You are on page 1of 1

VOLUME PEMBANGUNAN DRAINASE SONGA

Pembangunan Drainase Tipe 01 (panjang 122) Lebar Luas Tinggi Panjang BJ jumlah volume satuan
1 Galian Tanah - 1.45 - 122.00 - = 176.29 m3
2 Urugan Tanah/Sirtu/URUGAN KEMBALI 0.16 122.00 2.00 = 44.07 m3
3 Pas. Batu Dinding Drainase 1:4 0.30 122.00 2.00 = 73.20 m3
4 RABAT BETON lantai drainase TBL. 5 CM - 0.03 - 122.00 - = 3.97 m3
5 aanstamping batu kosong - 0.10 - 122.00 - = 11.90 m3
6 Plesteran Tbl. 1,5 cm - - 1.15 122.00 2.00 = 280.60 m2
7 Beton plat K-225 - 0.30 - 7.00 - = 2.10 m3
8 besi dia. 12 1.60 - - 7.40 0.89 - = 119.21 Kg
9 Pas. Batu Oprit 1:4 - 0.63 0.20 - 4.00 = 0.50 m3
10 Rabat beton lantai oprit tbl. 8 cm 1.31 - 0.08 6.60 2.00 = 1.38 m3
10 Urugan Kembali tanah (peninggian badan jalan/oprit) - 0.16 - 6.60 2.00 = 2.06 m3
11 Pas Baru Parapet 0.30 - 0.60 1.20 2.00 = 0.43 m3
11 Plesteran Parapet 0.30 - 0.60 1.20 2.00 = 4.32 m2
11 Acian Parapet 0.30 - 0.60 1.20 2.00 = 4.32 m2
11 Pengecatan Parapet 0.30 - 0.60 1.20 2.00 = 4.32 m2

Pembangunan Drainase Tipe 02 (panjang 36) Lebar Luas Tinggi Panjang BJ jumlah volume satuan
1 Galian Tanah - 1.87 - 36.00 - = 67.23 m3
2 Urugan Tanah/Sirtu/URUGAN KEMBALI 0.16 36.00 2.00 = 16.81 m3
3 Pas. Batu Dinding Drainase 1:4 0.40 36.00 2.00 = 28.80 m3
4 RABAT BETON lantai drainase TBL. 5 CM - 0.05 - 122.00 - = 5.49 m3
5 aanstamping batu kosong - 0.14 - 122.00 - = 16.47 m3
6 Plesteran Tbl. 1,5 cm - - 1.20 122.00 2.00 = 292.80 m2
7 Beton plat K-225 - 0.41 - 4.00 - = 1.65 m3
8 besi dia. 12 2.05 - - 4.40 0.89 - = 92.03 Kg
9 Pas. Batu Oprit 1:4 - 1.00 0.20 - 4.00 = 0.80 m3
10 Rabat beton lantai oprit tbl. 8 cm 2.03 - 0.08 3.60 2.00 = 1.17 m3
10 Urugan Kembali tanah (peninggian badan jalan/oprit) - 0.25 - 3.60 2.00 = 1.83 m3
11 Pas Baru Parapet 0.30 - 0.60 1.65 2.00 = 0.59 m3
11 Plesteran Parapet 0.30 - 0.60 1.65 2.00 = 5.67 m2
11 Acian Parapet 0.30 - 0.60 1.65 2.00 = 5.67 m2
11 Pengecatan Parapet 0.30 - 0.60 1.65 2.00 = 5.67 m2