CONCRETE
Concrete Proportion
Cement in Bag
Mixture Proportion Sand cu. Gravel cu.
Class m. m.
40kg 50kg
SLAB
From the floor plans:
Ground Floor Area = 100sqm.
Second Floor Area = 100sqm.
Roof Deck Floor Area = 100sqm.
Roof Slab Area = 16sqm
Slab Thickness = 0.125 m
Solution:
1) Determine the total volume of the proposed building.
Ground Floor Volume = 100 sqm. x 0.125 m = 12.5 cu.m.
Second Floor Volume = 100 sqm. x 0.125 m = 12.5 cu.m.
Roof Deck Volume = 100 sqm. x 0.125 m = 12.5 cu.m.
Roof Slab Volume = 16 sq.m.. x 0.125 m = 2 cu.m.
Total Volume = (12.5 * 3) + 2 cu.m.
Total Volume = 39.5 cu.m.
2) Using 40kg cement class A mixture, multiply the volume by the corresponding
values.
Cement = 39.5 cu.m. x 9 = 355.5~ 356 Bags
Sand = 39.5 cu.m. x 0.50 = 19.75 cu.m.
Gravel = 39.5 cu.m. x 1 = 39.5 cu.
FOOTING
From the Footing Details:
Solution:
1) Determine the total volume of footing of the proposed building.
F= (2.1 m x 2.1m x 0.5m) = 2.205 m3
Total volume of footing = 2.205 x 9
Total Volume = 19.845 cu.m.
2) Using 40kg cement class A mixture, multiply the volume by the corresponding
values.
Cement = 19.845 cu.m. x 9 = 178.605 ~179 Bags
Sand = 19.845 cu.m. x 0.5 = 13.81 m3 ᵙ 9.9225~ 10 cu.m.
Gravel = 19.845 cu.m. x 1 = 27.62 m3 ᵙ 19.845 cu.m.
COLUMN
TOTAL ₱ 170,615.00
BEAM
Cement (Portland) 150.00 Bags 224.00 Per bag 33,600.00
TOTAL ₱ 445,720.00
STAIRS
Wide Flange W12x14 (coated 18.00 Pcs. 2,000.00 Per pc. 36,000.00
with rectangular tube)
6mm THK Steel Plate 38.00 Pcs. 3,000.00 Per pc. 114,000.00
300x350mm
6mm THK Steel Plate W12x14 9.00 Pcs. 5,500.00 Per pc. 45,500.00
with 800mmx200mm (attached
to wood)
6mm THK Steel Plate Stiffener 44.00 Pcs. 2,500.00 Per pc. 110,000.00
6mm THK Steel Plate 800mm x 18.00 Pcs. 5,500.00 Per pc. 99,000.00
200mm x 6mm
TOTAL ₱418,250.00