Schedule of Materials & Labours

AIR VALVE CHAMBER

Ref :- M&L/AVC Drawing No. G - 25

Cement Sand Stone Gravel Wood Skilled Unskilled

S.N. Description Quantity Unit (bags) (m3) (m3) (m3) (m3) Labour Labour Miscellaneous Items

1 Site Clearance

2 Earthwork in excavation 1.10 m3 1.75

3 Dry stone filling 0.40 m3 0.44 0.40 1.40

4 Stone masonry in (1:6) C/S mortar 0.25 m3 0.53 0.12 0.28 0.38 1.25

5 Stone masonry work in mud mortar 0.27 m3 0.30 0.27 0.61

6 Installation of pipes & fittings L.S.

7 Selected material filling 0.25 m3 0.15

8 PCC (1:2:4) 0.07 0.45 0.03 0.06 0.07 0.28

9 Centering & Shuttering Works 0.32 0.02 0.06 0.08

10 600 mm ø Standard manhole cover 1.00 No.

Total 0.98 0.15 1.01 0.06 0.02 1.17 5.52


DEPARTMENT OF WATER SUPPLY & SEWERAGE
QUANTITY ESTIMATE

AIR VALVE CHAMBER

Page No. 1 of 1
Ref. No.: QNT-AIR Drawing No. G-25
S.N. Description No. Length Breadth Height Quantity Unit
1 Site Clearance L.S.

2 Earthwork in excavation in boulder mixed soil for 1.00 1.00 1.00 1.10 1.10 m³
foundation

3 Dry stone filling 1.00 1.00 1.00 0.40 0.40 m³

4 Stone masonry in (1:6) C/S mortar 1.00 2.60 0.35 0.28 0.25 m³

5 Stone masonry in mud mortar 1.00 2.60 0.35 0.30 0.27 m²

6 Plain Cement Concrete (1:2:4)


Slab cover 1.00 1.00 1.00 0.08 0.08
Deduction for manhole opening 1.00 ­x 0.30² 0.08 -0.02
Manhole cover 1.00 ­x 0.30² 0.05 0.01
0.07 m³

7 Centering & Shuttering Works 1.00 4.00 - 0.08 0.32 m²

8 Installation of pipes & fittings L.S.

9 Selected material filling 1.00 1.00 1.00 0.25 0.25 m³

10 Fixing standard manhole cover of 600 mm ø size 1.00 1.00 No.

____________________________ ____________________________
Prepared By Checked By

QTY-EST>AIR-VLV.WK1