAH HARGA TENAGA, BAHAN D


E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
10.000 Km 1 Pekerja Tidak Terlatih
7.00 Jam 2 Pekerja Terlatih
1.10 --- 3 Mandor

B. BAHAN
1 Kawat Bronjong
2 Batu Gunung

0.4200 Kg
1.2000 M3

C. PERALATAN
1.60 M2 1 Alat Bantu

8.00 orang
2.00 orang
1.00 orang

35.0000 Jam
8.7500 Jam
4.3750 Jam

D. JUMLAH HARGA TENAGA, BAHAN D


E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

10.000 Km A. TENAGA
0.05 M 1 Pekerja Tidak Terlatih
7.00 Jam 2 Pekerjan Terlatih
1.20 --- 2 Mandor
1.15 ---
150.00 50,0 %
35.00 38,0 % B. BAHAN
6.00 6,5 % 1 Agregat 3-5 cm
55.00 2 Agregat 1-2 cm
3 Aspal
1.80 Ton/M3
1.01 Ton/M3

C. PERALATAN
1 Dump Truck
2 Wheel Loader
3 Three Wheel Roller
4 Asphalt Sprayer
5 Alat Bantu

1.6667 M3
0.3889 M3
63.2500 Kg

D. JUMLAH HARGA TENAGA, BAHAN D


E. BIAYA UMUM DAN KEUNTUNGAN
1.50 M3 F. HARGA SATUAN Kegiatan/M3
0.90 --- G. HARGA SATUAN Kegiatan/M2
0.75 ---

2.00 menit
1.00 menit
3.00 menit
20.25 M3/Jam

0.0494 Jam

AN
71,146.30

KOEFISIEN SATUAN KET

6.00 M3
0.75 ---
40.00 Km/Jam
50.00 Km/Jam

15.00 menit
12.00 menit
30.00 menit
57.00 menit
4.74 M3/Jam

0.2111 Jam

1,200.00 Liter
0.75 ---
1.50 Jam
11.02 Liter/Jam

0.0908 Jam

3.00 Km/Jam
1.20 M
8.00 lintasan
0.70 ---
15.75 M3/Jam

0.0635 Jam

20.25 M3 /Jam
141.75 M3
24.00 orang
6.00 orang
2.00 orang

1.1852 Jam
0.2963 Jam
0.0988 Jam

71,146.30

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
1 Pekerja Tidak Terlatih
10.000 Km 2 Pekerja Terlatih
7.00 Jam 3 Mandor
0.75 75 %
0.25 25 %

0.80 80 % B. BAHAN
0.20 20 % 1 Batu Padas
2 Semen (PC)
2.00 Ton/M3 3 Pasir Pasangan
1.40 Ton/M3
1.60 Ton/M3
1.47 Ton/M3
1.24 Ton/M3
1.00 ---
1.00 ---

C. PERALATAN
1 Alat Bantu

1.1429 M3
0.0625 M3
77.5000 Zak
0.2041 M3
D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
4.00 M3 F. HARGA SATUAN Kegiatan

5.00 orang
1.00 orang
1.00 orang

8.7500 Jam
1.7500 Jam
1.7500 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN
A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor
0.15 M

1.50 Km B. BAHAN
1 Batu Padas

1.0000 M3

1.00 M3
0.90 ---
0.75 --- C. PERALATAN
1 Dump Truck
1.00 menit 2 Wheel Loader
1.00 menit 3 Vibratory Roller
2.00 menit 4 Alat Bantu
16.88 M3/Jam

0.0593 Jam

3.00 M3
0.75 --- D. JUMLAH HARGA TENAGA, BAHAN D
45.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
60.00 Km/Jam F. HARGA SATUAN Kegiatan

4.00 menit
2.00 menit
2.00 menit
8.00 menit
14.06 M3/Jam
0.0711 Jam

AN

KOEFISIEN SATUAN KET

4.00 Km/Jam
1.20 M
6.00 lintasan
0.75 ---
90.00 M3/Jam

0.0111 Jam

16.88 M3/Jam
118.13 M3

4.00 orang
1.00 orang

0.2370 Jam
0.0593 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

10.000 Km A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.10 --- 2 Mandor

0.40 56 %
0.60 44 %

1.05 Kg/Liter B. BAHAN


0.80 Kg/Liter 1 Aspal
2 Gasoline

C. PERALATAN
1 Asphalt Sprayer
2 Air Compressor
3 Dump Truck
1.10 Liter 4 Alat Bantu
0.4620 Kg
0.6600 Liter

200.00 Liter
0.75 ---
2.50 Jam
60.00 Liter/Jam D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
0.0167 Jam F. HARGA SATUAN Kegiatan

300.00 M2/Jam
0.70 Liter/M2
210.00 Liter/Jam
0.0048 Jam

AN
KOEFISIEN SATUAN KET

60.00 Liter

210.00 Liter/Jam
0.0048 Jam

60.00 Liter/Jam
420.00 Liter

12.00 orang
2.00 orang

0.1143 Jam
0.0190 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
KOEFISIEN SATUAN KET Satuan Pembayaran

NO KOMPONEN

20.000 Km A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
2 Mandor
400.00 M
1.05 -
0.15 M

B. BAHAN
1 Semen
C. PERALATAN
1 Dump Truck
1,050.00 Kg

6.00 Ton
0.80 -
45.00 Km/Jam
60.00 Km/Jam
D. JUMLAH HARGA TENAGA, BAHAN D
26.65 menit E. BIAYA UMUM DAN KEUNTUNGAN
19.99 menit F. HARGA SATUAN Kegiatan
40.00 menit
30.00 menit
10.00 menit
126.64 menit

0.4450 Jam

6.00 M
7.50 %
1.60 Ton/M3
43.2000 Ton

15.00 Orang
1.00 Orang

2.4300 Jam
0.1620 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
20.000 Km 1 Pekerja Tidak Terlatih
7.00 Jam 2 Mandor

400.00 M
1.20 -
0.15 M
B. BAHAN
1 Tanah Timbunan

C. PERALATAN
1 Dump Truck
2 Motor Greader
3 Water Tank Truck
4 Wheel Loader
5 Tandem Roller
6 P. Tire Roller
7 Fulvi Mixer
6 Alat Bantu

1.20 M3 Material Lepas


D. JUMLAH HARGA TENAGA, BAHAN D
1.25 M3 E. BIAYA UMUM DAN KEUNTUNGAN
0.85 --- Pemuatan Ringan F. HARGA SATUAN Kegiatan
0.83 ---

0.50 menit
0.50 menit
1.00 menit
55.09 M3

0.0182 Jam

AN

KOEFISIEN SATUAN KET

3.50 M3
0.80 ---
45.00 Km/Jam 143,972.91
60.00 Km/Jam

24.00 menit
19.99 menit
3.00 menit
46.99 menit
2.98 M3

0.2991 Jam

50.00 M
2.40 M
0.75 ---
4.00 Km/Jam
6.00 lintasan

1.15 menit
1.00 menit
2.15 menit
119.52 M3/Jam

0.0084 Jam

3.00 Km/Jam
1.20 M
8.00 lintasan 4 x pp
0.83 ---
56.03 M3

0.0178 Jam

5.00 Km/jam
1.50 M
8.00 Lintasan 4 x pp
0.83 ---

AN

KOEFISIEN SATUAN KET

116.72 M3

0.0086 Jam

4.00 M3
0.07 M3
3.00 kali
0.88 ---
142.29 M3

0.0070 Jam

2.50 Km/jam
1.00 M3
6.00 lintasan 3xpp
0.83 ---
51.88 M3

0.0193 Jam

55.09 M3/Jam
392.18 M3

7.00 orang
1.00 orang

1.2249 Jam
0.0178 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.000 Km 1 Pekerja Tidak Terlatih
0.04 M 2 Mandor
7.00 Jam
1.10 -
1.05 -

50.00 % B. BAHAN
39.00 % 1 Agregat Kasar
4.85 % 2 Agregat Halus
6.70 % 3 Filler
4 Aspal
2.25 ton/M3
1.80 ton/M3
2.00 ton/M3
1.03 ton/M3 C. PERALATAN
1 Dump Truck
2 Genset
3 Wheel Loader
4 Tandem Roller
5 P. Tire Roller
6 AMP
7 Asphalt Finisher
8 Alat Bantu

0.024 M3
0.060 M3 D. JUMLAH HARGA TENAGA, BAHAN D
3.502 Kg E. BIAYA UMUM DAN KEUNTUNGAN
2.850 Kg F. HARGA SATUAN Kegiatan
1.50 M3
0.90 ---
0.83 ---

1.50 menit
0.50 menit
2.00 menit
672.30 M3

0.0015 Jam

AN

KOEFISIEN SATUAN KET

6.00 M3
0.95 ---
50.00 Km/Jam
60.00 Km/Jam
0.50 tn
1.00 menit

6.00 menit
8.40 menit
2.00 menit
7.00 menit
23.40 menit
5.41 M3

0.1847 Jam

50.00 M
0.83 M
461.11 ton/Jam

0.0022 Jam

461.11 m2
0.0022 Jam

2.50 Km/Jam
1.20 M
4.00 lintasan
0.83 ---
622.50 M2

0.0016 Jam

40.00 ton/jam
0.83 M
368.89

0.0027

AN

KOEFISIEN SATUAN KET


3.50 Km/jam
1.20 M
8.00 Lintasan 4 x pp
0.83 ---
435.75 M3

0.0023 Jam

461.11 M2/Jam
3,227.78 M3

10.00 orang
1.00 orang

0.0217 Jam
0.0022 Jam

AAN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

10.000 Km A. TENAGA
7.00 Jam 1 Mandor Lapangan
1.10 --- 2 Kepala Tukang
1.05 --- 3 Pekerja Tak Terlatih
0.57 4 Pekerja Terlatih
0.119 11.9 %
0.357 35.7 %
0.524 52,4 % B. BAHAN
1 Pasir Ayak
2.40 Ton/M3 2 Semen PC
1.44 Ton/M3 3 Kayu Acuan
1.67 Ton/M3 4 Batu Kerikil
1.80 Ton/M3

C. PERALATAN

1 Concrete Mixer
325.0000 Kg 2 Concrete Vibrator
0.5389 M3 3 Water Pump
0.7124 M3 4 Alat Bantu
0.0217 M3

655.00 Liter
0.90 --- D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
4.00 menit F. HARGA SATUAN Kegiatan
3.00 menit
2.00 menit
2.00 menit
11.00 menit

3.22 M3/Jam

0.3110 Jam

AAN

KOEFISIEN SATUAN KET

0.3110 Jam

3.57 M3
0.16 M3
1.00 kali
0.75 ---
16.75 M3/Jam

0.0597 Jam

3.22 M3 /Jam
22.51 M3

4.00 orang
2.00 orang
1.00 orang

1.2440 Jam
0.6220 Jam
0.0833 Jam
0.3110 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor

B. BAHAN

1.00 Km

2.00 M3/Jam

0.5000 Jam C. PERALATAN


1 Dump Truck
2 Jack Hammer
3 Compressor
3.00 M3 4 Alat Bantu
0.80 ---
45.00 Km/Jam
55.00 Km/Jam

1.33 menit
1.09 menit
20.00 menit
10.00 menit D. JUMLAH HARGA TENAGA, BAHAN D
32.42 menit E. BIAYA UMUM DAN KEUNTUNGAN
3.70 M3/Jam F. HARGA SATUAN Kegiatan

0.2702 Jam
AN

KOEFISIEN SATUAN KET

2.50 M3/Jam
17.50 M3

6.00 orang
1.00 orang

2.4000 Jam
0.4000 Jam
AAN
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN
KOEFISIEN SATUAN KET

A. TENAGA
1 Pekerja Tidak Terlatih
2 Mandor
3 Operator Terlatih
7.00 Jam 4 Pembantu Operator

B. BAHAN
65.00 M
3.75 M C. PERALATAN
0.90 --- 1 Motor Grader
2.00 Km/Jam 2 Alat Bantu
6.00 lintasan

6.00 menit
2.00 menit
8.00 menit
274.22 M3/Jam

0.0036 Jam

D. JUMLAH HARGA TENAGA, BAHAN D


E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

8.00 orang
1.00 orang
1.00 orang
1.00 orang

0.0280 Jam
0.0040 Jam
0.0080 Jam
0.0070 Jam
AAN
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN
KOEFISIEN SATUAN KET

A. TENAGA
1 Pekerja Tidak Terlatih
2 Pekerjan Terlatih
3 Mandor

7.00
0.75
0.25 B. BAHAN
Portland Cement
1.67 Pasir Pasangan
1.44
1.05

C. PERALATAN
8.00 Kg
0.10 M3 1 Alat Bantu

0.25 Jam
0.15 Jam
0.01 Jam

D. JUMLAH HARGA TENAGA, BAHAN D


E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
10.000 Km 1 Pekerja Tidak Terlatih
7.00 Jam 2 Pekerja Terlatih
1.10 --- 3 Mandor

B. BAHAN
1 Kayu Meranti /Perancah
2 Paku Biasa

0.0400 M3
0.4000 Kg

12.00 Titik

6.00 orang
1.00 orang
1.00 orang C. PERALATAN
1 Alat Bantu
3.5000 Jam
0.5833 Jam
0.5833 Jam

D. JUMLAH HARGA TENAGA, BAHAN D


E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
10.000 Km 1 Pekerja Tidak Terlatih
7.00 Jam 2 Mandor
1.10 ---
B. BAHAN
1 Sealent
2 Diamnod Blade
2 Kayu Segitiga
0.2000 Kg
0.0012 Buah
1.0000 M1

30.00 M2/Jam

0.0333 Jam

C. PERALATAN
1 Compressor
2 Alat Bantu

40.00 M

1.00 orang
1.00 orang

0.1750 Jam D. JUMLAH HARGA TENAGA, BAHAN D


0.0275 Jam E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
10.000 Km 1 Pekerja Tidak Terlatih
7.00 Jam 2 Pekerja Terlatih
1.10 --- 3 Mandor
1.05 ---
0.50
0.154 15,4 %
0.385 38,5 % B. BAHAN
0.462 46,2 % 1 Semen (PC)
2 Pasir Beton (Palu)
2.40 Ton/M3 3 Koral Eks Palu
1.44 Ton/M3 4 Air
1.67 Ton/M3 5 Plastik Sheet
2.00 Ton/M3

C. PERALATAN
1 Concrete Mixer
2 Concrete Vibrator
3 Water Tank Truck
425.0400 Kg 4 Alat Bantu
0.6640 M3
0.6376 M3
30.0000 Liter
5.0000 M2

D. JUMLAH HARGA TENAGA, BAHAN D


600.00 Liter E. BIAYA UMUM DAN KEUNTUNGAN
0.70 --- F. HARGA SATUAN Kegiatan

3.00 menit
2.00 menit
2.00 menit
1.00 menit
8.00 menit
3.15 M3/Jam

0.3175 Jam

AN

KOEFISIEN SATUAN KET

0.3175 Jam

6.00 M3 1,425,216.58
0.15 M3
1.00 kali
0.85 ---
34.00 M3/Jam

0.0294 Jam
3.15 M3 /Jam
22.05 M3

30.00 orang
14.00 orang
3.00 orang

9.5238 Jam
4.4444 Jam
0.9524 Jam

AN
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.10 --- 2 Mandor
0.15 M
10.000 Km

B. BAHAN
1 Agregat Kelas C

1.1000 M3

1.50 M3 C. PERALATAN
0.90 --- 1 Dump Truck
0.75 --- 2 Motor Greader
3 Water Tank Truck
0.50 menit 4 Wheel Loader
0.50 menit 5 Vibratory Roller
1.00 menit 6 Alat Bantu
55.23 M3/Jam

0.0181 Jam

6.00 M3
0.75 --- D. JUMLAH HARGA TENAGA, BAHAN D
45.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
60.00 Km/Jam F. HARGA SATUAN Kegiatan

13.33 menit
10.00 menit
3.00 menit
26.33 menit
9.32 M3/Jam

0.1073 Jam

AN

KOEFISIEN SATUAN KET

50.00 M
2.40 M
0.75 ---
4.00 Km/Jam
6.00 lintasan

0.75 menit
1.00 menit
1.75 menit
77.14 M3/Jam

0.0130 Jam

2.00 Km/Jam
1.20 M
8.00 lintasan
0.75 ---
225.00 M3/Jam

0.0044 Jam

4.00 M3
0.07 M3
1.00 kali
0.75 ---
42.86 M3/Jam

0.0233 Jam

55.23 M3/Jam
386.59 M3

7.00 orang
1.00 orang

0.1267 Jam
0.0181 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET
NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.05 --- 2 Mandor
0.15 M

4.00 Km B. BAHAN
1 Pasir Urug Pasangan

1.0500 M3

C. PERALATAN
1 Alat Bantu

4.00 M3/Jam
28.00 M3

4.00 orang
1.00 orang

1.0000 Jam
0.2500 Jam

D. JUMLAH HARGA TENAGA, BAHAN D


E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
KOEFISIEN SATUAN KET Satuan Pembayaran

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor
0.20 M3/M2
10.000 Km

B. BAHAN
1 Batu Padas

1.0000 M3

1.00 M3 C. PERALATAN
0.80 --- 1 Dump Truck
0.80 --- 2 Wheel Loader
3 Three Wheel Roller
1.50 menit 4 Alat Bantu
0.50 menit
2.00 menit
96.00 M3/Jam

0.0104 Jam

5.00 M3
0.85 --- D. JUMLAH HARGA TENAGA, BAHAN D
40.00 Km/Jam E. BIAYA UMUM DAN KEUNTUNGAN
60.00 Km/Jam F. HARGA SATUAN Kegiatan

10.00 menit
7.00 menit
26.00 menit
43.00 menit
4.94 M3/Jam

0.2024 Jam

AN

KOEFISIEN SATUAN KET

3.00 Km/Jam
1.20 M
8.00 lintasan
0.75 ---
67.50 M3/Jam

0.0148 Jam
96.00 M3/Jam
672.00 M3

20.00 orang
2.00 orang

0.2083 Jam
0.0208 Jam
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN

A. Sewa Tanah
B. Peralatan
Lihat Lembar 1.2-2
C. Fasilitas Kantor (Barak Kerja)
- Serobong Kerja

D. Fasilitas Direksi Teknis


-Kantor
E. Mobilisasi Lain
F. Lain -Lain

- Papan Nama Proyek


- Direksi Keet

G. Demobilisasi
H. HARGA SATUAN Kegiatan

Lermbar No
Kegiatan

NO JENIS ALAT

B. PERALATAN

1 Air Compressor 4000-6500 L/m3


2 Dump Truck 3-4 m3
3 Dump Truck Mixer
4 Buldozer 100 - 150 Hp
5 Motor Grader > 100 HP
6 Excavator 80 - 140 Hp
7 Vibrator Roller
8 Concrete Vibrator
9 Concrete Finisher
10 Concrete Cutter
11 Water Tanker
12 Mesin Pancang

C. HARGA SATUAN Kegiatan

AN
Kegiatan
Item Pembayaran
Jenis Kegiatan
KOEFISIEN SATUAN KET Satuan Pembayaran

NO KOMPONEN

20.000 Km A. Sewa Tanah


7.00 Jam B. Peralatan
Lihat Lembar 1.2-2
400.00 M C. Fasilitas Kantor (Barak Kerja)
1.05 - -Barak Kerja
0.20 M
D. Fasilitas Direksi Teknis
-Kantor
E. Mobilisasi Lain
F. Lain -Lain
- Pengukuran Pematokan
- Papan Nama Proyek
- As Build Drawings
- Bongkaran

G. Demobilisasi

2,200.00 Kg

6.00 Ton
0.83 -
45.00 Km/Jam
60.00 Km/Jam

26.65 menit
19.99 menit
40.00 menit
30.00 menit
10.00 menit
126.64 menit H. HARGA SATUAN Kegiatan

0.4450 Jam

6.00 M Lermbar No
7.50 % Kegiatan
1.60 Ton/M3
43.2000 Ton
NO JENIS ALAT

15.00 Orang
1.00 Orang B. PERALATAN

2.4300 Jam
0.1620 Jam 1 Concrete Vibrator
2 Dump Truck 3-4 m3
3 Concrete Mixer
4 Dump Truck Mixer
5 Concrete Pump

AN

KOEFISIEN SATUAN KET C. HARGA SATUAN Kegiatan


20.000 Km
7.00 Jam Kegiatan
Item Pembayaran
400.00 M Jenis Kegiatan
1.20 - Satuan Pembayaran
0.15 M

NO KOMPONEN

A. Sewa Tanah
B. Peralatan
Lihat Lembar 1.2-2
C. Fasilitas Kantor (Barak Kerja)
-Barak Kerja

D. Fasilitas Direksi Teknis


-Kantor
E. Mobilisasi Lain
F. Lain -Lain
- Pengukuran Pematokan
- Papan Nama Proyek
1.20 M3 Material Lepas - As Build Drawings
- Jembatan Darurat/Sementara
- Bongkaran

1.25 M3 G. Demobilisasi
0.85 --- Pemuatan Ringan
0.83 ---

0.50 menit
0.50 menit
1.00 menit
44.09 M3

0.0227 Jam
AN

H. HARGA SATUAN Kegiatan

KOEFISIEN SATUAN KET

Lermbar No
3.50 M3 Kegiatan
0.80 ---
45.00 Km/Jam
60.00 Km/Jam NO JENIS ALAT

26.65 menit
19.99 menit B. PERALATAN
3.00 menit
49.64 menit
2.82 M3
1 Concrete Vibrator
0.2991 Jam 2 Dump Truck 3-4 m3
3 Concrete Mixer
50.00 M 4 Dump Truck Mixer
2.40 M 5 Concrete Pump
0.75 ---
4.00 Km/Jam
6.00 lintasan

1.15 menit
1.00 menit
2.15 menit
119.52 M3/Jam

0.0084 Jam
C. HARGA SATUAN Kegiatan
3.00 Km/Jam
1.20 M
8.00 lintasan 4 x pp
0.83 ---
56.03 M3

0.0178 Jam
Kegiatan
5.00 Km/jam Item Pembayaran
1.50 M Jenis Kegiatan
8.00 Lintasan 4 x pp Satuan Pembayaran
0.83 ---

NO KOMPONEN

AN
A. Sewa Tanah
B. Peralatan
Lihat Lembar 1.2-2
C. Fasilitas Kantor (Barak Kerja)
-Barak Kerja

D. Fasilitas Direksi Teknis


KOEFISIEN SATUAN KET -Kantor
E. Mobilisasi Lain
116.72 M3 F. Lain -Lain
- Pengukuran Pematokan
0.0086 Jam - Papan Nama Proyek
- As Build Drawings
- Bongkaran
4.00 M3
0.07 M3 G. Demobilisasi
3.00 kali
0.88 ---
142.29 M3

0.0070 Jam

2.50 Km/jam
1.00 M3
6.00 lintasan 3xpp
0.83 ---
51.88 M3

0.0193 Jam
H. HARGA SATUAN Kegiatan

44.09 M3/Jam
392.18 M3

7.00 orang
1.00 orang Lermbar No
Kegiatan
1.2249 Jam
0.0178 Jam
NO JENIS ALAT

B. PERALATAN

1 Air Compressor 4000-6500 L/m3


2 Dump Truck 3-4 m3
3 Asphalt Finisher
4 Tandem Roler 6 - 8 Ton
5 Motor Grader > 100 HP
6 Pneumatic Tire Roler 8 - 10 Ton
7 Tree Wheel Roler
8 Asphalt Spayer

C. HARGA SATUAN Kegiatan


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN

A. Sewa Tanah
B. Peralatan
Lihat Lembar 1.2-2
C. Fasilitas Kantor (Barak Kerja)
-Barak Kerja

D. Fasilitas Direksi Teknis


-Kantor
E. Mobilisasi Lain
F. Lain -Lain
- Pengukuran Pematokan
- Papan Nama Proyek
- As Build Drawings
- Bongkaran
- Jembatan Sementara
G. Demobilisasi
H. HARGA SATUAN Kegiatan

Lermbar No
Kegiatan

NO JENIS ALAT

B. PERALATAN

1 Dump Truck 3-4 m3

C. HARGA SATUAN Kegiatan


Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN

A. Sewa Tanah
B. Peralatan
Lihat Lembar 1.2-2
C. Fasilitas Kantor (Barak Kerja)
-Barak Kerja

D. Fasilitas Direksi Teknis


-Kantor
E. Mobilisasi Lain
F. Lain -Lain
- Pengukuran Pematokan
- Papan Nama Proyek
- As Build Drawings
- Bongkaran

G. Demobilisasi
H. HARGA SATUAN Kegiatan

Lermbar No
Kegiatan

NO JENIS ALAT

B. PERALATAN

1 Air Compressor 4000-6500 L/m3


2 Dump Truck 3-4 m3
3 Asphalt Finisher
4 Tandem Roler 6 - 8 Ton
5 Motor Grader > 100 HP
6 Pneumatic Tire Roler 8 - 10 Ton
7 Tree Wheel Roler
8 Asphalt Spayer

C. HARGA SATUAN Kegiatan


AAN
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN
KOEFISIEN SATUAN KET

A. TENAGA
1 Pekerja Tidak Terlatih
2 Pekerjan Terlatih
3 Mandor

7.00

B. BAHAN
Bearing Pad Uk. 406 x 406 x 50
Perekat/Baut

C. PERALATAN
1.00 Buah
1.00 Ls 1 Alat Bantu

4 Jam
0.4 Jam
0.04 Jam
D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
KOEFISIEN SATUAN KET Satuan Pembayaran

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.00 --- 2 Mandor
15.000 Km

B. BAHAN
1 Kawat Las

10.0000 Inch
0.3500 Kg
0.2450 Jam C. PERALATAN
1 Mesin Pancang
2 Welding Machine
4 Alat Bantu
0.80 ---
5.00 menit
9.60 Inch/Jam
0.1042 Jam

30.00 Jam
10.00 menit
2.33 M3/Jam
0.4286 Jam D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

40.00 M
20.00 orang
2.00 orang

3.5000 Jam
0.3500 Jam

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
KOEFISIEN SATUAN KET Satuan Pembayaran

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.00 --- 2 Mandor
15.000 Km
B. BAHAN
1 Kawat Las
2 Besi Siku 100.100.10 mm
3 Besi Plat

18.0000 M1
5.0000 Kg
2.0000 M1
1.0000 Ls C. PERALATAN
0.5556 Jam 1 Welding Machine
2 Alat Bantu

7.00 Jam
5.00 menit
5.00 InchJam
0.2000 Jam

40.00 M D. JUMLAH HARGA TENAGA, BAHAN D


10.00 orang E. BIAYA UMUM DAN KEUNTUNGAN
2.00 orang F. HARGA SATUAN Kegiatan

1.7500 Jam
0.3500 Jam
AAN
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN
KOEFISIEN SATUAN KET

A. TENAGA
1 Pekerja Tidak Terlatih
2 Pekerjan Terlatih
3 Mandor

7.00

B. BAHAN
Cat Anti Korosit Mutu Tinggi
Thinner

C. PERALATAN
0.20 Kg
0.09 Liter 1 Alat Bantu
1.00 Ls

3 Jam
0.3 Jam
0.03 Jam
D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

AN
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
1 Pekerja Tidak Terlatih
10.000 Km 2 Pekerja Terlatih
7.00 Jam 3 Mandor
0.69 69%
0.31 31%

0.69 69% B. BAHAN


0.31 31% 1 Batu Gunung
2 Semen (PC)
2.20 Ton/M3 3 Pasir Pasangan
2.00 Ton/M3
1.80 Ton/M3
1.67 Ton/M3
1.44 Ton/M3
1.20 ---
1.10 ---

C. PERALATAN
1 Alat Bantu

0.9108 M3
0.1292 M3
186.0496 Kg
0.3100 M3
D. JUMLAH HARGA TENAGA, BAHAN D
5.00 M3 E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan
10.00 orang
5.00 orang
1.00 orang

14.0000 Jam
7.0000 Jam
1.4000 Jam

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN

A. Sewa Tanah
B. Peralatan
Lihat Lembar 1.2-2
C. Fasilitas Kantor (Barak Kerja)
-Barak Kerja

D. Fasilitas Direksi Teknis


-Kantor
E. Mobilisasi Lain
F. Lain -Lain

- Papan Nama Proyek

G. Demobilisasi
H. HARGA SATUAN Kegiatan

Lermbar No
Kegiatan

NO JENIS ALAT

B. PERALATAN

1 Air Compressor 4000-6500 L/m3


2 Dump Truck 3-4 m3
3 Tandem Roler 6 - 8 Ton
4 Motor Grader > 100 HP
5 Vibrator Roller
6 Asphalt Sprayer
C. HARGA SATUAN Kegiatan

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN

A. Sewa Tanah
B. Peralatan
Lihat Lembar 1.2-2
C. Fasilitas Kantor (Barak Kerja)
-Barak Kerja

D. Fasilitas Direksi Teknis


-Kantor
E. Mobilisasi Lain
F. Lain -Lain

- Papan Nama Proyek

G. Demobilisasi
H. HARGA SATUAN Kegiatan

Lermbar No
Kegiatan

NO JENIS ALAT

B. PERALATAN

1 Air Compressor 4000-6500 L/m3


2 Dump Truck 3-4 m3
3 Dump Truck Mixer
4 Concrete Vibrator
5 Motor Grader > 100 HP
6 Conrete Cutter
7 Rigid Paver
C. HARGA SATUAN Kegiatan

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN

A. Sewa Tanah
B. Peralatan
Lihat Lembar 1.2-2
C. Fasilitas Kantor (Barak Kerja)
-Barak Kerja

D. Fasilitas Direksi Teknis


-Kantor
E. Mobilisasi Lain
F. Lain -Lain
- Pengukuran Pematokan
- Papan Nama Proyek
- As Build Drawings

G. Demobilisasi
H. HARGA SATUAN Kegiatan

Lermbar No
Kegiatan

NO JENIS ALAT

B. PERALATAN

1 Air Compressor 4000-6500 L/m3


2 Dump Truck 3-4 m3
3 Asphalt Finisher
4 Tandem Roler 6 - 8 Ton
5 Motor Grader > 100 HP
6 Pneumatic Tire Roler 8 - 10 Ton
7 Tree Wheel Roler
C. HARGA SATUAN Kegiatan

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.05 --- 2 Pekerja Terlatih
0.15 M 3 Mandor

4.00 Km B. BAHAN
1 Pasir Urug
2 Tanah Urug
3 Paving

0.0425 M3
0.0425 M3
35.00 Buah
C. PERALATAN
1 Alat Bantu

3.00 M2/Jam
21.00 M2

3.00 orang
2.00 orang
1.00 orang

1.0000 Jam D. JUMLAH HARGA TENAGA, BAHAN D


0.3333 Jam E. BIAYA UMUM DAN KEUNTUNGAN
0.0250 Jam F. HARGA SATUAN Kegiatan

AAN
Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran

NO KOMPONEN
KOEFISIEN SATUAN KET

A. TENAGA
1 Pekerja Tidak Terlatih
2 Pekerjan Terlatih
3 Mandor

7.00

B. BAHAN
Cat Tembok Anti Lumut

C. PERALATAN
0.20 Kg
1.00 Ls 1 Alat Bantu

2.5 Jam
0.25 Jam
0.025 Jam
D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan

AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
KOEFISIEN SATUAN KET Satuan Pembayaran

NO KOMPONEN

10.000 Km
0.05 M A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Pekerjan Terlatih
1.15 --- 2 Mandor

75.00 68.18%
30.00 27.27%
5.00 4.54% B. BAHAN
55.00
1 Debu Batu
1.80 Ton/M3 2 Aspal
1.01 Ton/M3

C. PERALATAN
1 Dump Truck
2 Wheel Loader
3 Three Wheel Roller
4 Asphalt Sprayer
5 Alat Bantu

0.8333 M3
0.3333 M3
63.2500 Kg

D. JUMLAH HARGA TENAGA, BAHAN D


1.50 M3 E. BIAYA UMUM DAN KEUNTUNGAN
0.90 --- F. HARGA SATUAN Kegiatan/M3
0.75 --- G. HARGA SATUAN Kegiatan/M2
2.00 menit
1.00 menit
3.00 menit
20.25 M3/Jam

0.0494 Jam

AN

KOEFISIEN SATUAN KET

6.00 M3
0.75 ---
40.00 Km/Jam
60.00 Km/Jam

15.00 menit
10.00 menit
30.00 menit
55.00 menit
4.91 M3/Jam

0.2037 Jam

1,200.00 Liter
0.75 ---
1.50 Jam
11.02 Liter/Jam

0.0908 Jam

8.00 Km/Jam
1.20 M
8.00 lintasan
0.75 ---
45.00 M3/Jam

0.0222 Jam

20.25 M3 /Jam
141.75 M3

24.00 orang
4.00 orang
2.00 orang

1.1852 Jam
0.1975 Jam
0.0988 Jam

AAN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KOEFISIEN SATUAN KET

NO KOMPONEN

10.000 Km A. TENAGA
7.00 Jam 1 Mandor Lapangan
1.10 --- 2 Pekerja Tak Terlatih
1.05 --- 3 Pekerja Terlatih
0.57
0.250 11.9 %
0.750 35.7 %
B. BAHAN
1 Kerb Beton K350
2.00 Buah 2 Pasir Ayak
1.44 Ton/M3 3 Semen PC
1.67 Ton/M3

C. PERALATAN

1 Concrete Mixer
0.0500 Kg 2 Alat Bantu
0.0200 M3

655.00 Liter
0.90 --- D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
3.00 menit F. HARGA SATUAN Kegiatan
3.00 menit
2.00 menit
2.00 menit
10.00 menit

3.54 M3/Jam

0.2827 Jam
AAN

KOEFISIEN SATUAN KET

3.54 M3 /Jam
24.76 M3

4.00 orang
2.00 orang
1.00 orang

1.1309 Jam
0.5655 Jam
0.2827 Jam
AN

Kegiatan
Item Pembayaran
Jenis Kegiatan
KOEFISIEN SATUAN KET Satuan Pembayaran

NO KOMPONEN

A. TENAGA
7.00 Jam 1 Pekerja Tidak Terlatih
1.20 --- 2 Mandor

0.000 Km

B. BAHAN
1 Pipa 1"
1.00 M

25.00 M1/jam C. PERALATAN


0.70 --- 1 Gergaji besi
17.50 M1/jam
0.06 Jam

250.00 M1/hari
1.00 Orang
2.00 Orang

0.03
0.06
D. JUMLAH HARGA TENAGA, BAHAN D
E. BIAYA UMUM DAN KEUNTUNGAN
F. HARGA SATUAN Kegiatan
ENGINEER'S ESTIMATE

FORMULIR STANDAR UNTUK


REKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 2.1 Perkiraan Kuantitas :
: Galian Parit Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.081 Jam 0.2092 7,500.00


L.061 Jam 0.0697 12,000.00

JUMLAH HARGA TENAGA

JUMLAH HARGA BAHAN

E.080 Jam 0.0844 189,640.54


E.100 Jam 0.0697 184,196.03
Ls 1.0000 2,000.00
JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
REKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 7.9 Perkiraan Kuantitas :
: Pasangan Batu + Adukan Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 14.0000 7,500.00


L.106 Jam 7.0000 10,000.00
L.061 Jam 1.4000 12,000.00

JUMLAH HARGA TENAGA

M.010 M3 0.9504 227,627.27


M.080 Kg 151.7824 1,420.77
M.040 M3 0.2921 130,000.00

JUMLAH HARGA BAHAN

Ls 1.0000 5,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 3.1.(1) Perkiraan Kuantitas :
: Galian Biasa Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.081 Jam 0.2789 7,500.00


L.061 Jam 0.0697 12,000.00

JUMLAH HARGA TENAGA


JUMLAH HARGA BAHAN

E.080 Jam 0.1239 189,640.54


E.100 Jam 0.0697 184,196.03
Ls 1.0000 5,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 3.2.(1a) Perkiraan Kuantitas :
: Urugan Biasa (Eks Galian) Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.081 Jam 0.1071 7,500.00


L.061 Jam 0.0178 12,000.00

JUMLAH HARGA TENAGA


JUMLAH HARGA BAHAN

E.220 Jam 0.0178 288,771.87


E.140 Jam 0.0076 337,729.37
E.230 Jam 0.0156 203,933.53
E.240 Ls 0.0104 225,825.20
Ls 1.0000 2,500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 3.2.(1) Perkiraan Kuantitas :
: Urugan Tanah Biasa Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.0254 7,500.00


L.061 Jam 0.0063 12,000.00

JUMLAH HARGA TENAGA

M.050 M3 1.2000 37,606.25

JUMLAH HARGA BAHAN

E.080 Jam 0.0262 189,640.54


E.230 Jam 0.0070 203,933.53
Ls 1.0000 1,500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
REKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 3.3 Perkiraan Kuantitas :
: Penyiapan Badan Jalan Total Harga :
: M2 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.0178 7,500.00


L.061 Jam 0.0044 12,000.00

JUMLAH HARGA TENAGA

JUMLAH HARGA BAHAN

E.140 Jam 0.0018 337,729.37


E.230 Jam 0.0200 203,933.53
E.240 Jam 0.0044 225,825.20
Ls 1.0000 400.00

JUMLAH HARGA PERALATAN


HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)
MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 3.2.(2) Perkiraan Kuantitas :
: Timbunan Tanah Pilihan Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.0415 7,500.00


L.061 Jam 0.0059 12,000.00

JUMLAH HARGA TENAGA

M.081 M3 1.2000 50,606.25

JUMLAH HARGA BAHAN

E.080 Jam 0.0173 189,640.54


E.140 Jam 0.0043 337,729.37
E.230 Jam 0.0165 203,933.53
E.220 Jam 0.0059 288,771.87
E.180 Jam 0.0105 177,571.03
Ls 1.0000 200.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 2.4 Perkiraan Kuantitas :
: Bahu Agregat Total Harga :
: M3 % Harga Jumlah Seluruh :
KOMPONEN SATUAN PERKIRAAN HARGA
KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.0823 7,500.00


L.061 Jam 0.0206 12,000.00

JUMLAH HARGA TENAGA

asar Kelas B M.035 M3 1.2000 286,000.00

JUMLAH HARGA BAHAN

E.080 Jam 0.1219 189,640.54


E.140 Jam 0.0090 337,729.37
E.230 Jam 0.0243 203,933.53
E.220 Jam 0.0206 288,771.87
E.180 Jam 0.0154 177,571.03
Ls 1.0000 200.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 5.1.(1). Perkiraan Kuantitas :
: Lapis Pondasi Klas A Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.0392 7,500.00


L.061 Jam 0.0131 12,000.00

JUMLAH HARGA TENAGA


asar Kelas A M.033 M3 0.7800 340,000.00
Halus Kelas A M.031 M3 0.4200 340,000.00

JUMLAH HARGA BAHAN

E.080 Jam 0.0737 189,640.54


E.140 Jam 0.0203 337,729.37
E.230 Jam 0.0243 203,933.53
E.220 Jam 0.0131 288,771.87
E.240 Jam 0.0044 225,825.20
Ls 1.0000 2,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 5.1.(2) Perkiraan Kuantitas :
: Lapis Pondasi Klas B Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.0658 7,500.00


L.061 Jam 0.0082 12,000.00

JUMLAH HARGA TENAGA

asar Kelas B M.035 M3 1.0200 286,000.00


Halus Kelas B M.040 M3 0.1800 286,000.00
JUMLAH HARGA BAHAN

E.080 Jam 0.0334 189,640.54


E.140 Jam 0.0048 337,729.37
E.230 Jam 0.0165 203,933.53
E.220 Jam 0.0082 288,771.87
E.240 Jam 0.0044 225,825.20
Ls 1.0000 500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


5.1.(3a) Perkiraan Kuantitas :
: Telford Batu Gunung Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.1127 7,500.00


L.061 Jam 0.0113 12,000.00

JUMLAH HARGA TENAGA

M.010 M3 1.2000 227,627.27

JUMLAH HARGA BAHAN

E.080 Jam 0.0508 189,640.54


E.220 Jam 0.0056 288,771.87
E.170 Jam 0.0100 177,571.03
Ls 1.0000 500.00
JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 6.1.(1) Perkiraan Kuantitas :
: Lapis Resap Pengikat Total Harga :
: Liter % Harga Jumlah Seluruh :
KOMPONEN SATUAN PERKIRAAN HARGA
KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.0718 7,500.00


L.061 Jam 0.0120 12,000.00

JUMLAH HARGA TENAGA

M.061 Kg 0.6468 8,604.43


M.063 Liter 0.4840 6,000.00

JUMLAH HARGA BAHAN

E.030 Jam 0.0052 191,257.49


E.040 Jam 0.0036 89,789.78
E.080 Jam 0.0036 189,640.54
Ls 1.0000 400.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 6.3 Perkiraan Kuantitas :
: Lapis Aus Asphalt Beton (AC-BC) Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.2667 7,500.00


L.061 Jam 0.0381 12,000.00

JUMLAH HARGA TENAGA


asar Hotmix M.090 M3 0.9600 302,000.00
Halus Hotmix M.161 M3 0.7040 286,000.00
M.062 Kg 172.8000 821.23
M.061 Kg 176.4000 8,604.43

JUMLAH HARGA BAHAN

E.010 Jam 0.0381 4,393,108.93


E.020 Jam 0.0706 140,792.20
E.080 Jam 0.9111 189,640.54
E.120 Jam 0.0381 302,062.70
E.180 Jam 0.0089 177,571.03
matic Roller E.190 Jam 0.0118 152,727.28
E.220 Jam 0.0342 288,771.87
Ls 1.0000 5,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 7.1 (5) Perkiraan Kuantitas :
: Beton K-350 Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)
dak Terlatih L.101 Jam 3.6250 7,500.00
L.106 Jam 1.5000 10,000.00
L.061 Jam 0.3750 12,000.00

JUMLAH HARGA TENAGA

dy Mix K- 350 M555 M3 1.0000 1,330,757.27


M.191 M2 5.0000 8,627.50
Lbr 6.0000 5,075.00

JUMLAH HARGA BAHAN

Jam 0.3500 54,205.20


Jam 0.5000 116,590.62
Ls 1.0000 1,289.47

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 7.1 (6) Perkiraan Kuantitas :
: Beton K-300 Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 5.0000 7,500.00


L.106 Jam 1.7500 10,000.00
L.061 Jam 0.3750 12,000.00

JUMLAH HARGA TENAGA

dy Mix K- 300 M.196 M3 1.0000 1,205,820.00


M.191 M2 5.0000 8,627.50
Lbr 6.0000 5,075.00
0 M1 2.2400 0.00

JUMLAH HARGA BAHAN

Jam 0.3500 54,205.20


Ls 1.0000 15,000.00
JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


; 7.1.(8) Perkiraan Kuantitas :
: Beton K-175 Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 12.0635 7,500.00


L.106 Jam 7.2381 10,000.00
L.061 Jam 1.2063 12,000.00

JUMLAH HARGA TENAGA


M.080 Kg 305.2500 1,420.77
M.041 M3 0.5484 344,177.27
M.082 M3 0.8494 364,477.27
- Liter 30.0000 150.00

JUMLAH HARGA BAHAN

E.060 Jam 1.2063 24,342.28


E.070 Jam 1.2063 54,205.20
E.230 Jam 0.1067 203,933.53
Ls 1.0000 5,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 7.3.(1) Perkiraan Kuantitas :
: Besi Tulangan Total Harga :
: Kg % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.1050 7,500.00


L.106 Jam 0.0350 10,000.00
L.061 Jam 0.0350 12,000.00

JUMLAH HARGA TENAGA

M.167 Kg 1.1000 7,285.99


M.170 Kg 0.2200 14,672.73
JUMLAH HARGA BAHAN

Ls 1.0000 300.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 7.6.(7) Perkiraan Kuantitas :
: Pancang Kayu Ulin Total Harga :
: Titik % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 1.7500 7,500.00


L.106 Jam 0.5833 10,000.00
L.061 Jam 0.5833 12,000.00

JUMLAH HARGA TENAGA

M.070 Titik 1.0000 145,692.27


M.181 M3 0.0075 3,642,306.82

JUMLAH HARGA BAHAN

Ls 1.0000 1,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 7.5.(3). Perkiraan Kuantitas :
: Bronjong Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 35.0000 7,500.00


L.106 Jam 8.7500 10,000.00
L.061 Jam 4.3750 12,000.00

JUMLAH HARGA TENAGA

M.162 Kg 0.4200 27,635.68


M.010 M3 1.2000 227,627.27

JUMLAH HARGA BAHAN

Ls 1.0000 1,500.00
JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 6.5.(1) Perkiraan Kuantitas :
: Lapen Macadam Total Harga :
: M2 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 1.1852 7,500.00


L.106 Jam 1.1852 10,000.00
L.061 Jam 0.2963 12,000.00
JUMLAH HARGA TENAGA

M.023 M3 1.6667 303,320.45


M.025 M3 0.3889 331,920.45
M.061 Kg 63.2500 8,604.43

JUMLAH HARGA BAHAN

E.080 Jam 0.2111 189,640.54


E.220 Jam 0.0494 288,771.87
E.170 Jam 0.0635 177,571.03
E.030 Jam 0.0908 191,257.49
Ls 1.0000 7,500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan/M3 (D + E)
ATUAN Kegiatan/M2 (D x 0.05)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


7.10. Perkiraan Kuantitas :
: Pas. Batu Padas Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 8.7500 7,500.00


L.106 Jam 1.7500 10,000.00
L.061 Jam 1.7500 12,000.00

JUMLAH HARGA TENAGA

M.011 M3 1.1429 106,575.00


M.080 Kg 77.5000 1,420.77
M.040 M3 0.2041 130,000.00
JUMLAH HARGA BAHAN

Ls 1.0000 500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 1.2 (3) Perkiraan Kuantitas :
: Urugan Padas Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.2370 7,500.00


L.061 Jam 0.0593 12,000.00

JUMLAH HARGA TENAGA

M.011 M3 1.0000 106,575.00

JUMLAH HARGA BAHAN

E.080 Jam 0.0711 189,640.54


E.220 Jam 0.0593 288,771.87
E.240 Jam 0.0111 225,825.20
Ls 1.0000 2,100.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 6.1.(2) Perkiraan Kuantitas :
: Lapis Perekat Total Harga :
: Liter % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.1143 7,500.00


L.061 Jam 0.0190 12,000.00

JUMLAH HARGA TENAGA

M.061 Kg 0.4620 8,604.43


M.184 Liter 0.6600 6,000.00

JUMLAH HARGA BAHAN

E.030 Jam 0.0167 191,257.49


E.040 Jam 0.0048 89,789.78
E.080 Jam 0.0048 189,640.54
Ls 1.0000 450.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 5.5 (1) Perkiraan Kuantitas :
: Semen Untuk Pondasi Tanah Semen Total Harga :
: Ton % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 2.4300 7,500.00


L.061 Jam 0.1620 12,000.00

JUMLAH HARGA TENAGA

M.12 Kg 1,050.0000 1,420.77


JUMLAH HARGA BAHAN

E.080 Jam 0.4450 189,640.54

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 5.5 (2) Perkiraan Kuantitas :
: Lapis Pondasi Tanah Semen Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 1.2249 7,500.00


L.061 Jam 0.0178 12,000.00

JUMLAH HARGA TENAGA

M.08 M3 1.2000 37,606.25

JUMLAH HARGA BAHAN

E.080 Jam 0.2991 189,640.54


E.140 Jam 0.0084 337,729.37
E.230 Jam 0.0070 203,933.53
E.220 Jam 0.0182 288,771.87
E.180 Jam 0.0178 177,571.03
E.019 Jam 0.0086 152,727.28
E.025 Jam 0.0193 111,887.70
Ls 1.0000 3,500.00

JUMLAH HARGA PERALATAN


HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)
MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 6.3.(6) Perkiraan Kuantitas :
: Lapis Aus Aspal Beton (AC-WC) Total Harga :
: M2 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.0217 7,500.00


L.061 Jam 0.0022 12,000.00

JUMLAH HARGA TENAGA

M3 0.0240 340,000.00
M3 0.0600 340,000.00
M3 3.5020 821.23
Kg 2.8500 8,604.43

JUMLAH HARGA BAHAN

E.080 Jam 0.1847 189,640.54


E.012 Jam 0.0022 302,062.70
E.220 Jam 0.0015 288,771.87
E.180 Jam 0.0016 177,571.03
E.019 Jam 0.0023 152,727.28
E.001 Jam 0.0022 4,393,108.93
E.020 Jam 0.0027 140,792.20
Ls 1.0000 1,500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 7.1.(10) Perkiraan Kuantitas :
: Beton Bo Total Harga :
: M3 % Harga Jumlah Seluruh :
KOMPONEN SATUAN PERKIRAAN HARGA
KUANTITAS SATUAN
(Rp.)

L.061 Jam 0.3110 12,000.00


L.073 Jam 0.0833 10,700.00
L.101 Jam 1.2440 7,500.00
L.106 Jam 0.6220 10,000.00
JUMLAH HARGA TENAGA

M.041 M3 0.5389 344,177.27


M.080 Kg 325.0000 1,420.77
M.180 M3 0.0217 2,342,306.82
M.012 M3 0.7124 282,520.45

JUMLAH HARGA BAHAN

E.060 Jam 0.3110 24,342.28


E.070 Jam 0.3110 54,205.20
E.230 Jam 0.0597 10,559.64
Ls 1.0000 10,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 2.1.(2) Perkiraan Kuantitas :
: Galian Tanah Keras/Batu Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)
dak Terlatih L.101 Jam 2.4000 7,500.00
L.061 Jam 0.4000 12,000.00

JUMLAH HARGA TENAGA

JUMLAH HARGA BAHAN

E.080 Jam 0.2702 189,640.54


E.130 Jam 0.5000 7,739.45
E.040 Ls 0.5000 89,789.78
Ls 1.0000 4,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 3.4.(1) Perkiraan Kuantitas :
: Pembersihan Semak Damija Total Harga :
: M2 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.0280 7,500.00


L.061 Jam 0.0040 12,000.00
L.081 Jam 0.0080 13,000.00
L.089 Jam 0.0070 1,400.00
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN

E.140 Jam 0.0036 337,729.37


Ls 1.0000 250.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN
: Pembangunan Jalan Dan Jembatan
: Perkiraan Kuantitas :
: Kegiatan Plesteran Total Harga :
: M2 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.2500 7,500.00


L.061 Jam 0.1500 12,000.00
L.061 Jam 0.0100 13,000.00

JUMLAH HARGA TENAGA

Kg 8.0000 1,420.77
M3 0.1000 130,000.00

JUMLAH HARGA BAHAN

Ls 1.0000 2,700.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


:- Perkiraan Kuantitas :
: Bekisting Total Harga :
: M2 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 3.5000 7,500.00


L.106 Jam 0.5833 10,000.00
L.061 Jam 0.5833 12,000.00

JUMLAH HARGA TENAGA

anti /Perancah M.180 M3 0.0400 2,342,306.82


M.166 Kg 0.4000 15,455.68

JUMLAH HARGA BAHAN

Ls 1.0000 2,500.00
JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 7.1.(6a) Perkiraan Kuantitas :
: Joint Sealent + Kayu Segitiga Total Harga :
: M1 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.1750 7,500.00


L.061 Jam 0.0275 12,000.00
JUMLAH HARGA TENAGA

M.189 Kg 0.2000 9,349.40


M.190 Buah 0.0012 862,750.00
M.191 M1 1.0000 3,552.50

JUMLAH HARGA BAHAN

E.040 Jam 0.0333 89,789.78


Ls 1.0000 750.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 7.1.(7) Perkiraan Kuantitas :
: Beton K 250 Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 9.5238 7,500.00


L.106 Jam 4.4444 10,000.00
L.061 Jam 0.9524 12,000.00

JUMLAH HARGA TENAGA

M.080 Kg 425.0400 1,420.77


M.041 M3 0.6640 344,177.27
M.082 M3 0.6376 364,477.27
- Liter 30.0000 150.00
M.191 M2 5.0000 8,627.50

JUMLAH HARGA BAHAN

E.060 Jam 0.3175 24,342.28


E.070 Jam 0.3175 54,205.20
E.230 Jam 0.0294 203,933.53
Ls 1.0000 25,000.00
JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN
: Pembangunan Jalan Dan Jembatan
: 5.1.(2). Perkiraan Kuantitas :
: Lapis Pondasi Kelas C Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.1267 7,500.00


L.061 Jam 0.0181 12,000.00

JUMLAH HARGA TENAGA

M.035 M3 1.1000 141,177.27

JUMLAH HARGA BAHAN

E.080 Jam 0.1073 189,640.54


E.140 Jam 0.0130 337,729.37
E.230 Jam 0.0233 203,933.53
E.220 Jam 0.0181 288,771.87
E.240 Jam 0.0044 225,825.20
Ls 1.0000 4,000.00

JUMLAH HARGA PERALATAN


HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)
MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: Perkiraan Kuantitas :
: Urugan Pasir Total Harga :
: M3 % Harga Jumlah Seluruh :
KOMPONEN SATUAN PERKIRAAN HARGA
KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 1.0000 7,500.00


L.061 Jam 0.2500 12,000.00

JUMLAH HARGA TENAGA

M.081 M3 1.0500 130,000.00

JUMLAH HARGA BAHAN

Ls 1.0000 500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan Perkiraan Kuantitas :


: 5.1(3b) Total Harga :
: Telford Batu Padas % Harga Jumlah Seluruh :
: M3

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.2083 7,500.00


L.061 Jam 0.0208 12,000.00

JUMLAH HARGA TENAGA

M.010 M3 1.0000 106,575.00

JUMLAH HARGA BAHAN

E.080 Jam 0.2024 189,640.54


E.220 Jam 0.0104 288,771.87
E.170 Jam 0.0148 177,571.03
Ls 1.0000 500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 1.2 Perkiraan Kuantitas :
: Mobilisasi Total Harga :
: Unit % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

M2 400.00 0.00

antor (Barak Kerja)


M2 24.00 200,000.00

Direksi Teknis

- - - -

ama Proyek Buah 1.00 500,000.00


M2 25.00 1,500,000.00

LS 1.00 9,593,195.70
ATUAN Kegiatan

: 1.2-2
: MOBILISASI

Harga
JENIS ALAT KODE ALAT SATUAN Kuantitas Satuan
(Rp.)

ressor 4000-6500 L/m3 E.040 Unit 1.00 314,264.24


E.080 Unit 10.00 189,640.54
E.020 Unit 5.00 140,792.20
100 - 150 Hp E.050 Unit 1.00 1,296,400.70
ader > 100 HP E.140 Unit 1.00 1,182,052.78
80 - 140 Hp E.100 Unit 1.00 644,686.12
E.240 Unit 1.00 790,388.20
E.070 Unit 1.00 54,205.20
- Unit 1.00 816,134.32
E.250 Unit 1.00 111,887.70
E.230 Unit 1.00 713,767.37
E.270 Unit 1.00 1,069,042.67

ATUAN Kegiatan

BILL OF QUANTITY (BOQ)


FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 1.2 Perkiraan Kuantitas :
: Mobilisasi Total Harga :
: Unit % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

M2 400.00

antor (Barak Kerja)


M2 20.00

Direksi Teknis

- -

ran Pematokan LS 1.00


ama Proyek Buah 1.00
Set 1.00
Ls 1.00

LS 1.00
ATUAN Kegiatan

: 1.2-2
: MOBILISASI

Harga
JENIS ALAT KODE ALAT SATUAN Kuantitas Satuan
(Rp.)

E.070 Unit 1.00


E.080 Unit 8.00
E.060 Unit 1.00
E.090 Unit 5.00
E.260 Unit 1.00

ATUAN Kegiatan

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 1.2 Perkiraan Kuantitas :
: Mobilisasi Total Harga :
: Unit % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

M2 400.00 6,000.00

antor (Barak Kerja)


M2 20.00 200,000.00

Direksi Teknis

- - - -

ran Pematokan LS 1.00 300,000.00


ama Proyek Buah 1.00 500,000.00
Set 1.00 500,000.00
n Darurat/Sementara Unit 1.00 24,000,000.00
Unit 1.00 7,000,000.00

LS 1.00 2,302,324.30
ATUAN Kegiatan

: 1.2-2
: MOBILISASI

Harga
JENIS ALAT KODE ALAT SATUAN Kuantitas Satuan
(Rp.)

E.070 Unit 1.00 54,205.20


E.080 Unit 5.00 189,640.54
E.060 Unit 1.00 24,342.28
E.090 Unit 5.00 194,485.62
E.260 Unit 1.00 303,146.03

ATUAN Kegiatan

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 1.2 Perkiraan Kuantitas :
: Mobilisasi Total Harga :
: Ls % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

M2 400.00 6,000.00

antor (Barak Kerja)


M2 16.00 155,000.00

Direksi Teknis

- - - -

ran Pematokan LS 1.00 150,000.00


ama Proyek Buah 1.00 500,000.00
Set 1.00 352,500.00
Set 1.00 2,500,000.00

LS 1.00 2,472,584.54
ATUAN Kegiatan

: 1.2-2
: MOBILISASI

Harga
JENIS ALAT KODE ALAT SATUAN Kuantitas Satuan
(Rp.)

ressor 4000-6500 L/m3 E.070 Unit 1.00 54,205.20


E.080 Unit 10.00 189,640.54
E.060 Unit 1.00 24,342.28
oler 6 - 8 Ton E.090 Unit 1.00 194,485.62
ader > 100 HP E.260 Unit 1.00 303,146.03
c Tire Roler 8 - 10 Ton 0 Unit 1.00 -
0 Unit 1.00 -
0 Unit 1.00 -

ATUAN Kegiatan

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 1.2 Perkiraan Kuantitas :
: Mobilisasi Total Harga :
: Ls % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

M2 400.00 5,000.00

antor (Barak Kerja)


M2 24.00 150,000.00

Direksi Teknis

- - - -

ran Pematokan LS 1.00 150,000.00


ama Proyek Buah 1.00 500,000.00
Set 1.00 250,000.00
Set 1.00 4,000,000.00
n Sementara Set 1.00 11,716,000.00
LS 1.00 1,137,843.25
ATUAN Kegiatan

: 1.2-2
: MOBILISASI

Harga
JENIS ALAT KODE ALAT SATUAN Kuantitas Satuan
(Rp.)

E.080 Unit 6.00 189,640.54

ATUAN Kegiatan

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN
: Pembangunan Jalan Dan Jembatan
: 1.2 Perkiraan Kuantitas :
: Mobilisasi Total Harga :
: Ls % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

M2 400.00 0.00

antor (Barak Kerja)


M2 24.00 150,000.00

Direksi Teknis

- - - -

ran Pematokan LS 1.00 150,000.00


ama Proyek Buah 1.00 500,000.00
Set 1.00 246,000.00
Set 1.00 0.00

LS 1.00 812,767.36
ATUAN Kegiatan

: 1.2-2
: MOBILISASI

Harga
JENIS ALAT KODE ALAT SATUAN Kuantitas Satuan
(Rp.)

ressor 4000-6500 L/m3 E.070 Unit 1.00 54,205.20


E.080 Unit 4.00 189,640.54
E.060 Unit 1.00 -
oler 6 - 8 Ton E.090 Unit 1.00 -
ader > 100 HP E.260 Unit 1.00 -
c Tire Roler 8 - 10 Ton 0 Unit 1.00 -
0 Unit 1.00 -
0 Unit 1.00 -

ATUAN Kegiatan

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN
: Pembangunan Jalan Dan Jembatan
: 7.12.(2) Perkiraan Kuantitas :
: Bearing Pad (406 x 406 x 50) Total Harga :
: Buah % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 4.0000 7,500.00


L.106 Jam 0.4000 10,000.00
L.061 Jam 0.0400 12,000.00

JUMLAH HARGA TENAGA

ad Uk. 406 x 406 x 50 Buah 1.0000 2,283,750.00


Ls 1.0000 25,000.00

JUMLAH HARGA BAHAN

Ls 1.0000 2,500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan Perkiraan Kuantitas :


: 7.6.(8) Total Harga :
: Pemancangan Tiang Pancang Beton □ 30 x 30 Cm % Harga Jumlah Seluruh :
:M

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 3.5000 7,500.00


L.061 Jam 0.3500 12,000.00

JUMLAH HARGA TENAGA

M.197 Kg 0.2450 50,750.00

JUMLAH HARGA BAHAN

E.270 Jam 0.1042 213,808.53


E.280 Jam 0.4286 45,802.70
Ls 1.0000 5,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan Perkiraan Kuantitas :


: 7.12.(5) Total Harga :
: Expantion Joint % Harga Jumlah Seluruh :
:M

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 1.7500 7,500.00


L.061 Jam 0.3500 12,000.00
JUMLAH HARGA TENAGA

M.197 Kg 0.5556 313,727.27


100.100.10 mm M.197 M1 0.5556 152,250.00
- Ls 1.0000 35,000.00

JUMLAH HARGA BAHAN

E.280 Jam 0.2000 134,964.20


Ls 1.0000 200.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: - Perkiraan Kuantitas :
: Pengecatan Besi Sekur Total Harga :
: M2 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 3.0000 7,500.00


L.106 Jam 0.3000 10,000.00
L.061 Jam 0.0300 12,000.00

JUMLAH HARGA TENAGA

Korosit Mutu Tinggi Kg 0.2000 120,000.00


Liter 0.0900 45,000.00

JUMLAH HARGA BAHAN

Ls 1.0000 2,500.00

JUMLAH HARGA PERALATAN


HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)
MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
REKAMAN ANALISA HARGA SATUAN
: Pembangunan Jalan Dan Jembatan
: 2.2 Perkiraan Kuantitas :
: Pasangan Batu Dengan Mortar Total Harga :
: M3 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 14.0000 7,500.00


L.106 Jam 7.0000 10,000.00
L.061 Jam 1.4000 12,000.00

JUMLAH HARGA TENAGA

M.010 M3 0.9108 227,627.27


M.080 Kg 186.0496 1,420.77
M.040 M3 0.3100 130,000.00

JUMLAH HARGA BAHAN

Ls 1.0000 5,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 1.2 Perkiraan Kuantitas :
: Mobilisasi Total Harga :
: Unit % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

antor (Barak Kerja)

Direksi Teknis

- - - -

ama Proyek Buah 1.00 600,000.00

LS 1.00 4,722,566.12
ATUAN Kegiatan

: 1.2-2
: MOBILISASI

Harga
JENIS ALAT KODE ALAT SATUAN Kuantitas Satuan
(Rp.)

ressor 4000-6500 L/m3 E.040 Unit 1.00 314,264.24


E.080 Unit 5.00 189,640.54
oler 6 - 8 Ton E.050 Unit 1.00 1,296,400.70
ader > 100 HP E.140 Unit 1.00 1,182,052.78
E.240 Unit 1.00 790,388.20
E.030 Unit 1.00 191,257.49
ATUAN Kegiatan

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 1.2 Perkiraan Kuantitas :
: Mobilisasi Total Harga :
: Unit % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

M2

antor (Barak Kerja)


M2

Direksi Teknis

- - - -

ama Proyek Buah 1.00 600,000.00

LS 1.00 4,138,035.74
ATUAN Kegiatan

: 1.2-2
: MOBILISASI

Harga
JENIS ALAT KODE ALAT SATUAN Kuantitas Satuan
(Rp.)

ressor 4000-6500 L/m3 E.040 Unit 1.00 314,264.24


E.080 Unit 4.00 189,640.54
E.090 Unit 5.00 194,485.62
E.070 Unit 1.00 184,196.03
ader > 100 HP E.240 Unit 1.00 790,388.20
E.250 Unit 1.00 302,062.70
- Unit 1.00 816,134.32
ATUAN Kegiatan

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 1.2 Perkiraan Kuantitas :
: Mobilisasi Total Harga :
: Unit % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

M2 400.00 5,000.00

antor (Barak Kerja)


M2 16.00 160,000.00

Direksi Teknis

- - - -

ran Pematokan LS 1.00 300,000.00


ama Proyek Buah 1.00 500,000.00
Set 1.00 322,000.00

LS 1.00 4,877,217.60
ATUAN Kegiatan

: 1.2-2
: MOBILISASI

Harga
JENIS ALAT KODE ALAT SATUAN Kuantitas Satuan
(Rp.)

ressor 4000-6500 L/m3 E.040 Unit 1.00 314,264.24


E.080 Unit 12.00 189,640.54
E.090 Unit 1.00 194,485.62
oler 6 - 8 Ton E.070 Unit 1.00 184,196.03
ader > 100 HP E.240 Unit 1.00 790,388.20
c Tire Roler 8 - 10 Ton E.250 Unit 1.00 302,062.70
- Unit 1.00 816,134.32
ATUAN Kegiatan

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 11.1 Perkiraan Kuantitas :
: Pekerjaan Paving Total Harga :
: M2 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 1.0000 7,500.00


L.061 Jam 0.3333 10,000.00
L.106 Jam 0.0250 12,000.00

JUMLAH HARGA TENAGA

M.050 M3 0.0425 37,606.25


M.081 M3 0.0425 37,606.25
- M2 35.0000 2,750.00

JUMLAH HARGA BAHAN


Ls 1.0000 500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: - Perkiraan Kuantitas :
: Pengecatan Lenning Total Harga :
: M2 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 2.5000 7,500.00


L.106 Jam 0.2500 10,000.00
L.061 Jam 0.0250 12,000.00

JUMLAH HARGA TENAGA

ok Anti Lumut Kg 0.2000 65,000.00

JUMLAH HARGA BAHAN

Ls 1.0000 2,500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)

ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 6.3.(2) Perkiraan Kuantitas :
: Latasir (SS-B) Total Harga :
: M2 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 1.1852 7,500.00


0.00 Jam 0.1975 10,000.00
L.061 Jam 0.0988 12,000.00

JUMLAH HARGA TENAGA

M.026 M3 0.3333 821.23


M.061 Kg 63.2500 8,604.43

JUMLAH HARGA BAHAN

E.080 Jam 0.2037 189,640.54


E.220 Jam 0.0494 288,771.87
E.170 Jam 0.0222 177,571.03
E.030 Jam 0.0908 191,257.49
Ls 1.0000 7,500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan/M3 (D + E)
ATUAN Kegiatan/M2 (D x 0.05)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


: 11.2 Perkiraan Kuantitas :
: Kerb Beton K350 Total Harga :
: M1 % Harga Jumlah Seluruh :

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)
L.061 Jam 0.2827 12,000.00
L.101 Jam 1.1309 7,500.00
0.00 Jam 0.5655 10,000.00

JUMLAH HARGA TENAGA

- Buah 2.0000 50,000.00


M.041 M3 0.0200 344,177.27
M.080 Kg 0.0500 1,420.77

JUMLAH HARGA BAHAN

E.060 Jam 0.2827 24,342.28


Ls 1.0000 2,500.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan Perkiraan Kuantitas :


: 7.1(5b) Total Harga :
: Pipa PVC 1" % Harga Jumlah Seluruh :
: M1

KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

dak Terlatih L.101 Jam 0.0560 7,500.00


L.061 Jam 0.0280 12,000.00

JUMLAH HARGA TENAGA

M.193 M1 1.0000 12,687.50


JUMLAH HARGA BAHAN

Jam 0.0571 5,000.00

JUMLAH HARGA PERALATAN

HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


MUM DAN KEUNTUNGAN 10 % x D
ATUAN Kegiatan (D + E)
METODE PELAKSAN

Kegiatan : Pembangunan Jalan Dan Jembatan


Item Pembayaran : 2.1
Jenis Kegiatan : Galian Manual
1.00 M3 Satuan Pembayaran : M3

NO URAIAN

JUMLAH
HARGA I ASUMSI
(Rp.) 1 Menggunakan alat berat (cara mekanik)
2 Lokasi Kegiatan : sepanjang jalan
3 Kondisi jalan : sedang / baik
1,568.63 4 Jam kerja efektif per hari
836.60 5 Faktor pengembangan material

II METODE PELAKSANAAN
2,405.23 1 Penggalian di lakukan dengan menggunakan Tenaga Manusia
2 Sekelompok pekerjan akan melakukan penggalian
3 Sekelompok pekerjan akan merapikan hasil galian
4 Sisa galian dia angkat ke atas Truck dan di buang ke tempat terentu
dan diijinkan oleh Direksi

1 ALAT BANTU
Di Perlukan Alat-Alat Bantu Kecil
- Cangkul
- Sekop
- Keranjang + Sapu
2 TENAGA
Produksi Menentukan =
16,000.92 Produksi Per Hari = Tk x Q1
12,841.55 Kebutuhan Tenaga
2,000.00 - Pekerja Tidak Terlatih
- Mandor
Koefisien Tenaga / M3
- Pekerja Tidak Terlatih= (Tk x P) : Qt
- Mandor = (Tk x M) : Qt

30,842.47

33,247.70
3,324.77
36,572.47

Catatan = Lr di sesuaikan dengan kondisi setempat (lihat INFORMASI UMUM)


1.00 M3

JUMLAH
HARGA
(Rp.)

105,000.00
70,000.00
16,800.00

191,800.00

216,336.96
215,648.29
37,978.06

469,963.31

5,000.00

5,000.00

666,763.31
66,676.33
733,439.65

1.00 M3

JUMLAH
HARGA
(Rp.)

2,091.50
836.60

2,928.10
23,489.65
12,841.55
5,000.00

41,331.20

44,259.31
4,425.93
48,685.24
1.00 M3

JUMLAH
HARGA
(Rp.)

803.21
214.19

1,017.40

19474.0948002259
0.00

5,154.34
2,561.26
3,172.30
2,352.35
2,500.00

15,740.25

16,757.65
1,675.77
18,433.42
1.00 M3

JUMLAH
HARGA
(Rp.)

190.48
76.19

266.67

45,127.50

45,127.50

4,964.73
1,433.27
1,500.00

7,898.00

53,292.17
5,329.22
58,621.38
1.00 M2

JUMLAH
HARGA
(Rp.)

133.33
53.33

186.67

603.09
4,078.67
1,003.67
400.00

6,085.43
6,272.09
627.21
6,899.30
1.00 M3

JUMLAH
HARGA
(Rp.)

311.42
71.18

382.60

60,727.50

60,727.50

3,289.39
1,437.95
3,358.91
1,712.93
1,856.95
200.00

11,856.13

72,966.23
7,296.62
80,262.86
1.00 M3
JUMLAH
HARGA
(Rp.)

617.28
246.91

864.20

343,200.00

343,200.00

23,119.76
3,040.26
4,956.72
5,941.81
2,740.29
200.00

39,998.84

384,063.03
38,406.30
422,469.34
1.00 M3

JUMLAH
HARGA
(Rp.)

294.12
156.86

450.98
265,200.00
142,800.00

408,000.00

13,979.91
6,840.58
4,956.72
3,774.80
1,003.67
2,000.00

32,555.68

441,006.66
44,100.67
485,107.32
1.00 M3

JUMLAH
HARGA
(Rp.)

493.83
98.77

592.59

291,720.00
51,480.00
343,200.00

6,341.61
1,608.24
3,358.91
2,376.72
1,003.67
500.00

15,189.14

358,981.74
35,898.17
394,879.91
1.00 M3

JUMLAH
HARGA
(Rp.)

845.49
135.28

980.77

273,152.73

273,152.73

9,641.22 6.67
1,627.69 766,000.00
1,782.84
500.00
13,551.75

287,685.24
28,768.52
316,453.76
1.00 Liter
JUMLAH
HARGA
(Rp.)

538.78
143.67

682.45

5,565.35
2,904.00

8,469.35

1,001.82
320.68
677.29
400.00

2,399.79

11,551.59
1,155.16
12,706.74
1.00 M3

JUMLAH
HARGA
(Rp.)

2,000.00
457.14

2,457.14
289,920.00
201,344.00
141,908.07
1,517,821.77

2,150,993.85

167,356.53
9,938.27
172,783.60
11,507.15
1,578.41
1,796.79
9,868.75
5,000.00

379,829.51

2,533,280.49
253,328.05
2,786,608.54
1.00 M3

JUMLAH
HARGA
(Rp.)
27,187.50
15,000.00
4,500.00

46,687.50

1,330,757.27
43,137.50
30,450.00

1,404,344.77

18,971.82
58,295.31
1,289.47

78,556.60

1,529,588.87
152,958.89
1,682,547.76
1.00 M3

JUMLAH
HARGA
(Rp.)

37,500.00
17,500.00
4,500.00

59,500.00

1,205,820.00
43,137.50
30,450.00
0.00

1,279,407.50

18,971.82
15,000.00
33,971.82

1,372,879.32
137,287.93
1,510,167.25

1.00 M3

JUMLAH
HARGA
(Rp.)

90,476.19
72,380.95
14,476.19

177,333.33
433,690.88
188,730.74
309,603.19
4,500.00

936,524.81

29,365.29
65,390.40
21,752.91
5,000.00

121,508.60

1,235,366.75
123,536.67
1,358,903.42
1.00 Kg

JUMLAH
HARGA
(Rp.)

787.50
350.00
420.00

1,557.50

8,014.59
3,228.00

;
11,242.59

300.00

300.00

13,100.09
1,310.01
14,410.10

1.00 Titik

JUMLAH
HARGA
(Rp.)

13,125.00
5,833.33
7,000.00

25,958.33

145,692.27
27,317.30

173,009.57

1,000.00

1,000.00

199,967.91
19,996.79
219,964.70
1.00 M3

JUMLAH
HARGA
(Rp.)

262,500.00
87,500.00
52,500.00

402,500.00

11,606.99
273,152.73

284,759.71

1,500.00
1,500.00

688,759.71
68,875.97
757,635.69

1.00 M2

JUMLAH
HARGA
(Rp.)

8,888.89
11,851.85
3,555.56
24,296.30

505,534.09
129,080.18
544,230.31

1,178,844.58

40,035.23
14,260.34
11,274.35
17,358.35
7,500.00

90,428.27

1,293,569.15
129,356.91
1,422,926.06
71,146.30
1.00 M3

JUMLAH
HARGA
(Rp.)

65,625.00
17,500.00
21,000.00

104,125.00

121,800.00
110,109.89
26,530.61
258,440.50

500.00

500.00

363,065.50
36,306.55
399,372.05

1.00 M3

JUMLAH
HARGA
(Rp.)

1,777.78
711.11

2,488.89

106,575.00

106,575.00

13,485.55
17,112.41
2,509.17
2,100.00

35,207.13

144,271.01
14,427.10
158,698.12
1.00 Ltr

JUMLAH
HARGA
(Rp.)

857.14
228.57

1,085.71

3,975.25
3,960.00

7,935.25

3,187.62
427.57
903.05
450.00

4,968.25

13,989.21
1,398.92
15,388.13
Ton

JUMLAH
HARGA
(Rp.)

18,225.00
1,944.00

20,169.00

1,491,811.36
1,491,811.36

84,390.04

84,390.04

1,596,370.40
159,637.04
1,756,007.44
M3

JUMLAH
HARGA
(Rp.)

9,186.75
213.60

9,400.35

45,127.50

45,127.50

56,721.49
2,825.71
1,433.22
5,241.82
3,169.21
1,308.49
2,156.66
3,500.00

76,356.61
130,884.46
13,088.45
143,972.91
M2

JUMLAH
HARGA
(Rp.)

162.75
26.40

189.15

8,160.00
20,400.00
2,875.94
24,522.63

55,958.57

35,033.59
655.08
429.53
285.25
350.49
9,527.25
380.14
1,500.00

48,161.33

104,309.05
10,430.91
114,739.96
M3
JUMLAH
HARGA
(Rp.)

3,731.98
891.31
9,329.94
6,219.96
20,173.19

185,484.76
461,751.14
50,828.06
201,262.19

899,326.14

7,570.40
16,857.71
630.40
10,000.00

35,058.51

954,557.84
95,455.78
1,050,013.62
1.00 M3

JUMLAH
HARGA
(Rp.)
18,000.00
4,800.00

22,800.00

51,241.26
3,869.73
44,894.89
4,000.00

104,005.87

126,805.87
12,680.59
139,486.46
1.00 M2

JUMLAH
HARGA
(Rp.)

210.00
48.00
104.00
9.80
371.80
1,231.61
250.00

1,481.61

1,853.41
185.34
2,038.75
1.00 M2

JUMLAH
HARGA
(Rp.)

1,875.00
1,800.00
130.00

3,805.00

11,366.18
13,000.00

24,366.18

2,700.00

2,700.00

30,871.18
3,087.12
33,958.30

1.00 M2

JUMLAH
HARGA
(Rp.)

26,250.00
5,833.33
7,000.00

39,083.33

93,692.27
6,182.27

99,874.55

2,500.00
2,500.00

141,457.88
14,145.79
155,603.67

JUMLAH
HARGA
(Rp.)

1,312.50
330.00
1,642.50

1,869.88
1,035.30
3,552.50

6,457.68

2,992.99
750.00

3,742.99

11,843.17
1,184.32
13,027.49
1.00 M3

JUMLAH
HARGA
(Rp.)

71,428.57
44,444.44
11,428.57

127,301.59

603,885.24
228,517.22
232,376.13
4,500.00
43,137.50

1,112,416.09

7,727.71
17,208.00
5,998.05
25,000.00
55,933.75

1,295,651.43
129,565.14
1,425,216.58
1.00 M3

JUMLAH
HARGA
(Rp.)

950.62
217.28

1,167.90

155,295.00

155,295.00

20,345.39
4,377.97
4,758.45
5,228.79
1,003.67
4,000.00

39,714.27
196,177.17
19,617.72
215,794.89
1.00 M3
JUMLAH
HARGA
(Rp.)

7,500.00
3,000.00

10,500.00

136,500.00

136,500.00

500.00

500.00

147,500.00
14,750.00
162,250.00
1.00 M3

JUMLAH
HARGA
(Rp.)

1,562.50
250.00

1,812.50

106,575.00

106,575.00

38,374.32
3,008.04
2,630.68
500.00

44,513.04

152,900.54
15,290.05
168,190.60
JALAN PENDEKAT MAHKOTA

JUMLAH
HARGA
(Rp.)

- #REF!

9,593,195.70 4,388,230.30

4,800,000.00 4,800,000.00

- #REF!

-
500,000.00 500,000.00
37,500,000.00 37,500,000.00
4,388,230.30

9,593,195.70
61,986,391.40 #REF!

JUMLAH
HARGA
(Rp.)

-
-
314,264.24 314,264.24
1,896,405.41 1,896,405.41
703,961.00 703,961.00
1,296,400.70 1,296,400.70
1,182,052.78 177,198.95
644,686.12
790,388.20
54,205.20
816,134.32
111,887.70
713,767.37
1,069,042.67

9,593,195.70 4,388,230.30
JALAN TURAP

JUMLAH
HARGA
(Rp.)

#REF!

#REF!

-
-
-
-
#REF!

JUMLAH
HARGA
(Rp.)

-
-
-
-
-
-
-

-
JEMBATAN BENANGA

JUMLAH
HARGA
(Rp.)

2,400,000.00 #REF!

2,302,324.30 1,999,178.27

4,000,000.00 4,000,000.00

- #REF!

300,000.00 300,000.00
500,000.00 500,000.00
500,000.00 500,000.00
24,000,000.00 1,999,178.27
7,000,000.00

2,302,324.30
43,304,648.61 #REF!

JUMLAH
HARGA
(Rp.)

-
-
54,205.20 54,205.20
948,202.70 948,202.70
24,342.28 24,342.28
972,428.08 972,428.08
303,146.03 -

2,302,324.30 1,999,178.27
JEMBATAN UNMUL
Ls

JUMLAH
HARGA
(Rp.)

2,400,000.00 #REF!

2,472,584.54 2,169,438.51

2,480,000.00 2,480,000.00

- #REF!

150,000.00 150,000.00
500,000.00 500,000.00
352,500.00 352,500.00
2,500,000.00 2,169,438.51

2,472,584.54
13,327,669.09 #REF!

JUMLAH
HARGA
(Rp.)

-
-
54,205.20 54,205.20
1,896,405.41 1,896,405.41
24,342.28 24,342.28
194,485.62 194,485.62
303,146.03 -
-
-
-

2,472,584.54 2,169,438.51
JEMBATAN KAPIH
Ls

JUMLAH
HARGA
(Rp.)

2,000,000.00 #REF!

1,137,843.25 1,137,843.25

3,600,000.00 3,600,000.00

- #REF!

150,000.00 150,000.00
500,000.00 500,000.00
250,000.00 250,000.00
4,000,000.00 1,137,843.25
11,716,000.00
1,137,843.25
24,491,686.49 #REF!

JUMLAH
HARGA
(Rp.)

-
-
-
1,137,843.25 1,137,843.25
-
-
-

1,137,843.25 1,137,843.25
JEMBATAN SEGIRI
Ls Jln Elang, Puspita

JUMLAH
HARGA
(Rp.)

- #REF!

812,767.36 812,767.36

3,600,000.00 3,600,000.00

- #REF!

150,000.00 150,000.00
500,000.00 500,000.00
246,000.00 246,000.00
- 812,767.36

812,767.36
6,121,534.73 #REF!

JUMLAH
HARGA
(Rp.)

-
-
-
54,205.20 54,205.20
758,562.16 758,562.16
- -
- -
-
-
-
-

812,767.36 812,767.36
1.00 Buah

JUMLAH
HARGA
(Rp.)

30,000.00
4,000.00
480.00

34,480.00

2,283,750.00
25,000.00

2,308,750.00

2,500.00

2,500.00

2,345,730.00
234,573.00
2,580,303.00

1.00 M

JUMLAH
HARGA
(Rp.)

26,250.00
4,200.00

30,450.00

12,433.75

12,433.75

22,271.72
19,629.73
5,000.00

46,901.45

89,785.20
8,978.52
98,763.72

1.00 M

JUMLAH
HARGA
(Rp.)

13,125.00
4,200.00
17,325.00

174,292.93
84,583.33
35,000.00

293,876.26

26,992.84
200.00

27,192.84

338,394.10
33,839.41
372,233.51
1.00 M2

JUMLAH
HARGA
(Rp.)

22,500.00
3,000.00
360.00

25,860.00

24,000.00
4,050.00

28,050.00

2,500.00

2,500.00
56,410.00
5,641.00
62,051.00
1.00 M3

JUMLAH
HARGA
(Rp.)

105,000.00
70,000.00
16,800.00

191,800.00

207,322.92
264,334.20
40,295.17

511,952.29

5,000.00

5,000.00

708,752.29
70,875.23
779,627.52

JALAN ANGGI

JUMLAH
HARGA
(Rp.)

#REF!

4,722,566.12 3,740,920.43

- #REF!

-
600,000.00 600,000.00
-
3,740,920.43

4,722,566.12
10,045,132.24 #REF!

JUMLAH
HARGA
(Rp.)

-
-
314,264.24 314,264.24
948,202.70 948,202.70
1,296,400.70 1,296,400.70
1,182,052.78 1,182,052.78
790,388.20 -
191,257.49
4,722,566.12 3,740,920.43

JALAN ANGGI BETON

JUMLAH
HARGA
(Rp.)

#REF!

4,138,035.74 2,229,450.52

- #REF!

-
600,000.00 600,000.00
-
2,229,450.52

4,138,035.74
8,876,071.48 #REF!

JUMLAH
HARGA
(Rp.)

-
-
314,264.24 314,264.24
758,562.16 758,562.16
972,428.08 972,428.08
184,196.03 184,196.03
790,388.20 -
302,062.70
816,134.32
4,138,035.74 2,229,450.52

LOKASI TERSEBAR

JUMLAH
HARGA
(Rp.)

2,000,000.00 #REF!

4,877,217.60 2,968,632.38

2,560,000.00 2,560,000.00

- #REF!

300,000.00 300,000.00
500,000.00 500,000.00
322,000.00 322,000.00
2,968,632.38

4,877,217.60
15,436,435.20 #REF!

JUMLAH
HARGA
(Rp.)

-
-
314,264.24 314,264.24
2,275,686.49 2,275,686.49
194,485.62 194,485.62
184,196.03 184,196.03
790,388.20 -
302,062.70
816,134.32
4,877,217.60 2,968,632.38

1.00 M2

JUMLAH
HARGA
(Rp.)

7,500.00
3,333.33
300.00

11,133.33

1,598.27
1,598.27
96,250.00

99,446.53
500.00

500.00

111,079.86
11,107.99
122,187.85

1.00 M2

JUMLAH
HARGA
(Rp.)

18,750.00
2,500.00
300.00

21,550.00

13,000.00

13,000.00

2,500.00

2,500.00

37,050.00
3,705.00
40,755.00

1.00 M2
JUMLAH
HARGA
(Rp.)

8,888.89
1,975.31
1,185.19

12,049.38

273.74
544,230.31

544,504.05

38,630.48
14,260.34
3,946.02
17,358.35
7,500.00

81,695.20

638,248.63
63,824.86
702,073.50
35,103.67
M1

JUMLAH
HARGA
(Rp.)
3,392.71
8,481.76
5,654.51

17,528.98

100,000.00
6,883.55
71.04

106,954.58

6,882.18
2,500.00

9,382.18

133,865.75
13,386.57
147,252.32
1.00 M1

JUMLAH
HARGA
(Rp.)

420.00
336.00

756.00

12,687.50
12,687.50

285.71

285.71

13,729.21
1,372.92
15,102.14
METODE PELAKSANAAN

Kegiatan
Item Pembayaran
Jenis Kegiatan
Satuan Pembayaran
KODE KOEFISIEN SATUAN KET

NO

A.
Tk 7.00 Jam 1
Fk 1.20 --- 2

kan Tenaga Manusia

i buang ke tempat terentu


Lpmb 1.00 Km

Q1 1.00 M3/Jam 1
Qt 7.00 M3

P 5.00 orang
M 1.00 orang
L.101 5.0000 Jam
L.061 1.0000 Jam

D.
E.
F.

ORMASI UMUM)
ENGINEER'S ESTIMATE

FORMULIR STANDAR UNTUK


REKAMAN ANALISA HARGA SATUAN

: Pembangunan Jalan Dan Jembatan


Item Pembayaran : 2.1 Perkiraan Kuantitas
Jenis Kegiatan : Galian Manual Total Harga
Satuan Pembayaran : M3 % Harga Jumlah Seluruh

KOMPONEN SATUAN PERKIRAAN


KUANTITAS

TENAGA
Pekerja Tidak Terlatih L.101 Jam 5.0000
Mandor L.061 Jam 1.0000

JUMLAH HARGA TENAGA

JUMLAH HARGA BAHAN

Alat Bantu Ls 1.0000


JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN


BIAYA UMUM DAN KEUNTUNGAN
HARGA SATUAN Kegiatan
ENGINEER'S ESTIMATE
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN

Kegiatan : Pembangunan Jalan Poros Siliwangi Sidodadi Desa Senipa


Item Pembayaran : 1.2
Jenis Kegiatan : Mobilisasi
Satuan Pembayaran : Unit

NO KOMPONEN

A. Sewa Tanah
B. Peralatan
Lihat Lembar 1.2-2
C. Fasilitas Kantor (Barak Kerja)
-Barak Kerja

D. Fasilitas Direksi Teknis


-Kantor
E. Mobilisasi Lain
F. Lain -Lain
- Pengukuran Pematokan
- Papan Nama Proyek
- Laporan Priodik Dan Administrasi
- As Build Drawings
G. Demobilisasi
H. HARGA SATUAN Kegiatan

Pembayaran No : : 1.2
Kegiatan : MOBILISASI

NO JENIS ALAT

1 Asphat Mixing Plant


2 Asphalt Finisher
3 Asphalt Sprayer
4 Air Compressor 4000-6500 L/m3
5 Bulldozer 100-150 HP
6 Concrete Mixer 0,3-0,6 m3
7 Concrete Vibrator
#REF! Excavator 80-140 HP
#REF! Generator Set
#REF! Tire Roller 8-10 Ton
#REF! Tamper Vibrator Plate
#REF! Water Pump 70-100 mm
#REF! Water Tanker 3000-4500 Liter
#REF! Vibratory Roller 5-8 Ton
#REF! Concrete Cuter
#REF! Fulvi Mixer
C. HARGA SATUAN Kegiatan
ATE

UNTUK DIREKTORAT JENDERAL BINA MARGA


GA SATUAN DIREKTORAT BINA Program JALAN
SUB. DIT PERENCANAAN JALAN
LOKAL DAN KABUPATEN
PROPINSI KODE
: 1.00 M3 KALIMANTAN TIMUR
:
mlah Seluruh : NO KOMPONEN

HARGA JUMLAH
SATUAN HARGA 1 1 Titik Pancangan (1.a. + 1.b. + 1.c.)
(Rp.) (Rp.) 1.a. 1 Titik Kepala & meruncing Tiang
Tukang Orang
Kepala Tukang Orang
7,500.00 37,500.00 Pekerja Tak Terlatih Orang
12,000.00 12,000.00 Mandor Orang
1.b. 1 Titik Memancang Kedalaman 4 m
Tukang Orang
ARGA TENAGA 49,500.00 Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
1.c. 1 Titik Menumbuk Tiang
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
2 1 m3 Kegiatan Kasar Gelagar
Tukang Orang
Kepala Tukang Orang
ARGA BAHAN Pekerja Tak Terlatih Orang
Mandor Orang
1,500.00 1,500.00 Kayu Ulin M3
Paku Ulin Kg
3 1 m2 Papan Lantai Jembatan
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
Paku Ulin Kg

ARGA PERALATAN 1,500.00

(A + B + C) 51,000.00 Perhitungan
10 % x D 5,100.00 Tiang Pancang 10/10 =
(D + E) 56,100.00 Sloop 10/10 =
Gelagar 10/10 =
Balok 5/10 =
Papan lantai 5/20 =
Papan Turap 3/20 =
Plat Beugel =
Bout =
Kebutuhan Biaya Pembulatan 1 Buah Goron

DIREKTORAT JENDERAL BINA MARGA


DIREKTORAT BINA Program JALAN
SUB. DIT PERENCANAAN JALAN
LOKAL DAN KABUPATEN

PROPINSI KODE
KALIMANTAN TIMUR

NO KOMPONEN

1 1 Titik Pancangan (1.a. + 1.b. + 1.c.)


1.a. 1 Titik Kepala & meruncing Tiang

Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
1.b. 1 Titik Memancang Kedalaman 4 m
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
1.c. 1 Titik Menumbuk Tiang
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
2 1 m3 Kegiatan Kasar Gelagar
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
Paku Ulin Kg
3 1 m2 Papan Lantai Jembatan
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
Paku Ulin Kg

Perhitungan
Tiang Pancang 15/15 =
Sloop 15/15 =
Balok, dll =
Papan lantai 5/20 =
Papan Turap 3/20 =
Plat Beugel =
Bout =

62.000 (2/20)
25.000 (5/20)
71.000 (5/7)
50.000 (5/10)
34.000 (6/12)
39.000 (8/8)
25.000 (10/10)

DINAS BINA MARGA


DAN PENGAIRAN KOTA
SAMARINDA
KABUPATEN / KOTA
PROPINSI KODE
KALIMANTAN TIMUR

NO KOMPONEN

1 1 Titik Pancangan (1.a. + 1.b. + 1.c.)


1.a. 1 Titik Kepala & meruncing Tiang
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
1.b. 1 Titik Memancang Kedalaman 4 m
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
1.c. 1 Titik Menumbuk Tiang
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
2 1 m3 Kegiatan Sloof
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
Paku Ulin Kg
3 1 m2 Papan Turap Ulin
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
Paku Ulin Kg

Perhitungan
Tiang Pancang 10/10 =

Papan Dinding 5/20 =

Baut =
Kebutuhan Biaya Pembuatan Turap Kayu

DIREKTORAT JENDERAL BINA MARGA


DIREKTORAT BINA Program JALAN
SUB. DIT PERENCANAAN JALAN
LOKAL DAN KABUPATEN

PROPINSI KODE
KALIMANTAN TIMUR

NO KOMPONEN

1 1 M3 Mengerjakan Gelagar Kayu Ulin 25/2


Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
2 1 M3 Mengerjakan Gelagar Kayu Ulin 10/1
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
3 1 M3 Mengerjakan Balok Pengaku, Suai, Ba
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
4 1 M3 Mengerjakan Lantai Ulin, Papan Railin
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3
Paku Ulin Kg
5 1 M3 Balok Klam Penyambung 10/30 Cm
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3

Perhitungan
Gelagar 25/25 =

Gelagar 10/10 =
Balok Pengaku, dll =
Papan lantai 5/20 =
Balok Klam 10/30 =
Plat Beugel =
Baut =

DINAS BINA MARGA


DAN PENGAIRAN KOTA
SAMARINDA
KABUPATEN / KOTA
PROPINSI KODE
KALIMANTAN TIMUR

NO KOMPONEN

1 1 Titik Pancangan (1.a. + 1.b. + 1.c.)


1.a. 1 Titik Kepala & meruncing Tiang
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
1.b. 1 Titik Memancang Kedalaman 8 m
Tukang Orang
Kepala Tukang Orang
Pekerja Tak Terlatih Orang
Mandor Orang
Kayu Ulin M3

Perhitungan
Tiang Pancang 25/25 =
ENGINEER'S ESTIMATE
RMULIR STANDAR UNTUK
MAN ANALISA HARGA SATUAN

nan Jalan Poros Siliwangi Sidodadi Desa Senipah Kecamatan Samboja


Perkiraan Kuantitas :
Total Harga :
% Harga Jumlah Seluruh :

MPONEN SATUANPERKIRAAN HARGAJUMLAH


KUANTITAS SATUANHARGA
(Rp.) (Rp.)

M2 400.00 5,000.00 ###

###

M2 16.00 ### ###

LS 1.00 ### ###

LS 1.00 ### ###


LS 1.00 ### ###
LS 1.00 ### ###
Set 1.00 ### ###
LS 1.00 ### ###
###

Harga JUMLAH
KODE ALAT SATUAN Kuantitas Satuan HARGA

E.010 Unit 0.00 0.00 ###


E.020 Unit 1.00 ### ###
E.030 Unit 1.00 ### ###
E.040 Unit 1.00 ### ###
E.050 Unit 1.00 ### ###
E.060 Unit 1.00 50,000.00 ###
E.070 Unit 1.00 35,000.00 ###
E.100 Unit 1.00 ### ###
E.120 Unit 1.00 #REF! ###
E.190 Unit 1.00 #REF! ###
E.200 Unit 1.00 #REF! ###
E.210 Unit 1.00 #REF! ###
E.230 Unit 1.00 #REF! ###
E.240 Unit 1.00 #REF! ###
E.250 Unit 1.00 #REF! ###
E.250 Unit 1.00 #REF! ###
###
AL BINA MARGA ANALISA SATUAN BIAYA Kegiatan
Program JALAN PEMBUATAN GORONG-GORONG KAYU ULIN KODE
NAAN JALAN
BUPATEN (MENGGUNAKAN BURUH)
KODE KOTA KODE DI SIAPKAN
KOTA SAMARINDA

PONEN KODE VOL HARGA HARGA HARGA JUMLAH


UPAH BAHAN SATUAN HARGA
(Rp.) (Rp.) (Rp.) (Rp.)

(1.a. + 1.b. + 1.c.)


meruncing Tiang
Orang L.073 1.750 10,000.00 17,500.00 534,197.27
Orang L.079 0.175 10,714.29 1,875.00
Orang L.101 0.700 7,500.00 5,250.00
Orang L.061 0.350 12,000.00 4,200.00
ng Kedalaman 4 m
Orang L.073 22.050 10,000.00 220,500.00
Orang L.079 2.205 10,714.29 23,625.00
Orang L.101 7.350 7,500.00 55,125.00
Orang L.061 3.675 12,000.00 44,100.00
M.181 0.040 3,642,306.82 145,692.27

Orang L.073 0.280 10,000.00 2,800.00


Orang L.079 0.028 10,714.29 300.00
Orang L.101 1.260 7,500.00 9,450.00
Orang L.061 0.315 12,000.00 3,780.00
sar Gelagar
Orang L.073 105.000 10,000.00 1,050,000.00 5,526,309.55
Orang L.079 10.500 10,714.29 112,500.00
Orang L.101 35.000 7,500.00 262,500.00
Orang L.061 1.750 12,000.00 21,000.00
M.181 1.100 3,642,306.82 4,006,537.50
M.166 3.000 24,590.68 73,772.05

Orang L.073 12.600 10,000.00 126,000.00 269,495.81


Orang L.079 1.260 10,714.29 13,500.00
Orang L.101 4.200 7,500.00 31,500.00
Orang L.061 0.210 12,000.00 2,520.00
M.181 0.025 3,642,306.82 91,057.67
M.166 0.200 24,590.68 4,918.14

70.00 Titik x Rp. 534,197.27 = Rp. 37,393,809.09


0.30 M3 x Rp. 5,526,309.55 = Rp. 1,657,892.86
0.62 M3 x Rp. 5,526,309.55 = Rp. 3,426,311.92
0.96 M3 x Rp. 5,526,309.55 = Rp. 5,305,257.16
30.00 M2 x Rp. 269,495.81 = Rp. 8,084,874.20
128.00 M2 x Rp. 269,495.81 = Rp. 34,495,463.27
62.00 Buah x Rp. 19,515.68 = Rp. 1,209,972.27
62.00 Buah x Rp. 106,575.00 = Rp. 6,607,650.00
Pembulatan 1 Buah Gorong-Gorong L 30 = Rp. 98,181,230.79

AL BINA MARGA ANALISA SATUAN BIAYA Kegiatan


Program JALAN JEMBATAN KAYU ULIN KODE
NAAN JALAN
BUPATEN (MENGGUNAKAN BURUH)

KODE KOTA KODE DI SIAPKAN


KOTA SAMARINDA

PONEN KODE VOL HARGA HARGA HARGA JUMLAH


UPAH BAHAN SATUAN HARGA
(Rp.) (Rp.) (Rp.) (Rp.)

(1.a. + 1.b. + 1.c.)


meruncing Tiang

Orang L.073 1.750 10,000.00 17,500.00 716,312.61


Orang L.079 0.175 10,714.29 1,875.00
Orang L.101 0.700 7,500.00 5,250.00
Orang L.061 0.350 12,000.00 4,200.00
ng Kedalaman 4 m
Orang L.073 22.050 10,000.00 220,500.00
Orang L.079 2.205 10,714.29 23,625.00
Orang L.101 7.350 7,500.00 55,125.00
Orang L.061 3.675 12,000.00 44,100.00
M.181 0.090 3,642,306.82 327,807.61

Orang L.073 0.280 10,000.00 2,800.00


Orang L.079 0.028 10,714.29 300.00
Orang L.101 1.260 7,500.00 9,450.00
Orang L.061 0.315 12,000.00 3,780.00
sar Gelagar
Orang L.073 105.000 10,000.00 1,050,000.00 5,526,309.55
Orang L.079 10.500 10,714.29 112,500.00
Orang L.101 35.000 7,500.00 262,500.00
Orang L.061 1.750 12,000.00 21,000.00
M.181 1.100 3,642,306.82 4,006,537.50
M.166 3.000 24,590.68 73,772.05

Orang L.073 12.600 10,000.00 126,000.00 269,495.81


Orang L.079 1.260 10,714.29 13,500.00
Orang L.101 4.200 7,500.00 31,500.00
Orang L.061 0.210 12,000.00 2,520.00
M.181 0.025 3,642,306.82 91,057.67
M.166 0.200 24,590.68 4,918.14

279.00 Titik x Rp. 534,197.27 = Rp. 149,041,039.09


1.35 M3 x Rp. 5,526,309.55 = Rp. 7,460,517.89
1.35 M3 x Rp. 5,526,309.55 = Rp. 7,460,517.89
156.00 M2 x Rp. 269,495.81 = Rp. 42,041,345.86
128.00 M2 x Rp. 269,495.81 = Rp. 34,495,463.27
62.00 Buah x Rp. 19,515.68 = Rp. 1,209,972.27
62.00 Buah x Rp. 106,575.00 = Rp. 6,607,650.00

(2/20) Keping
(5/20) Keping
(5/7) Keping
(5/10) Keping
(6/12) Keping
(8/8) Keping
(10/10) Keping ITEM PEMBAYARAN NO
JENIS Kegiatan
SATUAN PEMBAYARAN
MARGA ANALISA SATUAN BIAYA
AN KOTA PEMBUATAN TURAP KAYU ULIN KODE
DA TRP 001
/ KOTA (MENGGUNAKAN BURUH)
KODE KOTA KODE DI SIAPKAN
KOTA SAMARINDA

HARGA HARGA HARGA JUMLAH


PONEN KODE VOLUME UPAH BAHAN SATUAN HARGA
(Rp.) (Rp.) (Rp.) (Rp.)

(1.a. + 1.b. + 1.c.)


meruncing Tiang
Orang L.073 1.050 10,000.00 10,500.00
Orang L.079 0.070 10,714.29 750.00
Orang L.101 0.350 7,500.00 2,625.00
Orang L.061 0.070 12,000.00 840.00
ng Kedalaman 4 m
Orang L.073 2.800 10,000.00 28,000.00
Orang L.079 1.050 10,714.29 11,250.00
Orang L.101 0.560 7,500.00 4,200.00
Orang L.061 0.560 12,000.00 6,720.00
M.181 0.044 3,642,306.82

Orang L.073 0.280 10,000.00 2,800.00


Orang L.079 0.028 10,714.29 300.00
Orang L.101 1.260 7,500.00 9,450.00
Orang L.061 0.315 12,000.00 3,780.00

Orang L.073 4.200 10,000.00 42,000.00


Orang L.079 0.420 10,714.29 4,500.00
Orang L.101 0.490 7,500.00 3,675.00
Orang L.061 0.070 12,000.00 840.00
M.181 1.100 3,642,306.82
M.166 3.000 24,590.68

Orang L.073 4.200 10,000.00 42,000.00


Orang L.079 0.420 10,714.29 4,500.00
Orang L.101 0.630 7,500.00 4,725.00
Orang L.061 0.280 12,000.00 3,360.00
M.181 0.050 3,642,306.82
M.166 0.200 24,590.68

82.00 Titik x Rp. 534,197.27 = Rp. 43,804,176.36

120.00 M2 x Rp. 269,495.81 = Rp. 32,339,496.82

46.00 Buah x Rp. 106,575.00 = Rp. 4,902,450.00


a Pembuatan Turap Kayu Ulin = Rp. 81,046,123.18

AL BINA MARGA ANALISA SATUAN BIAYA Kegiatan


Program JALAN JEMBATAN KAYU ULIN KODE
NAAN JALAN
BUPATEN (MENGGUNAKAN BURUH)

KODE KOTA KODE DI SIAPKAN


KOTA SAMARINDA

PONEN KODE VOL HARGA HARGA HARGA JUMLAH


UPAH BAHAN SATUAN HARGA
(Rp.) (Rp.) (Rp.) (Rp.)

n Gelagar Kayu Ulin 25/25 Cm


Orang L.073 14.000 13,000.00 182,000.00 4,911,910.00
Orang L.079 10.500 10,700.00 112,350.00
Orang L.101 28.000 7,500.00 210,000.00
Orang L.061 0.630 12,000.00 7,560.00
M.181a 1.100 4,000,000.00 4,400,000.00
n Gelagar Kayu Ulin 10/10 Cm
Orang L.073 14.000 13,000.00 182,000.00 4,319,910.00
Orang L.079 10.500 10,700.00 112,350.00
Orang L.101 22.400 7,500.00 168,000.00
Orang L.061 0.630 12,000.00 7,560.00
M.181 1.100 3,500,000.00 3,850,000.00
n Balok Pengaku, Suai, Balok Gapit, Tiang Railing Dan Balok Railing 10/10 Cm
Orang L.073 14.000 13,000.00 182,000.00 4,403,910.00
Orang L.079 10.500 10,700.00 112,350.00
Orang L.101 33.600 7,500.00 252,000.00
Orang L.061 0.630 12,000.00 7,560.00
M.181 1.100 3,500,000.00 3,850,000.00
n Lantai Ulin, Papan Railing Dan Ban-banan 5/20 Cm
Orang L.073 14.000 13,000.00 182,000.00 4,453,049.20
Orang L.079 10.500 10,700.00 112,350.00
Orang L.101 35.000 7,500.00 262,500.00
Orang L.061 0.630 12,000.00 7,560.00
M.181 1.100 3,500,000.00 3,850,000.00
M.166 2.500 15,455.68 38,639.20
Penyambung 10/30 Cm
Orang L.073 12.600 13,000.00 163,800.00 4,611,302.00
Orang L.079 1.260 10,700.00 13,482.00
Orang L.101 4.200 7,500.00 31,500.00
Orang L.061 0.210 12,000.00 2,520.00
M.181 1.100 4,000,000.00 4,400,000.00

#REF! M3 x Rp. 4,911,910.00 = Rp. #REF!

#REF! M3 x Rp. 4,319,910.00 = Rp. #REF!


#REF! M3 x Rp. 4,403,910.00 = Rp. #REF!
#REF! M3 x Rp. 4,453,049.20 = Rp. #REF!
#REF! M3 x Rp. 4,611,302.00 = Rp. #REF!
#REF! Buah x Rp. 25,605.68 = Rp. #REF!
#REF! Buah x Rp. 4,290.68 = Rp. #REF!

MARGA ANALISA SATUAN BIAYA


AN KOTA PEMBUATAN PANCANG ULIN KODE
DA TRP 001
/ KOTA (MENGGUNAKAN BURUH)
KODE KOTA KODE DI SIAPKAN
KOTA SAMARINDA

HARGA HARGA HARGA JUMLAH


PONEN KODE VOLUME UPAH BAHAN SATUAN HARGA
(Rp.) (Rp.) (Rp.) (Rp.)

(1.a. + 1.b. + 1.c.)


meruncing Tiang
Orang L.073 1.400 13,000.00 18,200.00 2,604,530.00
Orang L.079 1.400 10,700.00 14,980.00
Orang L.101 2.100 7,500.00 15,750.00
Orang L.061 0.630 12,000.00 7,560.00
ng Kedalaman 8 m
Orang L.073 11.200 13,000.00 145,600.00
Orang L.079 8.400 10,700.00 89,880.00
Orang L.101 14.000 7,500.00 105,000.00
Orang L.061 0.630 12,000.00 7,560.00
M.181a 0.550 4,000,000.00 2,200,000.00

1.00 Titik x Rp. 2,604,530.00 = Rp. 2,604,530.00


FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN MOBILISASI (LUMPSUM)
: PERHUBUNGAN
Kegiatan DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
PAKET : PENINGKATAN JALAN RING ROAD III (TAHAP II)
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000
ITEM PEMBAYARAN NO : 1.1.
JENIS Kegiatan : MOBILISASI
SATUAN PEMBAYARAN : Lumpsum

NO KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

A. MOBILISASI PERALATAN
1 Dump Truck E.080 Unit 8.00 100,000.00
2 Excavator E.09 Unit 1.00 500,000.00
3 Motor Greader E.11 Unit 1.00 250,000.00
4 Water Tank Truck E.15 Unit 1.00 100,000.00
5 Wheel Loader E.16 Unit 1.00 350,000.00
6 Vibratory Roller E.17 Unit 1.00 350,000.00

JUMLAH A

B. FASILITAS LAIN-LAIN
1 Pembuatan Direksi Keet M2 36.00 40,000.00
2 Papan Nama Kegiatan Buah 2.00 150,000.00
3 Pengendalian Lalu Lintas Ls 1.00 405,000.00
4 Pengujian Laboratorium Ls 1.00 200,000.00
JUMLAH B

C. DEMOBILISASI
1 Demobilisasi Peralatan (25 %) Ls 1.00 587,500.00
JUMLAH C

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


E. BIAYA UMUM DAN KEUNTUNGAN 15 % x D
F. HARGA SATUAN Kegiatan (D + E)

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA HARGA SATUAN MOBILISASI (LUMPSUM)
: PERHUBUNGAN
Kegiatan DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
PAKET : PENINGKATAN JALAN M. SAID

LOKASI : DATI II KOMAS


TAHUN ANGGARAN : 1999/2000
ITEM PEMBAYARAN NO : 1.1.
JENIS Kegiatan : MOBILISASI
SATUAN PEMBAYARAN : Lumpsum

NO KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

A. MOBILISASI PERALATAN
1 Asphalt Mixing Plant E.01 Unit 1.00 0.00
2 Asphalt Finisher E.02 Unit 1.00 350,000.00
3 Asphalt Sprayer E.030 Unit 1.00 350,000.00
4 Air Compressor E.040 Unit 1.00 50,000.00
5 Dump Truck E.080 Unit 8.00 100,000.00
6 Excavator Hydraulic E.10 Unit 1.00 500,000.00
7 Generator Set E.120 Unit 1.00 100,000.00
8 Motor Grader E.140 Unit 1.00 350,000.00
9 Tire Pneumatic Roller E.190 Unit 1.00 250,000.00
10 Water Tank Truck E.230 Unit 1.00 100,000.00
11 Wheel Loader E.220 Unit 1.00 350,000.00
12 Vibartory Roller E.240 Unit 1.00 350,000.00
13 Concrete Mixer E.060 Unit 1.00 50,000.00
14 Concrete Vibrator E.070 Unit 1.00 50,000.00

JUMLAH A

B. FASILITAS LAIN-LAIN
1 Pembuatan Direksi Keet M2 36.00 40,000.00
2 Papan Nama Kegiatan Buah 2.00 150,000.00
3 Pengendalian Lalu Lintas Ls 1.00 1,000,000.00
4 Pengujian Laboratorium Ls 1.00 588,000.00
JUMLAH B

C. DEMOBILISASI
1 Demobilisasi Peralatan (25 %) Ls 1.00 912,500.00
JUMLAH C

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


E. BIAYA UMUM DAN KEUNTUNGAN 15 % x D
F. HARGA SATUAN Kegiatan (D + E)

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA HARGA SATUAN MOBILISASI (LUMPSUM)
: PERHUBUNGAN
Kegiatan DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
PAKET : PENINGKATAN JALAN MUGIREJO - LUBUK SAWA
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000
ITEM PEMBAYARAN NO : 1.1.
JENIS Kegiatan : MOBILISASI
SATUAN PEMBAYARAN : Lumpsum

NO KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

A. MOBILISASI PERALATAN
1 Asphalt Mixing Plant E.01 Unit 1.00 0.00
2 Asphalt Finisher E.02 Unit 1.00 350,000.00
3 Asphalt Sprayer E.030 Unit 1.00 350,000.00
4 Air Compressor E.040 Unit 1.00 50,000.00
5 Dump Truck E.080 Unit 8.00 100,000.00
6 Excavator Hydraulic E.10 Unit 1.00 500,000.00
7 Generator Set E.120 Unit 1.00 100,000.00
8 Motor Grader E.140 Unit 1.00 350,000.00
9 Tire Pneumatic Roller E.190 Unit 1.00 250,000.00
10 Water Tank Truck E.230 Unit 1.00 100,000.00
11 Wheel Loader E.220 Unit 1.00 350,000.00
12 Vibartory Roller E.240 Unit 1.00 350,000.00
13 Concrete Mixer E.060 Unit 1.00 50,000.00
14 Concrete Vibrator E.070 Unit 1.00 50,000.00

JUMLAH A

B. FASILITAS LAIN-LAIN
1 Pembuatan Direksi Keet M2 36.00 40,000.00
2 Papan Nama Kegiatan Buah 2.00 150,000.00
3 Pengendalian Lalu Lintas Ls 1.00 1,000,000.00
4 Pengujian Laboratorium Ls 1.00 568,000.00
JUMLAH B

C. DEMOBILISASI
1 Demobilisasi Peralatan (25 %) Ls 1.00 912,500.00
JUMLAH C

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


F. HARGA SATUAN Kegiatan (D + E)
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN MOBILISASI (LUMPSUM)
: PERHUBUNGAN
Program DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
PAKET Kegiatan : PEMELIHARAAN PERIODIK JALAN DALAM KOTA
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000
ITEM PEMBAYARAN NO : 1.1.
JENIS Kegiatan : MOBILISASI
SATUAN PEMBAYARAN : Lumpsum

NO KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

A. MOBILISASI PERALATAN
1 Asphalt Sprayer E.030 Unit 1.00 350,000.00
2 Dump Truck E.080 Unit 8.00 100,000.00
3 Excavator Hydraulic E.10 Unit 1.00 500,000.00
4 Three Wheel Roller E.17 Unit 1.00 150,000.00
5 Water Tank Truck E.230 Unit 1.00 100,000.00
6 Wheel Loader E.220 Unit 1.00 350,000.00
JUMLAH A

B. FASILITAS LAIN-LAIN
1 Pembuatan Direksi Keet M2 36.00 40,000.00
2 Papan Nama Kegiatan Buah 2.00 150,000.00
3 Pengendalian Lalu Lintas Ls 1.00 482,000.00
4 Pengujian Laboratorium Ls 1.00 250,000.00
JUMLAH B

C. DEMOBILISASI
1 Demobilisasi Peralatan (25 %) Ls 1.00 562,500.00
JUMLAH C

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


E. BIAYA UMUM DAN KEUNTUNGAN 15 % x D
F. HARGA SATUAN Kegiatan (D + E)

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA HARGA SATUAN MOBILISASI (LUMPSUM)
Kegiatan
: PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K)
PAKET : PENINGKATAN RUAS JALAN AIR TERJUN TANAH MERAH
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000
ITEM PEMBAYARAN NO : 1.1.
JENIS Kegiatan : MOBILISASI
SATUAN PEMBAYARAN : Lumpsum

NO KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

A. MOBILISASI PERALATAN
1 Asphalt Mixing Plant E.01 Unit 1.00 0.00
2 Asphalt Finisher E.02 Unit 1.00 350,000.00
3 Asphalt Sprayer E.030 Unit 1.00 350,000.00
4 Air Compressor E.040 Unit 1.00 50,000.00
5 Dump Truck E.080 Unit 8.00 100,000.00
6 Excavator Hydraulic E.10 Unit 1.00 500,000.00
7 Generator Set E.120 Unit 1.00 100,000.00
8 Motor Grader E.140 Unit 1.00 350,000.00
9 Tire Pneumatic Roller E.190 Unit 1.00 250,000.00
10 Water Tank Truck E.230 Unit 1.00 100,000.00
11 Wheel Loader E.220 Unit 1.00 350,000.00
12 Vibartory Roller E.240 Unit 1.00 350,000.00
13 Concrete Mixer E.060 Unit 1.00 50,000.00
14 Concrete Vibrator E.070 Unit 1.00 50,000.00

JUMLAH A

B. FASILITAS LAIN-LAIN
1 Pembuatan Direksi Keet M2 36.00 40,000.00
2 Papan Nama Kegiatan Buah 2.00 150,000.00
3 Pengendalian Lalu Lintas Ls 1.00 1,000,000.00
4 Pengujian Laboratorium Ls 1.00 991,000.00
JUMLAH B

C. DEMOBILISASI
1 Demobilisasi Peralatan (25 %) Ls 1.00 912,500.00
JUMLAH C
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)
E. BIAYA UMUM DAN KEUNTUNGAN 15 % x D
F. HARGA SATUAN Kegiatan (D + E)

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA HARGA SATUAN MOBILISASI (LUMPSUM)
Kegiatan
: PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K)
PAKET : PENINGKATAN RUAS JALAN BUKUAN ( PALARAN )
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000
ITEM PEMBAYARAN NO : 1.1.
JENIS Kegiatan : MOBILISASI
SATUAN PEMBAYARAN : Lumpsum

NO KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

A. MOBILISASI PERALATAN
1 Asphalt Sprayer E.030 Unit 1.00 350,000.00
2 Concrete Mixer E.060 Unit 1.00 50,000.00
3 Concrete Vibrator E.070 Unit 1.00 50,000.00
4 Dump Truck E.080 Unit 8.00 100,000.00
5 Excavator Hydraulic E.10 Unit 1.00 500,000.00
6 Three Wheel Roller E.17 Unit 1.00 150,000.00
7 Water Tank Truck E.230 Unit 1.00 100,000.00
8 Wheel Loader E.220 Unit 1.00 350,000.00
JUMLAH A

B. FASILITAS LAIN-LAIN
1 Pembuatan Direksi Keet M2 36.00 40,000.00
2 Papan Nama Kegiatan Buah 2.00 150,000.00
3 Pengendalian Lalu Lintas Ls 1.00 510,000.00
4 Pengujian Laboratorium Ls 1.00 250,000.00
JUMLAH B

C. DEMOBILISASI
1 Demobilisasi Peralatan (25 %) Ls 1.00 587,500.00
JUMLAH C

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


E. BIAYA UMUM DAN KEUNTUNGAN 15 % x D
F. HARGA SATUAN Kegiatan (D + E)

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA HARGA SATUAN MOBILISASI (LUMPSUM)
: PERHUBUNGAN
Program
DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
PAKET : PENINGKATAN RUAS JALAN BUKUAN ( PALARAN ) ( LANJUTAN )
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000
ITEM PEMBAYARAN NO : 1.1.
JENIS Kegiatan : MOBILISASI
SATUAN PEMBAYARAN : Lumpsum
NO KOMPONEN SATUAN PERKIRAAN HARGA
KUANTITAS SATUAN
(Rp.)

A. MOBILISASI PERALATAN
1 Asphalt Sprayer E.030 Unit 1.00 350,000.00
2 Dump Truck E.080 Unit 8.00 100,000.00
3 Three Wheel Roller E.17 Unit 1.00 150,000.00
4 Water Tank Truck E.230 Unit 1.00 100,000.00
5 Wheel Loader E.220 Unit 1.00 350,000.00

JUMLAH A

B. FASILITAS LAIN-LAIN
1 Pengendalian Lalu Lintas Ls 1.00 226,500.00

JUMLAH B

C. DEMOBILISASI
1 Demobilisasi Peralatan (25 %) Ls 1.00 437,500.00
JUMLAH C

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


E. BIAYA UMUM DAN KEUNTUNGAN 15 % x D
F. HARGA SATUAN Kegiatan (D + E)
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN MOBILISASI (LUMPSUM)
: PERHUBUNGAN
Program DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
PAKET Kegiatan : PENINGKATAN JALAN PELITA IV
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000
ITEM PEMBAYARAN NO : 1.1.
JENIS Kegiatan : MOBILISASI
SATUAN PEMBAYARAN : Lumpsum

NO KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

A. MOBILISASI PERALATAN
1 Asphalt Sprayer E.030 Unit 1.00 350,000.00
2 Concrete Mixer E.060 Unit 1.00 50,000.00
3 Concrete Vibrator E.070 Unit 1.00 50,000.00
4 Dump Truck E.080 Unit 8.00 100,000.00
5 Excavator Hydraulic E.10 Unit 1.00 500,000.00
6 Three Wheel Roller E.17 Unit 1.00 150,000.00
7 Water Tank Truck E.230 Unit 1.00 100,000.00
8 Wheel Loader E.220 Unit 1.00 350,000.00

JUMLAH A

B. FASILITAS LAIN-LAIN
1 Pembuatan Direksi Keet M2 36.00 40,000.00
2 Papan Nama Kegiatan Buah 2.00 150,000.00
3 Pengendalian Lalu Lintas Ls 1.00 1,000,000.00
4 Pengujian Laboratorium Ls 1.00 520,000.00
JUMLAH B

C. DEMOBILISASI
1 Demobilisasi Peralatan (25 %) Ls 1.00 587,500.00
JUMLAH C

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


E. BIAYA UMUM DAN KEUNTUNGAN 15 % x D
F. HARGA SATUAN Kegiatan (D + E)

KOP PERUSAHAAN
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA HARGA SATUAN MOBILISASI (LUMPSUM)
Kegiatan
: PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K)
PAKET : PENINGKATAN RUAS JALAN AIR TERJUN TANAH MERAH
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000
ITEM PEMBAYARAN NO : 1.1.
JENIS Kegiatan : MOBILISASI
SATUAN PEMBAYARAN : Lumpsum

NO KOMPONEN SATUAN PERKIRAAN HARGA


KUANTITAS SATUAN
(Rp.)

A. MOBILISASI PERALATAN
1 Asphalt Mixing Plant E.01 Unit 1.00 0.00
2 Asphalt Finisher E.02 Unit 1.00
3 Asphalt Sprayer E.030 Unit 1.00
4 Air Compressor E.040 Unit 1.00
5 Dump Truck E.080 Unit 8.00
6 Excavator Hydraulic E.10 Unit 1.00
7 Generator Set E.120 Unit 1.00
8 Motor Grader E.140 Unit 1.00
9 Tire Pneumatic Roller E.190 Unit 1.00
10 Water Tank Truck E.230 Unit 1.00
11 Wheel Loader E.220 Unit 1.00
12 Vibartory Roller E.240 Unit 1.00
13 Concrete Mixer E.060 Unit 1.00
14 Concrete Vibrator E.070 Unit 1.00

JUMLAH A

B. FASILITAS LAIN-LAIN
1 Pembuatan Direksi Keet M2 36.00
2 Papan Nama Kegiatan Buah 2.00
3 Pengendalian Lalu Lintas Ls 1.00
4 Pengujian Laboratorium Ls 1.00
JUMLAH B

C. DEMOBILISASI
1 Demobilisasi Peralatan (25 %) Ls 1.00
JUMLAH C

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


E. BIAYA UMUM DAN KEUNTUNGAN ......... x D
F. HARGA SATUAN Kegiatan (D + E)

SAMARINDA, 29 SEPTEMBER 1999


DI SIAPKAN OLEH :
PENAWAR
PT / CV. ............................

( NAMA JELAS )
Jabatan
Cap Perusahaan
INFORMASI UMUM
UMPSUM)

NO URAIAN

1 Kegiatan : Perhubungan Dan Penanganan Jalan Kotamadya Dati II Samarinda


2 Paket : Peningkatan Jalan Ring Road III (Tahap II)
3 Nomor Paket :

JUMLAH
HARGA 4 Lokasi Kegiatan
(Rp.) 5 Kondisi Jalan Lama
6 Panjang Efektif (lihat sketsa di bawah ini)
7 Lebar Jalan Lama (bahu + perkerasan + bahu) dalam (m)
800,000.00 8 Lebar Rencana (bahu + perkerasan + bahu) dalam (m)
500,000.00 9 Penampang jalan, jenis dan volume Kegiatan pokok
250,000.00 10 Jangka waktu pelaksanaan (hari kalender)
100,000.00
350,000.00
350,000.00 11 Jarak rata-rata Base Camp ke lokasi
Perhitungan di dasarkan pada sketsa di bawah ini
a' = (c + a/2) x a = 0.677

b' = (c + b/2) x b = 0.677

Leff = (a + b) = 2.136 kilometer

L = (a' + b') / Leff = 0.634 kilometer

Lq = Jarak penumpukan (Quary)

Lpmb = Jarak pembuangan

Lr = Jarak rata-rata = (Leff + L + Lq + Lpmb) =

Lr = Jarak rata-rata = (di ambil sebesar)

A 1.068 Km = a C

2,350,000.00 Sta 0+000 Sta 1+068

0.100

1,440,000.00 Base Camp


300,000.00
405,000.00
200,000.00
2,345,000.00
Jam kerja efektif dalam 1 hari
Asuransi, pajak untuk peralatan
587,500.00 Tingkat suku bunga investasi alat = 20 %
587,500.00 Biaya umum dan keuntungan = 15 %

5,282,500.00
792,375.00 12 Mobilisasi di laksanakan sesuai dengan ketentuan yang tercantum dalam lampiran
6,074,875.00 13 Kegiatan Drainase dengan produk akhir Galian Parit
14 Kegiatan Tanah di laksanakan untuk Persiapan Badan Jalan (Land Clearing)
15 Kegiatan Tanah selanjutnya adalah Urugan Biasa dan Urugan Pilihan
16 Kegiatan Perkerasan Berbutir adalah Agregat Kelas B
17 Kegiatan Struktur adalah Jembatan Kayu Ulin dan Gorong-Gorong Kayu Ulin

18 Lokasi Quary (Material on Site)

INFORMASI UMUM
UMPSUM)

NO URAIAN

1 Kegiatan : Perhubungan Dan Penanganan Jalan Kotamadya Dati II Samarinda


2 Paket : Peningkatan Jalan M. Said
3 Nomor Paket :

JUMLAH
HARGA 4 Lokasi Kegiatan
(Rp.) 5 Kondisi Jalan Lama

6 Panjang Efektif (lihat sketsa di bawah ini)


7 Lebar Jalan Lama (bahu + perkerasan + bahu) dalam (m)
0.00 8 Lebar Rencana (bahu + perkerasan + bahu) dalam (m)
350,000.00 9 Penampang jalan, jenis dan volume Kegiatan pokok
350,000.00 10 Jangka waktu pelaksanaan (hari kalender)
50,000.00
800,000.00
500,000.00 11 Jarak rata-rata Base Camp ke lokasi
100,000.00 Perhitungan di dasarkan pada sketsa di bawah ini
350,000.00 a' = (c + a/2) x a = 6.475
250,000.00 b' = (c + b/2) x b = 6.475
100,000.00 Leff = (a + b) = 7.000 kilometer
350,000.00 L = (a' + b') / Leff = 1.850 kilometer
350,000.00 Lq = Jarak penumpukan (Quary)
50,000.00 Lpmb = Jarak pembuangan
50,000.00 Lr = Jarak rata-rata = (Leff + L + Lq + Lpmb) =
Lr = Jarak rata-rata = (di ambil sebesar)

A 3.500 Km = a C
3,650,000.00 Sta 0+000 Sta 3+500
0.100

1,440,000.00 Base Camp


300,000.00
1,000,000.00
588,000.00
3,328,000.00
Jam kerja efektif dalam 1 hari
Asuransi, pajak untuk peralatan
912,500.00 Tingkat suku bunga investasi alat = 20 %
912,500.00 Biaya umum dan keuntungan = 15 %

7,890,500.00
1,183,575.00 12 Mobilisasi di laksanakan sesuai dengan ketentuan yang tercantum dalam lampiran
9,074,075.00 13 Kegiatan drainase dengan produk akhir parit pasangan dengan mortar
15 Kegiatan bahu jalan di perkuatan dengan Lapis Pondasi Kelas B dan Timbunan Tanah Pil
16 Kegiatan berbutir Lapis Pondasi Agregat Kelas A dan Telford Batu Gunung sebagai dasar
17 Kegiatan Lapis Pengikat sebelum Kegiatan Hotmix ATB
18 Produk akhir Kegiatan ATB (Asphalt Treated Base) dan Lapen Macadam

19 Lokasi Quary (Material on Site)

INFORMASI UMUM
UMPSUM)

NO URAIAN
1 Kegiatan : Perhubungan Dan Penanganan Jalan Kotamadya Dati II Samarinda
2 Paket : Peningkatan Jalan Mugirejo - Lubuk Sawa
3 Nomor Paket :

JUMLAH
HARGA 4 Lokasi Kegiatan
(Rp.) 5 Kondisi Jalan Lama
6 Panjang Efektif (lihat sketsa di bawah ini)
7 Lebar Jalan Lama (bahu + perkerasan + bahu) dalam (m)
0.00 8 Lebar Rencana (bahu + perkerasan + bahu) dalam (m)
350,000.00 9 Penampang jalan, jenis dan volume Kegiatan pokok
350,000.00 10 Jangka waktu pelaksanaan (hari kalender)
50,000.00
800,000.00
500,000.00 11 Jarak rata-rata Base Camp ke lokasi
100,000.00 Perhitungan di dasarkan pada sketsa di bawah ini
350,000.00 a' = (c + a/2) x a = 7.771
250,000.00 b' = (c + b/2) x b = 7.771
100,000.00 Leff = (a + b) = 7.687 kilometer
350,000.00 L = (a' + b') / Leff = 2.022 kilometer
350,000.00 Lq = Jarak penumpukan (Quary)
50,000.00 Lpmb = Jarak pembuangan
50,000.00 Lr = Jarak rata-rata = (Leff + L + Lq + Lpmb) =
Lr = Jarak rata-rata = (di ambil sebesar)

A 3.844 Km = a C
3,650,000.00 Sta 0+000 Sta 3+8435
0.100

1,440,000.00 Base Camp


300,000.00
1,000,000.00
568,000.00
3,308,000.00
Jam kerja efektif dalam 1 hari
Asuransi, pajak untuk peralatan
912,500.00 Tingkat suku bunga investasi alat = 20 %
912,500.00 Biaya umum dan keuntungan = 15 %

7,870,500.00
#REF! 13 Kegiatan drainase dengan produk akhir parit pasangan dengan mortar
14 Kegiatan tanah di laksanakan untuk persiapan badan jalan
15 Kegiatan bahu jalan di perkuatan dengan Lapis Pondasi Kelas B dan Timbunan Tanah Pil
16 Kegiatan berbutir Lapis Pondasi Agregat Kelas A dan Telford Batu Gunung sebagai dasar
17 Kegiatan Lapis Pengikat sebelum Kegiatan Hotmix ATB
18 Produk akhir Kegiatan ATB (Asphalt Treated Base) dan Lapen Macadam

19 Lokasi Quary (Material on Site)

INFORMASI UMUM
UMPSUM)

NO URAIAN

1 Kegiatan : Perhubungan Dan Penanganan Jalan Kotamadya Dati II Samarinda


2 Paket : Pemeliharaan Periodik Jalan Dalam Kota
3 Nomor Paket :

JUMLAH
HARGA 4 Lokasi Kegiatan
(Rp.) 5 Kondisi Jalan Lama
6 Panjang Efektif (lihat sketsa di bawah ini)
7 Lebar Jalan Lama (bahu + perkerasan + bahu) dalam (m)
350,000.00 8 Lebar Rencana (bahu + perkerasan + bahu) dalam (m)
800,000.00 9 Penampang jalan, jenis dan volume Kegiatan pokok
500,000.00 10 Jangka waktu pelaksanaan (hari kalender)
150,000.00
100,000.00
350,000.00 11 Jalan Muang-Bayur (127) = Perkerasan Subbase
Jalan Pampang (126) = Pacthing Lapen Mcadam
Jalan Damanhuri (128) = Pacthing Lapen Mcadam
Jalan Elang (172) = Pacthing Lapen Mcadam
(*) Target Menyesuaikan Dengan Harga Pasar
2,250,000.00

1,440,000.00
300,000.00
482,000.00
250,000.00
2,472,000.00

Jam kerja efektif dalam 1 hari


562,500.00 Asuransi, pajak untuk peralatan
562,500.00 Tingkat suku bunga investasi alat = 20 %
Biaya umum dan keuntungan = 15 %
5,284,500.00
792,675.00
6,077,175.00 12 Kegiatan akhir Lapen Macadam

13 Lokasi Quary (Material on Site)

ENGINEER'E ESTIMATE

INFORMASI UMUM
UMPSUM)
NO URAIAN

1 Kegiatan : Peningkatan Jalan Poros Desa / Kecamatan (PPJPD/K)


2 Paket : Peningkatan Ruas Jalan Air Terjun Tanah Merah
3 Nomor Paket :

JUMLAH
HARGA 4 Lokasi Kegiatan
(Rp.) 5 Kondisi Jalan Lama
6 Panjang Efektif (lihat sketsa di bawah ini)
7 Lebar Jalan Lama (bahu + perkerasan + bahu) dalam (m)
0.00 8 Lebar Rencana (bahu + perkerasan + bahu) dalam (m)
350,000.00 9 Penampang jalan, jenis dan volume Kegiatan pokok
350,000.00 10 Jangka waktu pelaksanaan (hari kalender)
50,000.00
800,000.00
500,000.00 11 Jarak rata-rata Base Camp ke lokasi
100,000.00 Perhitungan di dasarkan pada sketsa di bawah ini
350,000.00 a' = (c + a/2) x a = 0.096

250,000.00 b' = (c + b/2) x b = 0.096


100,000.00 Leff = (a + b) = 0.700 kilometer
350,000.00 L = (a' + b') / Leff = 0.275 kilometer
350,000.00 Lq = Jarak penumpukan (Quary)
50,000.00 Lpmb = Jarak pembuangan
50,000.00 Lr = Jarak rata-rata = (Leff + L + Lq + Lpmb) =
Lr = Jarak rata-rata = (di ambil sebesar)

A 0.350 Km = a C

3,650,000.00 Sta 0+000 Sta 0+350

0.100

1,440,000.00 Base Camp


300,000.00
1,000,000.00
991,000.00
3,731,000.00
Jam kerja efektif dalam 1 hari
Asuransi, pajak untuk peralatan
912,500.00 Tingkat suku bunga investasi alat = 20 %
912,500.00 Biaya umum dan keuntungan = 15 %
8,293,500.00
1,244,025.00 12 Mobilisasi di laksanakan sesuai dengan ketentuan yang tercantum dalam lampiran
9,537,525.00 13 Kegiatan Sub Base dengan LPB (Agregat Kelas B)
14 Kegiatan Base dengan LPA (Agregat Kelas B)
15 Kegiatan Lapis Pengikat sebelum Kegiatan Hotmix ATB
16 Produk akhir Kegiatan ATB (Asphalt Treated Base) dan Lapen Macadam

17 Lokasi Quary (Material on Site)

INFORMASI UMUM
UMPSUM)

NO URAIAN

1 Kegiatan : Peningkatan Jalan Poros Desa / Kecamatan (PPJPD/K)


2 Paket : Peningkatan Ruas Jalan Bukuan (Palaran)
3 Nomor Paket :

JUMLAH
HARGA 4 Lokasi Kegiatan
(Rp.) 5 Kondisi Jalan Lama
6 Panjang Efektif (lihat sketsa di bawah ini)
7 Lebar Jalan Lama (bahu + perkerasan + bahu) dalam (m)
350,000.00 8 Lebar Rencana (bahu + perkerasan + bahu) dalam (m)
50,000.00 9 Penampang jalan, jenis dan volume Kegiatan pokok
50,000.00 10 Jangka waktu pelaksanaan (hari kalender)
800,000.00
500,000.00
150,000.00 11 Jarak rata-rata Base Camp ke lokasi
100,000.00 Perhitungan di dasarkan pada sketsa di bawah ini
350,000.00 a' = (c + a/2) x a = 3.708

b' = (c + b/2) x b = 3.708


Leff = (a + b) = 5.250 kilometer
L = (a' + b') / Leff = 1.413 kilometer
Lq = Jarak penumpukan (Quary)
Lpmb = Jarak pembuangan
Lr = Jarak rata-rata = (Leff + L + Lq + Lpmb) =
Lr = Jarak rata-rata = (di ambil sebesar)

A 2.625 Km = a C

2,350,000.00 Sta 0+000 Sta 2+625

0.100

1,440,000.00 Base Camp

300,000.00
510,000.00
250,000.00
2,500,000.00
Jam kerja efektif dalam 1 hari
Asuransi, pajak untuk peralatan
587,500.00 Tingkat suku bunga investasi alat = 20 %
587,500.00 Biaya umum dan keuntungan = 15 %

5,437,500.00
815,625.00 12 Mobilisasi di laksanakan sesuai dengan ketentuan yang tercantum dalam lampiran
6,253,125.00 13 Kegiatan tanah di laksanakan untuk persiapan badan jalan
14 Kegiatan berbutir dengan Telford Batu Gunung sebagai dasar perkuatan
15 Kegiatan Lapen Macadam sebagai produk akhir ruas jalan ini

16 Lokasi Quary (Material on Site)

INFORMASI UMUM
UMPSUM)

( LANJUTAN ) NO URAIAN

1 Kegiatan : Perhubungan Dan Penanganan Jalan Kotamadya Dati II Samarinda


2 Paket : Peningkatan Ruas Jalan Bukuan (Palaran) (Lanjutan)
3 Nomor Paket :
JUMLAH
HARGA 4 Lokasi Kegiatan
(Rp.) 5 Kondisi Jalan Lama
6 Panjang Efektif (lihat sketsa di bawah ini)
7 Lebar Jalan Lama (bahu + perkerasan + bahu) dalam (m)
350,000.00 8 Lebar Rencana (bahu + perkerasan + bahu) dalam (m)
800,000.00 9 Penampang jalan, jenis dan volume Kegiatan pokok
150,000.00 10 Jangka waktu pelaksanaan (hari kalender)
100,000.00
350,000.00
11 Jarak rata-rata Base Camp ke lokasi
Perhitungan di dasarkan pada sketsa di bawah ini
a' = (c + a/2) x a = 3.708
b' = (c + b/2) x b = 3.708
Leff = (a + b) = 5.250 kilometer

L = (a' + b') / Leff = 1.413 kilometer

Lq = Jarak penumpukan (Quary)


Lpmb = Jarak pembuangan
Lr = Jarak rata-rata = (Leff + L + Lq + Lpmb) =
Lr = Jarak rata-rata = (di ambil sebesar)

A 2.625 Km = a C
1,750,000.00 Sta 0+000 Sta 2+625

0.100

226,500.00 Base Camp

226,500.00
Jam kerja efektif dalam 1 hari
Asuransi, pajak untuk peralatan
437,500.00 Tingkat suku bunga investasi alat = 20 %
437,500.00 Biaya umum dan keuntungan = 15 %

2,414,000.00
362,100.00 12 Mobilisasi di laksanakan sesuai dengan ketentuan yang tercantum dalam lampiran
2,776,100.00 13 Kegiatan tanah di laksanakan untuk persiapan badan jalan
14 Kegiatan berbutir dengan Telford Batu Gunung sebagai dasar perkuatan
15 Kegiatan Lapen Macadam sebagai produk akhir ruas jalan ini
16 Lokasi Quary (Material on Site)

INFORMASI UMUM
UMPSUM)

NO URAIAN

1 Kegiatan : Perhubungan Dan Penanganan Jalan Kotamadya Dati II Samarinda


2 Paket : Peningkatan Jalan PELITA IV
3 Nomor Paket :

JUMLAH
HARGA 4 Lokasi Kegiatan
(Rp.) 5 Kondisi Jalan Lama
6 Panjang Efektif (lihat sketsa di bawah ini)
7 Lebar Jalan Lama (bahu + perkerasan + bahu) dalam (m)
350,000.00 8 Lebar Rencana (bahu + perkerasan + bahu) dalam (m)
50,000.00 9 Penampang jalan, jenis dan volume Kegiatan pokok
50,000.00 10 Jangka waktu pelaksanaan (hari kalender)
800,000.00
500,000.00
150,000.00 11 Jarak rata-rata Base Camp ke lokasi
100,000.00 Perhitungan di dasarkan pada sketsa di bawah ini
350,000.00 a' = (c + a/2) x a = 0.178

b' = (c + b/2) x b = 0.178

Leff = (a + b) = 1.010 kilometer


L = (a' + b') / Leff = 0.353 kilometer
Lq = Jarak penumpukan (Quary)
Lpmb = Jarak pembuangan
Lr = Jarak rata-rata = (Leff + L + Lq + Lpmb) =
Lr = Jarak rata-rata = (di ambil sebesar)

A 0.505 Km = a C

2,350,000.00 Sta 0+000 Sta 0+505


0.100
1,440,000.00 Base Camp
300,000.00
1,000,000.00
520,000.00
3,260,000.00
Jam kerja efektif dalam 1 hari
Asuransi, pajak untuk peralatan
587,500.00 Tingkat suku bunga investasi alat = 20 %
587,500.00 Biaya umum dan keuntungan = 15 %

6,197,500.00
929,625.00 12 Mobilisasi di laksanakan sesuai dengan ketentuan yang tercantum dalam lampiran
7,127,125.00 13 Kegiatan berbutir Telford Batu Gunung sebagai dasar perkuatan
14 Produk akhir Kegiatan Lapen Macadam
15 Kegiatan struktur Slab Duiker dan Dinding Penahan Tanah

16 Lokasi Quary (Material on Site)

INFORMASI UMUM
UMPSUM)

NO URAIAN

1 Kegiatan : Peningkatan Jalan Poros Desa / Kecamatan (PPJPD/K)


2 Paket : Peningkatan Ruas Jalan Air Terjun Tanah Merah
3 Nomor Paket :

JUMLAH
HARGA 4 Lokasi Kegiatan
(Rp.) 5 Kondisi Jalan Lama
6 Panjang Efektif (lihat sketsa di bawah ini)
7 Lebar Jalan Lama (bahu + perkerasan + bahu) dalam (m)
( hasil = nol ) 8 Lebar Rencana (bahu + perkerasan + bahu) dalam (m)
9 Penampang jalan, jenis dan volume Kegiatan pokok
10 Jangka waktu pelaksanaan (hari kalender)
11 Jarak rata-rata Base Camp ke lokasi
Perhitungan di dasarkan pada sketsa di bawah ini
a' = (c + a/2) x a = 0.096

b' = (c + b/2) x b = 0.096


Leff = (a + b) = 0.700 kilometer
L = (a' + b') / Leff = 0.275 kilometer
Lq = Jarak penumpukan (Quary)
Lpmb = Jarak pembuangan
Lr = Jarak rata-rata = (Leff + L + Lq + Lpmb) =
Lr = Jarak rata-rata = (di ambil sebesar)

A 0.350 Km = a C

Sta 0+000 Sta 0+350


0.100

Base Camp

Jam kerja efektif dalam 1 hari


Asuransi, pajak untuk peralatan
Tingkat suku bunga investasi alat = 20 %
Biaya umum dan keuntungan = 15 %

12 Mobilisasi di laksanakan sesuai dengan ketentuan yang tercantum dalam lampiran


13 Kegiatan Sub Base dengan LPB (Agregat Kelas B)
14 Kegiatan Base dengan LPA (Agregat Kelas B)
RINDA, 29 SEPTEMBER 1999 15 Kegiatan Lapis Pengikat sebelum Kegiatan Hotmix ATB
DI SIAPKAN OLEH : 16 Produk akhir Kegiatan ATB (Asphalt Treated Base) dan Lapen Macadam
PENAWAR
PT / CV. ............................

( NAMA JELAS ) 17 Lokasi Quary (Material on Site)


Jabatan
Cap Perusahaan
SI UMUM HASIL PEREKAMAN ANALISA M
DAFTAR KUANTITAS
Kegiatan : PERHUBUNGAN DAN PENAN
INFORMASI PAKET : PENINGKATAN JALAN RING
LOKASI
TAHUN ANGGARAN
adya Dati II Samarinda
MATA KOMPONEN Kegiatan
PEMBA-
YARAN

Periksa peta lokasi DIV. I MOBILISASI


Agregat kurang baik 1.2. Mobilisasi

bahu) dalam (m) ( Jalan setapak / Semak ) Jumlah Harga Kegiatan Divisi 1 (Di pindahkan ke Rek
bahu) dalam (m) ( 4.5 + 26 + 4.5 )
DIV. II DRAINASE
2.1. Galian Parit

Jumlah Harga Kegiatan Divisi 2 (Di pindahkan ke Rek

DIV. III PERKERASAN BERBUTIR


3.3. Penyiapan Badan Jalan
3.2.(1). Urugan Tanah Biasa
3.2.(2). Urugan Tanah Pilihan
5.1.(2). Lapis Pondasi Aggregat Kelas B

Quary Jumlah Harga Kegiatan Divisi 3 (Di pindahkan ke Rek


Km

10.000 Km Lq 2 Km DIV. IV Kegiatan STRUKTUR


Bow.1. Gorong-Gorong Kayu Ulin
1.068 Km = b B Bow.2. Jembatan Kayu Ulin
Sta 2+135

Km = c Lpmb 1 Km Jumlah Harga Kegiatan Divisi 4 (Di pindahkan ke Rek

Pembuangan
7.00 Jam
2% x Harga Alat
0.20
0.15

ntum dalam lampiran

Land Clearing)

orong Kayu Ulin

Periksa lampiran

SI UMUM HASIL PEREKAMAN ANALISA M


DAFTAR KUANTITAS
Kegiatan : PERHUBUNGAN DAN PENAN
INFORMASI PAKET : PENINGKATAN JALAN M. SA

LOKASI
TAHUN ANGGARAN
adya Dati II Samarinda
MATA KOMPONEN Kegiatan
PEMBA-
YARAN

Periksa peta lokasi DIV. I MOBILISASI


Agregat kurang baik 1.2. Mobilisasi

bahu) dalam (m) ( 0.5 + 4+ 0.5 ) Jumlah Harga Kegiatan Divisi 1 (Di pindahkan ke Rek
bahu) dalam (m) ( 0.5 + 4+ 0.5 )
DIV. II PERKERASAN BERBUTIR
5.1.(1). Lapis Pondasi Aggregat Kelas A
5.1.(3). Lapis Telford Batu Gunung
Jumlah Harga Kegiatan Divisi 2 (Di pindahkan ke Rek

DIV. III PERKERASAN ASPAL


6.1.(1). Lapis Pengikat
6.3.(5). Asphalt Treated Base
8.1.(7). Lapen Macadam

Quary Jumlah Harga Kegiatan Divisi 3 (Di pindahkan ke Rek


Km
10.000 Km Lq 2 Km DIV. IV Kegiatan STRUKTUR
Komponen Slab Duiker (1 x 1)
3.500 Km = b B 2.1. Galian Parit
Sta 7+000 2.2. Pasangan Batu Mortar
Km = c Lpmb 1 Km 7.3. Pancangan Kayu Ulin
7.2. Baja Tulangan
Pembuangan 7.1.(1). Beton K-225
3.2.(2). Urugan Pilihan

Jumlah Harga Kegiatan Divisi 4 (Di pindahkan ke Rek

7.00 Jam
2% x Harga Alat
0.20
0.15

ntum dalam lampiran

B dan Timbunan Tanah Pilihan


Batu Gunung sebagai dasar perkuatan

Periksa lampiran

SI UMUM HASIL PEREKAMAN ANALISA M


DAFTAR KUANTITAS
Kegiatan : PERHUBUNGAN DAN PENAN
INFORMASI PAKET : PENINGKATAN JALAN MUG
LOKASI
TAHUN ANGGARAN
adya Dati II Samarinda
MATA KOMPONEN Kegiatan
PEMBA-
YARAN

Periksa peta lokasi DIV. I MOBILISASI


Agregat kurang baik 1.2. Mobilisasi

bahu) dalam (m) ( 0.5 + 4+ 0.5 ) Jumlah Harga Kegiatan Divisi 1 (Di pindahkan ke Rek
bahu) dalam (m) ( 0.5 + 4+ 0.5 )
DIV. II PERKERASAN BERBUTIR
5.1.(1). Lapis Pondasi Aggregat Kelas A
5.1.(2). Lapis Pondasi Aggregat Kelas B
5.1.(3). Lapis Telford Batu Gunung

Jumlah Harga Kegiatan Divisi 2 (Di pindahkan ke Rek

DIV. III PERKERASAN ASPAL


6.1.(1). Lapis Pengikat
6.3.(5). Asphalt Treated Base
8.1.(7). Lapen Macadam
Quary
Km Jumlah Harga Kegiatan Divisi 3 (Di pindahkan ke Rek
10.000 Km Lq 2 Km
DIV. IV Kegiatan STRUKTUR
3.844 Km = b B Komponen Slab Duiker (1 x 1)
Sta 7+687 2.1. Galian Parit
Km = c Lpmb 1 Km 2.2. Pasangan Batu Mortar
7.3. Pancangan Kayu Ulin
Pembuangan 7.2. Baja Tulangan
7.1.(1). Beton K-225
3.2.(2). Urugan Pilihan
Komponen Dinding Penahan
7.5.(3). Bronjong (Gabions)
7.00 Jam 7.3. Pancangan Kayu Ulin
2% x Harga Alat
0.20 Jumlah Harga Kegiatan Divisi 4 (Di pindahkan ke Rek
0.15
B dan Timbunan Tanah Pilihan
Batu Gunung sebagai dasar perkuatan

Periksa lampiran

SI UMUM HASIL PEREKAMAN ANALISA M


DAFTAR KUANTITAS
Program : PERHUBUNGAN DAN PENAN
INFORMASI PAKET Kegiatan : PEMELIHARAAN PERIODIK J
LOKASI
TAHUN ANGGARAN
adya Dati II Samarinda
MATA KOMPONEN Kegiatan
PEMBA-
YARAN

Periksa peta lokasi DIV. I MOBILISASI


Agregat kurang baik 1.2. Mobilisasi

bahu) dalam (m) ( 1+ L + 1) Jumlah Harga Kegiatan Divisi 1 (Di pindahkan ke Rek
bahu) dalam (m) ( 1+ L + 1)
DIV. II PERKERASAN BERBUTIR, ASPAL
JALAN PAMPANG (120 m2)
5.1.(3). Lapis Telford Batu Gunung 20 %
8.1.(7). Lapen Macadam
( 100 % x 3.000 m)
( 15 % x 30 m) JALAN ELANG (1.056 m2)
( 100 % x 155 m) 5.1.(3). Lapis Telford Batu Gunung 80 %
( 100 % x 264 m) 8.1.(7). Lapen Macadam

JALAN DAMANHURI (620 m2)


5.1.(3). Lapis Telford Batu Gunung 30 %
8.1.(7). Lapen Macadam

JALAN MUANG-BAYUR (3.000 m)


3.2.(2). Timbunan Batu Padas
5.1.(2). Lapis Pondasi Aggregat Kelas B

Jumlah Harga Kegiatan Divisi 2 (Di pindahkan ke Rek

7.00 Jam
2% x Harga Alat
0.20
0.15

Periksa lampiran

ESTIMATE

SI UMUM HASIL PEREKAMAN ANALISA M


DAFTAR KUANTITAS
Kegiatan : PENINGKATAN JALA
INFORMASI PAKET : PENINGKATAN RUAS JALAN
LOKASI
TAHUN ANGGARAN

MATA KOMPONEN Kegiatan


PEMBA-
YARAN

Periksa peta lokasi DIV. I MOBILISASI


Agregat kurang baik 1.2. Mobilisasi

bahu) dalam (m) ( 0.5 + 3+ 0.5 ) Jumlah Harga Kegiatan Divisi 1 (Di pindahkan ke Rek
bahu) dalam (m) ( 0.5 + 3+ 0.5 )
DIV. II PERKERASAN BERBUTIR
5.1.(1). Lapis Pondasi Aggregat Kelas A
5.1.(2). Lapis Pondasi Aggregat Kelas B

Jumlah Harga Kegiatan Divisi 2 (Di pindahkan ke Rek

DIV. III PERKERASAN ASPAL


6.1.(1). Lapis Pengikat
6.3.(5). Asphalt Treated Base

Jumlah Harga Kegiatan Divisi 3 (Di pindahkan ke Rek


Quary
Km DIV. IV Kegiatan STRUKTUR
10.000 Km Lq 2 Km Komponen Slab Duiker (1 x 1)
2.1. Galian Parit
0.350 Km = b B 2.2. Pasangan Batu Mortar
Sta 0+700 7.3. Pancangan Kayu Ulin
Km = c Lpmb 1 Km 7.2. Baja Tulangan
7.1.(1). Beton K-225
Pembuangan 3.2.(2). Urugan Pilihan

Jumlah Harga Kegiatan Divisi 4 (Di pindahkan ke Rek

7.00 Jam
2% x Harga Alat
0.20
0.15
ntum dalam lampiran

Periksa lampiran

SI UMUM HASIL PEREKAMAN ANALISA M


DAFTAR KUANTITAS
Kegiatan : PENINGKATAN JALA
INFORMASI PAKET : PENINGKATAN RUAS JALAN
LOKASI
TAHUN ANGGARAN

MATA KOMPONEN Kegiatan


PEMBA-
YARAN

Periksa peta lokasi DIV. I MOBILISASI


Agregat kurang baik 1.2. Mobilisasi

bahu) dalam (m) ( 1+ 3+ 1) Jumlah Harga Kegiatan Divisi 1 (Di pindahkan ke Rek
bahu) dalam (m) ( 1+ 3+ 1)
DIV. II PERKERASAN BERBUTIR
3.3. Penyiapan Badan Jalan
5.1.(3). Lapis Telford Batu Gunung

Jumlah Harga Kegiatan Divisi 2 (Di pindahkan ke Rek

DIV. III PERKERASAN ASPAL


8.1.(7). Lapen Macadam

Jumlah Harga Kegiatan Divisi 3 (Di pindahkan ke Rek


Quary DIV. IV Kegiatan STRUKTUR
Km Komponen Slab Duiker (1 x 1)
10.000 Km Lq 2 Km 2.1. Galian Parit
2.2. Pasangan Batu Mortar
2.625 Km = b B 7.3. Pancangan Kayu Ulin
Sta 5+250 7.2. Baja Tulangan
Km = c Lpmb 1 Km 7.1.(1). Beton K-225
3.2.(2). Urugan Pilihan
Pembuangan

Jumlah Harga Kegiatan Divisi 4 (Di pindahkan ke Rek

7.00 Jam
2% x Harga Alat
0.20
0.15

ntum dalam lampiran

Periksa lampiran

SI UMUM HASIL PEREKAMAN ANALISA M


DAFTAR KUANTITAS
Program : PERHUBUNGAN DAN PENAN
INFORMASI PAKET : PENINGKATAN RUAS JALAN
LOKASI
TAHUN ANGGARAN
adya Dati II Samarinda
MATA KOMPONEN Kegiatan
PEMBA-
YARAN
Periksa peta lokasi DIV. I MOBILISASI
Agregat kurang baik 1.2. Mobilisasi

bahu) dalam (m) ( 1+ 3+ 1) Jumlah Harga Kegiatan Divisi 1 (Di pindahkan ke Rek
bahu) dalam (m) ( 1+ 3+ 1)
DIV. II PERKERASAN BERBUTIR
3.3. Penyiapan Badan Jalan
5.1.(3). Lapis Telford Batu Gunung

Jumlah Harga Kegiatan Divisi 2 (Di pindahkan ke Rek

DIV. III PERKERASAN ASPAL


8.1.(7). Lapen Macadam

Jumlah Harga Kegiatan Divisi 3 (Di pindahkan ke Rek

Quary
Km
10.000 Km Lq 2 Km

2.625 Km = b B

Sta 5+250

Km = c Lpmb 1 Km

Pembuangan

7.00 Jam
2% x Harga Alat
0.20
0.15

ntum dalam lampiran


Periksa lampiran

SI UMUM HASIL PEREKAMAN ANALISA M


DAFTAR KUANTITAS
Program : PERHUBUNGAN DAN PENAN
INFORMASI PAKET Kegiatan : PENINGKATAN JALAN PELIT
LOKASI
TAHUN ANGGARAN
adya Dati II Samarinda
MATA KOMPONEN Kegiatan
PEMBA-
YARAN

Periksa peta lokasi DIV. I MOBILISASI


Agregat kurang baik 1.2. Mobilisasi

bahu) dalam (m) ( 0.5 + 5+ 0.5 ) Jumlah Harga Kegiatan Divisi 1 (Di pindahkan ke Rek
bahu) dalam (m) ( 0.5 + 5+ 0.5 )
DIV. II DRAINASE
2.1. Galian Parit
2.2. Pasangan Batu Mortar

Jumlah Harga Kegiatan Divisi 2 (Di pindahkan ke Rek

DIV. III PERKERASAN BERBUTIR


3.1.(1). Galian Biasa
3.2.(2). Urugan Pilihan
3.3. Penyiapan Badan Jalan
5.1.(1). Lapis Pondasi Aggregat Kelas A
Quary 6.1.(1).a. Lapis Pengikat + Debu Batu
Km 5.1.(3). Lapis Telford Batu Gunung
10.000 Km Lq 2 Km
Jumlah Harga Kegiatan Divisi 3 (Di pindahkan ke Rek
0.505 Km = b B

Sta 1+010 DIV. IV PERKERASAN ASPAL


Km = c Lpmb 1 Km 8.1.(7). Lapen Macadam
Pembuangan Jumlah Harga Kegiatan Divisi 4 (Di pindahkan ke Rek

DIV. V Kegiatan STRUKTUR


Komponen Slab Duiker (1 x 1)
2.1. Galian Parit
7.00 Jam 2.2. Pasangan Batu Mortar
2% x Harga Alat 7.3. Pancangan Kayu Ulin
0.20 7.2. Baja Tulangan
0.15 7.1.(1). Beton K-225
3.2.(2). Urugan Pilihan
Komponen Dinding Penahan
ntum dalam lampiran 2.3. Pasangan Batu Padas
7.3. Pancangan Kayu Ulin

Jumlah Harga Kegiatan Divisi 5 (Di pindahkan ke Rek

Periksa lampiran

KOP PERUSA
SI UMUM HASIL PEREKAMAN ANALISA M
DAFTAR KUANTITAS
Kegiatan : PENINGKATAN JALA
INFORMASI PAKET : PENINGKATAN RUAS JALAN
LOKASI
TAHUN ANGGARAN

MATA KOMPONEN Kegiatan


PEMBA-
YARAN

Periksa peta lokasi DIV. I MOBILISASI


Agregat kurang baik 1.2. Mobilisasi

bahu) dalam (m) ( 0.5 + 3+ 0.5 ) Jumlah Harga Kegiatan Divisi 1 (Di pindahkan ke Rek
bahu) dalam (m) ( 0.5 + 3+ 0.5 )
DIV. II PERKERASAN BERBUTIR
5.1.(1). Lapis Pondasi Aggregat Kelas A
5.1.(2). Lapis Pondasi Aggregat Kelas B

Jumlah Harga Kegiatan Divisi 2 (Di pindahkan ke Rek

DIV. III PERKERASAN ASPAL


6.1.(1). Lapis Pengikat
6.3.(5). Asphalt Treated Base

Jumlah Harga Kegiatan Divisi 3 (Di pindahkan ke Rek


Quary
Km DIV. IV Kegiatan STRUKTUR
10.000 Km Lq 2 Km Komponen Slab Duiker (1 x 1)
2.1. Galian Parit
0.350 Km = b B 2.2. Pasangan Batu Mortar
Sta 0+700 7.3. Pancangan Kayu Ulin
Km = c Lpmb 1 Km 7.2. Baja Tulangan
7.1.(1). Beton K-225
Pembuangan 3.2.(2). Urugan Pilihan

Jumlah Harga Kegiatan Divisi 4 (Di pindahkan ke Rek

7.00 Jam
2% x Harga Alat
0.20
0.15

ntum dalam lampiran

Periksa lampiran
PEREKAMAN ANALISA MASING-MASING HARGA R
DAFTAR KUANTITAS DAN HARGA
RHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Kegiatan
NINGKATAN JALAN RING ROAD III (TAHAP II) PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARAN

SATUAN PERKIRAAN HARGA JUMLAH NOMOR


KUANTITAS SATUAN HARGA MATA
(Rp.) (Rp.) PEMBAYARAN

DIVISI. I
Ls 1.00 6,074,875.00 6,074,875.00 DIVISI. II
DIVISI. III
Divisi 1 (Di pindahkan ke Rekapitulasi Biaya) 6,074,875.00 DIVISI. IV

A
M3 1,878.80 36,572.47 68,712,362.68 B
C
Divisi 2 (Di pindahkan ke Rekapitulasi Biaya) 68,712,362.68 D

LIMA RATUS TIGA PULUH TIGA JUT


M2 4,050.00 6,899.30 27,942,174.51
M3 2,956.50 18,433.42 54,498,394.35
M3 8,100.00 58,621.38 474,833,211.93
M3 2,145.68 394,879.91 847,283,949.49 DI PERIKSA OLEH :
KASUBSIE PERENCANAAN
Divisi 3 (Di pindahkan ke Rekapitulasi Biaya) 1,404,557,730.28 DATI II KOMAS

Buah 2.00 12,957,200.00 25,914,400.00


Buah 1.00 45,639,300.00 45,639,300.00 ACHMAD NAWAWI, ST
Nip. 550.011.214
Divisi 4 (Di pindahkan ke Rekapitulasi Biaya) 71,553,700.00

KEP
Ir. D

PEREKAMAN ANALISA MASING-MASING HARGA R


DAFTAR KUANTITAS DAN HARGA
RHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Kegiatan
NINGKATAN JALAN M. SAID PAKET

: DATI II KOMAS LOKASI


: 1999/2000 TAHUN ANGGARAN

SATUAN PERKIRAAN HARGA JUMLAH NOMOR


KUANTITAS SATUAN HARGA MATA
(Rp.) (Rp.) PEMBAYARAN

DIVISI. I
Ls 1.00 9,074,075.00 9,074,075.00 DIVISI. II

DIVISI. III
Divisi 1 (Di pindahkan ke Rekapitulasi Biaya) 9,074,075.00 DIVISI. IV

A
M3 1,006.25 485,107.32 488,139,242.72 B
M3 716.63 316,453.76 226,778,677.73 C
D
Divisi 2 (Di pindahkan ke Rekapitulasi Biaya) 714,917,920.45
ENAM RATUS EMPAT PULUH ENA

Liter 4,287.50 12,706.74 54,480,166.91


M3 306.25 2,786,608.54 853,398,866.43
M3 238.88 1,422,926.06 339,901,462.57 DI PERIKSA OLEH :
KASUBSIE PERENCANAAN
Divisi 3 (Di pindahkan ke Rekapitulasi Biaya) 1,247,780,495.91 DATI II KOMAS

Buah 9.00
M3 29.16 36,572.47 1,066,453.32 ACHMAD NAWAWI, ST
M3 147.78 66,676.33 9,853,428.26 Nip. 550.011.214
Titik 288.00 219,964.70 63,349,833.00
Kg 4,202.10 14,410.10 60,552,672.39
M3 27.90 1,682,547.76 46,943,082.45
M3 9.00 58,621.38 527,592.46 KEP

Divisi 4 (Di pindahkan ke Rekapitulasi Biaya) 182,293,061.87

Ir. D

PEREKAMAN ANALISA MASING-MASING HARGA R


DAFTAR KUANTITAS DAN HARGA
RHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Kegiatan
NINGKATAN JALAN MUGIREJO - LUBUK SAWA PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARAN

SATUAN PERKIRAAN HARGA JUMLAH NOMOR


KUANTITAS SATUAN HARGA MATA
(Rp.) (Rp.) PEMBAYARAN

DIVISI. I
Ls 1.00 #REF! #REF! DIVISI. II
DIVISI. III
Divisi 1 (Di pindahkan ke Rekapitulasi Biaya) #REF! DIVISI. IV

A
M3 207.75 485,107.32 100,781,046.14 B
M3 146.25 394,879.91 57,751,186.74 C
M3 1,140.00 316,453.76 360,757,289.54 D

Divisi 2 (Di pindahkan ke Rekapitulasi Biaya) 519,289,522.42 SEMBILAN RATUS EN

Liter 8,400.00 12,706.74 106,736,653.53


M3 600.00 2,786,608.54 1,671,965,126.08 DI PERIKSA OLEH :
M3 285.00 1,422,926.06 405,533,927.09 KASUBSIE PERENCANAAN
DATI II KOMAS
Divisi 3 (Di pindahkan ke Rekapitulasi Biaya) 2,184,235,706.69

Buah 5.00 ACHMAD NAWAWI, ST


M3 16.20 36,572.47 592,474.07 Nip. 550.011.214
M3 82.10 66,676.33 5,474,126.81
Titik 160.00 219,964.70 35,194,351.67
Kg 2,334.50 14,410.10 33,640,373.55
M3 15.50 1,682,547.76 26,079,490.25 KEP
M3 5.00 58,621.38 293,106.92
M1 36.20
M3 521.28 757,635.69 394,940,329.88
Titik 651.60 219,964.70 143,328,997.16
Ir. D
Divisi 4 (Di pindahkan ke Rekapitulasi Biaya) 639,543,250.30
PEREKAMAN ANALISA MASING-MASING HARGA R
DAFTAR KUANTITAS DAN HARGA
RHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Program
MELIHARAAN PERIODIK JALAN DALAM KOTA PAKET Kegiatan
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARAN

SATUAN PERKIRAAN HARGA JUMLAH NOMOR


KUANTITAS SATUAN HARGA MATA
(Rp.) (Rp.) PEMBAYARAN

DIVISI. I
Ls 1.00 6,077,175.00 6,077,175.00 DIVISI. II

Divisi 1 (Di pindahkan ke Rekapitulasi Biaya) 6,077,175.00 A


B
C
D
M3 3.60 316,453.76 1,139,233.55
M3 6.00 1,422,926.06 8,537,556.36 DUA RAT
9,676,789.91

M3 126.72 316,453.76 40,101,020.82


M3 52.80 1,422,926.06 75,130,495.97 DI PERIKSA OLEH :
115,231,516.78 KASUBSIE PERENCANAAN
DATI II KOMAS
M3 27.90 316,453.76 8,829,059.98
M3 31.00 1,422,926.06 44,110,707.86
52,939,767.84
UR (3.000 m) ACHMAD NAWAWI, ST
M3 2,400.00 158,698.12 380,875,477.68 Nip. 550.011.214
M3 313.20 394,879.91 123,676,387.61
504,551,865.29
Divisi 2 (Di pindahkan ke Rekapitulasi Biaya) 682,399,939.81
KEP

Ir. D

PEREKAMAN ANALISA MASING-MASING HARGA R


DAFTAR KUANTITAS DAN HARGA
: PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K) Kegiatan
NINGKATAN RUAS JALAN AIR TERJUN TANAH MERAH PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARAN

SATUAN PERKIRAAN HARGA JUMLAH NOMOR


KUANTITAS SATUAN HARGA MATA
(Rp.) (Rp.) PEMBAYARAN

DIVISI. I
Ls 1.00 9,537,525.00 9,537,525.00 DIVISI. II
DIVISI. III
Divisi 1 (Di pindahkan ke Rekapitulasi Biaya) 9,537,525.00 DIVISI. IV

A
M3 216.45 485,107.32 105,001,479.84 B
M3 288.60 394,879.91 113,962,341.84 C
D
Divisi 2 (Di pindahkan ke Rekapitulasi Biaya) 218,963,821.68
SERATUS LIMA PULUH JU

Liter 1,010.10 12,706.74 12,835,082.59


M3 72.15 2,786,608.54 201,053,806.41
DI PERIKSA OLEH :
Divisi 3 (Di pindahkan ke Rekapitulasi Biaya) 213,888,889.00 KASUBSIE PERENCANAAN
DATI II KOMAS

Buah 2.00
M3 6.48 36,572.47 236,989.63
M3 32.84 66,676.33 2,189,650.72 ACHMAD NAWAWI, ST
Titik 64.00 219,964.70 14,077,740.67 Nip. 550.011.214
Kg 933.80 14,410.10 13,456,149.42
M3 6.20 1,682,547.76 10,431,796.10
M3 2.00 58,621.38 117,242.77
KEP
Divisi 4 (Di pindahkan ke Rekapitulasi Biaya) 40,509,569.31

Ir. D
PEREKAMAN ANALISA MASING-MASING HARGA R
DAFTAR KUANTITAS DAN HARGA
: PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K) Kegiatan
NINGKATAN RUAS JALAN BUKUAN ( PALARAN ) PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARAN

SATUAN PERKIRAAN HARGA JUMLAH NOMOR


KUANTITAS SATUAN HARGA MATA
(Rp.) (Rp.) PEMBAYARAN

DIVISI. I
Ls 1.00 6,253,125.00 6,253,125.00 DIVISI. II
DIVISI. III
Divisi 1 (Di pindahkan ke Rekapitulasi Biaya) 6,253,125.00 DIVISI. IV

A
M2 9,002.00 6,899.30 62,107,519.74 B
M3 1,350.30 316,453.76 427,307,515.84 C
D
Divisi 2 (Di pindahkan ke Rekapitulasi Biaya) 489,415,035.58
EMPAT RATUS ENAM BELAS JU

M3 450.10 1,422,926.06 640,459,019.58

Divisi 3 (Di pindahkan ke Rekapitulasi Biaya) 640,459,019.58 DI PERIKSA OLEH :


KASUBSIE PERENCANAAN
DATI II KOMAS
Buah 9.00
M3 29.16 36,572.47 1,066,453.32
M3 147.78 66,676.33 9,853,428.26
Titik 288.00 219,964.70 63,349,833.00 ACHMAD NAWAWI, ST
Kg 4,202.10 14,410.10 60,552,672.39 Nip. 550.011.214
M3 27.90 1,682,547.76 46,943,082.45
M3 9.00 58,621.38 527,592.46

Divisi 4 (Di pindahkan ke Rekapitulasi Biaya) 182,293,061.87 KEP

Ir. D

PEREKAMAN ANALISA MASING-MASING HARGA R


DAFTAR KUANTITAS DAN HARGA
RHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Program
NINGKATAN RUAS JALAN BUKUAN ( PALARAN ) ( LANJUTAN ) PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARAN

SATUAN PERKIRAAN HARGA JUMLAH NOMOR


KUANTITAS SATUAN HARGA MATA
(Rp.) (Rp.) PEMBAYARAN
DIVISI. I
Ls 1.00 2,776,100.00 2,776,100.00 DIVISI. II
DIVISI. III
Divisi 1 (Di pindahkan ke Rekapitulasi Biaya) 2,776,100.00
A
B
M2 9,030.00 6,899.30 62,300,700.20 C
M3 1,354.50 316,453.76 428,636,621.65 D

Divisi 2 (Di pindahkan ke Rekapitulasi Biaya) 490,937,321.85 TIGA RATUS

M3 451.50 1,422,926.06 642,451,116.07


DI PERIKSA OLEH :
Divisi 3 (Di pindahkan ke Rekapitulasi Biaya) 642,451,116.07 KASUBSIE PERENCANAAN
DATI II KOMAS

ACHMAD NAWAWI, ST
Nip. 550.011.214

KEP

Ir. D
PEREKAMAN ANALISA MASING-MASING HARGA R
DAFTAR KUANTITAS DAN HARGA
RHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Program
NINGKATAN JALAN PELITA IV PAKET Kegiatan
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARAN

SATUAN PERKIRAAN HARGA JUMLAH NOMOR


KUANTITAS SATUAN HARGA MATA
(Rp.) (Rp.) PEMBAYARAN

DIVISI. I
Ls 1.00 7,127,125.00 7,127,125.00 DIVISI. II
DIVISI. III
Divisi 1 (Di pindahkan ke Rekapitulasi Biaya) 7,127,125.00 DIVISI. IV
DIVISI. V

M3 59.76 36,572.47 2,185,571.00 A


M3 34.86 66,676.33 2,324,336.91 B
C
Divisi 2 (Di pindahkan ke Rekapitulasi Biaya) 4,509,907.91 D

TIGA RATUS T
M3 577.20 48,685.24 28,101,118.80
M3 972.13 58,621.38 56,987,313.10
M2 2,075.00 6,899.30 14,316,052.37
M3 583.80 485,107.32 283,205,654.56 DI PERIKSA OLEH :
Liter 1,239.00 15,388.13 19,065,890.55 KASUBSIE PERENCANAAN
M3 744.00 316,453.76 235,441,599.49 DATI II KOMAS

Divisi 3 (Di pindahkan ke Rekapitulasi Biaya) 637,117,628.87

ACHMAD NAWAWI, ST
M3 289.80 1,422,926.06 412,363,972.17 Nip. 550.011.214
Divisi 4 (Di pindahkan ke Rekapitulasi Biaya) 412,363,972.17

KEP
Buah 1.00
M3 3.24 36,572.47 118,494.81
M3 16.42 66,676.33 1,094,825.36
Titik 32.00 219,964.70 7,038,870.33
Kg 466.90 14,410.10 6,728,074.71 Ir. D
M3 3.10 1,682,547.76 5,215,898.05
M3 1.00 58,621.38 58,621.38
M1 156.00
M3 295.78 399,372.05 118,124,667.01
Titik 314.00 219,964.70 69,068,915.15

Divisi 5 (Di pindahkan ke Rekapitulasi Biaya) 207,448,366.81

KOP PERUSAHAAN KO
PEREKAMAN ANALISA MASING-MASING HARGA R
DAFTAR KUANTITAS DAN HARGA
: PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K) Kegiatan
NINGKATAN RUAS JALAN AIR TERJUN TANAH MERAH PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARAN

SATUAN PERKIRAAN HARGA JUMLAH NOMOR


KUANTITAS SATUAN HARGA MATA
(Rp.) (Rp.) PEMBAYARAN

DIVISI. I
Ls 1.00 DIVISI. II
DIVISI. III
Divisi 1 (Di pindahkan ke Rekapitulasi Biaya) DIVISI. IV

A
M3 216.45 B
M3 288.60 C
D
Divisi 2 (Di pindahkan ke Rekapitulasi Biaya)
TERBILANG : ( .....

Liter 1,010.10
M3 72.15

Divisi 3 (Di pindahkan ke Rekapitulasi Biaya)

Buah 2.00
M3 6.48
M3 32.84
Titik 64.00
Kg 933.80
M3 6.20
M3 2.00

Divisi 4 (Di pindahkan ke Rekapitulasi Biaya)

SAMARINDA, 29 SEPTEMBER 1999


DI SIAPKAN OLEH :
PENAWAR
PT / CV. ............................

( NAMA JELAS )
Jabatan
Cap Perusahaan
REKAPITULASI Kegiatan

UBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Kegiatan


: PENINGKATAN JALAN RING ROAD III (TAHAP II) PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARA

KOMPONEN Kegiatan HARGA I


Kegiatan 1.2.
(Rp.)
II
MOBILISASI 6,074,875.00 2.1.
DRAINASE 68,712,362.68
PERKERASAN BERBUTIR 1,404,557,730.28 III
STRUKTUR 71,553,700.00 3.3.
3.2.(1).
JUMLAH HARGA 1,550,898,667.96 3.2.(2).
PPN (10 % x A) 155,089,866.80 5.1.(2).
JUMLAH TOTAL HARGA (A + B) 1,705,988,534.76
PEMBULATAN 1,705,988,000.00 IV
Bow.1.
A RATUS TIGA PULUH TIGA JUTA LIMA RATUS DELAPAN PULUH EMPAT RIBU RUPIAH Bow.2.

PERIKSA OLEH : DI SIAPKAN OLEH :


SIE PERENCANAAN PEMIMPIN Kegiatan
ATI II KOMAS PERHUBUNGAN DAN PENANGANAN
JALAN KOTAMADYA (PPJK) Catatan :

1.
MAD NAWAWI, ST H. THAMRIN. B
Nip. 550.011.214 Nip. 550.009.381
2.

DI SETUJUI OLEH :
KEPALA SEKSI BINA MARGA
DPU DATI II KOMAS
Ir. DADANG AIRLANGGA. N
Nip. 550.013.096

REKAPITULASI Kegiatan

UBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Kegiatan


: PENINGKATAN JALAN M. SAID PAKET

: DATI II KOMAS LOKASI


: 1999/2000 TAHUN ANGGARA

KOMPONEN Kegiatan HARGA I


Kegiatan 1.2.
(Rp.)
II
MOBILISASI 9,074,075.00 5.1.(1).
PERKERASAN BERBUTIR 714,917,920.45 5.1.(3).

PERKERASAN ASPAL 1,247,780,495.91


STRUKTUR 182,293,061.87 III
6.1.(1).
JUMLAH HARGA 2,154,065,553.24 6.3.(5).
PPN (10 % x A) 215,406,555.32 8.1.(7).
JUMLAH TOTAL HARGA (A + B) 2,369,472,108.56
PEMBULATAN 2,369,472,000.00 IV
AM RATUS EMPAT PULUH ENAM JUTA LIMA RATUS ENAM PULUH SATU RIBU RUPIAH 2.1.
2.2.
7.3.
7.2.
PERIKSA OLEH : DI SIAPKAN OLEH : 7.1.(1).
SIE PERENCANAAN PEMIMPIN Kegiatan 3.2.(2).
ATI II KOMAS PERHUBUNGAN DAN PENANGANAN
JALAN KOTAMADYA (PPJK)

MAD NAWAWI, ST H. THAMRIN. B


Nip. 550.011.214 Nip. 550.009.381

DI SETUJUI OLEH :
KEPALA SEKSI BINA MARGA
DPU DATI II KOMAS

Ir. DADANG AIRLANGGA. N


Nip. 550.013.096

REKAPITULASI Kegiatan

UBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Kegiatan


: PENINGKATAN JALAN MUGIREJO - LUBUK SAWA PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARA

KOMPONEN Kegiatan HARGA I


Kegiatan 1.2.
(Rp.)
II
MOBILISASI #REF! 5.1.(1).
PERKERASAN BERBUTIR 519,289,522.42 5.1.(2).
PERKERASAN ASPAL 2,184,235,706.69 5.1.(3).
STRUKTUR 639,543,250.30
III
JUMLAH HARGA #REF! 6.1.(1).
PPN (10 % x A) #REF! 6.3.(5).
JUMLAH TOTAL HARGA (A + B) #REF! 8.1.(7).
PEMBULATAN #REF!
IV
SEMBILAN RATUS ENAM PULUH DUA JUTA DUA RIBU RUPIAH
2.1.
2.2.
7.3.
PERIKSA OLEH : DI SIAPKAN OLEH : 7.2.
SIE PERENCANAAN PEMIMPIN Kegiatan 7.1.(1).
ATI II KOMAS PERHUBUNGAN DAN PENANGANAN 3.2.(2).
JALAN KOTAMADYA (PPJK)
7.5.(3).
7.3.
MAD NAWAWI, ST H. THAMRIN. B
Nip. 550.011.214 Nip. 550.009.381

DI SETUJUI OLEH :
KEPALA SEKSI BINA MARGA
DPU DATI II KOMAS

Ir. DADANG AIRLANGGA. N


Nip. 550.013.096
REKAPITULASI Kegiatan

UBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Kegiatan


: PEMELIHARAAN PERIODIK JALAN DALAM KOTA PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARA

KOMPONEN Kegiatan HARGA I


Kegiatan 1.2.
(Rp.)
DIV. II
MOBILISASI 6,077,175.00
PERKERASAN BERBUTIR & ASPAL 682,399,939.81 5.1.(3).
8.1.(7).
JUMLAH HARGA 688,477,114.81
PPN (10 % x A) 68,847,711.48
JUMLAH TOTAL HARGA (A + B) 757,324,826.29 5.1.(3).
PEMBULATAN 757,324,000.00 8.1.(7).

DUA RATUS LIMA PULUH JUTA RUPIAH


5.1.(3).
8.1.(7).

PERIKSA OLEH : DI SIAPKAN OLEH :


SIE PERENCANAAN PEMIMPIN Kegiatan 3.2.(2).
ATI II KOMAS PERHUBUNGAN DAN PENANGANAN 5.1.(2).
JALAN KOTAMADYA (PPJK)

MAD NAWAWI, ST H. THAMRIN. B


Nip. 550.011.214 Nip. 550.009.381
DI SETUJUI OLEH :
KEPALA SEKSI BINA MARGA
DPU DATI II KOMAS

Ir. DADANG AIRLANGGA. N


Nip. 550.013.096

REKAPITULASI Kegiatan
: PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K) Kegiatan
: PENINGKATAN RUAS JALAN AIR TERJUN TANAH MERAH PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARA

KOMPONEN Kegiatan HARGA I


Kegiatan 1.2.
(Rp.)
II
MOBILISASI 9,537,525.00 5.1.(1).
PERKERASAN BERBUTIR 218,963,821.68 5.1.(2).
PERKERASAN ASPAL 213,888,889.00
STRUKTUR 40,509,569.31 III
6.1.(1).
JUMLAH HARGA 482,899,804.98 6.3.(5).
PPN (10 % x A) 48,289,980.50
JUMLAH TOTAL HARGA (A + B) 531,189,785.48 IV
PEMBULATAN 531,189,000.00
2.1.
SERATUS LIMA PULUH JUTA TIGA RATUS EMPAT PULUH RIBU RUPIAH 2.2.
7.3.
7.2.
7.1.(1).
PERIKSA OLEH : DI SIAPKAN OLEH : 3.2.(2).
SIE PERENCANAAN PERENCANA
ATI II KOMAS CV. GEOMAP Consultant

MAD NAWAWI, ST Ir. MIRA FARENOLA


Nip. 550.011.214

DI SETUJUI OLEH :
KEPALA SEKSI BINA MARGA
DPU DATI II KOMAS

Ir. DADANG AIRLANGGA. N


Nip. 550.013.096
REKAPITULASI Kegiatan

: PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K) Kegiatan


: PENINGKATAN RUAS JALAN BUKUAN ( PALARAN ) PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARA

KOMPONEN Kegiatan HARGA I


Kegiatan 1.2.
(Rp.)
II
MOBILISASI 6,253,125.00 3.3.
PERKERASAN BERBUTIR 489,415,035.58 5.1.(3).
PERKERASAN ASPAL 640,459,019.58
STRUKTUR 182,293,061.87 III
8.1.(7).
JUMLAH HARGA 1,318,420,242.04
PPN (10 % x A) 131,842,024.20 IV
JUMLAH TOTAL HARGA (A + B) 1,450,262,266.24
PEMBULATAN 1,450,262,000.00 2.1.
2.2.
EMPAT RATUS ENAM BELAS JUTA DUA RATUS LIMA PULUH ENAM RIBU RUPIAH 7.3.
7.2.
7.1.(1).
3.2.(2).
PERIKSA OLEH : DI SIAPKAN OLEH :
SIE PERENCANAAN PEMIMPIN Kegiatan
ATI II KOMAS PENINGKATAN JALAN POROS DESA /
KECAMATAN (PPJPD/K)

MAD NAWAWI, ST BUDI TRISTRYONO, BE


Nip. 550.011.214 Nip. 550.013.606

DI SETUJUI OLEH :
KEPALA SEKSI BINA MARGA
DPU DATI II KOMAS

Ir. DADANG AIRLANGGA. N


Nip. 550.013.096

REKAPITULASI Kegiatan

UBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Kegiatan


: PENINGKATAN RUAS JALAN BUKUAN ( PALARAN ) ( LANJUTAN ) PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARA

KOMPONEN Kegiatan HARGA I


Kegiatan 1.2.
(Rp.)
II
MOBILISASI 2,776,100.00 3.3.
PERKERASAN BERBUTIR 490,937,321.85
PERKERASAN ASPAL 642,451,116.07

JUMLAH HARGA 1,136,164,537.92


PPN (10 % x A) 113,616,453.79 5.1.(3).
JUMLAH TOTAL HARGA (A + B) 1,249,780,991.71
PEMBULATAN 1,249,780,000.00

TIGA RATUS DUA PULUH LIMA JUTA RUPIAH

III
8.1.(7).
PERIKSA OLEH : DI SIAPKAN OLEH :
SIE PERENCANAAN PEMIMPIN Kegiatan
ATI II KOMAS PERHUBUNGAN DAN PENANGANAN
JALAN KOTAMADYA (PPJK)

MAD NAWAWI, ST H. THAMRIN. B


Nip. 550.011.214 Nip. 550.009.381

DI SETUJUI OLEH :
KEPALA SEKSI BINA MARGA
DPU DATI II KOMAS

Ir. DADANG AIRLANGGA. N


Nip. 550.013.096
REKAPITULASI Kegiatan

UBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA Program


: PENINGKATAN JALAN PELITA IV PAKET Kegiatan
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARA

KOMPONEN Kegiatan HARGA I


Kegiatan 1.2.
(Rp.)
II
MOBILISASI 7,127,125.00 2.1.
DRAINASE 4,509,907.91 2.2.
PERKERASAN BERBUTIR 637,117,628.87
PERKERASAN ASPAL 412,363,972.17
STRUKTUR 207,448,366.81 III
3.1.(1).
JUMLAH HARGA 1,268,567,000.76 3.2.(2).
PPN (10 % x A) 126,856,700.08 3.3.
JUMLAH TOTAL HARGA (A + B) 1,395,423,700.84 5.1.(1).
PEMBULATAN 1,395,423,000.00

TIGA RATUS TUJUH PULUH TUJUH JUTA RUPIAH


6.1.(1).a.
5.1.(3).

PERIKSA OLEH : DI SIAPKAN OLEH :


SIE PERENCANAAN PEMIMPIN Kegiatan
ATI II KOMAS PERHUBUNGAN DAN PENANGANAN
JALAN KOTAMADYA (PPJK) IV
8.1.(7).

MAD NAWAWI, ST M. AGUS HUSEIN V


Nip. 550.011.214 Nip. 550.009.250
2.1.
2.2.
DI SETUJUI OLEH : 7.3.
KEPALA SEKSI BINA MARGA 7.2.
DPU DATI II KOMAS 7.1.(1).
3.2.(2).

2.3.
Ir. DADANG AIRLANGGA. N 7.3.
Nip. 550.013.096

KOP PERUSAHAAN
REKAPITULASI Kegiatan

: PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K) Kegiatan


: PENINGKATAN RUAS JALAN AIR TERJUN TANAH MERAH PAKET
: DATI II KOMAS LOKASI
: 1999/2000 TAHUN ANGGARA

KOMPONEN Kegiatan HARGA I


Kegiatan 1.2.
(Rp.)
II
MOBILISASI 5.1.(1).
PERKERASAN BERBUTIR 5.1.(2).
PERKERASAN ASPAL
STRUKTUR III
6.1.(1).
JUMLAH HARGA 6.3.(5).
PPN (10 % x A)
JUMLAH TOTAL HARGA (A + B) IV
PEMBULATAN
2.1.
TERBILANG : ( .......... di tulis dengan huruf yang jelas ......... ) 2.2.
7.3.
7.2.
SAMARINDA, 29 SEPTEMBER 1999 7.1.(1).
DI SIAPKAN OLEH : 3.2.(2).
PENAWAR
PT / CV. ............................

( NAMA JELAS )
Jabatan
Cap Perusahaan
PERHITUNGAN VOLUME Kegiatan

: PERHUBUNGAN
KegiatanDAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
: PENINGKATAN JALAN RING ROAD III (TAHAP II)
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000

MOBILISASI
Mobilisasi = = 1.00

DRAINASE
Galian Parit = [(1,30 x 0,9) ÷ 2] x 0,8 x 2.135) = 1,878.80

PERKERASAN BERBUTIR
Penyiapan Badan Jalan = 135 x 30 = 4,050.00
Urugan Tanah Biasa = 135 x 30 x 0,73 = 2,956.50
Urugan Tanah Pilihan = 135 x 30 x 2.0 = 8,100.00
Lapis Pondasi Aggregat Kelas B = (0,15 x 6,7) x 2.135 = 2,145.68

STRUKTUR
Gorong-Gorong Kayu Ulin = = 2.00
Jembatan Kayu Ulin = = 1.00

Biaya Kegiatan untuk galian biasa di limpahkan untuk pembayaran hutang ganti rugi tanam tumbuh yang
belum terselesaikan pada Kegiatan BPJK T.A. 1998 / 1999 sebesar Rp. 39.000,000-

Biaya Kegiatan untuk gorong-gorong kayu ulin (1,00 x 1,00) di limpahkan untuk pembayaran pada
Kegiatan serupa menanggulangi banjir pada Kegiatan BPJK T.A. 1998 / 1999 sebesar Rp. 23.000,000-

Perihal ini saya buat berdasarkan hasil permasalahan yang terjadi, di mana kedua permasalahan ini
keperluannya sangat mendesak, sedangkan dana sangat terbatas. Sehingga CV. JAYA PERKASA ABADI
bersedia menanggulangi beban tersebut namun dengan syarat akan di realisasikan dalam T.A. sekarang.
Perihal ini kemungkinan belum di sampaikan oleh Pemimpin Kegiatan sebelumnya, namun karena saya di
saat Kegiatan tersebut berlangsung bertindak sebagai Konsultan Pengawas, sehingga permasalahan
tersebut saya mengerti duduk persoalannya.
Adapun perihal ini saya sampaikan dengan tujuan untuk mengantisipasi kemungkinan, apabila terjadi
permasalahan penuntutan hak tersebut di atas oleh Kontraktor Pelaksana.
Demikian perihal yang saya sampaikan.

PERHITUNGAN VOLUME Kegiatan

PERHUBUNGAN
Kegiatan
DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
: PENINGKATAN JALAN M. SAID

LOKASI : DATI II KOMAS


TAHUN ANGGARAN : 1999/2000

MOBILISASI
Mobilisasi = = 1.00

PERKERASAN BERBUTIR
Lapis Pondasi Aggregat Kelas A = (0,35 x 2,5 x 100) + (0,10 x 4) x 1.750 = 1,006.25
Lapis Pondasi Telford Batu Gunung = (0,15 x 3,5) x 1.365 = 716.63

PERKERASAN ASPAL
Lapis Pengikat = (0,7 Lt/m2 x 3,5) x 1.750 = 4,287.50
Asphalt Treated Base = (0,05 x 3,5) x 1.750 = 306.25
Lapen Macadam = (0,05 x 3,5) x 1.365 = 238.88

Kegiatan STRUKTUR
Komponen Slab Duiker (1 x 1) = = 9.00
Galian Parit
Pasangan Batu Mortar
Pancangan Kayu Ulin
Baja Tulangan
Beton K-225
Urugan Pilihan

PERHITUNGAN VOLUME Kegiatan

PERHUBUNGAN
Kegiatan
DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
: PENINGKATAN JALAN MUGIREJO - LUBUK SAWA
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000

MOBILISASI
Mobilisasi = = 1.00

PERKERASAN BERBUTIR
Lapis Pondasi Aggregat Kelas A = (0.1 x 3 x 3.675 x 10 %)+(0.1 x 3 x 325) = 207.75
Lapis Pondasi Aggregat Kelas B = (0,15 x 3) x 325 = 146.25
Lapis Pondasi Telford Batu Gunung = (0,20 x 3) x 1.900 = 1,140.00

PERKERASAN ASPAL
Lapis Pengikat = (0,7 Lt/m2 x 3) x 4.000 = 8,400.00
Asphalt Treated Base = (0,05 x 3) x 4.000 = 600.00
Lapen Macadam = (0,05 x 3) x 1.900 = 285.00

Kegiatan STRUKTUR
Komponen Slab Duiker (1 x 1) = = 5.00
Galian Parit
Pasangan Batu Mortar
Pancangan Kayu Ulin
Baja Tulangan
Beton K-225
Urugan Pilihan
Komponen Dinding Penahan = = 36.20
Bronjong (Gabions)
Pancangan Kayu Ulin
PERHITUNGAN VOLUME Kegiatan

PERHUBUNGAN
Kegiatan
DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
: PEMELIHARAAN PERIODIK JALAN DALAM KOTA
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000

MOBILISASI
Mobilisasi = = 1.00

PERKERASAN BERBUTIR & ASPAL


JALAN PAMPANG (120 m2)
Lapis Telford Batu Gunung = (30 x 4 x 0,15) x 20 % kerusakan = 3.60
Lapen Macadam = (30 x 4 x 0,05) = 6.00

JALAN ELANG (1.056 m2)


Lapis Telford Batu Gunung = (264 x 4 x 0,15) x 80 % kerusakan = 126.72
Lapen Macadam = (264 x 4 x 0,05) = 52.80

JALAN DAMANHURI (620 m2)


Lapis Telford Batu Gunung = (155 x 4 x 0,15) x 30 % kerusakan = 27.90
Lapen Macadam = (155 x 4 x 0,05) = 31.00

JALAN MUANG - BAYUR (3.000 m)


Timbunan Batu Padas = (3.000 x 4 x 0,20) = 2,400.00
Lapis Pondasi Aggregat Kelas B = (522 x 4 x 0,15) = 313.20
PERHITUNGAN VOLUME Kegiatan
: PENINGKATAN
Kegiatan JALAN POROS DESA / KECAMATAN (PPJPD/K)
: PENINGKATAN RUAS JALAN AIR TERJUN TANAH MERAH
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000

MOBILISASI
Mobilisasi = = 1.00

PERKERASAN BERBUTIR
Lapis Pondasi Aggregat Kelas A = (0,15 x 3 x 481) = 216.45
Lapis Pondasi Aggregat Kelas B = (0,20 x 3 x 481) = 288.60

PERKERASAN ASPAL
Lapis Pengikat = (0,7 Lt/m2 x 3) x 481 = 1,010.10
Asphalt Treated Base = (0,05 x 3) x 481 = 72.15

Kegiatan STRUKTUR
Komponen Slab Duiker (1 x 1) = = 2.00
Galian Parit
Pasangan Batu Mortar
Pancangan Kayu Ulin
Baja Tulangan
Beton K-225
Urugan Pilihan
PERHITUNGAN VOLUME Kegiatan

: PENINGKATAN
Kegiatan JALAN POROS DESA / KECAMATAN (PPJPD/K)
: PENINGKATAN RUAS JALAN BUKUAN ( PALARAN )
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000

MOBILISASI
Mobilisasi = = 1.00

PERKERASAN BERBUTIR
Penyiapan Badan Jalan = (3,5) x 2.572 = 9,002.00
Lapis Pondasi Telford Batu Gunung = (0,15 x 3,5) x 2.572 = 1,350.30

PERKERASAN ASPAL
Lapen Macadam = (0,05 x 3,5) x 2.572 = 450.10

Kegiatan STRUKTUR
Komponen Slab Duiker (1 x 1) = = 9.00
Galian Parit
Pasangan Batu Mortar
Pancangan Kayu Ulin
Baja Tulangan
Beton K-225
Urugan Pilihan
PERHITUNGAN VOLUME Kegiatan

PERHUBUNGAN
Kegiatan
DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
: PENINGKATAN RUAS JALAN BUKUAN ( PALARAN ) ( LANJUTAN )
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000

MOBILISASI
Mobilisasi = = 1.00
PERKERASAN BERBUTIR
Penyiapan Badan Jalan
Ruas I = (1,050 x 3) = 3,150.00
Ruas II = (1,400 x 3) + (560 x 3) = 5,880.00
= 9,030.00

Lapis Pondasi Telford Batu Gunung


Ruas I = (1,050 x 3 x 0,15) = 472.50
Ruas II = (1,400 x 3 x 0,15) + (560 x 3 x 0,15) = 882.00
= 1,354.50

PERKERASAN ASPAL
Lapen Macadam
Ruas I = (1,050 x 3 x 0,05) = 157.50
Ruas II = (1,400 x 3 x 0,05) + (560 x 3 x 0,05) = 294.00
= 451.50
PERHITUNGAN VOLUME Kegiatan

PERHUBUNGAN
Program
DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
KET Kegiatan : PENINGKATAN JALAN PELITA IV
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000

MOBILISASI
Mobilisasi = = 1.00

DRAINASE
Galian Parit = [(1,1 x 0,7) ÷ 2] x 0,8 x 83 m) = 59.76
Pasangan Batu Mortar = [(1,1 x 0,7) ÷ 2] x 0,8 -
[(0,7 x 0,3) ÷ 2] x 0,6 x 83 m) = 34.86

PERKERASAN BERBUTIR
Galian Biasa = (1,443 x 8 x 50) = 577.20
Urugan Pilihan = (5.05 x 192,5) = 972.13
Penyiapan Badan Jalan = (415 x 5) = 2,075.00
Lapis Pondasi Aggregat Kelas A = =
Jalan Ke RSS = (490 x 3,0 x 0,20) = 294.00
Jalan PELITA IV = (920 x 4,5 x 0,07) = 289.80
= 583.80
Lapis Pengikat + Debu Batu = (590 x 3 x 0,7) = 1,239.00
Lapis Pondasi Telford Batu Gunung = (440 x 4,5 x 0,20) = 396.00
= (480 x 1,0 x 0,20) = 96.00
= (480 x 3,5 x 0,15) = 252.00
= 744.00

PERKERASAN ASPAL
Lapen Macadam = (920 x 4,5 x 0,07) = 289.8

Kegiatan STRUKTUR
Komponen Slab Duiker (1 x 1) = = 1.00
Galian Parit
Pasangan Batu Mortar
Pancangan Kayu Ulin
Baja Tulangan
Beton K-225
Urugan Pilihan
Komponen Dinding Penahan = = 156.00
Pasangan Batu Padas
Pancangan Kayu Ulin

KOP PERUSAHAAN
PERHITUNGAN VOLUME Kegiatan

: PENINGKATAN
Kegiatan JALAN POROS DESA / KECAMATAN (PPJPD/K)
: PENINGKATAN RUAS JALAN AIR TERJUN TANAH MERAH
LOKASI : DATI II KOMAS
TAHUN ANGGARAN : 1999/2000

MOBILISASI
Mobilisasi = = 1.00

PERKERASAN BERBUTIR
Lapis Pondasi Aggregat Kelas A = (0,15 x 3 x 481) = 216.45
Lapis Pondasi Aggregat Kelas B = (0,20 x 3 x 481) = 288.60

PERKERASAN ASPAL
Lapis Pengikat = (0,7 Lt/m2 x 3) x 481 = 1,010.10
Asphalt Treated Base = (0,05 x 3) x 481 = 72.15
Kegiatan STRUKTUR
Komponen Slab Duiker (1 x 1) = = 2.00
Galian Parit
Pasangan Batu Mortar
Pancangan Kayu Ulin
Baja Tulangan
Beton K-225
Urugan Pilihan
SAMARINDA, 29 SEPTEMBER 1999
DI SIAPKAN OLEH :
PENAWAR
PT / CV. ............................

( NAMA JELAS )
Jabatan
Cap Perusahaan
atan PERHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
DAFTAR USULAN RENCANA KERJA Kegiatan : 1999/2000
Kegiatan DAERAH TINGKAT I : KALIMANTAN TIMUR
KOTAMADYA DAERAH TINGKAT II : SAMARINDA
NOMOR Kegiatan : 01

1 Nama Kegiatan : Peningkatan Jalan Ring Road III 11 Bendahara Kegiatan

2 Lokasi Kegiatan : Kotamadya Samarinda Nama


Ls 3 Jenis Penanganan : Galian, Timbunan, Perkerasan Badan Jalan Pangkat

4 Tujuan Manfaat Kegiatan : Membuka Jalan Baru Untuk Umum Jabatan

5 Volume Fisik : 2,135 M 12 Lampiran


M3 6 Jumlah Hari Kerja / Manday : 150 Hari kalender A
7 Perincian Jenis Pengeluaran Biaya : Dalam Ribuan Rupiah B
C

M2 JENIS PENGELUARAN JUMLAH %

M3 A Upah = Rp. 83,232,148.79 4.879

M3 B Bahan-Bahan Lokal = Rp. 212,573,444.60 12.460


M3 C Bahan-Bahan Lain = Rp. 225544891.14 13.221

D Alat-Alat = Rp. 1,178,562,640.47 69.084 Walikotamadya Kepala Daerah

E Lain-Lain = Rp. 6,074,875.00 0.356 Tingkat II Kotamadya Samarinda

Buah JUMLAH = Rp. 1,705,988,000.00 100.000

Buah 8 Sumber Pembiayaan Dalam Ribuan Rupiah

SUMBER PEMBIAYAAN JUMLAH % LUKMAN SAID

Dana APBN = Rp.

Dana BLN (SPL-OECF INP-23) = Rp. 1,705,988,000.00 100.000

JUMLAH = Rp. 1,705,988,000.00 100.000 An. Ketua Bappeda

9 RENCANA PELAKSANAAN Prop. Daerah Tingkat I

A Mulai Tanggal : Agustus 1999 Kalimantan Timur

B Selesai Tanggal : Desember 1999 Kabid Fisik & Prasarana

10 Pemimpin Kegiatan

umbuh yang Nama : H. THAMRIN. B

Pangkat : Ir. H. SYAIFUL BACHRI

Jabatan : Nip. 550009122

ran pada

alahan ini
ASA ABADI
A. sekarang.
arena saya di
masalahan

bila terjadi

atan PERHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA


DAFTAR USULAN RENCANA KERJA Kegiatan : 1999/2000
Kegiatan DAERAH TINGKAT I : KALIMANTAN TIMUR
KOTAMADYA DAERAH TINGKAT II : SAMARINDA

NOMOR Kegiatan : 02

1 Nama Kegiatan : Peningkatan Jalan M. Said 11 Bendahara Kegiatan

2 Lokasi Kegiatan : Kotamadya Samarinda Nama


Ls 3 Jenis Penanganan : ATB & Aspal Penetrasi Macadam Pangkat

4 Tujuan Manfaat Kegiatan : Menunjang Pelayanan Umum / Pendidikan Jabatan

5 Volume Fisik : 3,115 M 12 Lampiran


M3 6 Jumlah Hari Kerja / Manday : 150 Hari kalender A
M3 7 Perincian Jenis Pengeluaran Biaya : Dalam Ribuan Rupiah B

JENIS PENGELUARAN JUMLAH %

Liter A Upah = Rp. 10,732,636.55 0.453

M3 B Bahan-Bahan Lokal = Rp. 137,250,004.68 5.792


M3 C Bahan-Bahan Lain = Rp. 447,194,002.14 18.873
D Alat-Alat = Rp. 1,765,221,281.63 74.499 Walikotamadya Kepala Daerah

E Lain-Lain = Rp. 9,074,075.00 0.383 Tingkat II Kotamadya Samarinda


Buah JUMLAH = Rp. 2,369,472,000.00 100.000
8 Sumber Pembiayaan Dalam Ribuan Rupiah

SUMBER PEMBIAYAAN JUMLAH LUKMAN SAID

Dana APBN = Rp.


Dana BLN (SPL-OECF INP-23) = Rp. 2,369,472,000.00 100.000
JUMLAH = Rp. 2,369,472,000.00 100.000 An. Ketua Bappeda
9 RENCANA PELAKSANAAN Prop. Daerah Tingkat I
A Mulai Tanggal : Agustus 1999 Kalimantan Timur
B Selesai Tanggal : Desember 1999 Kabid Fisik & Prasarana
10 Pemimpin Kegiatan
Nama : H. THAMRIN. B

Pangkat : Ir. H. SYAIFUL BACHRI

Jabatan : Nip. 550009122

atan PERHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA


DAFTAR USULAN RENCANA KERJA Kegiatan : 1999/2000
Kegiatan DAERAH TINGKAT I : KALIMANTAN TIMUR
KOTAMADYA DAERAH TINGKAT II : SAMARINDA
NOMOR Kegiatan : 03
1 Nama Kegiatan : Peningkatan Jalan Mugirejo - Lubuk Sawa 11 Bendahara Kegiatan

2 Lokasi Kegiatan : Kotamadya Samarinda Nama

Ls 3 Jenis Penanganan : ATB & Aspal Penetrasi Macadam Pangkat

4 Tujuan Manfaat Kegiatan : Menunjang Pelayanan Umum / Pertanian Jabatan

5 Volume Fisik : 5,900 M 12 Lampiran


M3 6 Jumlah Hari Kerja / Manday : 150 Hari kalender A
M3 7 Perincian Jenis Pengeluaran Biaya : Dalam Ribuan Rupiah B
M3 C
JENIS PENGELUARAN JUMLAH %

A Upah = Rp. 74,123,910.87 #REF!


Liter B Bahan-Bahan Lokal = Rp. 244,619,484.81 #REF!
M3 C Bahan-Bahan Lain = Rp. 592,636,252.11 #REF!
M3 D Alat-Alat = Rp. #REF! #REF! Walikotamadya Kepala Daerah

E Lain-Lain = Rp. #REF! #REF! Tingkat II Kotamadya Samarinda

JUMLAH = Rp. #REF! #REF!


Buah 8 Sumber Pembiayaan Dalam Ribuan Rupiah

SUMBER PEMBIAYAAN JUMLAH LUKMAN SAID

Dana APBN = Rp.


Dana BLN (SPL-OECF INP-23) = Rp. #REF! #REF!
JUMLAH = Rp. #REF! #REF! An. Ketua Bappeda
9 RENCANA PELAKSANAAN Prop. Daerah Tingkat I
A Mulai Tanggal : Agustus 1999 Kalimantan Timur
M1 B Selesai Tanggal : Desember 1999 Kabid Fisik & Prasarana
10 Pemimpin Kegiatan
Nama : H. THAMRIN. B

Pangkat : Ir. H. SYAIFUL BACHRI

Jabatan : Nip. 550009122


atan PERHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
DAFTAR USULAN RENCANA KERJA Kegiatan : 1999/2000
Kegiatan DAERAH TINGKAT I : KALIMANTAN TIMUR
KOTAMADYA DAERAH TINGKAT II : SAMARINDA
NOMOR Kegiatan : 04

1 Nama Kegiatan : Pemeliharaan Periodik Jalan Dalam Kota 11 Bendahara Kegiatan

2 Lokasi Kegiatan : Kotamadya Samarinda Nama

Ls 3 Jenis Penanganan : Pacthing Lapen & Perkerasan Badan Jalan Pangkat

4 Tujuan Manfaat Kegiatan : Menunjang Pelayanan Umum Jabatan

5 Volume Fisik : 1,796 M2 12 Lampiran


6 Jumlah Hari Kerja / Manday : 150 Hari kalender A
M3 7 Perincian Jenis Pengeluaran Biaya : Dalam Ribuan Rupiah B
M3 C

JENIS PENGELUARAN JUMLAH %


A Upah = Rp. 699,650.50 0.092
M3 B Bahan-Bahan Lokal = Rp. 176,396,427.80 23.292

M3 C Bahan-Bahan Lain = Rp. 49,620,324.42 6.552

D Alat-Alat = Rp. 524,530,422.28 69.261 Walikotamadya Kepala Daerah


E Lain-Lain = Rp. 6,077,175.00 0.802 Tingkat II Kotamadya Samarinda
M3 JUMLAH = Rp. 757,324,000.00 100.000
M3 8 Sumber Pembiayaan Dalam Ribuan Rupiah
SUMBER PEMBIAYAAN JUMLAH LUKMAN SAID
Dana APBN = Rp.
M3 Dana BLN (SPL-OECF INP-23) = Rp. 757,324,000.00 100.000
M3 JUMLAH = Rp. 757,324,000.00 100.000 An. Ketua Bappeda
9 RENCANA PELAKSANAAN Prop. Daerah Tingkat I
A Mulai Tanggal : Agustus 1999 Kalimantan Timur
B Selesai Tanggal : Desember 1999 Kabid Fisik & Prasarana
10 Pemimpin Kegiatan
Nama : H. THAMRIN. B
Pangkat : Ir. H. SYAIFUL BACHRI
Jabatan : Nip. 550009122

PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K)


DAFTAR USULAN RENCANA KERJA Kegiatan : 1999/2000
Kegiatan DAERAH TINGKAT I : KALIMANTAN TIMUR
KOTAMADYA DAERAH TINGKAT II : SAMARINDA
NOMOR Kegiatan : 02

1 Nama Kegiatan : Peningkatan Jalan Air Terjun Tanah Merah 11 Bendahara Kegiatan

2 Lokasi Kegiatan : Kotamadya Samarinda Nama


Ls 3 Jenis Penanganan : ATB Pangkat

4 Tujuan Manfaat Kegiatan : Menunjang Pelayanan Umum / Pendidikan Jabatan

5 Volume Fisik : 481 M 12 Lampiran


M3 6 Jumlah Hari Kerja / Manday : 90 Hari kalender A
M3 7 Perincian Jenis Pengeluaran Biaya : Dalam Ribuan Rupiah B
C
JENIS PENGELUARAN JUMLAH %

Liter A Upah = Rp. 2,349,153.76 0.442


M3 B Bahan-Bahan Lokal = Rp. 6,385,092.63 1.202
C Bahan-Bahan Lain = Rp. 120,643,859.13 22.712
D Alat-Alat = Rp. 392,273,369.48 73.848 Walikotamadya Kepala Daerah

Buah E Lain-Lain = Rp. 9,537,525.00 1.796 Tingkat II Kotamadya Samarinda

JUMLAH = Rp. 531,189,000.00 100.000


8 Sumber Pembiayaan Dalam Ribuan Rupiah

SUMBER PEMBIAYAAN JUMLAH LUKMAN SAID

Dana APBN (Inpres Bantuan Khusus) = Rp. 531,189,000.00 100.000


Dana BLN = Rp.
JUMLAH = Rp. 531,189,000.00 100.000 An. Ketua Bappeda
9 RENCANA PELAKSANAAN Prop. Daerah Tingkat I
A Mulai Tanggal : Oktober 1999 Kalimantan Timur
B Selesai Tanggal : Desember 1999 Kabid Fisik & Prasarana
10 Pemimpin Kegiatan
Nama : BUDI TRISTRYONO, BE

Pangkat : Ir. H. SYAIFUL BACHRI

Jabatan : Nip. 550009122


PENINGKATAN JALAN POROS DESA / KECAMATAN (PPJPD/K)
DAFTAR USULAN RENCANA KERJA Kegiatan : 1999/2000
Kegiatan DAERAH TINGKAT I : KALIMANTAN TIMUR
KOTAMADYA DAERAH TINGKAT II : SAMARINDA
NOMOR Kegiatan : 01

1 Nama Kegiatan : Peningkatan Jalan Bukuan (Palaran) 11 Bendahara Kegiatan

2 Lokasi Kegiatan : Kotamadya Samarinda Nama


Ls 3 Jenis Penanganan : Aspal Penetrasi Macadam Pangkat

4 Tujuan Manfaat Kegiatan : Menunjang Pelayanan Umum / Pertanian Jabatan

5 Volume Fisik : 2,572 M 12 Lampiran


M2 6 Jumlah Hari Kerja / Manday : 90 Hari kalender A
M3 7 Perincian Jenis Pengeluaran Biaya : Dalam Ribuan Rupiah B
C
JENIS PENGELUARAN JUMLAH %

M3 A Upah = Rp. 10,695,685.84 0.738

B Bahan-Bahan Lokal = Rp. 233,206,140.23 16.080


C Bahan-Bahan Lain = Rp. 133,463,600.02 9.203
Buah D Alat-Alat = Rp. 1,066,643,448.91 73.548 Walikotamadya Kepala Daerah

E Lain-Lain = Rp. 6,253,125.00 0.431 Tingkat II Kotamadya Samarinda

JUMLAH = Rp. 1,450,262,000.00 100.000


8 Sumber Pembiayaan Dalam Ribuan Rupiah

SUMBER PEMBIAYAAN JUMLAH LUKMAN SAID

Dana APBN (Inpres Bantuan Khusus) = Rp. 1,450,262,000.00 100.000


Dana BLN = Rp.
JUMLAH = Rp. 1,450,262,000.00 100.000 An. Ketua Bappeda
9 RENCANA PELAKSANAAN Prop. Daerah Tingkat I
A Mulai Tanggal : Oktober 1999 Kalimantan Timur
B Selesai Tanggal : Desember 1999 Kabid Fisik & Prasarana
10 Pemimpin Kegiatan
Nama : BUDI TRISTRYONO, BE

Pangkat : Ir. H. SYAIFUL BACHRI

Jabatan : Nip. 550009122

atan PERHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA


DAFTAR USULAN RENCANA KERJA Kegiatan : 1999/2000
Kegiatan DAERAH TINGKAT I : KALIMANTAN TIMUR
KOTAMADYA DAERAH TINGKAT II : SAMARINDA
NOMOR Kegiatan : 01 (Lanjutan)

1 Nama Kegiatan : Peningkatan Jalan Bukuan (Palaran) 11 Bendahara Kegiatan

2 Lokasi Kegiatan : Kotamadya Samarinda Nama


Ls 3 Jenis Penanganan : Aspal Penetrasi Macadam (Lanjutan) Pangkat

4 Tujuan Manfaat Kegiatan : Menunjang Pelayanan Umum / Pertanian Jabatan


5 Volume Fisik : 3,208 M 12 Lampiran
6 Jumlah Hari Kerja / Manday : 90 Hari kalender A
M2 7 Perincian Jenis Pengeluaran Biaya : Dalam Ribuan Rupiah B
M2 + C

M2 JENIS PENGELUARAN JUMLAH %

A Upah = Rp. 1,485,598.29 0.119


B Bahan-Bahan Lokal = Rp. 205,233,117.85 16.422
M3 C Bahan-Bahan Lain = Rp. 89,259,985.38 7.142

M3 + D Alat-Alat = Rp. 951,025,198.48 76.095 Walikotamadya Kepala Daerah

M3 E Lain-Lain = Rp. 2,776,100.00 0.222 Tingkat II Kotamadya Samarinda


JUMLAH = Rp. 1,249,780,000.00 100.000

8 Sumber Pembiayaan Dalam Ribuan Rupiah

SUMBER PEMBIAYAAN JUMLAH LUKMAN SAID


Dana APBN (Inpres Bantuan Khusus) = Rp.
M3 Dana BLN (SPL-OECF INP-23) = Rp. 1,249,780,000.00 100.000
M3 + JUMLAH = Rp. 1,249,780,000.00 100.000 An. Ketua Bappeda
M3 9 RENCANA PELAKSANAAN Prop. Daerah Tingkat I
A Mulai Tanggal : Januari 2000 Kalimantan Timur
B Selesai Tanggal : Maret 2000 Kabid Fisik & Prasarana
10 Pemimpin Kegiatan
Nama : H. THAMRIN. B

Pangkat : Ir. H. SYAIFUL BACHRI

Jabatan : Nip. 550009122


atan PERHUBUNGAN DAN PENANGANAN JALAN KOTAMADYA DATI II SAMARINDA
DAFTAR USULAN RENCANA KERJA Kegiatan : 1999/2000
Kegiatan DAERAH TINGKAT I : KALIMANTAN TIMUR
KOTAMADYA DAERAH TINGKAT II : SAMARINDA
NOMOR Kegiatan : 01

1 Nama Kegiatan : Peningkatan Jalan PELITA IV 11 Bendahara Kegiatan

2 Lokasi Kegiatan : Kotamadya Samarinda Nama


Ls 3 Jenis Penanganan : Telford & Lapen Macadam Pangkat

4 Tujuan Manfaat Kegiatan : Menunjang Pelayanan Umum Jabatan

5 Volume Fisik : 1M 12 Lampiran


M3 6 Jumlah Hari Kerja / Manday : 90 Hari kalender A
7 Perincian Jenis Pengeluaran Biaya : Dalam Ribuan Rupiah B
M3 C
JENIS PENGELUARAN JUMLAH %
A Upah = Rp. 13,610,869.97 0.975
M3 B Bahan-Bahan Lokal = Rp. 170,300,135.87 12.204
M3 C Bahan-Bahan Lain = Rp. 155,588,443.51 11.150
M2 D Alat-Alat = Rp. 1,048,796,425.65 75.160 Kepala Seksi
E Lain-Lain = Rp. 7,127,125.00 0.511 Bina Marga DPU Dati II

M3 JUMLAH = Rp. 1,395,423,000.00 100.000 Kotamadya Samarinda

M3 8 Sumber Pembiayaan Dalam Ribuan Rupiah


M3 SUMBER PEMBIAYAAN JUMLAH

Liter Dana APBN = Rp. 1,395,423,000.00 100.000 Ir. DADANG AIRLANGGA. N

M3 Dana BLN = Rp. Nip. 550.013.096


M3 JUMLAH = Rp. 1,395,423,000.00 100.000
M3 9 RENCANA PELAKSANAAN
M3 A Mulai Tanggal : Oktober 1999
B Selesai Tanggal : Desember 1999 Daera
10 Pemimpin Kegiatan
M3 Nama : M. AGUS HUSEIN

Pangkat : D

Jabatan : Staff Sub.Bag Perencanaan


Buah
M1

Ls

M3
M3

Liter
M3
Buah

TEMBER 1999
OLEH :
AR
...............

AS )

aan
DURP
DAFTAR USULAN RENCANA Kegiatan

Kegiatan
BANTUAN PENINGKATAN JALAN KABUPATEN / KOTAM
(BPJK)
TAHUN ANGGARAN 1999 / 2000

PAKET NO : 08
PEMELIHARAAN PERIODIK JALAN DALAM KOTA
SAMARINDA

DINAS Kegiatan UMUM


DAERAH TINGKAT II KOTAMADYA SAMARINDA
Bendahara Kegiatan

Nama :
Pangkat :

Jabatan :

Lampiran
Lembar Rencana Kerja
Analisa Biaya & Kegiatan
Daftar Upah

Samarinda, 30 Juni 1999


Mengetahui :

Walikotamadya Kepala Daerah Kepala Dinas Kegiatan Umum

Tingkat II Kotamadya Samarinda Kodya Dati II Samarinda

LUKMAN SAID Drs. MUHAMADDIN DJAPRIE

Nip. 550007460

An. Ketua Bappeda Kepala Biro Pembangunan Kepala Sub. Dinas

Prop. Daerah Tingkat I Prop. Daerah Tingkat I Bina Marga DPU Tk. I

Kalimantan Timur Kalimantan Timur Kalimantan Timur

Kabid Fisik & Prasarana

Ir. H. SYAIFUL BACHRI SULAIMAN GAFUR, SE Ir. D. SIMBOLON

Nip. 550009122 Nip. 550006587 Nip. 110025674


Bendahara Kegiatan

Nama :
Pangkat :

Jabatan :

Lampiran
Lembar Rencana Kerja
Analisa Biaya & Kegiatan

Daftar Upah

Samarinda, 30 Juni 1999


Mengetahui :
Walikotamadya Kepala Daerah Kepala Dinas Kegiatan Umum

Tingkat II Kotamadya Samarinda Kodya Dati II Samarinda


LUKMAN SAID Drs. MUHAMADDIN DJAPRIE

Nip. 550007460

An. Ketua Bappeda Kepala Biro Pembangunan Kepala Sub. Dinas


Prop. Daerah Tingkat I Prop. Daerah Tingkat I Bina Marga DPU Tk. I
Kalimantan Timur Kalimantan Timur Kalimantan Timur
Kabid Fisik & Prasarana

Ir. H. SYAIFUL BACHRI SULAIMAN GAFUR, SE Ir. D. SIMBOLON

Nip. 550009122 Nip. 550006587 Nip. 110025674


Bendahara Kegiatan

Nama :

Pangkat :

Jabatan :

Lampiran
Lembar Rencana Kerja
Analisa Biaya & Kegiatan
Daftar Upah

Samarinda, 30 Juni 1999


Mengetahui :
Walikotamadya Kepala Daerah Kepala Dinas Kegiatan Umum

Tingkat II Kotamadya Samarinda Kodya Dati II Samarinda

LUKMAN SAID Drs. MUHAMADDIN DJAPRIE

Nip. 550007460

An. Ketua Bappeda Kepala Biro Pembangunan Kepala Sub. Dinas


Prop. Daerah Tingkat I Prop. Daerah Tingkat I Bina Marga DPU Tk. I
Kalimantan Timur Kalimantan Timur Kalimantan Timur
Kabid Fisik & Prasarana

Ir. H. SYAIFUL BACHRI SULAIMAN GAFUR, SE Ir. D. SIMBOLON

Nip. 550009122 Nip. 550006587 Nip. 110025674


Bendahara Kegiatan

Nama :

Pangkat :

Jabatan :

Lampiran
Lembar Rencana Kerja
Analisa Biaya & Kegiatan

Daftar Upah

Samarinda, 30 Juni 1999

Mengetahui :

Walikotamadya Kepala Daerah Kepala Dinas Kegiatan Umum


Tingkat II Kotamadya Samarinda Kodya Dati II Samarinda

LUKMAN SAID Drs. MUHAMADDIN DJAPRIE


Nip. 550007460

An. Ketua Bappeda Kepala Biro Pembangunan Kepala Sub. Dinas


Prop. Daerah Tingkat I Prop. Daerah Tingkat I Bina Marga DPU Tk. I
Kalimantan Timur Kalimantan Timur Kalimantan Timur
Kabid Fisik & Prasarana
Ir. H. SYAIFUL BACHRI SULAIMAN GAFUR, SE Ir. D. SIMBOLON
Nip. 550009122 Nip. 550006587 Nip. 110025674
Bendahara Kegiatan

Nama :

Pangkat :

Jabatan :

Lampiran
Lembar Rencana Kerja
Analisa Biaya & Kegiatan
Daftar Upah

Samarinda, 30 Juni 1999


Mengetahui :
Walikotamadya Kepala Daerah Kepala Dinas Kegiatan Umum

Tingkat II Kotamadya Samarinda Kodya Dati II Samarinda

LUKMAN SAID Drs. MUHAMADDIN DJAPRIE

Nip. 550007460

An. Ketua Bappeda Kepala Biro Pembangunan Kepala Sub. Dinas


Prop. Daerah Tingkat I Prop. Daerah Tingkat I Bina Marga DPU Tk. I
Kalimantan Timur Kalimantan Timur Kalimantan Timur
Kabid Fisik & Prasarana

Ir. H. SYAIFUL BACHRI SULAIMAN GAFUR, SE Ir. D. SIMBOLON

Nip. 550009122 Nip. 550006587 Nip. 110025674


Bendahara Kegiatan

Nama :
Pangkat :

Jabatan :

Lampiran
Lembar Rencana Kerja
Analisa Biaya & Kegiatan
Daftar Upah

Samarinda, 30 Juni 1999


Mengetahui :
Walikotamadya Kepala Daerah Kepala Dinas Kegiatan Umum

Tingkat II Kotamadya Samarinda Kodya Dati II Samarinda

LUKMAN SAID Drs. MUHAMADDIN DJAPRIE

Nip. 550007460

An. Ketua Bappeda Kepala Biro Pembangunan Kepala Sub. Dinas


Prop. Daerah Tingkat I Prop. Daerah Tingkat I Bina Marga DPU Tk. I
Kalimantan Timur Kalimantan Timur Kalimantan Timur
Kabid Fisik & Prasarana

Ir. H. SYAIFUL BACHRI SULAIMAN GAFUR, SE Ir. D. SIMBOLON

Nip. 550009122 Nip. 550006587 Nip. 110025674

Bendahara Kegiatan

Nama :
Pangkat :

Jabatan :
Lampiran
Lembar Rencana Kerja
Analisa Biaya & Kegiatan
Daftar Upah

Samarinda, 30 Juni 1999


Mengetahui :

Walikotamadya Kepala Daerah Kepala Dinas Kegiatan Umum

Tingkat II Kotamadya Samarinda Kodya Dati II Samarinda

LUKMAN SAID Drs. MUHAMADDIN DJAPRIE


Nip. 550007460

An. Ketua Bappeda Kepala Biro Pembangunan Kepala Sub. Dinas

Prop. Daerah Tingkat I Prop. Daerah Tingkat I Bina Marga DPU Tk. I
Kalimantan Timur Kalimantan Timur Kalimantan Timur
Kabid Fisik & Prasarana

Ir. H. SYAIFUL BACHRI SULAIMAN GAFUR, SE Ir. D. SIMBOLON

Nip. 550009122 Nip. 550006587 Nip. 110025674


Bendahara Kegiatan

Nama : DEDI SUPRIYADI


Pangkat :

Jabatan : Staff Sub.Bag TU

Lampiran
Lembar Rencana Kerja
Analisa Biaya & Kegiatan
Daftar Upah

Samarinda, 30 Juni 1999

MENGETAHUI :
Kepala Seksi Kepala Sub. Seski Pemimpin Kegiatan
Bina Marga DPU Dati II Perencanaan Bina Marga Perhubungan Dan Penanganan

Kotamadya Samarinda Jalan Kotamadya Dati II Samarinda

Ir. DADANG AIRLANGGA. N Ir. AKHMAD NAWAWI AGUS HUSAIN

Nip. 550.013.096 Nip. 550.011.214 Nip. 550.009.250

Kepala Dinas Kegiatan Umum


Daerah Tingkat II Kotamadya Samarinda

Drs. MUHAMADDIN DJAPRIE

Nip. 550.007.460
URP
N RENCANA Kegiatan

giatan
LAN KABUPATEN / KOTAMADYA
PJK)
ARAN 1999 / 2000

T NO : 08
DIK JALAN DALAM KOTA
ARINDA

giatan UMUM
OTAMADYA SAMARINDA
FORMULIR STANDAR UNTUK
REKAMAN ANALISA HARGA SATUAN

Kegiatan : UPTD WILAYAH II


Item Pembayaran : 2.1
Jenis Kegiatan : Galian Manual
Satuan Pembayaran : M3

NO KOMPONEN SATUAN PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Tidak Terlatih L.101 Jam 1.1667 9,000.00 10,500.00
2 Mandor L.061 Jam 0.1667 14,000.00 2,333.33

JUMLAH HARGA TENAGA 12,833.33

JUMLAH HARGA BAHAN

1 Flet Bed Truck Jam 0.3069 189,640.54 58,195.94


2 Alat Bantu Ls 1.0000 3,000.00 3,000.00

JUMLAH HARGA PERALATAN 61,195.94

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 74,029.27


E. BIAYA UMUM DAN KEUNTUNGAN 10 % x D 7,402.93
F. HARGA SATUAN Kegiatan (D + E) 81,432.20
LAMPIRAN BERITA ACARA HASIL EVALUSI DAN NEGOSIASI PENAWARAN HARGA

NAMA KEGIATAN : UPTD WILAYAH II KOTA SAMARINDA


NAMA PAKET : PENURAPAN DAN NORMALISASI JL. PANG. BENDAHARA
WILAYAH : KECAMATAN SAMARINDA SEBERANG
SUMBER DANA : TAHUN ANGGARAN 2012

Perkiraan CV. BAMBU BORNEO HPS / OE NEGOSIASI


Mata Pemb URAIAN Satuan Kuantitas Harga Satuan Total Harga Harga Satuan Total Harga Harga Satuan Total Harga KET
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
1 2 3 4 7 8 9 10 11

A PEKERJAAN UMUM

1 Papan Nama Kegiatan Ls 1.00 500,000.00 500,000.00 500,000.00 500,000.00 500,000.00 500,000.00 Tetap

500,000.00 500,000.00 500,000.00

B PEKERJAAN DRAINASE

1 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air M3 300.00 81,432.20 24,429,660.53 82,106.00 24,631,799.69 81,432.20 24,429,660.53 Tetap

24,429,660.53 24,631,799.69 24,429,660.53

C STRUKTUR

1 Pemancangan kayu ulin uk. 10 /10 M1 123.00 79,071.67 9,725,815.00 76,254.44 9,379,296.67 76,254.44 9,379,296.67 Nego
2 Papan Dinding 2/20 - 4M M2 120.00 132,336.11 15,880,333.33 134,004.44 16,080,533.33 132,336.11 15,880,333.33 Tetap
3 Struktur Kayu Ulin M3 3.46 6,375,233.33 22,071,057.80 6,433,753.33 22,273,654.04 6,375,233.33 22,071,057.80 Tetap

47,677,206.13 47,733,484.04 47,330,687.80


A JUMLAH 72,606,867 72,865,284 72,260,348
B PPN 10% 7,260,687 7,286,528 7,226,035
C TOTAL 79,867,553 80,151,812 79,486,383
D DIBULATKAN 79,867,000 80,151,000 79,486,000

MENGETAHUI, PANITIA UNIT LAYANAN PENGADAAAN


KONTRAKTOR

1. BUDI SANTOSO, ST : .....................


Pejabat Pengadaan Barang dan Jasa

ASNOPY PIRADE,S.Hut
Direktur
JADWAL PELAKSANAAN PEKERJAAN (TIME SCHEDULLE)

NAMA KEGIATAN : UPTD WILAYAH II KOTA SAMARINDA


NAMA PAKET : PENURAPAN DAN NORMALISASI JL. PANG. BENDAHARA
WILAYAH : KECAMATAN SAMARINDA SEBERANG

No. JUMLAH HARGA APRIL MEI


URAIAN VOLUME SATUAN ( Rp ) BOBOT KETERANGAN
DIV. Minggu Ke-2 Minggu Ke-3 Minggu Ke-4 Minggu Ke-1
(%)
1 DIVISI I UMUM
100%
Papan Nama Kegiatan 1.00 LS 500,000.00 0.69% 0.28%

2 PEKERJAAN DRAINASE
Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 300.00 M3 24,429,660.53 33.81% 33.81%

3 DIVISI 7 STRUKTUR
Pemancangan kayu ulin uk. 10 /10 123.00 M1 9,379,296.67 12.98% 6.49% 6.49% 50%

Papan Dinding 2/20 - 4M 120.00 M2 15,880,333.33 21.98% 7.33% 7.33% 7.33%

Struktur Kayu Ulin 3.46 M3 22,071,057.80 30.54% 10.18% 10.18% 10.18%


0%

Jumlah Nilai Pekerjaan 100%

Kemajuan Pekerjaan Bulanan (%) 34.09% 24.00% 24.00% 17.51%

Kemajuan Pekerjaan Kumulatif (%) 0.00% 34.09% 58.08% 82.08% 100%

MENGETAHUI,
KONTRAKTOR
CV. BAMBU BORNEO

ASNOPY PIRADE, S.Hut


9,879,296.67

72,260,348.33

34,308,957.20
KEGIATAN : UPTD WILAYAH II KOTA SAMARINDA
PEKERJAAN : PENURAPAN DAN NORMALISASI JL. PANG. BENDAHARA
LOKASI : KECAMATAN SAMARINDA SEBERANG
PAGU DANA Rp 80,151,000.00

Evaluasi harga dilakukan terhadap Penawaran yang memenuhi Persyaratan (Evaluasi) Administrasi dan Teknis, dengan penilaian terhadap Harga Penawaran
meliputi :
a. Koreksi Aritmatika
b. Kewajaran Harga

Adalah sebagai berikut :


a. Koreksi Aritmatika

1. CV. BAMBU BORNEO


PENAWARAN PENAWARAN TERKOREKSI
NO. URAIAN PEKERJAAN KODE SAT. VOLUME HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH SELISIH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) (%)

I UMUM
1 Papan Nama Kegiatan Ls 1.00 500,000.00 500,000.00 500,000.00 500,000.00 0.00

II PEKERJAAN DRAINASE
1 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air M3 300.00 81,432.20 24,429,660.53 81,432.20 24,429,660.53 0.00

III STRUKTUR
1 Pemancangan kayu ulin uk. 10 /10 M1 123.00 76,254.44 9,379,296.67 76,254.44 9,379,296.67 0.00
2 Papan Dinding 2/20 - 4M M2 120.00 132,336.11 15,880,333.33 132,336.11 15,880,333.33
3 Struktur Kayu Ulin M3 3.46 6,375,233.33 22,071,057.80 6,375,233.33 22,071,057.80

JUMLAH HARGA 72,260,348.33 72,260,348.33 0.00


PPN 10 % 7,226,034.83 7,226,034.83 0.00
JUMLAH TERMASUK PPN 10 % 79,486,383.17 79,486,383.17 0.00
DIBULATKAN 79,486,000.00 79,486,000.00 0.00

b. Kewajaran harga

NO. NAMA PENAWAR HARGA PENAWARAN PROSENTASE THD KETERANGAN


PAGU DANA

1 CV. BAMBU BORNEO Rp. 79,486,000.00 99.17 Wajar

UNIT LAYANAN PENGADAAN :

NO. NAMA PANITIA Tanda Tangan

1 BUDI SANTOSO,ST Pejabat Pengadaan Barang dan Jasa ……………………………

You might also like