ACTIVITY #1

I. MASONRY WORKS
CONC. BLOCKS 6”- M^2 (PHP. 650/M^2)
CONC. BLOCKS 4”- M^2 (PHP. 650/M^2)
PLASTERING-M^2 (PHP. 3500/M^3)

6” CHB LAYING G/F


6.7 x 2.8 = 18.76 - 1.44- 1.68 = 15.64
6.7 x 2.8 = 18.76 – 1.80–0.72 = 16.24
4.8 x 2.8 = 13.44 – 1.80 = 11.64
3.85 x 2.8 = 10.78 – 2.10 = 8.68
2.15 x 2.8 = 6.02 = 6.02
3.05 x 2.8 = 8.54 – 1.68 – 0.1225 = 6.7373
64.9575 X PHP. 650 = PHP. 42,222.37

4” CHB LAYING G/F


I.0 x 2.8 = 2.80
I.01 1.25 x 2.8 = 3.5
I.02 1.75 x 2.8 = 1.365 = 3.535
9.835 X PHP. 650 = PHP. 6,392.75

6”CHB LAYING 2nd FLR


6.7 X 2.8 = 18.76 – 1.44 – 0.1225 – 1.44 = 15.87
6.7 X 2.8 = 18.76 – 1.44 - 0.72 – 0.72 = 15.88
4.8 X 2.8 = 18.76 – 13.44 - 0.1225 – 1.80 = 11.51
3.85 X 2.8 = 10.78 – 1.44 – 0.72 = 8.62
2.15 X 2.8 = 6.02 – 1.44 = 4.58
3.05 X 2.8 = 8.54 – 1.44 = 7.10
63.56 X PHP. 650 = PHP. 41,314

4” CHB LAYING 2ND FLR


2.75 X 2.8 = 7.7 – 1.68 = 6.02
2.70 X 2.8 = 7.56 – 1.68 = 5.88
1.50 X 2.8 = 4.2 – 1.365 = 2.835
0.5 X 2.8 = 1.4
2.55 X 2.8 = 7.14
3.50 X 2.8 = 9.8 – 1.68 = 8.12
2.85 X 2.8 = 7.98
1.75 X 2.8 = 4.9 – 1.365 = 3.535
0.90 X 2.8 = 2.52
45.53 X PHP. 650 = PHP. 29,529.50
PLASTERING
G/F = 73.275 + 9.835 = 83.11 X PHP. 3500 = PHP. 290,885
2ND FLR = 63.56 + 45.43 = 108.99 X PHP. 3500 = PHP. 381,465

II. ARCHITECTURAL WORKS


1.0 FLOOR TILES

G/F = 2.92 X PHP. 1350 = PHP. 3,942

2ND FLR = 6.5 X PHP. 1350 = PHP. 8,775

2.0 BASE BOARD


G/F = 20.79
2ND FLR = 34.55
55.34 L m X PHP. 500 = PHP. 27,670

BASE BOARD
G/F = 20.79 L m X PHP. 500 = PHP. 10.395
2ND FLR = 33.75 L m X PHP.500 = PHP. 16, 876
ACTIVITY #2

I. SOIL POISONING: ( FOR RESIDENTIAL)

FLOOR AREA= 7.00 M X 7.00 M = 49.00 M^2


PHP. 10,000 – PHP. 15,000

II. BACKFILLING
NO. OF WORKERS X PHP. 300/ DAY
9 LABORS X PHP. 300= PHP.2700 X 3 DAYS = PHP. 8,100

III. COLUMNS
BAR DIA. UNIT WT LENGTH TOTAL WT PRICE/ TOTAL
(mm) (Kg.m) (m) (Kg.) KILO AMOUNT
10 0.617 115.2 71.0784 75.39 5,358.60
12 0.888 383.62 340.65 118.69 40,431.87
16 1.578 681.696 1,075.71 193.15 207,774.60

IV. BEAMS

BAR DIA. UNIT WT LENGTH TOTAL WT TOTAL


(mm) (Kg.m) (m) (Kg.) AMOUNT
10 0.617 115.2 71.08 5,643
12 0.888 672 596.736 70,826.59
16 0.578 105.6 166.637 22,528.44
ACTIVITY #

I. ONE WAY SLAB

V= L X W X H
V= 7 X 7 X 0.30
V= 14.7 M^3

A= L X H
A= 7.00M X 7.00M = 49 M^2

1) L/4 = 7/4 = 1.75 1.75


2) .30 .30
3) L/5 = 7/5 = 1.4 1.40
4) 0.10 0.10
3.55 M
7-((L/5+BEND BAR))2
7- (.80)2
7= 1.6
=5.4 M

7/.15= 46.6 pcs 7/.30= 23.3 pcs

TIE WIRE

49M^2 X .228 = 11.172 = 12 kg

RENTAL: MIXER @ 500 x 3 days = PHP. 1,500

LABOR

ENGR. @550

FOREMAN @500

LABORER @1200

PHP 2250 X 3 DAYS = 6,700 + 1,500 + 6,664

=PHP. 14,914
CLASS A MIXTURE

40kg/ CEMENT ITEM PRICE TOTAL AMOUNT

14.7 x 9.0 = 132 cu. M cement @220 PHP. 29,150


14.7 x .50 = 7.35 cu. M sand @420 PHP. 3,087
14.7 x 1.0 = 14.7 cu. M gravel @650 PHP. 9,555
PHP. 41,792

UNIT COST
QUANTITY PRICE AMOUNT
27 pcs. @320 8, 640
13 pcs. @320 4,160
4 kg @70 280
PHP. 13,080
ACTIVITY #

-WALL (LEFT SIDE AND REAR)

MATERIAL COST:

RUNNING BOND= LX H X NO. OF PCS.

12.5 pcs = 6”

= 7 m x 3 m x 12.5 pcs = 262.5 pcs.

= 262.5 X PHP. 8.50 = PHP. 2,231. 25

LABOR COST:

PHP. 350/ (4)PERSON = PHP 1,400

5 DAYS = DURATION

PHP.1,400 X 5 DAYS = PHP. 14,000

-WALL (FRONT)

12.5 = 6”

= 5 m X 3 m X 12.5 pcs = 187.5 pcs

=187.5 x PHP. 8.50 = PHP. 1,593.75

12.5 = 6”

= 2m x 3m x 12.5 pcs = 75 pcs

= 75 x PHP. 8.50 = PHP. 637.50

-WALL (RIGHT SIDE)

12.5 pcs = 6”

= 4m x 3m x 12.5 pcs = 150 pcs

= 150 x PHP. 8.50 = PHP. 1,275

12.5 PCS =6”

=3m x 3m x 12.5 = 112.5 pcs.

=112.5 pcs x PHP. 8.50 = PHP. 956.25


ACTIVITY# / QUIZ #1

I. TWO WAY SLAB

L/4 = 7.00/4 = 1.75


L/5 = 7.00/5 = 1.40
Column width = 0.20 m

CUT BARS
0.20 + 1.40 = 1.60 x 10 x 4 = 64 = 10.66 = 11 pcs
6

TEMP. BARS
7.00 X .10 = 0.70
3.00 X .10 = 0.30
4.00 X .10 = 0.40
4.10 X .10 = 0.41
3.10 X .10 = 0.31
0.90 X .10 = 0.09
2.21/6 = 36.83 = 37 pcs x 2 = 74 pcs
+ 11 pcs
85 pcs

QUIZ #1
II. GYPSUM PLASTER BOARD

Ceiling area of 2nd flr = 42.2 m^2

 Gypsum plaster board coverage area = 3.00 m^2

42.2/ 3.00 = 14.06 = 14 pcs of sheet  Gypsum board with Styrofoam

 Gypsum plaster board (interior wall)


Wall Area = Aw

Aw = 9.3/3.00 = 3.1 = 3 pcs (for master bedroom)


Aw = 12.3/3.00 = 4.10 = 4 pcs (for master bedroom)
Aw = 8.4/3.00 = 2.80 = 3 pcs (for BR1 & BR2)
Aw = 3/ 3.00 = 1 pc = (for BR1 & BR2)

TOTAL: 11pcs of Gypsum board green laminated waterproof

MATERIAL COST:

 For Ceiling  14pcs x PHP. 1,610 = PHP. 22, 540.00


 For Interior wall  11pcs x PHP. 885 = PHP. 9,735.00

QUIZ #1
I. DOORS

TYPES OF DOOR/S NO. OF ITEMS PRICE AMOUNT


Regular Panel Type Door 6 2,880 17,280.00
Flush Type Door 3 1,500 4,500.00
Lock Sets 9 3,200 28,800.00
Door Jambs 9 1,200 10,800.00
Total PHP. 61,380.00
II. WINDOWS

TYPES OF WINDOWS NO. OF ITEMS PRICE AMOUNT


Sliding Window 9 3,245 29,205.00
Fixed Window 4 6,215 24,860.00
Awning Window 3 19,140 57,420.00
Total PHP. 111,485.00

LABOR COST

3 DAYS X 3 PERSONS

PHP. 300-450/DAY

= PHP. 4,050.00 TOTAL LABOR COST

ACTIVITY NO. 6
I. ELECTRICAL

WIRING & CABLES


-Solid Wire #12 – PHP. 37.75/ mt.
Total = 4.35m
1.35m + 1.00m + 2.00m = 4.35m x PHP. 37.35 = PHP. 164.2125/ rm./ light

ACCESSORIES
-Single Gang Wall Switch – PHP. 64.00 (4 pcs) = 256.00
-Two Gang Wall Switch – PHP. 99.00 (2pcs) = 198.00
-Three Gang Wall Switch – PHP. 144.00 (3pcs)= 432.00
-Duplex Convenience Outlet – PHP. 94.75 (12pcs) = 1,137.00
PHP. 2,023.00

LIGHTING FIXTURES
-Chandelier PHP. 4,000.00 (1pc) = 4,000.00
-Surface Mounted Downlight PHP. 395.00 (12PCS)= 4,740.00
-Wall Mounted Downlight PHP. 500.00 (6PCS) = 3,000.00
PHP. 11,740.00

-Contemporary Pendant Lighting PHP. 1,500.00 (1pc) = 1,500.00


-Bathroom Lighting PHP. 150.00 (6pcs) = 900.00
-Panel Board PHP. 1,000.00 (1pc) = 1,000.00
-Pin Light PHP. 250.00 (8pcs) = 2,000.00
-Led Light Bulb PHP. 150.00 (4pcs) = 600.00
PHP. 6,000.00

MATERIAL COST
(PHP. 19,763) (35%) = PHP. 6,917.05 + PHP. 6,400.00
= PHP. 13,317.05
BUILDING TECH 4
_____________________________________________________________________________________

COST & ESTIMATES

NICERIO, FRANZ JOSEPH N. AR. RONALD DALMACIO

BS ARCHITECTECTURE/5TH YR MARCH 22, 2016