129.04 m²
8.0 m²/day
= 16.13 days
8 masons
= 2 DAYS for 1st floor exterior wall 2 days (1st floor exterior wall)
1 day (2nd floor exterior wall)
77.39 m² 1 day (1st floor partition wall)
8.0 m²/day 2 days (2nd floor partition wall)
= 9.67 days 6 DAYS to install CHB on exterior and partition walls
8 masons
= 1 DAY for 2nd floor exterior wall
93.41 m²
8.0 m²/day
= 11.68 days 6 days ( P400 x 8 masons)
8 masons = 6 x P3,200
= 1 DAY for 1st floor partition wall
= P19,200
137.42 m²
8.0 m²/day
= 17 days
8 masons 2,580 pcs (exterior)
= 2 DAYS for 2nd floor partition wall
2,885 pcs (partition)
5,465 total number of CHB