You are on page 1of 5

FOOTING - 8

0.05m

0.45m

2.5m

0.05m
2.5m

PLYWOOD
AREA OF FORMS:

[ ( 0.05+0.05+ 2.5 )∗( 0.45 ) + ( 2.5∗0.45 ) ]∗2=4.59m2∗8=36.72 m2


1
COMMERCIAL LENGTH OF PLYWOOD: 4’ x 8’ x ' = 1.2m*2.4m
4

36.72 1
nPLYWOOD = =12.75 pcs ≈ 13 pcs−4 ' x 8' x marine plywoo
1.2∗2.4 2

BRACING
12.71 BF
AREA OF FORMS = 36.72m2 FACTOR: FOR 2” x 2”
m2

12.71 BF
BFT = 36.72m2 x = 466.7112BF
m2
14 ' BF
RoL = 2”x2”x = 4.67BF/pc
12
466.7112 BF
n2x2x14 = = 99.9382pcs ≈ 100pcs – 2” x 2” x 14’ RoL
4.67 BF / pc

No.4 CWN – 0.17kg/Length of column


No. 1 ½ CWN – 0.17kg/No. of Plywood

N0. 4 CWN – 0.17 * 0.9 * 8 = 1.224 ≈ 2kg

N0. 1 ½ CWN – 0.17 * 13 = 2.21 ≈ 3 kg

COLUMNS
PLYWOOD
AREA OF FORMS:
COLUMNS - FOOTING TOP LEVEL

[ ( 0.05+0.05+ 0.4 )∗2+ ( 0.4∗2 ) ]∗0.9=1.62 m2∗8=12.96 m2


INTERSECTION (2 SIDES)

[ ( 0.05+0.05+ 0.4 ) + ( 0.4 ) ]∗0.45=0.405 m2∗8=3.24 m2


AREA=3.24 + 12.96 = 16.2
m2

COLUMNS – GROUND LEVEL TO FIRST FLOOR, 3.5m IN HEIGHT

[ ( 0.05+0.05+ 0.4 )∗2+ ( 0.4∗2 ) ]∗( 3.5−0.45 )=5.49 m2∗4=21.96 m2


INTERSECTION (2 SIDES)

[ ( 0.05+0.05+ 0.4 ) + ( 0.4 ) ]∗0.45=0.405 m2∗2=0.81m2


INTERSECTION (1 SIDE) 0.4∗0.45=0.18 m 2∗2=0.36 m2

AREA = 21.96 + 0.81 + 0.36 = 23.13m 2

COLUMNS –FIRST FLOOR TO SECOND FLOOR, 3.5m IN HEIGHT

[ ( 0.05+0.05+ 0.4 )∗2+ ( 0.4∗2 ) ]∗( 3.5−0.45 )=5.49 m2∗8=43.92 m2


INTERSECTION (2 SIDES) [ ( 0.05+0.05+ 0.4 ) + ( 0.4 ) ]∗0.45=0.405 m 2∗2=0.81m 2

INTERSECTION (1 SIDE) 0.4∗0.45=0.18 m 2∗4=0.72m 2


AREA = 43.92 + 0.81 + 0.72 = 45.45 m 2

*use 50% of formworks from ground level: 45.45– (0.5*23.13) = 33.885m2

COLUMNS –SECOND FLOOR TO THIRD FLOOR, 3.5m IN HEIGHT

[ ( 0.05+0.05+ 0.4 )∗2+ ( 0.4∗2 ) ]∗( 3.5−0.45 )=5.49 m2∗8=43.92 m2


INTERSECTION (2 SIDES) [ ( 0.05+0.05+ 0.4 ) + ( 0.4 ) ]∗0.45=0.405 m 2∗4=1.62 m 2

INTERSECTION (1 SIDE) 0.4∗0.45=0.18 m 2∗4=0.72m 2

AREA = 43.92 + 1.62 + 0.72 = 46.26 m2

*use 50% of formworks from first level:46.26– (0.5*45.45) = 23.535m2

COLUMNS – THIRD FLOOR TO FOURTH FLOOR, 3.0m IN HEIGHT

[ ( 0.05+0.05+ 0.4 )∗2+ ( 0.4∗2 ) ]∗(3−0.4 )=4.68 m2∗8=37.44 m2


INTERSECTION (2 SIDES) [ ( 0.05+0.05+ 0.4 ) + ( 0.4 ) ]∗0.4=0.36 m 2∗4=1.44 m 2

INTERSECTION (1 SIDE) 0.4∗0.4=0.16 m2∗4=0.64 m 2

AREA = 43.92 + 1.44+ 0.64 = 39.52 m2

*use 50% of formworks from first level:39.52– (0.5*46.26) = 16.39m 2

TOTAL AREA = 16.2 + 23.13 + 33.885 + 23.535 + 16.39 = 113.14m 2

113.14 1
nPLYWOOD = =39.285≈ 40 pcs−4 ' x 8’ x marine plywoo
1.2∗2.4 2

BRACING
AREA OF FORMS = 113.14m2
12.71 BF
FACTOR = FOR 2 x2
m2
12.71 BF
BFT = 113.14m2 x = 1438.009BF
m2
RoL = 4.67BF/pc
1438.009
n2x2x14 = = 307.925pcs ≈ 308 pcs – 2” x 2” x 14’
4.67

No.4 CWN – 0.17kg/Length of column


No. 1 ½ CWN – 0.17kg/No. of Plywood

N0. 4 CWN – 0.17 * (3.05 * 18 + 2.6 * 8 + 0.45 * 26 + 0.4 *8) = 15.402 ≈ 16kg

N0. 1 ½ CWN – 0.17 * 40= 6.8 ≈ 7 kg

SCAFFOLDING
Htot Footing = 0.9m*8 = 7.20m

31.67
BFtot= 7.20 m∗ 7+ ( 2 )
+ 17.5 =290.412 BF

290.412 BF
=41.487 pcs .
# of pcs.= BF
7
pc
Htot Ground floor to First Floor = 3.05m*4 = 12.2m

31.67
BFtot= 12.2 m∗ 7+ ( 2 )
+17.5 =492.087 BF

492.087 BF
=70.298 pcs .
# of pcs.= BF
7
pc
Htot First Floor to Second Floor = 3.05m*6= 18.3m

31.67
BFtot= 18.3 m∗ 7+ ( 2 )
+17.5 =738.1305 BF

738.1305 BF
=105.4472 pcs .
# of pcs.= BF
7
pc
Htot Second Floor to Third Floor = 3.5m*8= 24.4m
31.67
BFtot= 24.4 m∗ 7+( 2 )
+17.5 =984.174 BF

984.174 BF 70.298
−( )=105.447 pcs .
# of pcs.= BF 2
7
pc
Htot Third Floor to Fourth Floor= 2.6m*8= 20.8m

31.67
BFtot= 20.8 m∗ 7+( 2 )
+ 17.5 =838.968 BF

838.968 BF 105.4472
−( )=67.129 pcs .
# of pcs.= BF 2
7
pc
Total # of Pcs = 41.487+70.298+105.4472+105.447+67.129 = 389.8082 pcs = 390 pcs
2”x3”x14’ rough lumber
No. 4 CWN = (7.20+12.20+18.30+24.40+20.80) m x 0.73 kg/m
No. 4 CWN = 82.9 m x 0.73 kg/m
No. 4 CWN = 60.517 kg = 61 kg